33
LOPA An efficient Safety Barrier Management tool Presented by: Fabienne Salimi @ BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND NATURE 2010 Mary Kay O’Connor Process Safety Center International Symposium October 26-28, 2010

BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

LOPAAn efficient Safety Barrier Management tool

Presented by: Fabienne Salimi @

BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND NATURE

2010 Mary Kay O’Connor Process Safety Center International Symposium

October 26-28, 2010

Page 2: BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

Layer of protection according to

IEC-61511COMMUNITY EMERGENCY RESPONSE

Emergency broadcasting

PLANT EMERGENCY RESPONSE

Evacuation procedures

MITIGATION

Mechanical mitigation system

Safety Instrumented control system

Safety instrumented mitigation systems

Operator supervision

PREVENTION

Mechanical protection system

Process alarms with operator corrective action

Safety Instrumented control system

Safety instrumented prevention systems

CONTROL and MONITORING

Basic Process Control Systems

Monitoring system (process alarms)

Operator supervision

PROCESS

Page 3: BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

What are we protecting?COMMUNITY EMERGENCY RESPONSE

Emergency broadcasting

PLANT EMERGENCY RESPONSE

Emergency Power

Emergency Communication

Emergency Lighting

MITIGATION (Fire & Explosion) PREVENTION OF ESCALTION

Fire &Gas Detection System

Emergency Shutdown (ESD-1)

Blowdown & Drainage System

Active & Passive Fire Protection

MITIGATION (Process Safeguarding)

Mechanical mitigation system (eg pressure relief, dike,…)

PREVENTION

Process Shutdown (ESD-3 & ESD-2)

Process alarms with operator corrective action

CONTROL and MONITORING

Basic Process Control Systems

Monitoring system (process alarms)

Operator supervision

PROCESS

(EUC)

Fire Zone

AUC

EER Area

AUC

EUC: Equipment Under Control

AUC: Area Under Control

Page 4: BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

No Major Accident!

An occurrence resulting from uncontrolled developments in the course of

the operation of any onshore establishment or pipeline or offshore

installation, and leading to serious danger to human health or the

environment, immediate or delayed, inside or outside the onshore

establishment or offshore installation, and involving one or more dangerous

substances.

This includes in particular a major:

Emission

Fire

Explosion.

Page 5: BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

Major Accident Hazard Tree

From API 14J

Vessel

Overflow

Equipment

Failure

Opening a

closed system

Vent/flare system

discharge

• Inflow exceeds

outflow

• Overpressure*

• Leak: Corrosion, Erosion, Maintenance

• Excessive temperature*

• Hit by object

• Material; quality

• Sudden failure of mechanical seal*

• Valve

operation

• Inadequate scrubber size

• Scrubber inflow exceeds outflow*

Oil Spill Escaping gas

Air

Pollution

Inadequate drain

system

Water pollution

Air

Pollution

Asphyxiation/

poisoningInjury

Oxygen

xxxx

Fuel

Ignition

Source

• Lightning

• Static electricity

• Electrical short

• Electrical sparks

• Human induced

• Flashback

• Hot surfaces

• Exhaust sparks

• Open flame

• Fire tube

Electric

shock

• Lightning

• Electrical short

• Inadequate ground

• Exposed live connections

Physical

impact

• Fall

• Tripping

• Slip on slick surfaces

• Hit by object

• Overpressure

• Cranes

• Boats

• helicopter

Large

fire

• Insufficient or inoperable fire fighting equipment

• Wrong location of F/F equipment

• Inability of shut off fuel

• Lack of adequate warning

Asphyxiation/

poisoning

• Gas leak in confined space

• Leak of toxic chemicals

• Discharge of fire extinguishing agent in confined space

• Smoke from fire

Burns

shock

• Hot surfaces

• Flare radiation

• Burning fluids

Inability to

escape

• Blocked escape route

• Insufficient lighting

• Inappropriate survival capsule design or location

• Lack of fire barriers

• Lack of adequate warning

• Lack of communications

• Lack of visibility

• Inadequate training

Injury

* Sources which can be anticipated by sensing charges in process conditions

Fire Explosion

Page 6: BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

Hierarchy of Safety Critical Barriers

Gas

Release

Page 7: BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

Fishbone Analysis (Six Sigma)

Page 8: BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

Life Cycle HSE Management

Project Management

Engineering Procurement Manufacturing Construction Commissioning

Plant Management

Operation Maintenance

Page 9: BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

Bow-Tie Diagram

Page 10: BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

Example

HSE Management for PSV

Page 11: BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

Hierarchy of Safety Critical Barriers

Gas

Release

Page 12: BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

Overpressure Safety Barriers

Structural Integrity Process Control

Strategy &

Tuning

Design Quality Assurance

Operating

ProceduresSafe Operating

Pressure

Gas

Release

Incident Prevention

-

Post Incident

Control and Mitigation

Overpressure

HAZOPCode

Compliance

High Pressure

Trip

Pressure

Relief Valve

Multiple Failures

Page 13: BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

PSV Safety Barriers

Manufacturing

EPC Contractor

Quality Assurance

Construction

Overpressure <

Failure pressure of vessel

Vessel

Failure

Incident Prevention Post Incident

Control and

Mitigation

Pressure Relief

Failure

ProcurementDesign

Maintenance

Commissioning

Client Quality

Assurance

Page 14: BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

Design Safety Barriers

Competent

Checker

Design Quality AssuranceProper Design

Wrong

specification

Incident Prevention

-

Post Incident

Control and

Mitigation

Design Failure

Competent

originator

Technical Work

Practice

Independent

Competent auditor

Disciplinary Check IDC

Independent

EPC Audit

Suitable

SoftwareCompetent

Approval

Authority

?

