BLUE MOUNTAINS LOCAL PLANNING PANEL ITEM NO: 2.1– 24 JUNE 2019 1 of 22 ITEM No. 2.1 REPORT: DEVELOPMENT APPLICATION No. X/168/2019 for the demolition of the existing dwelling and construction of a two storey dwelling with a deck, pergola, rainwater tanks, shed, fence, landscaping and solid fuel heater at 7 Cunningham Street, HAZELBROOK NSW 2779 Reason for report There is a conflict of interest. The applicant is a member of Council staff who holds delegations to exercise Council’s functions under the Environmental Planning and Assessment Act 1979. RECOMMENDATION That Development Application X/168/2019 for the demolition of the existing dwelling and construction of a two storey dwelling with a deck, pergola, rainwater tanks, shed, fence, landscaping and solid fuel heater on 7 Cunningham Street, Hazelbrook NSW 2779 be determined in accordance with s4.16 of the Environmental Planning and Assessment Act, by the granting of consent subject to the conditions stated in Part 3 of the this report. Reason/s in support of the recommended decision 1. The proposed development generally complies with the relevant State and local planning instruments and policies. 2. The development is an appropriate redevelopment of the site which will enhance the character of the existing residential area. 3. Adjoining property owners were notified of the proposed development in accordance with Council’s policy and no submissions were received. Disclosure Disclosure of any political donation and/or gift - No Declaration of interest The Applicant has declared a conflict of interest as a staff member of Blue Mountains City Council Report author/s Senior Environmental Health and Building Surveyor – Ian Catto Report authoriser Acting Manager, Building & Compliance – Paul Weston PART 1 Development proposal PART 2 Council assessment PART 3 Proposed conditions of consent

BLUE MOUNTAINS LOCAL PLANNING PANEL ITEM NO: 2.1– 24 JUNE … · 2019-06-13 · BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019 . 8 of 22 . City wide infrastructure

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: BLUE MOUNTAINS LOCAL PLANNING PANEL ITEM NO: 2.1– 24 JUNE … · 2019-06-13 · BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019 . 8 of 22 . City wide infrastructure

BLUE MOUNTAINS LOCAL PLANNING PANEL

ITEM NO: 2.1– 24 JUNE 2019

1 of 22

ITEM No. 2.1

REPORT: DEVELOPMENT APPLICATION No. X/168/2019 for the demolition of the existing dwelling and construction of a two storey dwelling with a deck, pergola, rainwater tanks, shed, fence, landscaping and solid fuel heater at 7 Cunningham Street, HAZELBROOK NSW 2779

Reason for report There is a conflict of interest. The applicant is a member of Council staff who holds delegations to exercise Council’s functions under the Environmental Planning and Assessment Act 1979.

RECOMMENDATION That Development Application X/168/2019 for the demolition of the existing dwelling and construction of a two storey dwelling with a deck, pergola, rainwater tanks, shed, fence, landscaping and solid fuel heater on 7 Cunningham Street, Hazelbrook NSW 2779 be determined in accordance with s4.16 of the Environmental Planning and Assessment Act, by the granting of consent subject to the conditions stated in Part 3 of the this report.

Reason/s in support of the recommended decision

1. The proposed development generally complies with the relevant State and local planning instruments and policies.

2. The development is an appropriate redevelopment of the site which will enhance the character of the existing residential area.

3. Adjoining property owners were notified of the proposed development in accordance with Council’s policy and no submissions were received.

Disclosure Disclosure of any political donation and/or gift - No

Declaration of interest The Applicant has declared a conflict of interest as a staff member of Blue Mountains City Council

Report author/s Senior Environmental Health and Building Surveyor – Ian Catto

Report authoriser Acting Manager, Building & Compliance – Paul Weston

PART 1 Development proposal

PART 2 Council assessment

PART 3 Proposed conditions of consent

Page 2: BLUE MOUNTAINS LOCAL PLANNING PANEL ITEM NO: 2.1– 24 JUNE … · 2019-06-13 · BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019 . 8 of 22 . City wide infrastructure

BLUE MOUNTAINS LOCAL PLANNING PANEL – ITEM NO. 2.1- 24 JUNE 2019

2 of 22

Page 3: BLUE MOUNTAINS LOCAL PLANNING PANEL ITEM NO: 2.1– 24 JUNE … · 2019-06-13 · BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019 . 8 of 22 . City wide infrastructure

BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019

3 of 22

PART 1: Development proposal

Applicant Mr C Brown

Land owner Ms A E Davis

Location 7 Cunningham Street, HAZELBROOK NSW 2779

Lot & DP Lot 33 Section 2 DP 4641

Date lodged 11 March 2019

Value of works $405,000.00

Proposal in detail The development proposal seeks approval for the demolition of the existing dwelling and construction of a two storey dwelling with a deck, pergola, rainwater tanks, shed, fence, landscaping and solid fuel heater.

Departure or variation to a development standard

The applicant is not seeking to vary a development standard.

Supporting documentation

The plans and documents lodged are considered sufficient to enable assessment of the application. The application is supported by:

o Architectural plans

o Landscape plan

o Concept stormwater drainage plan

o Statement of environmental effects

o Request to vary the DCP setback requirements for the shed and dwelling

Documentation online Plans to scale and key documents lodged with the application can be viewed online. Go to www.bmcc.nsw.gov.au/development – Track and View applications. Search and select X/168/2019.

Reduced site and elevation plans are below.

Page 4: BLUE MOUNTAINS LOCAL PLANNING PANEL ITEM NO: 2.1– 24 JUNE … · 2019-06-13 · BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019 . 8 of 22 . City wide infrastructure

BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019

4 of 22

Site plan

Page 5: BLUE MOUNTAINS LOCAL PLANNING PANEL ITEM NO: 2.1– 24 JUNE … · 2019-06-13 · BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019 . 8 of 22 . City wide infrastructure

BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019

5 of 22

Elevation plans

Page 6: BLUE MOUNTAINS LOCAL PLANNING PANEL ITEM NO: 2.1– 24 JUNE … · 2019-06-13 · BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019 . 8 of 22 . City wide infrastructure

BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019

6 of 22

Page 7: BLUE MOUNTAINS LOCAL PLANNING PANEL ITEM NO: 2.1– 24 JUNE … · 2019-06-13 · BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019 . 8 of 22 . City wide infrastructure

BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019

7 of 22

PART 2: Council assessment 2.1 Overview and summary of issues

Location 7 Cunningham Street, HAZELBROOK NSW 2779

Lot & DP Lot 33 Section 2 DP 4641

Zoning Local Environmental Plan 2015 – Zone E4 Environmental Living

Characterisation of use The proposed development is characterised as a dwelling house.

Permissibility The proposed development is permissible within the zone.

Existing use rights The proposed development does not rely on existing use rights.

Type of development Local

Applicable environmental planning instrument/s

o State Environmental Planning Policy (Building Sustainability Index: BASIX)

o State Environmental Planning Policy (Sydney Drinking Water Catchment)

o Local Environmental Plan 2015

o Development Control Plan 2015

Applicable additional local provisions

o Consideration of character and landscape

o Essential services

o Council infrastructure development

Applicable additional local clauses

Nil

Bushfire prone land The property is not mapped as bushfire prone.

Heritage significance The property is not listed as a heritage item nor is it within a heritage conservation area.

Aboriginal significance No Aboriginal objects are recorded or Aboriginal places declared in or near the subject property.

Potentially contaminated land

The land is not listed on the Council’s potentially contaminated land register and none of the activities that may cause contamination, listed in Table 1 of Planning NSW’s Managing Land Contamination Planning Guidelines, are being or are known to have been carried out on the site.

Site description The site is located on the corner of Cunningham Street and Beechmount Avenue and is a single lot with a total area of 1226m2. The site falls from the western corner to the eastern corner by approximately 6.5m. The site contains an existing dwelling, shed and established landscaping.

Page 8: BLUE MOUNTAINS LOCAL PLANNING PANEL ITEM NO: 2.1– 24 JUNE … · 2019-06-13 · BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019 . 8 of 22 . City wide infrastructure

BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019

8 of 22

City wide infrastructure contribution

The Citywide infrastructure contribution applies. The applicant has valued the proposed development at $405,000. The rate of the levy with a value of more than $200,000 is 1%. A levy $4,050.00 is applicable for this development. This contribution is included as a condition of consent.

Referral authorities Referrals were not required.

