Upload
dodieu
View
217
Download
0
Embed Size (px)
Citation preview
Case No. 147 of 2014 Page 1 of 22
Before the
MAHARASHTRA ELECTRICITY REGULATORY COMMISSION
World Trade Centre, Centre No.1, 13th Floor, Cuffe Parade, Mumbai 400005.
Tel. 022 22163964/65/69 Fax 22163976
Email: [email protected] Website: www.mercindia.org.in, www.merc.gov.in
Case No. 147 of 2014
Petition under Section 86 of the Electricity Act, 2003 for adjustment in tariff under the
Power Purchase Agreements (PPA’s) dated 22 April, 2010 and 5 June, 2010 executed
between Maharashtra State Electricity Distribution Company Limited and Indiabulls
Power Limited pursuant to impact on tariff due to shortage in domestic coal availability
and consequent changes in New Coal Distribution Policy dated 18 October, 2007
Smt. Chandra Iyengar, Chairperson
Shri Vijay L. Sonavane, Member
Shri Azeez M. Khan, Member
Parties to the present case:
Indiabulls Power Limited (“IPL”) ...…..Petitioner
Maharashtra State Electricity Distribution Company Limited (“MSEDCL”) ..…Respondent
Present on behalf of the Petitioner Shri Sanjay Sen, Advocate
Shri Rajiv Rattan
Present on behalf of the Respondent Smt. Deepa Chawan
Authorised Consumer Representatives Dr. Ashok Pendse, TBIA
ORDER
Dated: 20 August, 2014
Case No. 147 of 2014 Page 2 of 22
Three Generators (Indiabulls Power Limited, Adani Power Limited and JSW Energy Limited)
which had tied up power under the Case 1 route of the “Guidelines for Determination of Tariff
by Bidding Process for Procurement of Power by Distribution Licensees" issued by Ministry of
Power, Government of India (hereinafter referred to as “Competitive Bidding Guidelines” with
Maharashtra State Electricity Distribution Company Limited (hereinafter referred to as
“MSEDCL”), had approached the Commission for compensation/adjustment in Tariff due to
shortage of domestic coal availability, increase of price of imported coal, etc. in Case No. 154,
189 and 118 of 2013. Considering the common issues involved in the matters, the Commission
had heard the cases jointly and approved a framework for compensatory fuel charge in Order
dated 15 July, 2014. The Commission had directed the three Petitioners in those cases to
approach the Commission with detailed justification of their hardships to claim the compensatory
fuel charge under the approved framework. Accordingly, Indiabulls Power Limited (hereinafter
referred to as “IPL”), the Petitioner in Case No. 154 of 2013, has filed the present Petition for
approval of compensatory fuel charge.
2. IPL has made the following prayers in the present Petition:-
“
a) condone the delay in filing the present petition;
b) allow 100% transportation and transaction costs which would be incurred by the
Petitioner post the CCEA notification dated 21 June, 2013 and the amendment of NCDP
dated 26 July, 2013;
c) Allow full pass through of incremental cost in procuring alternate coal for meeting the
shortfall quantity by modifying the formula in para 33.1.2 of Order dated 15.07.2014 as
below:
i. change in Step - 1 by using the actual ‘as received’ GCV for calculation of Units
generated from domestic coal instead of using Baseline GCV
OR
ii. revise the Step - 4 so that compensation calculated in Step - 3 is multiplied with
Units generated by units from imported coal, calculated in Step – 2
OR
iii. apportion the incremental cost of alternate coal over actual units delivered
Hon’ble Commission may consider option (iii) above for the reasons enumerated
in this Petition.
d) the Hon’ble Commission may recognize the losses suffered by the Petitioner on account
of lower generation resulting from supply of lower grade of coal vis-à-vis the grade
assured by the LoAs compensate the Petitioner for the same;
e) pass such other order or order(s) as this Hon’ble Commission deems fit in the facts and
circumstances of the present case.”
Case No. 147 of 2014 Page 3 of 22
3. In its Petition, IPL submitted as follows:
3.1 IPL has executed two Power Purchase Agreements (hereinafter referred to as “PPA”), for
supply of aggregate 1200 MWs (450 MWs and 750 MWs respectively) of power to the
MSEDCL. There has been a substantial increase in the fuel cost due to non-supply of
assured quantity of coal by the State owned coal supplier Coal India Limited and its
subsidiaries (hereinafter referred to as “CIL”), and also failure to supply the assured grade
of coal. On the said matter, the Petitioner had filed a Petition, which was numbered as Case
No. 154 of 2013. The Commission had issued an Order on 15 July, 2014 in the said matter.
In the aforesaid Order, the Commission has recognised hardships being faced by the
Petitioner and has proposed a methodology for allowing Compensatory Fuel Charge on
account of changes in the business environment related to coal demand-supply situation,
prices of coal in the international market, etc.
3.2 IPL submitted that while accepting most of the findings of the Order in Case No. 154 of
2013, it is seeking clarification on the following issues in the present Petition:
i. under recovery of entire cost of incremental Alternate coal;
ii. recovery of only 60 % of the transportation and transaction cost;
iii. Non recovery of entire cost of Alternate coal to be sourced due to slippage in
assured quality of domestic coal.
iv. Not adopting the principles of the Article 10.2.1 of the PPA which stipulates as
follows:
“while determining the consequences of Change in Law under this Article 10, the
parties shall have due regards to the principle that the purpose of compensating
the party affected by such Change in Law, is to restore through monthly tariff
payment, to the extent contemplated in this Article 10, the affected party to the
same economic position as if such Change in Law has not occurred.”
