Upload
durgeshsharma2
View
253
Download
0
Embed Size (px)
Citation preview
8/2/2019 Boiler Operations and Control
1/41
Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
A Course on Thermal Power PlantA Course on Thermal Power Plant
Prof. P. K. Das
Professor
Mechanical EngineeringDepartment
IIT Kharagpur
8/2/2019 Boiler Operations and Control
2/41
Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
A Course on Thermal Power PlantA Course on Thermal Power Plant
2
Boiler Operations
Objectives of boiler operations:
Satisfy the current power demand according tothe load curve Ensure the highest service life Ensure highest efficiency of the boiler plant
8/2/2019 Boiler Operations and Control
3/41
Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
A Course on Thermal Power PlantA Course on Thermal Power Plant
3
Operation procedures depend on
Type of system Circulating, Once through Coal fired, Gas fired, Oil fired Stokers System, Pulverized Fuel System
Applications
Power, Process Utility Size
Todays operation principle depends on; sensor technology,
control software, improved design of generator orhardware
A balance is sought between best equipmentperformance with safety requirements and
8/2/2019 Boiler Operations and Control
4/41
Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
A Course on Thermal Power PlantA Course on Thermal Power Plant
4
Fundamental Principles:In spite of massive developments in boilerdesign and power production basic operatingprinciples till applyCombustion safety and proper steam/water
cooling of boiler parts are essential
History of accidents:
Accident due to high pressure, accident infurnace
8/2/2019 Boiler Operations and Control
5/41
Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
A Course on Thermal Power PlantA Course on Thermal Power Plant
8/2/2019 Boiler Operations and Control
6/41
Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
A Course on Thermal Power PlantA Course on Thermal Power Plant
ASME CODES
1884 Code for the Conduct of Trials of Steam Boilers first Performance
Test Code
1911 Establishment of a committee to propose a Boiler code
1956 Committee established for ASME Pressure Vessel Code for Nuclear
Age
1963 Proposed Section III (Nuclear Power) of ASME Boiler and Pressure
Vessel Committee
1983 ASME Boiler and Pressure Vessel Code published in bothconventional and metric units
1989 Boiler and Pressure Vessel Code published on CD-ROM
8/2/2019 Boiler Operations and Control
7/41Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
A Course on Thermal Power PlantA Course on Thermal Power Plant
Combustion Safety and Steam/water cooling Requirements
Purging Before firing a furnace there must be no lingering
combustible materials inside the unit
Purging ensures furnace is ready for firing
Standard Operating Rule for Multi-burners - No less than 25%
of maximum continuous rating (MCR) mass air flow for at
least 5 Minutes
8/2/2019 Boiler Operations and Control
8/41Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
A Course on Thermal Power PlantA Course on Thermal Power Plant
8
Once combustion is established, Correct air/fuel ratio must be maintained Insufficient air flow forms pockets ofcombustible gas- Potential for explosion Sufficient air flow with a small amount ofexcess air- covers imperfect mixing, promotes
good air and fuel distribution Over fire air (OFA) ports installed in the uppercombustion zone of furnaces- emission reduction Controlled introduction of combustion air does
not eliminate the need of excess air for safetyIt is important to verify the boiler water levels Combustion should never be established untiladequate cooling water is in the tubes and thesteam drum, particularly in NCB
Or minimum flow rate is there in once
8/2/2019 Boiler Operations and Control
9/41Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
A Course on Thermal Power PlantA Course on Thermal Power Plant
9
General Safety Consideration: Pressure for failure- A major concern and commonfeature in the boiler industry all over the world Codes by ASME, National Board of Boiler andPressure Vessel Inspectors, Other Licensing andInspecting Authorities have issued extensive codes
to minimize such failures Codes are continuously updated
Safety Attentions to be paid to combustion products-CO2, CO, SO2 Chlorine compounds
CO2 reduces O2 availability in the flue gas SO2 forms acids when breadth into the lungs
Chlorine compounds can form HCl acids orCarcinogens such as de-oxine
8/2/2019 Boiler Operations and Control
10/41Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
A Course on Thermal Power PlantA Course on Thermal Power Plant
10
Enough safe guards to be taken for maintenanceand work on out-of-service boilers Confined space- Insufficient Oxygen Insufficient Lighting Ash accumulation high temperature andother health hazards
Safety of fuel ash should be considered
Ashes contain:Hazardous materials- Heavy metals, ArsenicResidual combustion may continue in ashcollected in hoppers
Carbon- In -ash characteristics may be alteredunder low Nox firing configurations
8/2/2019 Boiler Operations and Control
11/41Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
A Course on Thermal Power PlantA Course on Thermal Power Plant
11
Operator Requirements:Good operation begin before equipmentinstallation is complete
Training of operators Preparation of equipments
Every operator should have a knowledge of all
components Functions Design Limitations and relationship to other
componentsthrough inspection of the equipments, studying,drawing and instructionsDistributed control system (DCS) integrates theindividual process controllers
8/2/2019 Boiler Operations and Control
12/41Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
A Course on Thermal Power PlantA Course on Thermal Power Plant
12
Simulator Training Offer real time environment
Working understanding of the various steam generationsystem Reaction time and the rate of the equipment Can be combined with simulated equipment failures andwhat-if-events simulators
Preparation for Start Up:Systematic approach is required for the installation of thenew boiler or when any boiler has undergone majorrepairs or alterationsThe steps are
