Blow molding tool – Material Requirements Planning
Szentkirályi 1.5 liter sparkling mineral water bottle
Borián Marcell AOC4BP
2011.12.10.
2
Table of Contents
Table of Contents ............................................................................................................ 2
1. Estimated Demand ................................................................................................... 3
2. Bill of Materials ........................................................................................................ 4
3. Conditions ................................................................................................................ 5
3.1. Time ........................................................................................................................ 5
3.2. Lots ......................................................................................................................... 5
3.3. Master Data............................................................................................................. 5
3.4. Master production schedule for the complete tooling assembly .............................. 5
4. Component MRPs ................................................................................................... 6
4.1. MRP Assembly #100 – Left tool assembly set ........................................................ 6
4.2. MRP Assembly #200 – Right tool assembly set ...................................................... 6
4.3. MRP Part #300 - Bottom tool .................................................................................. 7
4.4. MRP Part #101 – Right side tool ............................................................................. 7
4.5. MRP Part #102 – Cooling cover .............................................................................. 8
4.6. MRP Part #103 - Bolts ............................................................................................ 8
4.7. MRP Part #201 – Left side tool ............................................................................... 9
5. MRP output ........................................................................................................... 10
3
1. Estimated Demand
To estimate how many blow molding tools will the Szentkirályi Company need, we
will have to estimate the yearly return of the company. Hungary’s yearly mineral water
consumption has the following distribution regarding the carbon dioxide content of the
product:
It is known that Szentkirályi sells overall 200 million liters of mineral water a year,
which means it sells approximately 114 million liters of sparkling water. Since this
amount contains the 0.5 liter bottles and the huge 20 liter balloons together –which has
a small percentage in the whole selling, we can approximate the amount of sparkling
water sold in 1.5 liter bottles is about 105 million liters. This means 70 million bottles a
year.
Regarding the fact that around 1 million bottles can be produced with one set of
tool, the total need for a year is 70 toolsets per a year.
Let we assume that the demand for new tool sets has the following distribution for a
year:
57% 37%
6%
Mineral water consuption in Hungary - 2010
Sparkling
Non-carbonated
Still
0123456789
Re
qu
ire
d n
ew
to
ol s
ets
[p
cs] Master Production Schedule
4
2. Bill of Materials
TOOLING ASSEMBLY
#100 LEFT TOOL ASSY.
#101 LEFT TOOL
#102 COOLING
COVER
#103 (6) M5X8 BOLT
#200 RIGHT TOOL
ASSY.
#201 RIGHT TOOL
#102 COOLING
COVER
#103 (6) M5X8 BOLT
#300 BOTTOM TOOL
5
3. Conditions
3.1. Time
The time bucket of this planning will be a month and the whole plan is evaluated
for a period of a year.
3.2. Lots
The side and bottom tool manufacturing can be started with the minimum amount
of 10 units.
3.3. Master Data
Part / Assy.
On-hand
Scheduled receipt Lot-sizing rule
Lead time
(month) Due Qty
#100 8 - - LFL 1
#200 8 - - LFL 1
#300 10 - - FOQ, 10+ pcs 1
#101 22 - - FOQ, 10+ pcs 1
#102 24 3 36 LFL 1
#103 148 3 400 FOP, 3 months 1
#201 22 - - FOQ, 10+ pcs 1
3.4. Master production schedule for the complete tooling assembly
Month 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements (MPS) 3 3 5 6 7 8 8 8 7 6 5 4
Available 4 1 - - - - - - - - - -
Net requirement - 2 5 6 7 8 8 8 7 6 5 4
6
4. Component MRPs
4.1. MRP Assembly #100 – Left tool assembly set
LLC = 1
Demand from tooling assembly
Month 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 2 5 6 7 8 8 8 7 6 5 4 -
Scheduled receipts - - - - - - - - - - - -
Adjusted Scheduled Receipts - - - - - - - - - - - -
Available 8 6 1 0 0 0 0 0 0 0 0 0
Net requirement 0 0 5 7 8 8 8 7 6 5 4 0