On Recovery of Alternate coal costs under the proposed mechanism
3.3 The Petitioner submitted that the Commission has laid down a methodology to recover
Compensatory fuel charge in paragraph 32 of the said Order. IPL has worked out the actual
recovery under the said methodology applying various formulae specified therein at
Paragraph 32, 33, 33 and 34 of the said Order dated 15 July, 2014. Following are the
underlying parameters:
Case No. 147 of 2014 Page 4 of 22
Table 1: Underlying parameters for computing Compensatory fuel charge
Sr. No Parameter Unit Value Description/Remark
1 Baseline quantity MTPA 5.493 As per the Fuel Supply Agreement
(hereinafter referred to as “FSA”) executed
with the South Eastern Coalfields Limited
(hereinafter referred to as “SECL”), the
Subsidiary Company of CIL
2 P Linkage INR/MT 2,298 As per the existing landed coal costs from
SECL
3 Baseline GCV Kcal/kg 4,150 As per the FSA, G10, G11 and G12 grades
of coal are allocated. However, currently,
SECL is supplying G11 grade of coal and
accordingly, the mid-point GCV of G11
grade of coal i.e. 4150 Kcal/kg is
considered. Range of G11 grade coal is
4000 – 4300 Kcal/kg.
4 Shortfall quantity
of domestic coal
MTPA 1.648 Currently, the Petitioner is receiving ~ 70%
of FSA quantity and hence the quantum of
coal supply would be 3.845 (70% of
baseline quantity i.e. 70% x 5.493) MTPA.
Accordingly, the shortfall quantity to be
Minimum of:
(a) 5.493 – 3.845 = 1.648; and
(b) 65% of 5.493 = 3.570
Kindly note that the coal supplies from
SECL are commenced in phased manner,
as and when each unit gets commissioned
on pro-rata basis of commissioned capacity
of 2 units (2x270MW). Realisation of
~70% of coal against FSA quantum is an
approximate number which will be
computed based on actual coal received
during the period under consideration vis-
a-vis entitlement of domestic coal under
FSA.
5 (i) Revised GCV of
alternate source
kcal/kg 5000 Based on Argus (5000 Kcal/kg GAR)
Index for Indonesian coal for the purpose
of computation
5 (ii) Shortfall quantity
of alternate coal
required
MTPA 1.368 (Shortfall Quantity of domestic coal x
Baseline GCV ) / Revised GCV of
alternate source
i.e. (1.648 x 4150) / 5000
Case No. 147 of 2014 Page 5 of 22
Sr. No Parameter Unit Value Description/Remark
6 Revised price of
alternate source
Rs/ton 4,814 Price based on Argus (ICI3, 5000 Kcal/kg
GAR) indices for Indonesian coal. The
break-up of coal price is given in the Table
2
7 Net SHR kcal/kWh 2692 Norms specified by CERC taken in to
consideration
Turbine Heat Rate - 1955 kcal/kWh
Boiler Efficiency - 85%
Multiplying factor - 1.065
Auxiliary consumption - 9%
Net SHR = {(1955/85%) * 1.065}/(1-
9%)
8 Units generated
from alternate coal
MUs 2541 Quantity of Alternate Coal in MTPA x
10^3 x Revised GCV of imported/alternate
source (kCal/kg)/Net SHR (kCal/kWh)
i.e. (1.368 x 10^3 x 5000 / 2692)
9 Units that can be
generated with
domestic coal at
baseline GCV
MUs 5928 = Quantity supplied under FSA x baseline
GCV x 10^3 / net SHR
= (5.493 x 70% x 4150 x 1000)/2692
10 Actual units
generated with
domestic coal at
actual GCV of
3600 kcal/kg
MUs 5142 = Quantity supplied under FSA x actual
GCV x 10^3 / net SHR
= (5.493 x 70% x 3600 x 10^3)/2692
11 Actual units that
will be delivered
with available
domestic coal at
actual GCV and
coal sourced from
alternate source
MUs 7683 5142 + 2541
Table 2: Break-up of PAlternate as per approved methodology
Component Price Recovery
FOB Price ($/ton) 51.33 100%
Sea Freight ($/ton) 8.50 $/ton 60%
Insurance ($/ton) 1 $/ton 60%
CIF Price ($/ton) 60.83
Rupee -$ rate 60.85
CIF Price (Rs/ton) 3,702
Case No. 147 of 2014 Page 6 of 22
Component Price Recovery
Port handling charges (Rs/ton) 500 60%
Duties, cess and taxes on coal (Rs/ton) 305 100%
Railway freight from Dahej to plant – distance ~740 KMs
(Rs/ton) 969 60%
Duties, cess and taxes on railway freight (Rs/ton) 244 60%
Total coal cost (Rs/ton) 5,720
Transit loss (0.2%) 11 100%
Actual Landed Coal Cost (Rs/ton) (P Alternate_ Actual) 5,731
Coal cost for recovery at 60% considered by Hon’ble
Commission (Rs/ton) (P Alternate) 4,814
3.4 Accordingly, the compensatory fuel charge is worked out as follows:
Table 3: Computation of compensatory fuel charge
Sr. No. Parameter Computation
I Quantity of Alternate coal
in MTPA
= (Shortfall in CIL Qty x Baseline GCV) /Alternate Coal
GCV
= (1.648 x 4150) /5000
= 1.368 MTPA
II Compensatory Fuel Charge
(Rs/kWh)
(i) Cost of Alternate Coal = (Q Alternate x P
Alternate(Actual))
= (1.368 x 5731) = Rs. 784 Crores
(ii) Cost of Alternate Coal with 60% restriction on
transaction and transportation costs
= (Q Alternate x P Alternate)
= (1.368 x 4814) = Rs. 658 Crores
(iii) Cost of Domestic Coal = (Q Shortfall x P Linkage)
= (1.648 x 2298)
= Rs. 379 Crores
(iv) Actual incremental cost incurred on Alternate coal =
Cost of Alternate Coal – Cost of Domestic coal
= Rs 784 Crores – Rs 379 Crores
= Rs 405 Crores
(v) Hence, Actual Compensatory fuel charge at 100%
