Boiler Operations and Control

Embed Size (px)

Citation preview

  • 8/2/2019 Boiler Operations and Control

    1/41

    Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    A Course on Thermal Power PlantA Course on Thermal Power Plant

    Prof. P. K. Das

    Professor

    Mechanical EngineeringDepartment

    IIT Kharagpur

  • 8/2/2019 Boiler Operations and Control

    2/41

    Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    A Course on Thermal Power PlantA Course on Thermal Power Plant

    2

    Boiler Operations

    Objectives of boiler operations:

    Satisfy the current power demand according tothe load curve Ensure the highest service life Ensure highest efficiency of the boiler plant

  • 8/2/2019 Boiler Operations and Control

    3/41

    Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    A Course on Thermal Power PlantA Course on Thermal Power Plant

    3

    Operation procedures depend on

    Type of system Circulating, Once through Coal fired, Gas fired, Oil fired Stokers System, Pulverized Fuel System

    Applications

    Power, Process Utility Size

    Todays operation principle depends on; sensor technology,

    control software, improved design of generator orhardware

    A balance is sought between best equipmentperformance with safety requirements and

  • 8/2/2019 Boiler Operations and Control

    4/41

    Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    A Course on Thermal Power PlantA Course on Thermal Power Plant

    4

    Fundamental Principles:In spite of massive developments in boilerdesign and power production basic operatingprinciples till applyCombustion safety and proper steam/water

    cooling of boiler parts are essential

    History of accidents:

    Accident due to high pressure, accident infurnace

  • 8/2/2019 Boiler Operations and Control

    5/41

    Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    A Course on Thermal Power PlantA Course on Thermal Power Plant

  • 8/2/2019 Boiler Operations and Control

    6/41

    Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    A Course on Thermal Power PlantA Course on Thermal Power Plant

    ASME CODES

    1884 Code for the Conduct of Trials of Steam Boilers first Performance

    Test Code

    1911 Establishment of a committee to propose a Boiler code

    1956 Committee established for ASME Pressure Vessel Code for Nuclear

    Age

    1963 Proposed Section III (Nuclear Power) of ASME Boiler and Pressure

    Vessel Committee

    1983 ASME Boiler and Pressure Vessel Code published in bothconventional and metric units

    1989 Boiler and Pressure Vessel Code published on CD-ROM

  • 8/2/2019 Boiler Operations and Control

    7/41Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    A Course on Thermal Power PlantA Course on Thermal Power Plant

    Combustion Safety and Steam/water cooling Requirements

    Purging Before firing a furnace there must be no lingering

    combustible materials inside the unit

    Purging ensures furnace is ready for firing

    Standard Operating Rule for Multi-burners - No less than 25%

    of maximum continuous rating (MCR) mass air flow for at

    least 5 Minutes

  • 8/2/2019 Boiler Operations and Control

    8/41Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    A Course on Thermal Power PlantA Course on Thermal Power Plant

    8

    Once combustion is established, Correct air/fuel ratio must be maintained Insufficient air flow forms pockets ofcombustible gas- Potential for explosion Sufficient air flow with a small amount ofexcess air- covers imperfect mixing, promotes

    good air and fuel distribution Over fire air (OFA) ports installed in the uppercombustion zone of furnaces- emission reduction Controlled introduction of combustion air does

    not eliminate the need of excess air for safetyIt is important to verify the boiler water levels Combustion should never be established untiladequate cooling water is in the tubes and thesteam drum, particularly in NCB

    Or minimum flow rate is there in once

  • 8/2/2019 Boiler Operations and Control

    9/41Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    A Course on Thermal Power PlantA Course on Thermal Power Plant

    9

    General Safety Consideration: Pressure for failure- A major concern and commonfeature in the boiler industry all over the world Codes by ASME, National Board of Boiler andPressure Vessel Inspectors, Other Licensing andInspecting Authorities have issued extensive codes

    to minimize such failures Codes are continuously updated

    Safety Attentions to be paid to combustion products-CO2, CO, SO2 Chlorine compounds