Planned order receipt 5 7 8 8 8 7 6 5 4
Planned order release 5 7 8 8 8 7 6 5 4
4.2. MRP Assembly #200 – Right tool assembly set
LLC = 1
Demand from tooling assembly
Month 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 2 5 6 7 8 8 8 7 6 5 4 -
Scheduled receipts - - - - - - - - - - - -
Adjusted Scheduled Receipts - - - - - - - - - - - -
Available 8 6 1 0 0 0 0 0 0 0 0 0
Net requirement 0 0 5 7 8 8 8 7 6 5 4 0
Planned order receipt 5 7 8 8 8 7 6 5 4
Planned order release 5 7 8 8 8 7 6 5 4
7
4.3. MRP Part #300 - Bottom tool
LLC = 1
Demand from tooling assembly
Minimum Order Quantity: 10+ units
Month 1 2 3 4 5 6 7 8 9 10 11 12
Gross requirements 2 5 6 7 8 8 8 7 6 5 4 -
Scheduled receipts - - - - - - - - - - - -
Adjusted Scheduled Receipts - - - - - - - - - - - -
Available 10 8 3 7 0 2 4 6 9 3 8 4
Net requirement 0 0 3 0 8 6 4 1 0 2 0 0
Planned order receipt 10 10 10 10 10 10
Planned order release 10 10 10 10 10 10
4.4. MRP Part #101 – Right side tool
LLC = 2
Demand from #100 assembly
Minimum Order Quantity: 10+ units
Month 1 2 3 4 5 6 7 8 9 10 11 12
Requirement from #100 5 7 8 8 8 7 6 5 4 - - -
Gross requirements 5 7 8 8 8 7 6 5 4 - - -
Scheduled receipts - - - - - - - - - - - -
Adjusted Scheduled Receipts - - - - - - - - - - - -
Available 3 7 0 2 4 6 9 3 8 4 4 4
Net requirement 2 0 8 6 4 1 0 2 0 0 0 0
Planned order receipt 10 10 10 10 10 10
Planned order release 10* 10 10 10 10 10
8
4.5. MRP Part #102 – Cooling cover
LLC = 2
Demand from assembly #100 and #200
Month 1 2 3 4 5 6 7 8 9 10 11 12
Requirement from #100 5 7 8 8 8 7 6 5 4 - - -
Requirement from #200 5 7 8 8 8 7 6 5 4 - - -
Gross requirements 10 14 16 16 16 14 12 10 8 - - -
Available 22 12 34 18 2 0 0 0 0 0 0 0
Net requirement 0 2 0 0 14 14 12 12 8 - - -
Scheduled receipts - - 36 - - - - - - - - -
Adjusted Scheduled Receipts - 36 - - - - - - - - - -
Planned order receipt 14 14 12 12 8
Planned order release 14 14 12 12 8
4.6. MRP Part #103 - Bolts
LLC = 2
Demand from assembly #100 and #200 (6 units per assembly!)
Month 1 2 3 4 5 6 7 8 9 10 11 12
Requirement from #100 30 42 48 48 48 42 36 30 53 - - -
Requirement from #200 30 42 48 48 48 42 36 30 53 - - -
Gross requirements 60 84 96 96 96 84 72 60 106 - - -
Available 148 88 4 308 212 116 44 166 106 0 0 0
Net requirement 0 0 0 0 0 0 28 0 0 0 0 0
Scheduled receipts - - 400 - - - - - - - - -
Adjusted Scheduled Receipts - - - - - - - - - - - -
Planned order receipt 194
Planned order release 194
9
4.7. MRP Part #201 – Left side tool
LLC = 2
Demand from assembly #200
Minimum Order quantity: 10+ units
Month 1 2 3 4 5 6 7 8 9 10 11 12
Requirement from #200 5 7 8 8 8 7 6 5 4 - - -
Gross requirements 5 7 8 8 8 7 6 5 4 - - -
Scheduled receipts - - - - - - - - - - - -
Adjusted Scheduled Receipts - - - - - - - - - - - -
Available 3 7 0 2 4 6 9 3 8 4 4 4
Net requirement 2 0 8 6 4 1 0 2 0 0 0 0
Planned order receipt 10 - 10 10 10 10 - 10 - - - -
Planned order release 10* 10 10 10 10 - 10 - - - - -
10
5. MRP output
Transaction Part # Old due Release
date New due Quantity Notice
Change Notice #102 3 2 36 expedite
Planned order release #100 2 3 5 OK
Planned order release #100 3 4 7 OK
Planned order release #100 4 5 8 OK
Planned order release #100 5 6 8 OK
Planned order release #100 6 7 8 OK
Planned order release #100 7 8 7 OK
Planned order release #100 8 9 6 OK
Planned order release #100 9 10 5 OK
Planned order release #100 10 11 4 OK
Planned order release #200 2 3 5 OK
Planned order release #200 3 4 7 OK
Planned order release #200 4 5 8 OK
Planned order release #200 5 6 8 OK
Planned order release #200 6 7 8 OK
Planned order release #200 7 8 7 OK
Planned order release #200 8 9 6 OK
Planned order release #200 9 10 5 OK
Planned order release #200 10 11 4 OK
Planned order release #300 2 3 10 OK
Planned order release #300 4 5 10 OK
Planned order release #300 5 6 10 OK
Planned order release #300 6 7 10 OK
Planned order release #300 7 8 10 OK
Planned order release #300 9 10 10 OK
Planned order release #101 1 1 10 Late
Planned order release #101 2 3 10 OK
Planned order release #101 3 4 10 OK
Planned order release #101 4 5 10 OK
Planned order release #101 5 6 10 OK
Planned order release #101 7 8 10 OK
11
Planned order release #102 4 5 14 OK
Planned order release #102 5 6 14 OK
Planned order release #102 6 7 12 OK
Planned order release #102 7 8 12 OK
Planned order release #102 8 9 8 OK
Planned order release #103 6 7 194 OK
Planned order release #201 1 1 10 Late
Planned order release #201 2 3 10 OK
Planned order release #201 3 4 10 OK
Planned order release #201 4 5 10 OK
Planned order release #201 5 6 10 OK
Planned order release #201 7 8 10 OK