recovery of entire cost of alternate coal
= (Q Alternate x P Alternate Actual) - (Q Shortfall x P
Linkage)
Units generated from alternate coal
= 784 Crores – 379 Crores
(2541/10)
= Rs 1.59/kWh
(vi) As per the Order dated 15 July, 2014, passed in Case
No. 154 of 2013 Compensatory fuel charge at 60% recovery
of transportation and transaction costs of alternate coal will
be:
= 658 Crores – 379 Crores
(2541/10)
Case No. 147 of 2014 Page 7 of 22
Sr. No. Parameter Computation
= Rs 1.10/kWh
III Computation of total
amount of compensatory
charge
Step 1: Units from domestic coal
= (Baseline Quantity – Shortfall Quantity) x Baseline GCV/
Net SHR
= (5.493 – 1.648) x (4150 / 2692)
= 5928 MUs
Step 2: Actual units generated from Alternate coal
= Quantity of Alternate Coal in MTPA x ‘Revised GCV of
imported/alternate source’/Net SHR
= (1.368 x 5000 x 10^3)/2692
= 2541 MUs
Step 3: The denominator for the formula for compensatory
fuel charge per unit shall be computed using the Units from
imported coal in Step 2
Step 4: Compensatory fuel charge payable shall be the
compensatory fuel charge per unit payable in Step 3
multiplied by minimum of:
(i) Actual units delivered at delivery point from
the contracted capacity – Units from domestic coal as
computed in Step 1
= (7683 – 5928)
= 1755 MUs
(ii) Units from imported coal computed in Step
2
= 2541 MUs
Hence, the Compensatory fuel charge arrived at above i.e. Rs
1.10/kWh will be applied on 1755 MUs (minimum at step 4),
and will work out to Rs 193 Crores i.e., (Rs 1.10/kWh x 1755
MUs/ 10)
3.5 Based on the above, the Petitioner has claimed that:
The total compensation as per the adopted formula will be Rs 193 Crores, whereas the
total incremental cost incurred by the Petitioner is Rs 405 Crores as computed at Sr.
No. II (iv) in the Table 3 above leading to under recovery of 212 Crores, i.e., 52%.
The actual units generated with domestic coal, i.e., 5142 MUs are significantly lower
due to slippage in quality of coal. Using theoretical units generated from domestic coal
of 5928 MUs in Step 4 (Sr. No. III in Table 3) above is leading to recovery of
compensatory fuel charge on far lesser units than the actual units generated with
imported coal.
Reasons for under recovery of Alternate coal costs under the proposed methodology:
Case No. 147 of 2014 Page 8 of 22
3.6 IPL submitted while the incremental cost for alternate coal is Rs. 405 Crores, it is being
granted compensation of Rs. 193 Crores only. The primary reasons of this under recovery
to the extent of 52% of actual costs are:
Restriction imposed at Step 4 (Sr. No. III in Table 3) above on number of units allowed
to claim Compensatory fuel charge (21% of the actual costs); and
Only 60% recovery of transportation and transaction cost of Alternate coal (31% of the
actual costs).
3.7 The following tables depict the impact of above two factors:
Table 4: Impact of restriction on number of units on which compensatory fuel charge will
be applicable
Factor Rs Crores % of under
recovery
[Units generated with imported coal, i.e., 2541 MUs
minus
Units for which compensation granted, i.e., 1755 MUs
Hence, units for which Compensatory fuel charge of Rs
1.10/kWh not applied are
(2541 – 1755) = 786 MUs
Rs 87 Crores
(786 MUs x Rs
1.10 kWh)
21%
Table 5: Impact of restriction imposed for 60% recovery of transportation and transaction
cost of alternate coal
Factor Rs Crores % of under
recovery
Revised Compensatory fuel charge based on 100%
transportation and transaction costs, i.e., Rs 1.59/kWh
minus
Compensatory fuel charge at 60% cost recovery of
transportation and transaction costs, i.e., Rs 1.10/kWh
multiplied with total generation from alternate coal, i.e.,
2541 MUs
Rs 125 Crores
(1.59 – 1.10)
Rs/kWh x 2541
MU)
31%
Case No. 147 of 2014 Page 9 of 22
3.8 The following tables summarises the total recovery and under-recovery of the cost incurred
on alternate coal:
Table 6: The total incremental cost of Rs 405 Crores incurred by the Petitioner is
bifurcated as follows:
Factor Rs Crores In % terms
Cost recovered by the Petitioner as per
the formula
193 48%
Unrecovered cost due to restriction
imposed on units
87 21%
Unrecovered cost due to restriction
imposed on recovery of only 60% of
transaction and transportation cost
125 31%
Total incremental cost on Alternate
Coal incurred by the Petitioner
405 100%
Changes that may be considered in the proposed methodology to address the under
recovery in costs of Alternate coal
3.9 IPL submitted that the formula adopted by the Commission for calculating the
Compensatory fuel charge for the under recovery of the cost of imported coal does not
entail full recovery of incremental coal cost as enumerated above. IPL submitted that the
formula applies Baseline GCV instead of using actual ‘as received’ GCV. Since ‘as
received’ GCV is significantly lower than the Baseline GCV, the actual units generated
from domestic coal (5142 MUs) are significantly lower than theoretical units calculated.