Inspection Cleaning Hydrostatic tests Pre calibration of instruments and controls Auxiliary equipment preparations Chemical cleaning
Steam line cleaning (Blowing)
8/2/2019 Boiler Operations and Control
13/41Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
A Course on Thermal Power PlantA Course on Thermal Power Plant
13
Inspection: Familiarizes the operator with the equipments
Verifies condition of the equipments Provision or lack of provision for expansion (Thermaland pressure) should be carefully checked Temporary braces, hangers, ties needed forconstructions should be removed
Cleaning:Collection of debris, foreign materials duringtransport, storage, erection and repair
Accumulated debris chokes the water line Alters gas or air flows May ignite at elevated temperature
Special attention should be given for the cleaning of
oil and gas lines, burnersSteam cleaning is recommended for all oil and gas
A C Th l P Pl
8/2/2019 Boiler Operations and Control
14/41Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
A Course on Thermal Power PlantA Course on Thermal Power Plant
14
Hydrostatic test is conducted first time in new boilers fillingit with waterWater with high level of purity to prevent internal foulingand corrosionsDemineralized water with 10 ppm of ammonia for pH control
and 500ppm of hydrazine for the control of oxygen shouldbe used for all non drainable reheaters and superheatersClean filtered water is suitable for components that will bedrained immediately after the test ASME code suggests water temperature of 210C but itshould never be higher than 560C No air should be trapped during the test
Hydrostatic Test: To be conducted after the pressure parts are assembled
but before the refractory and casing are installed 1.5 times the boiler design pressure is applied to allpressure parts Pressure is maintained for sufficient time to detect leaks Testing is equally important following pressure part
replacement
A C Th l P PlA C Th l P Pl t
8/2/2019 Boiler Operations and Control
15/41Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
A Course on Thermal Power PlantA Course on Thermal Power Plant
15
Instrumentations and Controls:Natural Circulation Boilers-
water/steam pressure gauge Water level gauge glass Temperature gauge if superheated are used
Once through type boilers- steam pressure gauge flow meter temperature indicator
operation should not been attended without calibrationcalibration should include corrections in the actualworking range
Most modern boilers are controlled automatically oncethey are fully commissionedBefore start up controls must be operated manually untilautomatic controls have been adjusted for site specific
conditions
A C Th l P Pl tA C Th l P Pl t
8/2/2019 Boiler Operations and Control
16/41Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
A Course on Thermal Power PlantA Course on Thermal Power Plant
16
Auxiliary Equipments:
Fan feed water pumps fuel equipments air heaters
economizer ash removal equipment drain system to drain the boiler shoot blowing system for clearing heattransfer surfaces
post combustion environmental controlequipments
Auxiliary equipments must also be prepared
for operations
A C Th l P Pl tA C Th l P Pl t
8/2/2019 Boiler Operations and Control
17/41Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
A Course on Thermal Power PlantA Course on Thermal Power Plant
17
Chemical Cleaning:Lack of water side cleanliness can lead to
Boiler tube failure Carry over of solids in the steam- failure ofsuperheaters and turbine blade
damage
Flashing of all lose debris from feed water system andboiler and use of high quality water for hydrostatic testmust be supplemented by proper water side cleaning beforestart up. It removes grease paints oilNatural circulation boiler is given caustic and phosphateboil out after the feed water system is given a phosphateflush
After flashing out products of corrosion is still remain inthe form of iron oxide and mill scaleAcid cleaning is recommended for scale removal
A C Th l P Pl tA Course on Thermal Power Plant
8/2/2019 Boiler Operations and Control
18/41Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
A Course on Thermal Power PlantA Course on Thermal Power Plant
18
Steam line blowing:Cleaning steam lines of loose solid particle and mill scale is
essential for protecting the turbine blades
Fine mesh strainers in turbine inlet prevents turbineblades and valves from scale and the other solid materials High velocity steam cleaning before coupling the steam
line to the turbine Temporary piping for flow bypass to the atmosphere
Several Methods for blowing steam linesHigh velocity air and steam mixture removes loose scale
due to temperature shock and velocity effectSufficient shock is obtained with a series of blows byvarying steam temperature
Source of steam for blowing: High pressure steam from boiler Steam from flush tank for forced circulation unit A Course on Thermal Power PlantA Course on Thermal Power Plant
8/2/2019 Boiler Operations and Control
19/41Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
A Course on Thermal Power PlantA Course on Thermal Power Plant
19
Safety Valves: The set point of each safety valve should be
checked and adjusted after reaching the fulloperating pressure first time Safety valves seats are susceptible to damagefrom wet steam and grit. Cleaning of boiler and steam blowing should bedone before testing safety valves
Testing of safety valves always requires cautionValve exhaust piping and vent piping should not
exert any excessive forces on the safety valve. Gagsshould always be used while making adjustment tothe valves
Alternately, they can be tested with boiler pressure
below the design pressure with a hydraulic liftattached to the valve steam. This will reduce the
A Course on Thermal Power PlantA Course on Thermal Power Plant
8/2/2019 Boiler Operations and Control
20/41Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
A Course on Thermal Power PlantA Course on Thermal Power Plant
20
Start up:
Objectives to be included in all operating procedureof every boiler,1. Protection of pressure parts against corrosion,over healing and thermal stress.
