22
Blackout Theory EE8725 Apoorva Mysore Nataraja 1

Blackout Theory - Electrical and Computer Engineering Theory.pdf · July 2012 India blackout 620 India 30-31 July 2012 January 2001 India blackout 230 India 02-Jan-01 2015 Pakistan

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Blackout Theory - Electrical and Computer Engineering Theory.pdf · July 2012 India blackout 620 India 30-31 July 2012 January 2001 India blackout 230 India 02-Jan-01 2015 Pakistan

Blackout Theory

EE8725Apoorva Mysore Nataraja

1

Page 2: Blackout Theory - Electrical and Computer Engineering Theory.pdf · July 2012 India blackout 620 India 30-31 July 2012 January 2001 India blackout 230 India 02-Jan-01 2015 Pakistan

Northeast Blackout of 2003

2

Page 3: Blackout Theory - Electrical and Computer Engineering Theory.pdf · July 2012 India blackout 620 India 30-31 July 2012 January 2001 India blackout 230 India 02-Jan-01 2015 Pakistan

Major power outages in history

Blackouts People affected (millions)

Location Date

July 2012 India blackout 620 India 30-31 July 2012

January 2001 India blackout 230 India 02-Jan-01

2015 Pakistan blackout 140 Pakistan 26-Jan-15

2005 Java–Bali blackout 100 Indonesia 18-Aug-05

1999 Southern Brazil blackout 97 Brazil 11-Mar-99

2009 Brazil and Paraguay blackout 87 Brazil, Paraguay 10-11 Nov 2009

2015 Turkey blackout 70 Turkey 31-Mar-15

Northeast blackout of 2003 55 United States, Canada 14-15 Aug 2003

3

Page 4: Blackout Theory - Electrical and Computer Engineering Theory.pdf · July 2012 India blackout 620 India 30-31 July 2012 January 2001 India blackout 230 India 02-Jan-01 2015 Pakistan

Series of events1 - Aug 14, 2003● Hours before the Aug. 14 blackout, FirstEnergy were importing thousands of megawatts from southern Ohio, and

exporting VAR's outside their system the whole day. Voltage across their system was below normal, a sign of

insufficient reactive power.

● By 1:15 p.m., voltage had dropped 3 to 4 percent, close to the 5 percent threshold considered a serious problem.

● FirstEnergy then adjusted nine power plants to produce more reactive power, but trouble at one plant forced the

generator off.

● At 2:02 p.m., a brush fire caused a major line in southwest Ohio to fail, redirecting power loads onto other lines, and

once again increasing the need for reactive power.

● Then, starting at 3:05 p.m., a series of lines linking the Cleveland area to its power supplies to the south failed.

● At 4:09 p.m., the last links between northern and southern Ohio shut down. The system began to falter, and within two

minutes, the blackout had struck.

41 http://www.nytimes.com/2003/09/23/us/elusive-force-may-lie-at-root-of-blackout.html?pagewanted=all

Page 5: Blackout Theory - Electrical and Computer Engineering Theory.pdf · July 2012 India blackout 620 India 30-31 July 2012 January 2001 India blackout 230 India 02-Jan-01 2015 Pakistan

How blackouts happen?● Lack of reactive support close to the loads to sustain adequate voltage levels● Voltage collapse due to overloading● Multiple contingencies, internal breakdown● Weather conditions● Ageing equipments● Maintenance practises

5

Page 6: Blackout Theory - Electrical and Computer Engineering Theory.pdf · July 2012 India blackout 620 India 30-31 July 2012 January 2001 India blackout 230 India 02-Jan-01 2015 Pakistan

Reactive effects of transmission loss:

ΣIl2xl - Σ(V2

from end of line lBcap l + V2to end of line lBcap l) - ΣVi

2Bfixed cap at

bus i

6

Reactive loss on transmission line

Reactive power injected into the system from line charging capacitance

Reactive injections from fixed capacitors

● Summing the above three terms gives the reactive power loss.● When a line is lost, it leads to increased current flow in the other lines and

causes bus voltages to drop, thereby increasing reactive power loss.● Decreased var injections increase var demand on generators, and if they hit their

var limits, generator terminal voltage drops.

Page 7: Blackout Theory - Electrical and Computer Engineering Theory.pdf · July 2012 India blackout 620 India 30-31 July 2012 January 2001 India blackout 230 India 02-Jan-01 2015 Pakistan

Voltage collapse

7

● As more reactive power is drawn from the system, voltage drops.

● At the critical point, the system will have to solution.

● Voltage collapse occurs when the system is trying to support much more load than the voltage can support.