IPL stated that as a result, the Compensatory fuel charge computed as per the approved
methodology (Rs 1.10/kWh) is being multiplied with lower number of units (1755 MUs)
than actual units generated from alternate coal over which it would need to be applied, i.e.,
2541 MUs, so as to allow complete recovery of cost incurred in procuring alternate coal.
IPL submitted that the under recovery is to the extent of 52% of cost incurred in procuring
imported coal.
3.10 The Petitioner has proposed that to enable full recovery of cost of alternate coal, the
Commission may make one of the changes in the Steps mentioned on Page 36 of the Order
dated 15 July, 2014:
Make change in Step - 1 by using the actual ‘as received’ GCV instead of baseline
GCV for calculation of actual units delivered;
Case No. 147 of 2014 Page 10 of 22
OR
Revise the Step - 4 so that compensation calculated in Step - 3 is multiplied with Units
generated with Alternate coal, calculated in Step – 2;
OR
Apportion the incremental cost of alternate coal over actual units delivered.
3.11 IPL submitted that instead of measurement of power generation from different coal sources
which is impracticable technically and consequent computation of Tariff which would be
highly theoretical, the cost of blended coal should be considered and the consequent
Compensatory fuel charge should be based on the total generation. In the case of MSPGCL
power plants using blended coal, the practice followed is Tariff computation considering
cost of blended coal and total generation rather than computation of Tariff separately for
different sources of coal.
3.12 IPL submitted that sourcing of coal from alternative sources entails significantly increased
transportation and transaction costs which were not part of the bid assumptions, and is a
recurring expenditure which needs to be compensated in terms of the provisions relating to
Change in Law. The principle of granting a compensatory fuel charge in the present case
has to be in line with the principle laid down under the Change in Law provisions of the
PPA, and as such the Commission may allow recovery of 100% of such costs to the
Petitioner in entirety. Hence, the allowance of only 60% of the transportation and
transaction costs is an anomaly. Further, by allowing only 60% of the transportation and
transaction cost, the Commission has also gone against the principles laid down under
Section 61(d) of the Electricity Act, 2003, which are relevant for granting Compensatory
fuel charge.
3.13 IPL submitted the under-recovery on various costs of transportation and transaction costs
as follows:
Table 7: Indicates various components of Transportation and Transaction costs which are
proposed to be recovered to the extent of 40% by the Commission
Indicative Components of Transportation
and Transaction cost
(Rs/ton) Under recovery (40%)
Rs/ton
Ocean Freight
Case No. 147 of 2014 Page 11 of 22
- Sea Freight (8.5$ x Rs 60.85/$) 517 207
Port Handling Charges 500 200
Inland Transportation
- Railway freight from Dahej to plant –
distance ~740 KMs
969 388
- Duties, cess and taxes on railway
freight
244 98
Transaction Cost
- Insurance (1$ x Rs 60.85/$) 61 24
Total Transportation and transaction cost 2291 917
3.14 Based on the above break-up, against the landed cost of Rs. 5731 per ton, the Petitioner
would be allowed only Rs, 4814 considering the approach of allowing 60% of
transportation and transaction costs.
Quantity shortfall due to low GCV coal supplied by CIL
3.15 IPL submitted that the Commission accepted that the generator/ developer needs to be
compensated for any additional changes resulting from the changes in New Coal
Distribution Policy, 2007 (hereinafter referred to as “NCDP, 2007”). The following may be
noted in this respect:
As per NCDP 2007, power utilities including Independent Power Producers (IPPs)
have to be provided with 100% of coal required for operating the plant at Normative
Availability.
Letter of Assurances (“LOAs”) for certain quantity of particular grade (quality) are
issued to fulfill such requirement of the IPPs to operate the plant at Normative
Availability as per the NCDP, 2007.
The quantity for which LOAs are issued are always driven by the grade (quality) of
coal – higher quantity for low grade coal and vice versa;
In case the GCV supplied is less, then the quantity has to be adjusted accordingly so
that plant can operate at Normative Availability, which is not the case in the present
matter.