Notification period The application was notified to adjoining and nearby property owners for the period 27 March 2019 to 10 April 2019 and no submissions were received.

Summary of assessment issues

Key issues determined in the assessment are:

o Building setbacks

Assessment issues are detailed below.

2.2 Evaluation The application has been assessed in accordance with s4.15 of the Environmental Planning and Assessment Act 1979 (EP&A Act). Only those provisions relevant to the proposed development have been addressed.

Page 9: BLUE MOUNTAINS LOCAL PLANNING PANEL ITEM NO: 2.1– 24 JUNE … · 2019-06-13 · BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019 . 8 of 22 . City wide infrastructure

BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019

9 of 22

State Environmental Planning Policy (SEPP) – s4.15(1)(a)(i)

The following table provides for an assessment against the provisions applicable State Environmental Planning Policies.

SEPP (Building Sustainability Index: BASIX)

A BASIX Certificate has been submitted with the application – Certificate Number 915914S dated 3 March 2019.

Condition of consent A condition has been included for compliance with the commitments indicated in the certificate.

SEPP (Sydney Drinking Water Catchment)

Standard Discussion Compliance Y/N

Impact of development on drinking water catchment

An assessment has been carried out using the Water NSW’s on line NorBE tool and the development satisfies the requirements for neutral or beneficial effect.

Y

Local Environmental Plan 2015 [LEP2015] – s4.15(1)(a)(i)

The proposed development has been assessed against the provisions of LEP 2015 with significant points identified and discussed below.

Part 1 Preliminary

Clause Standard Discussion Compliance Y/N

1.2 Aims of Plan

The proposed development is considered to satisfy the Aims of LEP 2015.

Y

Part 2 Permitted or prohibited development

Clause Standard Discussion Compliance Y/N

Land Use Table

Permissibility The proposed use is categorised as a dwelling house.

A dwelling house is permissible with development consent in the E4 – Environmental Living zone.

Y

2.3 Zone objectives The objectives of the zone are met, in particular the objective of the E4 zone, ‘To ensure that the form and siting of buildings are appropriate for, and

Y

Page 10: BLUE MOUNTAINS LOCAL PLANNING PANEL ITEM NO: 2.1– 24 JUNE … · 2019-06-13 · BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019 . 8 of 22 . City wide infrastructure

BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019

10 of 22

Part 2 Permitted or prohibited development

Clause Standard Discussion Compliance Y/N

harmonise with, the bushland character of the locality’.

Part 4 Principal development standards

Building

Clause Standard Control Proposed Compliance Y/N

4.3 Height of buildings The Height of Buildings Map shows a maximum height of 8 metres.

The dwelling will have a maximum height of 6.3m

Y

4.4A Site coverage and landscaped area

Maximum site cover permitted is 322.6m2 based on a site area of 1226m2.

Minimum 60% of the lot will comprise pervious areas.

175m2

73%

Y

Y

Part 5 Miscellaneous provisions

Clause Standard Discussion Compliance Y/N

5.10.8 Aboriginal places of heritage significance

A search of the Aboriginal Heritage Information Management System (AHIMS) register on the Office of Environment & Heritage website shows no aboriginal sites or places on or within 50 m of the land.

Y

Part 6 Additional local provisions

Clause Standard Discussion Compliance Y/N

Impact on natural environment

6.1 Impact on environmentally sensitive land

The site does not contain any environmentally sensitive land.

Y

6.9 Stormwater management The stormwater will be connected to rainwater tanks with a total capacity of 8,000L and the

Y

Page 11: BLUE MOUNTAINS LOCAL PLANNING PANEL ITEM NO: 2.1– 24 JUNE … · 2019-06-13 · BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019 . 8 of 22 . City wide infrastructure

BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019

11 of 22

Part 6 Additional local provisions

Clause Standard Discussion Compliance Y/N

overflow will be connected to an absorption trench to allow for water infiltration into the ground.

6.14 Earthworks The proposed cut and fill is not considered to have significant environmental or amenity impacts. The proposed 1m cut is considered appropriate in the residential area.

Y

Impact on built environment

6.17 Consideration of character and landscape

The proposed development is considered to enhance the established character of the buildings, gardens and streetscape. The scale, massing, building materials, colours and design is considered suitable.