    CO2 reduces O2 availability in the flue gas SO2 forms acids when breadth into the lungs

    Chlorine compounds can form HCl acids orCarcinogens such as de-oxine

  • 8/2/2019 Boiler Operations and Control

    10/41Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    A Course on Thermal Power PlantA Course on Thermal Power Plant

    10

    Enough safe guards to be taken for maintenanceand work on out-of-service boilers Confined space- Insufficient Oxygen Insufficient Lighting Ash accumulation high temperature andother health hazards

    Safety of fuel ash should be considered

    Ashes contain:Hazardous materials- Heavy metals, ArsenicResidual combustion may continue in ashcollected in hoppers

    Carbon- In -ash characteristics may be alteredunder low Nox firing configurations

  • 8/2/2019 Boiler Operations and Control

    11/41Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    A Course on Thermal Power PlantA Course on Thermal Power Plant

    11

    Operator Requirements:Good operation begin before equipmentinstallation is complete

    Training of operators Preparation of equipments

    Every operator should have a knowledge of all

    components Functions Design Limitations and relationship to other

    componentsthrough inspection of the equipments, studying,drawing and instructionsDistributed control system (DCS) integrates theindividual process controllers

  • 8/2/2019 Boiler Operations and Control

    12/41Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    A Course on Thermal Power PlantA Course on Thermal Power Plant

    12

    Simulator Training Offer real time environment

    Working understanding of the various steam generationsystem Reaction time and the rate of the equipment Can be combined with simulated equipment failures andwhat-if-events simulators

    Preparation for Start Up:Systematic approach is required for the installation of thenew boiler or when any boiler has undergone majorrepairs or alterationsThe steps are

    Inspection Cleaning Hydrostatic tests Pre calibration of instruments and controls Auxiliary equipment preparations Chemical cleaning

    Steam line cleaning (Blowing)

  • 8/2/2019 Boiler Operations and Control

    13/41Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    A Course on Thermal Power PlantA Course on Thermal Power Plant

    13

    Inspection: Familiarizes the operator with the equipments

    Verifies condition of the equipments Provision or lack of provision for expansion (Thermaland pressure) should be carefully checked Temporary braces, hangers, ties needed forconstructions should be removed

    Cleaning:Collection of debris, foreign materials duringtransport, storage, erection and repair

    Accumulated debris chokes the water line Alters gas or air flows May ignite at elevated temperature

    Special attention should be given for the cleaning of

    oil and gas lines, burnersSteam cleaning is recommended for all oil and gas

    A C Th l P Pl

  • 8/2/2019 Boiler Operations and Control

    14/41Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    A Course on Thermal Power PlantA Course on Thermal Power Plant

    14

    Hydrostatic test is conducted first time in new boilers fillingit with waterWater with high level of purity to prevent internal foulingand corrosionsDemineralized water with 10 ppm of ammonia for pH control

    and 500ppm of hydrazine for the control of oxygen shouldbe used for all non drainable reheaters and superheatersClean filtered water is suitable for components that will bedrained immediately after the test ASME code suggests water temperature of 210C but itshould never be higher than 560C No air should be trapped during the test

    Hydrostatic Test: To be conducted after the pressure parts are assembled

    but before the refractory and casing are installed 1.5 times the boiler design pressure is applied to allpressure parts Pressure is maintained for sufficient time to detect leaks Testing is equally important following pressure part

    replacement

    A C Th l P PlA C Th l P Pl t

  • 8/2/2019 Boiler Operations and Control

    15/41Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    A Course on Thermal Power PlantA Course on Thermal Power Plant

    15

    Instrumentations and Controls:Natural Circulation Boilers-

    water/steam pressure gauge Water level gauge glass Temperature gauge if superheated are used

    Once through type boilers- steam pressure gauge flow meter temperature indicator

    operation should not been attended without calibrationcalibration should include corrections in the actualworking range