3.16 IPL submitted that with the available quality and quantity, it is barely in position to run the
Case No. 147 of 2014 Page 12 of 22
power plant at ~ 50% Plant load factor (“PLF”). Running the power plant at lower PLF as
compared to the Normative Availability as envisaged at the time of bidding makes the
Tariff offered at the time of bidding untenable and causes severe hardships to the Petitioner
due to inability to completely recover all costs. The Commission has recognised the
quantity shortfall in supplies from CIL and passed an Order to address the same. However,
the loss in generation on account of grade slippages in supplies from CIL has not been
addressed. This grade slippage has caused additional shortfall which needs to be addressed
by the Commission. This shortfall is further resulting into lower PLF as compared to the
PLF assumed at the time of bidding. IPL submitted that it is incurring huge losses on a
regular basis on account of such hardships. Therefore, in case this situation continues, it
will result the power plant of the Petitioner becoming a Non Performing Asset and
ultimately the operations of the power plant may have to be stopped. The same will
deprive the State of Maharashtra, the advantage of having access to cheaper power from a
power plant located within the State of Maharashtra.
4. The Commission held the hearing in this matter on 12 August, 2014. The Commission
directed MSEDCL to submit its arguments if any by 14 August, 2014.
5. MSEDCL made a submission on 14 August, 2014. The arguments made by MSEDCL in
the said submission are as follows:
5.1 Quoting its earlier submission in Case No. 118, 154 and 189 of 2013 and the methodology
adopted by the Commission, MSEDCL submitted that as per its interpretation, the award
of the transportation and transaction cost is understood to mean computation of the said
60% transportation and transaction cost upon appropriate deduction / adjustment of the
transportation and transaction cost to the extent of the composition of fuel — imported /
domestic as included in the original bid / PPA. MSEDCL averred that any other
interpretation to the above dispensation of the Commission would result in going beyond
what was envisaged in the CCEA decision (guidelines).
5.2 To clarify its interpretation, MSEDCL submitted an illustration as follows:-
“If 1 Rs/ Kwh works out to be total cost of transportation and transaction costs imported
coal, 0.60 Rs/ Kwh will be allowed as per order 154 of 2013. MSEDCL respectfully
submits that if 0.20 Rs/Kwh has already been considered while computation of Energy
charge in the bid/PPA then only 0.40 Rs/Kwh (0.60-0.20) should be allowed as a part of
transportation and transaction cost.”
Case No. 147 of 2014 Page 13 of 22
5.3 MSEDCL further submitted that the computation of shortfall quantity is not as per the
formula provided by the Commission in its Order in Case No. 118, 154 and 189 of 2013.
As per the said formula, the shortfall quantity will be minimum of:
Baseline Quantity - Actual Quantity received from CIL; and
Baseline Quantity - Quantity assured under amended NCDP, 2007.
5.4 MSEDCL added that the above methodology has not been adopted by the Petitioner.
5.5 MSEDCL submitted that the computation of SHR and Auxiliary Consumption provided by
the Petitioner is not in line with the formula approved by the Commission. For
computation of SHR and Auxiliary Consumption, lower of actual or CERC/ MERC norms
are required to be adopted as approved in Case No. 118, 154 and 189 of 2013. However,
Petitioner has computed the above said parameters by following CERC computation
methodology.
5.6 MSEDCL further submitted that the date of applicability of Compensatory fuel charge
should be with effect from the date of Judgement.
5.7 In respect of the figures / computation / contentions relating to the purported under
recovery as stated by the Petitioner, MSEDCL submitted that it refrains from dealing with
the same as presently the Order dated 15 July, 2014 passed by the Commission in Case No.
154 of 2013 is being implemented. MSEDCL submitted that it reserves its right to deal
with the same if the occasion so arises and does not accept the said figures / computation /
contentions.
6. On 16 August, 2014, Dr. Ashok Pendse, Thane Belapur Industries Association (hereinafter
referred to as “TBIA”), Authorised Consumer Representative, submitted the following:
6.1 The scope of the Order was to determine the Compensatory Fuel Charge as per formula
advised by the Consultant, KPMG. TBIA added that the Petitioner is enlarging the scope
of Order by introducing additional parameters, which will increase the Compensatory Fuel
Charge. The Petitioner has suggested change in the following parameters:
a) Change from Baseline GCV to GCV on as received basis
b) Consideration of 100% of transportation costs
c) Change of generation on account of imported coal mandated as per Order
Case No. 147 of 2014 Page 14 of 22
6.2 TBIA submitted that the scope of Compensatory Fuel Charge cannot be enlarged at this
stage. TBIA submitted that the Petitioner is within its legal rights to move another Petition.
TBIA submitted that the Compensatory Fuel Charge shall be calculated as per formula
only and no effect should be given on account of additional parameters pointed out by the
Petitioner.
7. On 14 August, 2014, Prayas requested the Commission to allow additional time to submit
its views on the Petition.
7.1 The said request has been received after the matter was reserved for Order. Further, the
present proceedings are limited to implementation of the Order dated 15 July, 2014.
Hence, the extension of time cannot be granted.
Commission’s Analysis
8. As per the ruling in Order in Case No. 154 of 2013, IPL approached the Commission
seeking a suitable adjustment to Tariff on account of shortage in domestic coal availability
and consequent amendment to NCDP, 2007 dated 26 July, 2013 which reduced the assured
quantum of domestic coal. IPL has approached the Commission for compensatory fuel
charge for the PPAs dated 22 April, 2010 and 5 June, 2010 with MSEDCL. IPL has signed
these PPAs for 1200 MW from the Amravati Power Project (hereinafter referred to as
“Amravati Project”) having an installed capacity of 1350 MW.
