Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
Best Practices & innovations in GIS delta update, MDAS and loss
reduction
Maharashtra State Electricity Distribution Company Ltd
Wednesday, September 10, 2014
Communication Network
MPLS
Cloud
BusinessIntelligenceCentralized
Customer Care
Kiosk
GIS Delta Update/MDS
InternetWeb Portal
(WSS)
IntranetPortal
Disconnection
Energy Audit/NDM GIS
Network Analysis
Identity Access Management
New Connection
Integration Middleware
RAPDRP MODULES
CRM
MDAS
VPN
IT Infrastructure at 1579 offices
Juno device to capture coordinates
EMS/NMS
Challenge Strategy /Best Practice
Awareness 1. Project kick-off meetings arranged upto town level2. Initiatives taken by management for awareness drives 3. Continuous interaction with all stakeholders4. Timely Completion of trainings
Change Adoption 1. Project Charter and its adherence 2. Mandatory Usage of R-APDRP Solution3. Rigorous track on usage4. Disciplinary actions against non compliances
Data Update Continuous Delta Updates/Regular updates in all application databefore and after full roll out
Accountability & Coordination
Accountability of Field Officers/Town In-charge for coordination with agencies for meeting Go Live requirements
Performance of ITIA 1. Day to day Monitoring and weekly reviews2. Timely readiness for Roll Out requirements: Meters, Site readiness,
Approvals, IT Infra etc.
Go-Live Process: Challenges and Strategies
GIS Best PracticesThe GIS (Geographical Information System) module forms an integral part of R-APDRP Software ecosystem.
• System Development:
• A core team of IT and Electrical Engineers both from HO & Field was formed.
• Detailed verification of the AS-IS and TO-BE documents by the core teambefore approval informed to ITIA.
• Like other RAPDRP applications, the Web based GIS application can only beaccessed through Single Sign On (SSO) feature. The town user can view/editGIS data related to his town, only.
• Additional dummy fields were reserved in GIS Data model for futurerequirements (the Data Model has fields mentioned in the RFP and MSEDCLspecific requirements).
• GIS system is seamlessly integrated with other applications.• In the New Connection module, technical feasibility & DTC load profile is calculated by GIS
system
• The Energy Audit Module considers billed consumption of only those consumers who are in GIS.
• Disconnection & Dismantling module integrated with GIS for generating shortest route map ofdefaulters.
GIS Best PracticesPre-Survey:
• Workshop of agencies conducted before the survey.• Were told to keep GIS survey limited to the information significant to MSEDCL.
• Proper Id Cards issued to the agency persons conducting the survey.
• Process defined for Consumer Indexing & Asset mapping and made mandatory
Survey/Managed Data Services:
Consumer Indexing & Asset Mapping is done by ITIA/MDS agency as per theprocess approved by MSEDCL.
For a faster GIS update, New Connection module is designed to add NewConsumers from R-APDRP towns to the GIS database directly withoutopening the GIS web application window. Managed Data Services Agency then undertakes Survey of these New Consumers and bring
details such as Building ID, Pole ID, Coordinates, etc
MSEDCL town in charge verifies the location specific details of New connections such as Pole-
Id, DTC-code etc and with the help of the MDS agency directly update into GIS system.
Post Survey:
– Survery done by ITIA/MDS agency verified & approved by respective town incharge
• Surveyed GIS data is regularly verified with the billing data & in case of discrepancythe same is communicated to the ITIA/MDS agency.
– Third party quality assurance of digitized GIS data was done (M/s Indycos). Correctionssuggested were verified by town incharge & corrected by MDS agency.
System Operations:
– Specific Responsibilities were entrusted to Town Officers vide the GIS responsibilitymatrix.
• The town in charge was made responsible for town level GIS activitiesincluding updation of day to day changes of network and consumers in GIS.
– MSEDCL has adopted policy to release payments to vendors only after Town GISdata viz. Sub Station, Feeder or Transformer data is visible in GIS application.
– Network Augmentation Schemes are prepared using the GIS based NetworkAnalysis Module.
GIS Best Practices
GIS MANAGED DATA SERVICES
DELTA- GIS Data gap between start of GIS survey & digitization process of the Town by ITIA and
the Go-live of Data Center & R-APDRP modules (when GIS updates can be done directly
through R-APDRP systems)
Why? :
• Need of dedicated resources to cater to delta update process requirements.• Insufficient Field Staff and lack of skill of GIS data collection and Update.• Handholding training to MSEDCL staff by skilled resources required.• Importance of Timely update of GIS data.
Solution: Outsourcing Managed Data Services (MDS) by hiring dedicated trainedmanpower for Town activities and GIS experts for DC activities onService Level Agreement (SLA) basis.
Post Go-live, MSEDCL has appointed an independent third party Managed Data Services Agency (M/s ADCC Infocad Pvt Ltd) for helping MSEDCL staff to carry out GIS delta update and regular update work and training/handholding.
