Blue Spider Kevin) Kuang

Embed Size (px)

Citation preview

  • 7/31/2019 Blue Spider Kevin) Kuang

    1/3

    Blue Spider OM761 Zhiyun(Kevin) Kuang

    Problem:

    Gary was given the opportunity to be the Project Manager because of his R&D

    background, but he doesnt have the experience or skills to manage a project. Technical

    background itself will not make an efficient project manager.

    Major Issues:

    1. Gary focused too much on R&D works or administrative paper works without abalance.

    2. Error on financial planning.3. No standby schedule when the formal one was interrupted by predictably possible

    changes.4. Lack of communication with the Lord since the beginning which leaded to cost more

    than double time on communication after that.

    5. Gary can not find Gable when he needed support. And Gable intervene the projectseveral times without noticing Gary, which makes the project management works

    more chaos, it leaded to reschedule or re-do works at the last minute.

    Recommendations:

    1. Pauls job is to take most responsibility for the R&D works. Additional staff can takeresponsibility for additional administrative paper works. Gary can spend most of his

    time on managing the whole project through managing other people.2. Discussion with Elliot will be useful before submitting any plan to top managers.3. Make a standby schedule for different stages and hand out to every department with

    the formal schedules. Standby schedule can be made based on slack time or differenttime for specific task.

    4. Meet with Lord at every stage of the project. Can use electronic detailed schedule andtask sheets and update them daily, this will help both parties know where they are andwhere they are going.

    5. Schedule of meeting with Gable is important. Gable, Gary and Paul should work as ateam. Since they already knew there was possibility to change material in the middle

    of the project, they should make appropriate preparation in the beginning, instead ofre-doing everything when changes did happen.

    Limitations:

    1. If there was continue communication problems, Gary might do not have updatedinformation from the R&D or from the administrative works, or both.

    2 Changes in the middle of the project are unavoidable standby schedule can be not

  • 7/31/2019 Blue Spider Kevin) Kuang

    2/3

    Blue Spider Profile

    0 10 20 30 40 50 60 70 80 90 100

    1. Project Mission

    2. Top Management Support

    3. Project Schedule

    4. Client Consultation

    5. Personnel

    6. Technical Tasks

    7. Client Acceptance

    8. Monitoring and Feedback

    9. Communication

    10. Troubleshooting

    Project Success

    Percentile Rankings

  • 7/31/2019 Blue Spider Kevin) Kuang

    3/3

    PIP - Blue Spider Project

    0% 10% 20% 30% 40% 50% 60% 70% 80% 90%

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    Percen

    tileRankings

    Ten Critical Success Factors

    Series1