9. The proceedings were limited to implementation of the formula provided in the Order in
Case No. 154 of 2013 for calculation of Compensatory Fuel Charge. While deciding the
implementation aspects of the formula, the Commission has taken into account the issues
raised by the Petitioner supported by analysis and impacts. The Commission has taken into
consideration submissions and representations made by all the stakeholders including the
consumer representatives.
10. The Commission has analysed this matter under the following heads:
A. Petitioner’s eligibility for compensatory fuel charge as per framework outlined by the
Commission in Order dated 15 July, 2014
B. Issues raised by the Petitioner/Stakeholders with respect to the framework
C. Approved Methodology
Case No. 147 of 2014 Page 15 of 22
A. Petitioner’s eligibility for compensatory fuel charge as per framework outlined by the
Commission in Order dated 15 July, 2014
11. The following excerpts of the Order dated 15 July, 2014 are relevant to determine the
applicability of framework in the present case:
“32.1 The objective of the Commission, while arriving at the methodology to determine
compensatory fuel charge is to enforce the decision of CCEA dated 21 June, 2013 and
MoP advice dated 31 July, 2013….
…
36. The CCEA in it decision, dated 21st June 2013, has addressed two categories of
projects. The first category project are those which fall in the identified list of project
accounting for 78000 MW and for which CIL has to sign FSAs and which are to be
commissioned by 31st March 2015. The second category projects are those which are
likely to be commissioned by 31st March 2015 but do not have any coal linkage and have
obligations to supply power under long-term PPA with high bank exposure.
37. With respect to the second category of projects, the CCEA decision mentions “(v)
Mechanism will be explored to supply coal subject to its availability to the TPPs with
4660 MW capacity and other similar cases which are not having any coal linkage but are
likely to be commissioned by 31.03.2015, having long term PPAs and a high Bank
exposure ……….”
38. The current Petitions before the Commission cover multiple projects. Of these
projects mentioned in these petitions, the Commission notes that there are some units
which fall under the second category. All the units which fall under second category are
either commissioned or likely to be commissioned by 31st March 2015. The mechanism
reflected in the CCEA decision for second category projects with no coal linkage is yet to
be laid down. Till such time the mechanism is laid down, the Petitioners of such units
may approach the Commission, with a proposed mechanism to address the issue. The
Commission, after examining the merits of the cases, may decide to address the issue
appropriately.
……
44. For units that fall in the second category mentioned in para 36-38, the Petitioners
may approach the Commission suggesting the proposed mechanism with detailed
justification for the same.”
12. The Commission notes that IPL has signed the FSA on 22 December, 2012 for the
Case No. 147 of 2014 Page 16 of 22
Amravati power project, from which it has contracted power under the PPAs dated 22
April, 2010 and 5 June, 2010. As per the FSA of the Petitioner, the threshold level of
penalty for the balance period of the 12th five year plan is 65%, 65%, 70% and 75%.
However, as per the Amendment dated 22 August, 2013, the threshold levels of penalty
have been revised as 65%, 65%, 67% and 75% for the balance period of 12th
five year
plans.
13. The Commission noted that Amravati Project is included in the list of projects with a
capacity of 78000 MW, which was referred to in the CCEA decision dated 21 June, 2013.
Therefore, the framework for compensatory fuel charge as per the Order dated 15 July,
2014 is applicable is applicable to the PPAs dated 22 April, 2010 and 5 June, 2010.
B. Issues raised by the Petitioner/Stakeholders with respect to lacunae in the framework
Computation of Units from Domestic Coal
14. The Petitioner has claimed that the present formula does not take into account the fact that
the GCV of coal actually received at the power station is lower than the expected GCV as
per the LoA/FSA. As a result, actual units generated from domestic coal are lower than the
units arrived using the formula stipulated by the Commission which considers GCV as per
FSA/LoA.
15. The Petitioner has further submitted that the Compensatory Fuel Charge is applicable only
to incremental generation after considering the generation from domestic coal. To arrive at
the units generated from domestic coal, the formula stipulated by the Commission
considers GCV as per FSA whereas the actual generation is much lesser due to the lower
GCV of coal received, thereby leading to a higher estimate of units generated from
domestic coal. This computation results in reducing the amount of incremental units
generated. Therefore, the compensatory fuel charge is being applicable to a lower number
of incremental units leading to under-recovery for the Petitioner. The Commission notes
that as per the claim of the Petitioner, it may under recover cost of alternate coal to the
extent of Rs. 87 Crores.
16. In this regard, as the payment has to be made to CIL as per the invoice, the Commission
enquired whether the Petitioner has made the payment under protest bringing to the
attention of CIL the difference in the GCV of coal received and GCV committed as per
LoA/FSA. In reply, the Petitioner submitted that it had taken up the issue with CIL from
Case No. 147 of 2014 Page 17 of 22
time to time, and has submitted letters dated 17 June, 2014, 24 July, 2014 and 1 August,
2014 written to CIL informing the deficiency in quality of coal. The Petitioner further
submitted that they have not received any response from CIL to these letters.
17. The Commission notes the concerns of the Petitioner on the formula which considers
Baseline GCV leading to under-recovery of cost of alternate coal determined under the
methodology. However, the present proceeding is limited to implementation of the
methodology laid out in Order dated 15 July, 2014. Therefore the request for a change in
formula cannot be considered under the present proceedings. However, the Petitioner is at
liberty to approach Commission under separate proceedings.