ITIA
MDS
Substations
86.55%
13.45%
Substation Feeders DTC HT Consumers Cross OverLT
ConsumersTOTAL
ITIA MDS ITIA MDS ITIA MDS ITIA MDS ITIA MDS ITIA MDS ITIA MDS
341 53 1577 235 29855 4191 3295 706 251 98 3180082 758848 3215401 764131
GIS Update Achievements
ITIA
MDS
Feeders
87.03%
12.97%
ITIA
MDS
DTC
87.69%
12.31 %
ITIA
MDS
HT Consumers
82.35%
17.65%
ITIA MDS
80.73 %
19.27 %
LT CONSUMERS
ITIA
MDS
Crossovers
71.92 %
28.08 %
• Delta update completed at 120 towns.
• 117 Towns are declared Go-live
Key Challenges faced/being faced for MDS implementation
• Rapid changes in network due to new consumer
additions and creation of new electrical infrastructure
under RAPDRP Part ‘B’.
• Low awareness and availability of MSEDCL users for
MDS activities resulted into little delayed results.
• Improper connectivity was a demotivating factor.
• Coordination between ITIA and MDS agency.
Impact of Managed Data Services
• MSEDCL field staff learnt the process of GIS & GIS
update.
• CCCC services improved because of proper indexing
• Accuracy in Network Analysis
• R-APDRP application issues (GIS, EA, MBC, etc) are
properly identified and immediately resolved;
Best Practices - MDASAutomated Meter Reading(AMR) System is implemented for High Tension Consumer, Feeder Meters
and Distribution Transformer
MDAS Software
• The MDAS software (API Caller module) is developed & maintained in-house by MSEDCL.
• Therefore enhancements to the software (based on user feedback) are done to the software almost
immediately.
• To utilize the software and resources fully and to get the maximum benefits MSEDCL has extended use of
this application to non-RAPDRP areas also.
Standardization
• Process of healthy metering infrastructure (meter, CT, cable, meter box) is defined.
• All the meters are set in MD Auto Reset Mode.
• RS232 port pin configuration was standardized.
Reachability
• Services from Multiple service providers (viz. Reliance Communications, Vodafone, Airtel, Tata
Teleservices) are being used. Service providers having connectivity in a particular area are preferred for
increasing meter-modem read count.
Approach
• For successful implementation of AMR : AMR Responsibility Charter is prepared
• Progress of MDAS is reviewed at various levels.
• Approx. 35,000 Meters are read successfully every month
• 10705 HT Consumers Meters read successfully in month of AUG-14 and bills are issued
Best Practices - MDAS
0
2000
4000
6000
8000
10000
12000
HT CONSUMERS BILLED AS PER MDAS READINGS
HT
CO
NSU
MER
S
Loss reduction: Best Practices & Innovatory efforts
• Every year approx. 5% meters get faulty (ie. Approx. 11 lakh meters) & are replaced
• Meter-infrastructure/reading related issues:
– Under-billing due to old electromechanical & faulty meters form a major part of the distribution losses.
– Erroneous meter reading due to human intervention (manual meter reading)
• Replacement of these meters as one of the measure to reduce losses has proved to
be the most effective one.
• MSEDCL realized that to reduce losses and increase demand, existing metering
infrastructure needs to be strengthened.
• Therefore, MSEDCL has adopted new metering technologies such as Meters with Infra-
Red (IR) ports, Meters with Radio Frequency (IR) Ports & AMR enabled meters.
IR , RF Meters and Development of Common Protocol :
• IR port meters for Low Tension consumers in scattered (mostly rural) areas and to
install RF port meters in densely populated (mostly urban) areas
• Protocols were developed in-house by MSEDCL and made mandatory for all the
manufacturers bidding for the tender.
• Due to common protocol it is possible to catch readings of different makes of IR or RF
meters using the same hand held device.
Loss reduction: Best Practices & Innovatory efforts
• Accordingly till date, 37.93 lakh IR and 7.21 lakh RF meters have been installed in MSEDCL.
• In the year 2013-2014, MSEDCL has observed 22% rise in the sale and demand compared toprevious year & which can be attributed to the renovation of metering infrastructure using newmetering technologies.
• Necessary actions are taken on regular basis on the following exceptional reports generated bythe system,
– Consumers billed on Average (Locked/Faulty),
– Consumers billed as per RNA/RNT
– Consumers billed in the range 0 to 30 units
• The meter reading program cycles are scheduled as per the schedule of feeder meter readings tominimize approximation in Energy Audit.
• All possible care is taken to keep the feeder load, transformer load & transformer phase balanced.
• New connections released are fed & monitored through the New connection system and billingof these consumers is timely started , thereby avoiding delay in issue of first bill to the consumers.This eventually lead to minimising unbilled new connections, thereby reducing distribution losses.