    Most modern boilers are controlled automatically oncethey are fully commissionedBefore start up controls must be operated manually untilautomatic controls have been adjusted for site specific

    conditions

    A C Th l P Pl tA C Th l P Pl t

  • 8/2/2019 Boiler Operations and Control

    16/41Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    A Course on Thermal Power PlantA Course on Thermal Power Plant

    16

    Auxiliary Equipments:

    Fan feed water pumps fuel equipments air heaters

    economizer ash removal equipment drain system to drain the boiler shoot blowing system for clearing heattransfer surfaces

    post combustion environmental controlequipments

    Auxiliary equipments must also be prepared

    for operations

    A C Th l P Pl tA C Th l P Pl t

  • 8/2/2019 Boiler Operations and Control

    17/41Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    A Course on Thermal Power PlantA Course on Thermal Power Plant

    17

    Chemical Cleaning:Lack of water side cleanliness can lead to

    Boiler tube failure Carry over of solids in the steam- failure ofsuperheaters and turbine blade

    damage

    Flashing of all lose debris from feed water system andboiler and use of high quality water for hydrostatic testmust be supplemented by proper water side cleaning beforestart up. It removes grease paints oilNatural circulation boiler is given caustic and phosphateboil out after the feed water system is given a phosphateflush

    After flashing out products of corrosion is still remain inthe form of iron oxide and mill scaleAcid cleaning is recommended for scale removal

    A C Th l P Pl tA Course on Thermal Power Plant

  • 8/2/2019 Boiler Operations and Control

    18/41Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    A Course on Thermal Power PlantA Course on Thermal Power Plant

    18

    Steam line blowing:Cleaning steam lines of loose solid particle and mill scale is

    essential for protecting the turbine blades

    Fine mesh strainers in turbine inlet prevents turbineblades and valves from scale and the other solid materials High velocity steam cleaning before coupling the steam

    line to the turbine Temporary piping for flow bypass to the atmosphere

    Several Methods for blowing steam linesHigh velocity air and steam mixture removes loose scale

    due to temperature shock and velocity effectSufficient shock is obtained with a series of blows byvarying steam temperature

    Source of steam for blowing: High pressure steam from boiler Steam from flush tank for forced circulation unit A Course on Thermal Power PlantA Course on Thermal Power Plant

  • 8/2/2019 Boiler Operations and Control

    19/41Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    A Course on Thermal Power PlantA Course on Thermal Power Plant

    19

    Safety Valves: The set point of each safety valve should be

    checked and adjusted after reaching the fulloperating pressure first time Safety valves seats are susceptible to damagefrom wet steam and grit. Cleaning of boiler and steam blowing should bedone before testing safety valves

    Testing of safety valves always requires cautionValve exhaust piping and vent piping should not

    exert any excessive forces on the safety valve. Gagsshould always be used while making adjustment tothe valves

    Alternately, they can be tested with boiler pressure

    below the design pressure with a hydraulic liftattached to the valve steam. This will reduce the

    A Course on Thermal Power PlantA Course on Thermal Power Plant

  • 8/2/2019 Boiler Operations and Control

    20/41Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    A Course on Thermal Power PlantA Course on Thermal Power Plant

    20

    Start up:

    Objectives to be included in all operating procedureof every boiler,1. Protection of pressure parts against corrosion,over healing and thermal stress.

    2. Prevention of furnace explosions.

    3. Production of stream at desired temperature,pressure and purity.

    4. Compliance with environmental regulations.

    Filling

    High quality water to be used for fillingTemperature of the water is controlled to reducetemperature differential (< 56C)

    Air venting assure complete filling, reduceoxygen corrosion

    Correct water level in drum type boilers. At cold

    A Course on Thermal Power PlantA Course on Thermal Power Plant

  • 8/2/2019 Boiler Operations and Control

    21/41

    Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    A Course on Thermal Power PlantA Course on Thermal Power Plant

    21

    CirculationCertain amount of circulation is needed to avoidoverheating of the pressure parts. Gradualincrease in firing rate can achieve this in NCBIn case of once through boiler the turbines should

    be by passed still the steaming rate is reached.