Y

6.21 Sustainable resource management

A valid BASIX Certificate has been submitted with the application and the dwelling has been designed with sustainable practices in mind. Materials from the demolition of the dwelling will be recycled or re-used where possible.

Y

6.23 Essential Services All services are available. Y

Development Control Plan 2015 – s4.15(1)(a)(iii)

The proposed development has been assessed against the provisions of the Blue Mountains Development Control Plan 2015 with significant points of consideration identified and discussed in the table below.

Part B Context, site analysis and design

Clause Standard Discussion Compliance Y/N

B1 Site and context analysis The submitted plans and the statement of environmental effects allows for the analysis of the context of the proposed development.

Y

B2 Building envelope Front Setback

Part B2.3.1 requires the front building setback to be within 20% of the average setback of buildings on immediately adjoining properties. The front setback range permitted to Cunningham Street is calculated to be 10.8m to 16.2m. The dwelling is proposed to be located on the site of the existing dwelling which is to be demolished. The proposed setback of 27.3m is not within the range however it is considered that the building will comply with the

Y

Page 12: BLUE MOUNTAINS LOCAL PLANNING PANEL ITEM NO: 2.1– 24 JUNE … · 2019-06-13 · BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019 . 8 of 22 . City wide infrastructure

BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019

12 of 22

Part B Context, site analysis and design

Clause Standard Discussion Compliance Y/N

objectives of Part B2.3.1 despite a numeric non-compliance. The bulk and scale is consistent with the streetscape and promotes a landscape setting by maintaining and adding to the established garden. Solar access to adjoining properties will not be impacted. The building responds to the site constraints and care has been taken to retain existing vegetation. The setback will allow the current landscaped frontage to Cunningham Street to be maintained.

Secondary frontage setback

A minimum secondary frontage setback of 3m is required to Beechmount Avenue. The dwelling complies with a setback to the deck of 4.9m and 6.1m to the dwelling wall. The shed is proposed with a 2m setback which does not meet the numeric control. The shed is proposed to replace a smaller existing prefabricated metal shed. The location of the shed was selected to minimise the removal of established vegetation. Moving the shed back 1m would require the removal of a tree. The shed is a minor structure at 17m2 and 3.13m high and will be clad with timber to blend with the landscaping. Landscape screening is proposed between the shed and the secondary road frontage. Buildings within 3m of the frontage are not out of character in the street and it is considered that the setback will not have an adverse impact on the streetscape and will achieve the objectives of Part B2.3.1.

Y

B3 Character and design The development is considered to be site responsive and the scale, materials and colours and design are appropriate for the site given the varied character of the area.

Y

Part C Environmental management

Clause Standard Discussion Compliance Y/N

C1 Biodiversity and Natural resources

The majority of existing trees and vegetation will be retained. The site disturbance is reduced as the new dwelling will be in a similar location to the existing dwelling.

Y

Page 13: BLUE MOUNTAINS LOCAL PLANNING PANEL ITEM NO: 2.1– 24 JUNE … · 2019-06-13 · BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019 . 8 of 22 . City wide infrastructure

BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019

13 of 22

Part C Environmental management

Clause Standard Discussion Compliance Y/N

C2 Bushland and weed management

The applicant responded to Councils request for the existing Bamboo Rhizomatouson which is a declared weed on the northwest boundary to be removed and a suitable amended landscape plan was provided. The privet (Ligustrum sinense) hedge along the Beechmount frontage is a declared weed and will also be removed.

Y

C3 Landscaping The existing landscaping is extensive and the majority will be retained. New suitable landscaping will be provided to the dwelling setback in accordance with the landscape plan.

Y

C5 Tree and vegetation preservation

The majority of existing vegetation will be retained. Y

C6 Water management Stormwater will be connected to rainwater tanks with overflow infiltrate into the ground through an absorption trench in accordance with the stormwater plan.

Y

Part D Heritage management

Clause Standard Discussion Compliance Y/N

D1 Heritage A search of the AHIMS register on the OEH website shows no aboriginal sites or places on or within 50 m of the land. The site is not located within a heritage conservation area.

