Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
Blackout Theory
EE8725Apoorva Mysore Nataraja
1
Northeast Blackout of 2003
2
Major power outages in history
Blackouts People affected (millions)
Location Date
July 2012 India blackout 620 India 30-31 July 2012
January 2001 India blackout 230 India 02-Jan-01
2015 Pakistan blackout 140 Pakistan 26-Jan-15
2005 Java–Bali blackout 100 Indonesia 18-Aug-05
1999 Southern Brazil blackout 97 Brazil 11-Mar-99
2009 Brazil and Paraguay blackout 87 Brazil, Paraguay 10-11 Nov 2009
2015 Turkey blackout 70 Turkey 31-Mar-15
Northeast blackout of 2003 55 United States, Canada 14-15 Aug 2003
3
Series of events1 - Aug 14, 2003● Hours before the Aug. 14 blackout, FirstEnergy were importing thousands of megawatts from southern Ohio, and
exporting VAR's outside their system the whole day. Voltage across their system was below normal, a sign of
insufficient reactive power.
● By 1:15 p.m., voltage had dropped 3 to 4 percent, close to the 5 percent threshold considered a serious problem.
● FirstEnergy then adjusted nine power plants to produce more reactive power, but trouble at one plant forced the
generator off.
● At 2:02 p.m., a brush fire caused a major line in southwest Ohio to fail, redirecting power loads onto other lines, and
once again increasing the need for reactive power.
● Then, starting at 3:05 p.m., a series of lines linking the Cleveland area to its power supplies to the south failed.
● At 4:09 p.m., the last links between northern and southern Ohio shut down. The system began to falter, and within two
minutes, the blackout had struck.
41 http://www.nytimes.com/2003/09/23/us/elusive-force-may-lie-at-root-of-blackout.html?pagewanted=all
How blackouts happen?● Lack of reactive support close to the loads to sustain adequate voltage levels● Voltage collapse due to overloading● Multiple contingencies, internal breakdown● Weather conditions● Ageing equipments● Maintenance practises
5
Reactive effects of transmission loss:
ΣIl2xl - Σ(V2
from end of line lBcap l + V2to end of line lBcap l) - ΣVi
2Bfixed cap at
bus i
6
Reactive loss on transmission line
Reactive power injected into the system from line charging capacitance
Reactive injections from fixed capacitors
● Summing the above three terms gives the reactive power loss.● When a line is lost, it leads to increased current flow in the other lines and
causes bus voltages to drop, thereby increasing reactive power loss.● Decreased var injections increase var demand on generators, and if they hit their
var limits, generator terminal voltage drops.
Voltage collapse
7
● As more reactive power is drawn from the system, voltage drops.
● At the critical point, the system will have to solution.
● Voltage collapse occurs when the system is trying to support much more load than the voltage can support.
Case 1: All lines in service
8
Voltage is 100% rated voltage(300 MVARs required by lines)
East generator is below 1200 MVAR limit
● 3000 MW transfer● 500 MW per line
Case 2: One line out
9
Voltage is 100% rated voltage(362 MVARs required by lines)
East generator is below 1200 MVAR limit
● 3000 MW transfer● 600 MW per line
Case 3: Two lines out
10
Voltage is 100% rated voltage(453 MVARs required by lines)
East generator is at 1200 MVAR limit
● 3000 MW transfer● 750 MW per line
Case 4: Three lines out
11
Voltage is 99% rated voltage(611 MVARs required by lines)
East generator is at 1200 MVAR limit
● 3000 MW transfer● 1000 MW per line
Case 5: Four lines out
12
Voltage has dropped to 97% of rated voltage(957 MVARs required by lines)
East generator is at 1200 MVAR limit
● 3000 MW transfer● 1500 MW per line
Case 6: System collapse
13
Voltage has dropped to 77% of rated voltage
● This simulation could not solve the case of 3,000 MW transfer with five lines out. Numbers shown are from the model’s last attempt to solve. The West generator’s unlimited supply of VARs is still not sufficient to maintain the voltage at the East bus.
Case 7: Two lines out - Full voltage control
14
(452 MVARs required by lines)
Case 8: Three lines out - Full voltage control
15
(606 MVARs required by lines)
Case 9: Four lines out - Full voltage control
16
(922 MVARs required by lines)
Case 10: Five lines out - Full voltage control
17
(2000 MVARs required by lines)
Case 11: How much could the line have handled?
18
4900 MW
NERC (n-1) ruleNo single generation outage will result in so large a frequency drop that other generators will be forced off line.
No single transmission or generation outage will result in other components experiencing such a large flow or voltage change that new limit violations occur.
19
How to prevent blackouts?1. System monitoring and Audits
- Run state estimation- Test power flows, voltage magnitudes against limit values- Maintain critical alarm monitoring systems
2. Contingency analysis (What if analysis)- Detect abnormal system conditions- Detect components/parameters that will be out of limit
3. Security constrained OPF4. Public policy, Transmission and future investments
- Long term investments, replacement of ageing infrastructure- Transmission grid upgradation
20
References● Peter W. Sauer, ‘Reactıve Power and Voltage Control’, NSF Workshop on
applied mathematics for deregulated power systems, Nov 3-4, 2003, Alexandria, VA.
● Damir Novosel, Energy pulse article http://www.energypulse.net/centers/article/article_print.cfm?a_id=495
● Bruce F. Wollenberg, ‘Power System Securıty - Lecture 11A’ https://www.youtube.com/watch?v=hOGlLQFJ3m0
21
Thank you
22