    PurgingCaution against furnace explosion.Burning fuel in suspension is more vulnerable.

    Most explosions during start up and low load.Accumulation of combustible gases or dirt is to be

    avoidedBurners to be lighted only after a thorough

    purging.Purging rate should be at least 25% of the full air

    A Course on Thermal Power PlantA Course on Thermal Power Plant

  • 8/2/2019 Boiler Operations and Control

    22/41

    Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    A Course on Thermal Power PlantA Course on Thermal Power Plant

    22

    Protection of economizerDuring pressure rising period amount of water is

    very littleNo feed water flow through the economizer steam

    formed in them can remain trapped. Makes drumlevel control difficult, produces water hammer.To overcome this, difficulty feed water should be

    supplied continuously by venting the economizer orby re-circulating through the economizer.Protection of primary, secondary and reheat

    super-heaters

    During start up before stream flow through eachtube combustion gas temperature is to becontrolled.Maximum metal temperature: Carbon steel-

    482C

    Alloy steel- 510C-538C

    A Course on Thermal Power PlantA Course on Thermal Power Plant

  • 8/2/2019 Boiler Operations and Control

    23/41

    Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    A Course on Thermal Power PlantA Course on Thermal Power Plant

    23

    It should be ensured that water flow througheach section and total stream flow > 10% of the

    rated flow.Water should be drained from drainable parts or

    should be boiled off.No steam flow through partially filled tubes.Super-heaters adjacent to side walls and division

    wall are subjected to late boil-of. Theirtemperature should be monitored.

    A Course on Thermal Power PlantA Course on Thermal Power Plant

  • 8/2/2019 Boiler Operations and Control

    24/41

    Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    A Course on Thermal Power PlantA Course on Thermal Power Plant

    24

    Protection of drums and headers:In most cases start up time time to raise pressure

    and to protect super headers from thermal stress.In some case start up and shut down time time

    required to limit stress in drum headers

    Drum & headers made of rolled tube joints thin

    section quick contraction expansion tube seat leakTemperature rise should be controlled. 56C/hr. Largetemperature differential in the tube headers to beavoided.Tubes connected to drum have water below and steam

    at the top. Allowable temperature difference should beselected based on drum material.Additional inside and outside temperature of the

    drums should be monitored.There are two periods when steam at the top of drum

    is hotter than water in the lower half

    Soon after firing begins

    A Course on Thermal Power PlantA Course on Thermal Power Plant

  • 8/2/2019 Boiler Operations and Control

    25/41

    Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    A Course on Thermal Power PlantA Course on Thermal Power Plant

    25

    Steam drum temperature can be equalized by flooding thedrum with water

    Operating Techniques for maximum Efficiency Fuel is the major cost Minimize fuel consumption and maximize steamgeneration Boiler efficiency depends on design It can be maintained by reducing loss in stackand ash pit

    Stack Loss: Heat loss depends on mass flow rate and temperature of

    flue gas Mass flow rate depends on mass of fuel+ excess air Excess air should be controlled efficiency Temperature of the flue gas affected by cleanliness ofboiler and heat transfer

    surfaces Pro er o eration of soot blower and air heater

    A Course on Thermal Power PlantA Course on Thermal Power Plant

  • 8/2/2019 Boiler Operations and Control

    26/41

    Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    A Course on Thermal Power PlantA Course on Thermal Power Plant

    26

    Pressure and Temperatures: Pressure and temperatures are unique parameters for the

    turbine output or process requirement Deviation from set point indicate loss of efficiency

    For Power generation, modern controllers adjust the supplytemperature to turbine within 60C

    Each 280

    C reduction in temperature reduces plant efficiencyby 1% in supercritical units

    Variable pressure operation is another option forincreasing efficiency Can improve cycle efficiency at low loads Boiler pressure can be varied to meet the turbinerequirements- slow dynamics

    For fast response throttle valve control is used. Boilerpressure is increased in the next instant.