Y

Part E Site development and management

Clause Standard Discussion Compliance Y/N

E1 Services Existing services are available to the site. Y

E2 Traffic, parking and access

The driveway is capable of complying with AS2890.1 and will be in a similar position to the existing driveway. The driveway allows for 1 parking space within the property as marked on the landscape plan.

Y

E4 Site management A suitable erosion and sediment control plan has been provided. Sediment controls will be required prior to the commencement of works.

Y

Page 14: BLUE MOUNTAINS LOCAL PLANNING PANEL ITEM NO: 2.1– 24 JUNE … · 2019-06-13 · BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019 . 8 of 22 . City wide infrastructure

BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019

14 of 22

Part E Site development and management

Clause Standard Discussion Compliance Y/N

E6 Waste management Materials from the demolition will be re-used and recycled where possible. Other materials like asbestos will be disposed of at a legal waste management facility.

Y

Part F Specific development types

Clause Standard Discussion Compliance Y/N

Low Density Residential

F1.1.1 Private open space Private open space is available in a number of areas on the site.

Y

F1.1.2 Visual privacy The dwelling will have minimal impact to the privacy of the adjoining properties.

Y

F1.1.4 Sunlight access There will be minimal overshadowing to the adjoining properties.

Y

F1.1.5 Views Existing views will not be impacted by the development.

Y

F1.1.6 Driveways and parking The driveway location is suitable and is similar to the existing driveway and is located on the secondary frontage. There are a number of dwellings with parking close to the boundary on Beechmount Avenue and therefore the parking space in line with the shed is not considered to be out of character or have an adverse impact to the streetscape.

Y

Ancillary development

F1.3.1 Fences A privet (Ligustrum sinense) hedge along the front boundary is a declared weed under Part C DCP 2015 and will be removed. The 1.5m high open style timber batten fence to 22m of the secondary frontage is suitable to replace the existing privet hedge. The fence will allow for a level of privacy, security and passive surveillance without adversely impacting the streetscape.

Y

F1.3.3 Sheds The proposed shed will replace an existing prefabricated shed. The shed is not located behind the building line of the dwelling however it does meet the objectives of the clause. The shed is setback 2m from Beechmount Avenue and is an appropriate scale and will not impact the amenity of

Y

Page 15: BLUE MOUNTAINS LOCAL PLANNING PANEL ITEM NO: 2.1– 24 JUNE … · 2019-06-13 · BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019 . 8 of 22 . City wide infrastructure

BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019

15 of 22

Part F Specific development types

Clause Standard Discussion Compliance Y/N

the area. It is not out of character in the street to have outbuildings forward of the building line on the secondary frontage and the shed will be partially screened by vegetation.

Planning Agreement – s4.15(1)(a)(iiia)

There are no planning agreements that apply to the proposed development or the subject site.

Regulations – s4.15(1)(a)(iv)

The Environmental Planning and Assessment Regulation, provides controls and regulations that relate to the management of the proposed development. These requirements are inherent in the assessment processes undertaken for the proposal.

Likely impacts – s4.15(1)(b)

Likely impacts on the natural and built environment

Discussion

Vegetation removal and management

The development has been designed to minimise the removal of valued existing vegetation.

Character and amenity The proposed development will not have an adverse impact on the character and amenity of the area.

Stormwater drainage Stormwater will be collected for re-use and the overflow will infiltrate into the site.

Parking Parking in the driveway is suitable and will not be out of character in the area.

It is considered that the development does not have an adverse impact on the natural and built environment.

Likely social impacts

Discussion

It is considered that the development does not have adverse social impacts.

Likely economic impacts

Discussion

It is considered that the development does not have an adverse economic impact.

Page 16: BLUE MOUNTAINS LOCAL PLANNING PANEL ITEM NO: 2.1– 24 JUNE … · 2019-06-13 · BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019 . 8 of 22 . City wide infrastructure

BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019

16 of 22

Suitability of the site for the development – s4.15(1)(c)

Site suitability The site is considered suitable for the proposed development for the following reasons:

o The site is within an established residential area and the dwelling will enhance the character.

o The proposed dwelling is of an appropriate scale and form to fit within the established landscaping on the site with minimal tree removal.

Submissions – s4.15(1)(d)

Notification

Consultation was undertaken in accordance with the requirements of Part H (Public Participation) of Blue Mountains Development Control Plan 2015 and the requirements under the Environmental Planning and Assessment Regulations.