Consideration of transportation charges upto 60%
18. With respect to transportation charges, the Commission notes the CCEA decision to
consider the pass-through of imported coal on a cost plus basis. The landed costs will
include all elements of costs including the transportation costs.
Table 8: Breakup of cost of imported coal
Particular Amount %
FoB price 3,123.43 54.5%
Port charges 500.00 8.7%
Ocean freight 517.23 9.0%
Domestic transportation 1213.00 21.2%
Taxes and duties on coal 305.00 5.3%
Others 71.85 1.3%
Landed price 5,730.51
19. Transportation forms a significant part of the landed cost of coal. Based on the breakup
provided by the Petitioner, domestic transportation forms 21%, ocean freight 9% and port
charges 8.7% of the total landed cost of coal. Therefore, the disallowance of transportation
costs would dissuade the Generator from procuring such alternate coal.
20. The Commission notes that the transportation costs for domestic transport have been
benchmarked to the Railway Freight notified by Indian Railways owned and operated by
Government of India. Further, the port handling charges for various activities such as
unloading, loading have been benchmarked to the Tariff for such activity of the nearest port
for which Tariff is approved by Tariff Authority of Major Ports. Further, widely accepted
Case No. 147 of 2014 Page 18 of 22
and stringent benchmarks have been provided for ocean freight and other charges.
Therefore, the Commission is of the view that transportation charges be allowed in full
subject to the benchmarks provided by the Commission.
Not considering compensation for quality
21. The Commission in its Order has adopted the framework for compensatory fuel charge
based on the decision of CCEA dated 21 June, 2013 and MoP advice dated 31 July, 2013 in
its Order dated 15 July, 2014. The MoP advice, as highlighted in the Order, only relates to
the aspect of shortfall in quantity. Therefore, the compensation for shortfall in quality or
any other hardships is outside the purview of the present proceedings, which relate to the
enforcement of decision of CCEA and advice of MoP.
Not considering SHR, Auxiliary Consumption and shortfall quantity as per approved
methodology
22. MSEDCL has argued that the Petitioner has not considered the shortfall quantity, SHR and
Auxiliary Consumption as per the framework approved by the Commission.
23. The Commission has not allowed any variation in the above parameters and the
methodology prescribed in Order dated 15 July, 2014 will continue to be applicable.
C. Approved Methodology
24. Based on the discussion in the above paragraphs, the approved methodology and
parameters are as follows:
Where:
Parameter Unit Description
Case No. 147 of 2014 Page 19 of 22
Parameter Unit Description
Baseline quantity MTPA Coal quantity as per LoA/ FSA/ relevant documents
PLinkage INR/MT Existing Landed coal price based on CIL’s notified prices and
logistics cost linked to index/benchmark
Baseline GCV kcal/kg As per LoA/ FSA/ relevant documents. In case of range of GCV
is given, the mid-point GCV of such range shall be considered
Shortfall quantity MTPA Minimum of:
(a) Baseline Quantity – Actual Quantity received from CIL;
and
(b) Baseline Quantity – Quantity assured under amended
NCDP, 2007 (CIL to supply minimum
65%,65%,67%,75% for the remaining four years of 12th
five year plan).
For clarity, if there is an actual shortfall of 1 MTPA but as per
the Amended NCDP, 2007, the shortfall from CIL was to be a
maximum of 0.8 MTPA, the shortfall quantity shall be
considered as 0.8 MTPA
For computation of provisional compensatory fuel charge, one
year trailing average of actual shortfall from Baseline quantity,
or 65% of LoA quantity, as per CCEA notifications for the first
year.
Revised GCV of
alternate source
kcal/kg GCV of imported/ alternate coal required for achieving optimal
blend
Revised price of
alternate source
INR/MT Landed price of imported/alternate coal (which may include e-
auction coal), derived from relevant indices/ benchmarks
Net SHR kcal/kWh For SHR and Auxiliary Consumption, lower of actual and norms
specified for new thermal generating stations in CERC (Terms
and Conditions of Tariff), 2014. Shall be computed as (Gross
SHR / (1 - Auxiliary Consumption ));
Units generated from
alternate coal**
MU ‘Quantity of Alternate Coal in MTPA’ * 10^3 x ‘Revised GCV
of imported/alternate source’ (kCal/kg)/Net SHR (kCal/kWh)
## For the purpose of true up, in case the Generator imports lesser than the ‘Quantity of
Alternate Coal in MTPA’, the values of Qshortfall and QAlternate will need to be revised to take
account of the actual coal imported. QAlternate will be taken as actual quantity of coal imported
and QShortfall will be arrived based on the following formulae.
Case No. 147 of 2014 Page 20 of 22
Further QAlternate will be limited to the Alternate/Imported Coal Requirement arrived at in the
formula for ‘Quantity of Alternate Coal in MTPA’.
** At the time of true-up, the compensatory fuel charge payment will be computed as follows:
Step 1: Units from domestic coal = (Baseline Quantity – Shortfall Quantity) x Baseline GCV /
Net SHR
Step 2: Units from imported coal = Quantity of Alternate Coal in MTPA x ‘Revised GCV of
imported/alternate source’/Net SHR
Step 3: The denominator for the formula for compensatory fuel charge per unit shall be
computed using the Units from imported coal in Step 2.