    Emission Requirements:

    A Course on Thermal Power PlantA Course on Thermal Power Plant

  • 8/2/2019 Boiler Operations and Control

    27/41

    Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    A Course on Thermal Power PlantA Course on Thermal Power Plant

    27

    To ensure minimum ammonia usage, thegeneration of NO

    xby combustion should be

    controlled.Trade off between NO

    xgeneration and

    increase in CO and un-burnt carbon in ash to bemadeCombustion operation

    Modern distributed control systemrequires more information and analysis.Closed loop neural network and other intelligentcontrol techniques are used.

    Special attention to be paid to the followingpoints

    A Course on Thermal Power PlantA Course on Thermal Power Plant

  • 8/2/2019 Boiler Operations and Control

    28/41

    Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    A Course on Thermal Power PlantA Course on Thermal Power Plant

    28

    Burner adjustmentsBurner adjustments not only affect the

    performance of the said unit but also theperformance of the other burners.

    All the burners should be identical. All the burners should be equallyadjusted.

    Burners should be adjusted toincrease turbulence Increased air-fuel mixing Increased combustion intensity

    Faster heat release Lesser demand for excess air Lesser un-burned carbon But it also amounts to

    Increased NOx formation

    Higher fan power requirement

    A Course on Thermal Power PlantA Course on Thermal Power Plant

  • 8/2/2019 Boiler Operations and Control

    29/41

    Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    A Course on Thermal Power Plant

    29

    Overfire air (OFA) port adjustment

    For NOx reduction burners are usuallyoperated with less than theoretical air forcomplete combustion.The remaining air needed for completingcombustion is introduced separately abovehighest burner zone. The OFA is typicallyvaried as a function of load based on testsconducted during commissioning.Adjustment is needed if type of fuel is

    altered.

    Excess Air Total combustion air by adjusting FD and ID fan dampers

    Excess air gives combustion intensity, reduced carbon loss and COformation

    Reduced slag formation Increased fan power Increased stack loss Increased tube erosion and possibly increased NOx formation

    A Course on Thermal Power PlantA Course on Thermal Power Plant

  • 8/2/2019 Boiler Operations and Control

    30/41

    Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur 30

    Abnormal Operations: Low Water

    In case water level falls below the prescribed minimum,fuel firing should be stopped Caution should be taken while adding water to avoidtemperature shock Water should be added periodically with soak timesprovided to allow drum temperature to equalize Thermocouple readings from the top and bottom of thedrum should be taken time to time to control the process ofcleaningTube Failure: Operating a boiler with a known tube leak is not

    recommended Steam or water escaping from a small leak can cut othertubes by impingement and set up a chain reaction of tubefailures Loss of water and steam alters boiler circulations- over

    heating For this furnace risers of once throu h t e of boilers

    A Course on Thermal Power PlantA Course on Thermal Power Plant

  • 8/2/2019 Boiler Operations and Control

    31/41

    Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur 31

    Detection of Tube failures:

    Unusual rise in temperature of furnacerisers Abnormal loss of water from the system Loss of chemical from a drum type boiler Sound made by the leak Boilers should be shut down as soon asnormal operating procedures permit after aleak A leak is then detect by hydrostatic

    testing

    A thorough inspection is needed after a tubefailure is located. It includes

    a visual inspection of the failed tube laboratory analysis Background information like locations offailure, length of time the unit is in operation,

    load conditions start up and shut down

    A Course on Thermal Power PlantA Course on Thermal Power Plant

  • 8/2/2019 Boiler Operations and Control

    32/41

    Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur 32

    Shut Down Operations:Boiler shut down is less complicated than start upEmphasis is on safety and protection of equipment

    Two shut down situations: Control shut down shut down in an emergency

    Control shut down: Firing rate is gradually reduced. Fuel is shut off when combustion equipments at itsminimum capacity