Notification The application was notified to nearby and adjoining properties from 27 March 2019 until 10 April 2019.

No submissions were received.

Public interest – s4.15(1)(e)

Public interest No issues have arisen during the assessment that would indicate the proposed development is not in the public interest

Page 17: BLUE MOUNTAINS LOCAL PLANNING PANEL ITEM NO: 2.1– 24 JUNE … · 2019-06-13 · BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019 . 8 of 22 . City wide infrastructure

BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019

17 of 22

PART 3 Proposed conditions of consent

Confirmation of relevant plans and documentation

1. To confirm and clarify the terms of consent, the development shall be carried out in accordance with the following plans and accompanying supportive documentation, except as otherwise provided or modified by the conditions of this consent:

Document/plans Prepared by: Sheet No Revision Date Cover sheet Cale Brown 1 03/03/2019 Site, demolition & shed Cale Brown 2 03/03/2019 Lower floor Cale Brown 3 03/03/2019 Upper floor Cale Brown 4 03/03/2019 Elevations A Cale Brown 5 03/03/2019 Elevations B Cale Brown 6 A 15/05/2019 Sections A Cale Brown 7 03/03/2019 Sections B Cale Brown 8 03/03/2019 Glazing schedule Cale Brown 9 03/03/2019 Landscape Cale Brown 10 B 29/05/2019 Erosion & Sediment Control Plan Cale Brown 12 24/03/2019 Stormwater Cale Brown 13 15/05/2019

City-wide Local Infrastructure Contribution

2. In accordance with the Blue Mountains City Council City-wide Local Infrastructure Contributions Plan adopted 27 June 2017 (“the Contributions Plan”), a contribution of $4,050.00 shall be paid to Council.

This amount will be adjusted* at the time of payment in accordance with Section 3.7 of the Contributions Plan.

The contribution shall be paid prior to the issue of a construction certificate, or commencement of the use of the land, whichever occurs sooner.

The Contributions Plan is available for inspection at Council’s offices or on Council’s website at www.bmcc.nsw.gov.au.

*Using the All Groups Consumer Price Index (Sydney), as published by the Australian Bureau of Statistics. You are advised to check the current amount payable with Council prior to any payment.

Sydney Water building plan approval

Prior to works commencing

3. A building plan approval must be obtained from Sydney Water Tap inTM to ensure that the approved development will not impact Sydney Water infrastructure.

A copy of the building plan approval receipt from Sydney Water Tap inTM must be submitted to the Principal Certifying Authority prior to works commencing.

Please refer to the web site www.sydneywater.com.au - Plumbing, building & developing - Sydney Water Tap inTM, or telephone 13 20 92.

Page 18: BLUE MOUNTAINS LOCAL PLANNING PANEL ITEM NO: 2.1– 24 JUNE … · 2019-06-13 · BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019 . 8 of 22 . City wide infrastructure

BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019

18 of 22

Construction certificate 4. A construction certificate is required prior to the commencement of any building works. This certificate can be issued either by Council as a certifying authority or by an accredited certifier.

Notification of Home Building Act 1989 requirements

5. Prior to commencement of building works, the Principal Certifying Authority is to provide Council with written notice of:

• In the case of work for which a principal contractor is required to be appointed:

o The name and licence number of the principal contractor, and

o The name of the insurer by which the work is insured under Part 6 of the Home Building Act 1989.

• In the case of work to be done by an owner-builder:

o The name of the owner-builder, and

o If the owner-builder is required to hold an owner-builder permit under the Act, the number of the owner-builder permit.

Building Code of Australia 6. All building work must be carried out in accordance with the provisions of the Building Code of Australia.

BASIX 7. Under clause 97A(2) of the Environmental Planning & Assessment Regulation 2000, it is a condition of this development consent that all the commitments listed in the BASIX Certificate for the development are fulfilled.

In this condition:

1. Relevant BASIX Certificate means:

a) A BASIX Certificate that was applicable to the development when this development consent was granted (or, if the development consent is modified under section 96 of the Act, a BASIX Certificate that is applicable to the development when this development consent is modified); or

b) If a replacement BASIX Certificate accompanies any subsequent application for a Construction Certificate, the replacement BASIX Certificate; and

2. BASIX Certificate has the meaning given to that term in the Environmental Planning & Assessment Regulation 2000.

Survey report 8. To ensure that the building does not encroach on the minimum required setbacks and is located within the boundaries of the property, a survey report by a registered Land Surveyor must be provided to the Principal Certifying Authority prior to the work proceeding beyond:

a) peg out of buildings.