Step 4: Compensatory fuel charge payable shall be the compensatory fuel charge per unit
payable in Step 3 multiplied by minimum of:
(i) Actual units delivery at delivery point from the contracted capacity – Units from
domestic coal as computed in Step 1
(ii) Units from imported coal computed in Step 2
For clarity, if the ‘((Q Alternate x P Alternate)- (Q shortfall * x P linkage))’ is Rs. 200 Crore and units generated
from imported coal considering Net SHR is 1000 MU. The compensatory charge is Rs. 2/kWh. However, if the units
generated from imported coal is 900 MU instead of 1000 MU, the generator shall recover only 900 MU * Rs.2/kWh,
i.e. Rs.180 Crore (instead of Rs. 200 Crore).
Table 9: Approved Indices/ Benchmarks for imported coal
Factor Category Description
FoB price of imported
coal
Relevant indices as identified by CERC for composite imported coal
escalation rates
Platts (5000 Kcal/kg GAR) and Argus ( ICI3, 5000 Kcal/kg GAR) indices
for Indonesian coal with equal weightage
API4 index for South African coal
Global COAL New Castle Index for Australian coal
Forex rate Reference Exchange Rate as mentioned in the PPA, since the rate is provided
in PPA
Ocean Freight Lower of :
Ocean freight as per appropriate index sourced from reputed publishers
such as Clarkson, Lloyds etc.; and
Actual ocean freight
Transit losses as per CERC norms or actuals, whichever is lower
Port handling charges Lower of:
Actual port handling charges, and
Port handling charges of nearest port approved by Tariff Authority for
Major Ports.
Inland Transportation Commercial Freight rates as published by Indian railways
Actual cost for road transport subject to a maximum of 110% of the rail
Case No. 147 of 2014 Page 21 of 22
Factor Category Description
freight for the same distance, as per new Case I SBD guidelines
Table 10: Approved Indices/ Benchmarks for domestic coal
Factor Category Description
Ex mine price of coal Based on CIL notified price structure and project specifics
Government duties and
taxes
As per the relevant regulations
Inland Transportation Commercial Freight rates as published by Indian railways
Actual cost for road transport subject to a maximum of 110% of the rail
freight for the same distance, as per new Case I SBD guidelines
Transit losses to be considered as per actual or CERC norms, whichever is
lower
E-Auction Coal
25. The Petitioner may either procure imported coal or procure coal through e-auction coal to
meet its shortfall. For e-auction coal, the price discovered through the pricing mechanism
for e-auction will be allowed at actuals. All other costs will be allowed as per benchmarks
suggested for domestic coal, subject to the restriction on transportation and transactional
costs.
Commission’s Ruling
26. The Commission in Order dated 15 July, 2014 had approved the framework for
compensatory fuel charge and ruled as follows:
“The Commission approves the formulae as described in Paragraph 33. The
Commission has provided a framework for treatment of shortfall in quantity and will
deal with the merits and facts of each of the cases separately.”
27. The Commission has implemented the above framework based on the proceedings in
the present Petition filed by the Petitioner as per the above ruling. In the current
proceedings, the Commission has addressed the issues raised by the stakeholders on
merits as elaborated in Commission’s Analysis section of this Order. On the basis of
issues and facts placed before the Commission and various submissions by the parties,
the Commission considered the impact of transportation costs and rules that all
transportation and transaction costs will be considered in full while computing the
compensatory fuel charge, subject to the prescribed benchmarks.
Case No. 147 of 2014 Page 22 of 22
28. The Commission notes the concerns of the Petitioner on the formula which considers
Baseline GCV leading to under-recovery of cost of alternate coal determined under
the methodology. However, the present proceeding is limited to implementation of the
methodology laid out in Order dated 15 July, 2014. Therefore the request for a
change in formula cannot be considered under the present proceedings. However, the
Petitioner is at liberty to approach the Commission under separate proceedings.
29. The framework for compensatory fuel charge outlined in Order dated 15 July, 2014 is
applicable for PPAs dated 22 April, 2010 and 5 June, 2010 between IPL and
MSEDCL.
30. The indicative compensatory fuel charge at the current level of linkage
materialisation (70% of quantity) works out to ~Rs. 1.55 per kWh and is applicable
only to the incremental generation from imported coal. Generation from domestic
coal received under the FSA shall continue to be at the Tariff as per the PPA.
However, the amount pertaining to the indicative compensatory fuel charge shall be
reduced when the Petitioner progressively secures higher materialisation of domestic
linkage coal.
31. The compensatory fuel charge shall be applicable from the date which is later of (a)
date of MoP Advice (31 July, 2013); (b) Scheduled Date of Delivery; and (c) Actual
Date of Delivery.
32. A periodic review of compensatory fuel charge is required on account of changes in
the business environment related to coal demand-supply situation, prices of coal in
the international market, etc. Further, the amendment to NCDP, 2007 and advice of
MoP relates to the period of the 12th
plan only. Accordingly, the compensatory fuel
charge will be reviewed by the Commission at the end of FY 2016-17. Further,
Procurer may approach the Commission intermittently for review of any aspect of the
compensatory fuel charge with changing scenarios.
With the above, Indiabulls Power Limited’s Petition in Case No. 147 of 2014 is disposed of.
sd/- sd/- sd/-
(Azeez M. Khan) (Vijay L. Sonavane) (Chandra Iyengar)
Member Member Chairperson