    Boiler is purged with afresh air If some pressure is to be maintained, the fans areshut down and the dampers are closed Drum pressures are gradually lower as heat is loss

    from the boiler setting Minimal amount of air drifts out of the stack

    A Course on Thermal Power PlantA Course on Thermal Power Plant

  • 8/2/2019 Boiler Operations and Control

    33/41

    Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur 33

    Emergency Shut Down:

    Fuel is immediately shut offBoiler is purged of combustible gases

    Additional procedure may apply to the fuel feed

    equipment

    Boiler may be held at a reduced pressure or may becompletely cooled as described above

    A Course on Thermal Power PlantA Course on Thermal Power Plant

  • 8/2/2019 Boiler Operations and Control

    34/41

    Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    Different Control Strategies for Steam Generation

    Boiler following control system

    Boiler follows the turbine response

    MW load control is the responsibility

    of the turbine-generator

    Boiler is assigned the secondary

    responsibility of throttle control

    Load change repositions turbine

    control valve

    Boiler control modifies firing rate and

    restores throttle pressure

    It has a rapid load response storedenergy in the boiler provides the initial

    change in load

    Less stable throttle control

    A Course on Thermal Power PlantA Course on Thermal Power Plant

  • 8/2/2019 Boiler Operations and Control

    35/41

    Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    Turbine follows the boiler response

    MW load control is the responsibility of

    the boiler

    T-G is assigned the secondary

    responsibility of throttle control

    With load change boiler control

    increases the firing rate, this increases

    the throttle pressure.

    To maintain the throttle pressure,turbine control valve open increasing

    Megawatt output.It provides minimal steam pressure and

    temperature fluctuations during a load

    change

    Turbine following control system

    A Course on Thermal Power PlantA Course on Thermal Power Plant

  • 8/2/2019 Boiler Operations and Control

    36/41

    Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    Coordinated-boiler turbine generator control system

    A Course on Thermal Power PlantA Course on Thermal Power Plant

  • 8/2/2019 Boiler Operations and Control

    37/41

    Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    Coordinated boiler turbine control

    Both of the above systems can provide satisfactorily control the boiler

    operations but have inherent disadvantages

    None of them can fully exploit the capabilities of both the boiler and

    turbine generators

    The two control options can be combined to do so

    boiler is not capable of producing rapid changes in steam generationat constant pressure

    Turbine is used to provide the initial load response

    For a change in load throttle pressure set point is modified using MW

    error (demand)

    Turbine control valve responds to this change in set point and give the

    new load quickly

    Boiler modifies the firing rate to reach new load and restore throttle

    pressure

    A Course on Thermal Power PlantA Course on Thermal Power Plant

  • 8/2/2019 Boiler Operations and Control

    38/41

    Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    The throttle pressure set point returns to its normal value

    The result is fast and efficient production of electric power by a proper

    coordination between the boiler and turbine

    The response is much faster than turbine following system

    But not as fast as boiler following system because the effect of MW error is

    limited to maintain a balance between boiler response and stability

    Wider limits would provide a faster response but a narrower limit will give

    more stability

    A Course on Thermal Power PlantA Course on Thermal Power Plant

  • 8/2/2019 Boiler Operations and Control

    39/41

    Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    A Course on Thermal Power PlantA Course on Thermal Power Plant

    Turbine3000 rpm

  • 8/2/2019 Boiler Operations and Control

    40/41

    Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur

    Pl

    S

    H

    R

    H

    R

    H

    F

    S

    H

    Eco

    PSH

    147Kg/cm25400C

    Generator

    TransformerGenerator

    Boiler

    Coal Bunkers

    Primary Air Fans

    Coal

    Mills

    Raw

    Coal Fdr

    Chimne

    y

    Flue Gas Duct

    Induced Draft Fan

    Coal

    Conveyer

    SECL

    Coal

    Bunker

    CSEB Crusher

    House

    400/220 KV

    15.75KV

    Condenser

    Coal Handling Plant

    Boiler

    Drum

    3000 rpm

    210MW

    ESPESP

    AH

    A Course on Thermal Power PlantA Course on Thermal Power Plant

  • 8/2/2019 Boiler Operations and Control

    41/41