Supporting studies

(input data)

Option1: Distribution Matrix

Option2: Brainstorming

Project

Page 15: BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

There are no Perfect

Safety Barriers

Probability of failure on demand can be reduced or eliminated by different

techniques including:

• Intrinsically safe,

• Fail safe,

• Redundancy,

• Shorter inspection, test and planned maintenance routines and more,

• advanced technology.

Page 16: BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

LOPA should be repeated for ALL undesirable

deviation within equipment

1 2 3 4

Overpressure (Suction)

Excluding fire3 Yes 4

For parallel operation suction

scrubber is inherently safe:

- design pressure = 210 barg

- Surge recycle line pressure = 144

barg

Overpressure (Discharge)

Excluding fire4 Yes 4

Low pressure 3 Yes 1

Excess Temperature 3 Yes 1

Low Temperature 3 Yes 1

Liquid overflow in suction

scrubber2 Yes 1

No considerable liquid is expected in

this vessel.

Reverse flow 3 Yes 3

Double check valve with two different

type are considered as SIL2

secondary protection.

Leak 3 Yes 31PZA-2p20-LL can be an indication

of gas leak to atmpsphere.

External fire 2 Yes 4

The suction scrubbers and

pipeworks outside compressor house

are protected by the PFP.

L0- Inherently Safe, L1- BPCS, L2- Alarm, operator, L3- SIS, L4- Mechanical/ Relief devices

L5- Physical protection: L5.1 - ESD, L5.2 - EDP, L5.3 - Passive fire protection, L5.4 - Active fire protection

5Total

Achieved

SIL

Remarks/ Recommmendations /

ActionsUndeirable event

1 2 3

No. of protection Layers

0

Protection

Adequate?4

SUMMARY OF THE PROTECTION MEASURES

Page 17: BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

API 14CA prescriptive approach to LOPA

Page 18: BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

Process Safeguarding

• Overpressure

• Leak

• Liquid Overflow

• Gas Blowby

• Under-pressure

• Excess Temperature

• Direct Ignition Source

• Excess combustion vapour

Following scenarios are the most common undesirable events which can

lead to an Emission and/or Fire & Explosion Major Accident in a plant

which processes the flammable and/or toxic materials:

According API 14C at least two levels of protection independent and

diverse shall be provided wherever these hazards are credible.

Page 19: BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

Example: Overpressure Protection

Page 20: BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

Example of Safety Analysis Table for

Compressor

Page 21: BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

Example Safety Analysis Checklist

Page 22: BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

Location of safety systems according to

API 14C

Page 23: BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

Survivability

Page 24: BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

Can our Safety Barrier fulfill its function under

accident Conditions?

Jet fire Thermal radiation UCVCE Blast Overpressure

Page 25: BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

• Goals

• Boundaries

• Functionalities

• Reliability / Availability

• Survivability

• Interaction / Dependences.

Verification schemes define the risk based inspection to ensure that the

performance standards are maintained during operation (Fig-7).

Performance standards are prepared to summarise the following

requirements for the safety critical system, subsystems and elements with

a traceable and auditable manner:

Performance Standard

Page 26: BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

Performance Standard Tables

Page 27: BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

HAZOP

Dynamic Simulation for an objective

Consequence analysis

Page 28: BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

OTS High Fidelity Dynamic Simulation

(Demo: http://www.adepp.com/Site_Demo/ADEPP_HSE_Toolkit.html)

Page 29: BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

With permission and courtesy of Ventimar LLC and SimApp

Full report is available @ http://www.simapp.com/simulation-tutorials

Laplace Transform & Dynamic Simulation

Page 30: BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

ADEPP MonitorA tool for Life cycle LOPA

Page 31: BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

• Dynamic & Knowledge based HAZOPs

• BPCS Control strategy

• Alarm Management Analysis

• API 14C

• SIL Assessment

• Fire & Explosion study

• Performance Standards

• Verification Schemes

ADEPP LOPA monitor combines the followings to cover the life cycle

issues of the required layers of protection:

A tool for Life cycle LOPA

Both Code based and Risk based are used in ADEPP LOPA monitor.

Page 32: BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

ADEPP LOPA monitor

(Demo: http://www.adepp.com/Site_Demo/ADEPP_HSE_Toolkit.html)

Page 33: BEYOND REGULATORY COMPLIANCE, MAKING SAFETY SECOND …psc.tamu.edu/files/symposia/2010/presentations/track3/Salimi.pdf · • API 14C • SIL Assessment • Fire & Explosion study

Thank you for

your kind attention!

For more information contact: [email protected]

©2010, Copyright. No part of this Course may be copied or broadcast unless authorised.

ADEPP is protected by APP (http://app.legalis.net). Copying is illegal and subject to prosecution.