Page 19: BLUE MOUNTAINS LOCAL PLANNING PANEL ITEM NO: 2.1– 24 JUNE … · 2019-06-13 · BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019 . 8 of 22 . City wide infrastructure

BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019

19 of 22

Signage 9. To ensure that the site is easily identifiable for deliveries and provides information on the person responsible for the site, a sign displaying the following information is to be erected in a prominent position on the site prior to building, subdivision or demolition works commencing:

• The name, address and telephone number of the principal certifying authority for the work.

• The name of the principal contractor for any building work and a telephone number on which that person may be contracted outside working hours, and

• The statement that “Unauthorised entry to the site is prohibited”.

Site management 10. To safeguard the local amenity, reduce noise nuisance and to prevent environmental pollution during the construction period:

• Site and building works (including the delivery of materials to and from the property) shall be carried out Monday to Friday between 7am-6pm and on Saturdays between 8am-3pm, excluding public holidays. Alteration to these hours may be possible for safety reasons but only on the agreement of Council.

• Stockpiles of topsoil, sand, aggregate, spoil or other material shall be stored clear of any drainage path or easement, natural watercourse, footpath, kerb or road surface and shall have measures in place to prevent the movement of such material off site.

• Building operations such as brickcutting, washing tools, concreting and bricklaying shall be undertaken on the building block, with pollutants contained on site.

• Builders waste generated under this consent (including felled trees, tree stumps and other vegetation) must not be burnt or buried on site.

• All waste must be contained and removed to an approved Waste Disposal Depot or in the case of vegetation, with the exception of environmental and declared noxious weeds, mulched for re-use on site.

Workers amenities 11. Before work starts, toilet facilities must be provided for construction personnel on the site. Amenities are to be installed and operated in an environmentally responsible and sanitary manner.

Erosion & sediment controls 12. To preserve the unique environment of the Blue Mountains and to contain soil and sediment on the property, controls in accordance with the Development Control Plan are to be implemented prior to clearing of the site vegetation and the commencement of site works. This will include:

• The installation of a sediment fence with returned ends across the low side of the site so that all water flows through. These shall be maintained at no less than 70% capacity at all times. Drains, gutters, roadways etc., shall be kept clean and free of sediment.

• To prevent the movement of soil off site, a single entry/exit point to the property shall be constructed of 40mm blue metal aggregate or recycled concrete to a depth of 150mm. The length must be at least 5 metres with the

Page 20: BLUE MOUNTAINS LOCAL PLANNING PANEL ITEM NO: 2.1– 24 JUNE … · 2019-06-13 · BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019 . 8 of 22 . City wide infrastructure

BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019

20 of 22

width at least 3 metres.

Soil erosion fences shall remain and must be maintained until all disturbed areas are restored by turf, paving or revegetation.

Stormwater drainage 13. To control rainwater runoff, roof water shall be connected to stormwater drainage lines discharging to:

a) rainwater tank/s with a total capacity of 8000 litres in accordance with BASIX.

The overflow from the tank is to be conveyed to:

a) stormwater pits (600mm wide x 600mm deep x 2m long, for each downpipe. Pits shall be located at least 4m from any building or property boundary). Note: A 100mm x 50mm downpipe is considered capable of draining up to 45m2 of roof area, or

It is recommended that the drainage system be installed at the same time as the footings/slab. It must be operational as soon as the roof is clad.

Materials & colours 14. To have regard of the amenity of the area, the materials and colours to be used shall be in accordance with the external finishes schedule on the approved plans. Any variation to the above materials/colours will require the prior agreement of Council.

Development involving bonded asbestos material and friable asbestos material

15. Work involving the removal of bonded asbestos removal (of an area of more than 10 square metres) or friable asbestos must be undertaken by a person licensed to undertake such work under clause 458 of the Work Health and Safety Regulation 2017;

Notification to Council and adjoining residents of demolition of buildings

16. The applicant is to notify Council and adjoining residents, in writing, at least ten (10) working days prior to demolition commencing, of their intention to commence demolition works. In the case of adjoining residents, such notification is to be a clearly written note, on at least note pad size paper, giving the date demolition will commence and be placed in the letterbox of every premises (including every residential flat or unit, if any) either side and immediately to the rear of the demolition site.

