Boeing North Bridge in Washington State

Gregory A. Banks

Western Bridge Engineers SeminarSeptember 2015

Page 2: Boeing North Bridge in Washington State

2

Project Overview - Location

• Located in Renton, WA

RENTON

PROJECT SITE

Page 3: Boeing North Bridge in Washington State

3

Project Overview – Site Layout

Boeing Company

Lake Washington

Existing Bridge

Page 4: Boeing North Bridge in Washington State

4

Project Overview – Existing Bridge Condition

• Bridge Seismically Deficient • Bridge is on critical path for production • Damage or loss poses economic risk

1940 Construction1969 Construction

Page 5: Boeing North Bridge in Washington State

5

Project Overview – Replacement BridgeGeneral

• 3-Span Continuous (245-feet total length)• Main Span: 134’-0” | End Spans: 55’-6”

Page 6: Boeing North Bridge in Washington State

6

• Prefabricated Bridge Elements– Steel Plate Girders– Full depth precast deck panels– Columns and Crossbeams

Project Overview – Replacement BridgeGeneral

Page 7: Boeing North Bridge in Washington State

7

Project Overview – Replacement BridgeSteel Plate Girders

Page 8: Boeing North Bridge in Washington State

8

Project Overview – Replacement BridgeFull Depth Precast Deck Panels

Page 9: Boeing North Bridge in Washington State

9

Project Overview – Replacement BridgeFull Depth Precast Deck Panels

8’-0”

50’-0”

Page 10: Boeing North Bridge in Washington State

10

Project Overview – Replacement BridgeFull Depth Precast Deck Panels

Page 11: Boeing North Bridge in Washington State

11

Project Overview – Replacement BridgeFull Depth Precast Deck Panels

Page 12: Boeing North Bridge in Washington State

12

Project Overview – Replacement BridgeColumns and Crossbeams

6’-6” Drilled Shafts150-foot length

Page 13: Boeing North Bridge in Washington State

13

Project Overview – Replacement BridgeColumns and Crossbeams

4’-0” Precast Columns

Page 14: Boeing North Bridge in Washington State

14

Project Overview – Replacement BridgeColumns and Crossbeams

Stage 1 – Precast Crossbeam

Page 15: Boeing North Bridge in Washington State

15

Project Overview – Replacement BridgeColumns and Crossbeams

Stage 2 – CIP Crossbeam Infill

Page 16: Boeing North Bridge in Washington State

16

Project Overview – Replacement BridgeColumns and Crossbeams

-StraightPre-tensioning

-DrapedPost-tensioning

SECTION BSECTION A SECTION C

Page 17: Boeing North Bridge in Washington State

17

Project Overview – Replacement BridgeSeismic Resisting Connections

Column to Crossbeam

Column to Shaft

Page 18: Boeing North Bridge in Washington State

18

Project Overview – Replacement BridgeSeismic Resisting Connections

Page 19: Boeing North Bridge in Washington State

19

Project Overview – Replacement BridgeSeismic Resisting Connections

Page 20: Boeing North Bridge in Washington State

20

Why ABC?

• Schedule Savings• Bridge on critical path for 737MAX rollout• Prefabricated elements

– Added float to the construction schedule – Environmental benefits with reduced CIP

concrete over salmon bearing waters

Page 21: Boeing North Bridge in Washington State

21

Construction Constraints/ScheduleEnvironmental

SCHEDULED 737MAX

ROLL-OUT

Page 22: Boeing North Bridge in Washington State

22

1. EXISTING 2. EXISTING + TEMP

3. NEW BRIDGE + TEMP 4. NEW BRIDGE

Construction Constraints/Schedule

Page 23: Boeing North Bridge in Washington State

23

Construction Constraints/ScheduleBoeing Production

Boeing Company

Renton Municipal Airport

Page 24: Boeing North Bridge in Washington State

24

Construction Constraints/ScheduleRenton Airport Height Threshold

Page 25: Boeing North Bridge in Washington State

25

Construction – Change Proposal

• Slow Start-Up– Delayed Permits– Coordination (Airport requiring night work)– Late commissioning of temporary bridge

• Permit Adjustment– Allowed for large cofferdams– Allowed for falsework at Piers 2 & 3– Contractor submitted a no-cost change

proposal to switch substructure to CIP

Page 26: Boeing North Bridge in Washington State

26

Construction – Change Proposal

• Change Proposal Details– Safety Concerns– Quality Concerns– Schedule Concerns

Page 27: Boeing North Bridge in Washington State

27

Construction - Change Proposal

• Safety Concern: Setting of precast crossbeam

Page 28: Boeing North Bridge in Washington State

28

Construction - Change Proposal

• Quality Concern: Grouting, # Joints, Tolerances

Page 29: Boeing North Bridge in Washington State

29

Construction - Change Proposal

• Schedule Concern: Night work with no time savings

Page 30: Boeing North Bridge in Washington State

30

Construction - Change Proposal

• Schedule Concern: Night work with no time savings

• Response:– Several opportunities

for time savings– Crane required

regardless

Page 31: Boeing North Bridge in Washington State

31

Construction - Precast Deck Panels

• Precast Deck Construction Details– UHPC (Ultra High Performance Concrete) – Girder Fabrication and Panel Erection

Page 32: Boeing North Bridge in Washington State

32

Lessons Learned

• Understand Construction Constraints/Risks

• Cost Savings with Standards & Repetition

• Certified PCI Prefabricator Required?

• Required Equipment Size

• Shift in Construction Philosophy

Page 33: Boeing North Bridge in Washington State

33

Questions?

[email protected]

Page 34: Boeing North Bridge in Washington State

34

• Developed for the FHWA Technology Partnership Program

• Culminated in demonstration project completed by WSDOT.

• Marked excellent collaboration between Owner, Researchers, Designers, Precaster, and Contractor

Project Overview – Replacement BridgeSeismic Resisting Connections

Page 35: Boeing North Bridge in Washington State

35

• Final Report• Appendices

A. Design SpecificationsB. Design Example No. 1C. Design Example No. 2

• Testing Report – Spread Footings

• Testing Report – Drilled Shafts

http://www.fhwa.dot.gov/hfl/

Project Overview – Replacement BridgeSeismic Resisting Connections

Page 36: Boeing North Bridge in Washington State

36

• Design Specifications– Formatted in AASHTO Guide Spec Language– Address design with HfL bent details

• Construction Specifications– Material controls– Tolerance control– Recommendations for contract control

Project Overview – Replacement BridgeSeismic Resisting Connections