Page 8: Blackout Theory - Electrical and Computer Engineering Theory.pdf · July 2012 India blackout 620 India 30-31 July 2012 January 2001 India blackout 230 India 02-Jan-01 2015 Pakistan

Case 1: All lines in service

8

Voltage is 100% rated voltage(300 MVARs required by lines)

East generator is below 1200 MVAR limit

● 3000 MW transfer● 500 MW per line

Page 9: Blackout Theory - Electrical and Computer Engineering Theory.pdf · July 2012 India blackout 620 India 30-31 July 2012 January 2001 India blackout 230 India 02-Jan-01 2015 Pakistan

Case 2: One line out

9

Voltage is 100% rated voltage(362 MVARs required by lines)

East generator is below 1200 MVAR limit

● 3000 MW transfer● 600 MW per line

Page 10: Blackout Theory - Electrical and Computer Engineering Theory.pdf · July 2012 India blackout 620 India 30-31 July 2012 January 2001 India blackout 230 India 02-Jan-01 2015 Pakistan

Case 3: Two lines out

10

Voltage is 100% rated voltage(453 MVARs required by lines)

East generator is at 1200 MVAR limit

● 3000 MW transfer● 750 MW per line

Page 11: Blackout Theory - Electrical and Computer Engineering Theory.pdf · July 2012 India blackout 620 India 30-31 July 2012 January 2001 India blackout 230 India 02-Jan-01 2015 Pakistan

Case 4: Three lines out

11

Voltage is 99% rated voltage(611 MVARs required by lines)

East generator is at 1200 MVAR limit

● 3000 MW transfer● 1000 MW per line

Page 12: Blackout Theory - Electrical and Computer Engineering Theory.pdf · July 2012 India blackout 620 India 30-31 July 2012 January 2001 India blackout 230 India 02-Jan-01 2015 Pakistan

Case 5: Four lines out

12

Voltage has dropped to 97% of rated voltage(957 MVARs required by lines)

East generator is at 1200 MVAR limit

● 3000 MW transfer● 1500 MW per line

Page 13: Blackout Theory - Electrical and Computer Engineering Theory.pdf · July 2012 India blackout 620 India 30-31 July 2012 January 2001 India blackout 230 India 02-Jan-01 2015 Pakistan

Case 6: System collapse

13

Voltage has dropped to 77% of rated voltage

● This simulation could not solve the case of 3,000 MW transfer with five lines out. Numbers shown are from the model’s last attempt to solve. The West generator’s unlimited supply of VARs is still not sufficient to maintain the voltage at the East bus.

Page 14: Blackout Theory - Electrical and Computer Engineering Theory.pdf · July 2012 India blackout 620 India 30-31 July 2012 January 2001 India blackout 230 India 02-Jan-01 2015 Pakistan

Case 7: Two lines out - Full voltage control

14

(452 MVARs required by lines)

Page 15: Blackout Theory - Electrical and Computer Engineering Theory.pdf · July 2012 India blackout 620 India 30-31 July 2012 January 2001 India blackout 230 India 02-Jan-01 2015 Pakistan

Case 8: Three lines out - Full voltage control

15

(606 MVARs required by lines)

Page 16: Blackout Theory - Electrical and Computer Engineering Theory.pdf · July 2012 India blackout 620 India 30-31 July 2012 January 2001 India blackout 230 India 02-Jan-01 2015 Pakistan

Case 9: Four lines out - Full voltage control

16

(922 MVARs required by lines)

Page 17: Blackout Theory - Electrical and Computer Engineering Theory.pdf · July 2012 India blackout 620 India 30-31 July 2012 January 2001 India blackout 230 India 02-Jan-01 2015 Pakistan

Case 10: Five lines out - Full voltage control

17

(2000 MVARs required by lines)

Page 18: Blackout Theory - Electrical and Computer Engineering Theory.pdf · July 2012 India blackout 620 India 30-31 July 2012 January 2001 India blackout 230 India 02-Jan-01 2015 Pakistan

Case 11: How much could the line have handled?

18

4900 MW

Page 19: Blackout Theory - Electrical and Computer Engineering Theory.pdf · July 2012 India blackout 620 India 30-31 July 2012 January 2001 India blackout 230 India 02-Jan-01 2015 Pakistan

NERC (n-1) ruleNo single generation outage will result in so large a frequency drop that other generators will be forced off line.

No single transmission or generation outage will result in other components experiencing such a large flow or voltage change that new limit violations occur.

19

Page 20: Blackout Theory - Electrical and Computer Engineering Theory.pdf · July 2012 India blackout 620 India 30-31 July 2012 January 2001 India blackout 230 India 02-Jan-01 2015 Pakistan

How to prevent blackouts?1. System monitoring and Audits

- Run state estimation- Test power flows, voltage magnitudes against limit values- Maintain critical alarm monitoring systems

2. Contingency analysis (What if analysis)- Detect abnormal system conditions- Detect components/parameters that will be out of limit

3. Security constrained OPF4. Public policy, Transmission and future investments

- Long term investments, replacement of ageing infrastructure- Transmission grid upgradation

20

Page 21: Blackout Theory - Electrical and Computer Engineering Theory.pdf · July 2012 India blackout 620 India 30-31 July 2012 January 2001 India blackout 230 India 02-Jan-01 2015 Pakistan

References● Peter W. Sauer, ‘Reactıve Power and Voltage Control’, NSF Workshop on

applied mathematics for deregulated power systems, Nov 3-4, 2003, Alexandria, VA.

● Damir Novosel, Energy pulse article http://www.energypulse.net/centers/article/article_print.cfm?a_id=495

● Bruce F. Wollenberg, ‘Power System Securıty - Lecture 11A’ https://www.youtube.com/watch?v=hOGlLQFJ3m0

21

Page 22: Blackout Theory - Electrical and Computer Engineering Theory.pdf · July 2012 India blackout 620 India 30-31 July 2012 January 2001 India blackout 230 India 02-Jan-01 2015 Pakistan

Thank you

22