Disposal of asbestos 17. All asbestos material, including asbestos cement, is to be disposed of to an approved waste management facility licensed to receive asbestos.

Display of signage 18. The developer will display appropriate asbestos/demolition signage prior to and during demolition works.

Demolition management 19. The work is to be executed by a competent person, with due regard for safe working practices and in accordance with the requirements of the SafeWork NSW and AS 2601 The demolition of structures.

Page 21: BLUE MOUNTAINS LOCAL PLANNING PANEL ITEM NO: 2.1– 24 JUNE … · 2019-06-13 · BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019 . 8 of 22 . City wide infrastructure

BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019

21 of 22

At all times during demolition a competent person shall directly supervise work. It is the responsibility of the person to ensure that:

• The structure to be demolished and all its components shall be maintained in a stable and safe condition at all stages of the demolition work. Temporary bracing, guys, shoring or any combination of these, shall be added for stability where necessary.

• Precautions are taken to ensure that the stability of all parts of the structure and the safety of persons on and outside the site are maintained particularly in the event of sudden and severe weather changes. Severe weather changes refer primarily to the localised high winds. In these circumstances loose debris can become airborne, particularly if it is in sheet form.

• The site shall be secured at all times against the unauthorised entry of persons or vehicles.

• Utility services within the structure not required to be maintained during the demolition work shall be properly disconnected and sealed off before any stripping or demolition commences.

Approval under the Roads Act 1993 required

20. Before work commences in Council's roads, plans and specifications are to be submitted to and approved by the Council under the Roads Act 1993.

All works in Council's road are to be at no cost to Council.

Works required in Council’s Roads

21. The following engineering works shall be constructed by the applicant at the applicant’s expense;

• The construction of an apron crossing, 4 metres wide at the edge of bitumen and 3 metres wide at the property boundary, 150mm full width thick concrete with F72 mesh.

Details are to be provided with the Roads Act application for approval.

Certification by Council for works within road reserve

22. Prior to the issue of a final Occupation Certificate, a certificate shall be obtained from Council to verify that all works within the road reserve have been completed in accordance with the approved plans and to Council’s satisfaction.

Weed control 23. Systematic control of noxious and environmental weeds is to be undertaken concurrently with the establishment of the landscape, and to ensure eradication of all mature noxious and significant environmental weeds, the depletion of soil stored seed and other propagules. Techniques used must be consistent with best practice and low impact bushland regeneration techniques, following the guidelines available in DCP 2015 Part C2.2 Weed Management; http://www.bmcc.nsw.gov.au/files/Part%20C.pdf

This work must coincide with supplementary activities designed to:

• Reduce continuing opportunities for weeds to establish

• Reduce the factors promoting weeds on the site

• Enhance the ecological processes operating on the site

Page 22: BLUE MOUNTAINS LOCAL PLANNING PANEL ITEM NO: 2.1– 24 JUNE … · 2019-06-13 · BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019 . 8 of 22 . City wide infrastructure

BLUE MOUNTAINS LOCAL PLANNING PANEL - ITEM NO. 2.1 – 24 JUNE 2019

22 of 22

• Ensure the successful establishment of landscaping

Where herbicide is proposed for use within the weed control strategy, operators must ensure that all chemicals are registered for use and used in strict accordance with a current, registered label. Failure to do so may constitute a breach of the Pesticides Act 2000.

Landscaping (and ongoing maintenance)

24. Landscaping of the property is to ensure that the development retains or re-establishes a bushland character.

To achieve this, landscape works are to be undertaken in accordance with the approved landscape plan.

Solid fuel heater installation 25. The solid fuel heater is to be installed in accordance with the manufacturer’s specifications.

Advisory note 1. In accordance with NSW Addressing User Manual, property databases will be updated to record:

o The property is to be identified as 14 Beechmont Avenue, HAZELBROOK, NSW 2779.

Address databases will be updated on receipt of the ‘Notice of Commencement’