Blue Grass Chemical Agent- Destruction Pilot Plant Quarterly Update March 12, 2013 Presented to: Kentucky Chemical Demilitarization Citizens’ Advisory Commission and Kentucky Chemical Destruction Community Advisory Board Presented by: Jeff Brubaker Site Project Manager

Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12, 2013 Version 2

Embed Size (px)

DESCRIPTION

Presented to: Kentucky Chemical Demilitarization Citizens’ Advisory Commission and Kentucky Chemical Destruction Community Advisory Board Presented by: Jeff Brubaker Site Project Manager

Citation preview

Page 1: Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12, 2013 Version 2

Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update

March 12, 2013

Presented to:

Kentucky Chemical Demilitarization Citizens’ Advisory Commission and

Kentucky Chemical Destruction Community Advisory Board

Presented by:

Jeff Brubaker

Site Project Manager

Page 2: Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12, 2013 Version 2

A Partnership for Safe Chemical Weapons Destruction

2

Programmatic Update

New Program Executive Office, Assembled Chemical Weapons Alternatives Chief of Staff

Federal funding situation ? National Research Council project

visit Participation in Blue Grass

Chemical Activity’s Safe, Secure video update ?

Program Executive Office, Assembled Chemical Weapons Alternatives Chief of Staff Robert Q. Eldringhoff . Eldringhoff was previously Deputy Director of the U.S. Army Chemical Materials Activity.

Page 3: Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12, 2013 Version 2

A Partnership for Safe Chemical Weapons Destruction

Construction now more than 65 percent complete

Systemization activities now more than 9 percent complete

Completion of the structural steel on the Munitions Demilitarization Building (MDB)

Delivery of the Munitions Washout System and Rocket Shear Machine equipment

Completion and delivery of the first of two MDB filter bank Clean-Air Exhaust Stacks

Blue Grass Chemical Agent-Destruction Pilot Plant Update

3

One half of the first 120-foot Clean-Air Exhaust Stack is offloaded for temporary storage in the Hwy. 52 lay-down yard. It will be installed in accordance with the construction schedule.

Page 4: Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12, 2013 Version 2

A Partnership for Safe Chemical Weapons Destruction

Final Munitions Demilitarization Building Filter Bank Concrete Placement video on Facebook

Blue Grass Chemical Agent-Destruction Pilot Plant Update (cont’d)

4

The workers spent approximately 8 hours placing 540 cubic yards of concrete to complete the second half of the east filter bank foundation.

Page 5: Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12, 2013 Version 2

A Partnership for Safe Chemical Weapons Destruction

5

Northwestern Corner - Observation Point

1 2

1

3

5

2

6

Blue Grass Chemical Agent-Destruction Pilot Plant Construction Site (March 2013)

Control and Support Building

Munitions Demilitarization Building (MDB)

MDB Filter Banks

Utility Building

Supercritical Water Oxidation Building (not visible in photo)

Laboratory Building (not visible in photo)

6 5

4

4

3

Page 6: Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12, 2013 Version 2

A Partnership for Safe Chemical Weapons Destruction

Explosive Destruction Technologies

Header Text

– Sub-bullet text

– Sub-bullet text Header Text

– Sub-bullet text

6

Page 7: Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update March 12, 2013 Version 2

A Partnership for Safe Chemical Weapons Destruction

Questions/Discussion

7

For more information about the Blue Grass Chemical Agent-Destruction Pilot Plant project, please contact the Blue Grass Chemical Stockpile Outreach Office at (859) 626-8944