2. Prevention of furnace explosions.
3. Production of stream at desired temperature,pressure and purity.
4. Compliance with environmental regulations.
Filling
High quality water to be used for fillingTemperature of the water is controlled to reducetemperature differential (< 56C)
Air venting assure complete filling, reduceoxygen corrosion
Correct water level in drum type boilers. At cold
A Course on Thermal Power PlantA Course on Thermal Power Plant
8/2/2019 Boiler Operations and Control
21/41
Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
A Course on Thermal Power PlantA Course on Thermal Power Plant
21
CirculationCertain amount of circulation is needed to avoidoverheating of the pressure parts. Gradualincrease in firing rate can achieve this in NCBIn case of once through boiler the turbines should
be by passed still the steaming rate is reached.
PurgingCaution against furnace explosion.Burning fuel in suspension is more vulnerable.
Most explosions during start up and low load.Accumulation of combustible gases or dirt is to be
avoidedBurners to be lighted only after a thorough
purging.Purging rate should be at least 25% of the full air
A Course on Thermal Power PlantA Course on Thermal Power Plant
8/2/2019 Boiler Operations and Control
22/41
Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
A Course on Thermal Power PlantA Course on Thermal Power Plant
22
Protection of economizerDuring pressure rising period amount of water is
very littleNo feed water flow through the economizer steam
formed in them can remain trapped. Makes drumlevel control difficult, produces water hammer.To overcome this, difficulty feed water should be
supplied continuously by venting the economizer orby re-circulating through the economizer.Protection of primary, secondary and reheat
super-heaters
During start up before stream flow through eachtube combustion gas temperature is to becontrolled.Maximum metal temperature: Carbon steel-
482C
Alloy steel- 510C-538C
A Course on Thermal Power PlantA Course on Thermal Power Plant
8/2/2019 Boiler Operations and Control
23/41
Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
A Course on Thermal Power PlantA Course on Thermal Power Plant
23
It should be ensured that water flow througheach section and total stream flow > 10% of the
rated flow.Water should be drained from drainable parts or
should be boiled off.No steam flow through partially filled tubes.Super-heaters adjacent to side walls and division
wall are subjected to late boil-of. Theirtemperature should be monitored.
A Course on Thermal Power PlantA Course on Thermal Power Plant
8/2/2019 Boiler Operations and Control
24/41
Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
A Course on Thermal Power PlantA Course on Thermal Power Plant
24
Protection of drums and headers:In most cases start up time time to raise pressure
and to protect super headers from thermal stress.In some case start up and shut down time time
required to limit stress in drum headers
Drum & headers made of rolled tube joints thin
section quick contraction expansion tube seat leakTemperature rise should be controlled. 56C/hr. Largetemperature differential in the tube headers to beavoided.Tubes connected to drum have water below and steam
at the top. Allowable temperature difference should beselected based on drum material.Additional inside and outside temperature of the
drums should be monitored.There are two periods when steam at the top of drum
is hotter than water in the lower half
Soon after firing begins
A Course on Thermal Power PlantA Course on Thermal Power Plant
8/2/2019 Boiler Operations and Control
25/41
Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
A Course on Thermal Power PlantA Course on Thermal Power Plant
25
Steam drum temperature can be equalized by flooding thedrum with water
Operating Techniques for maximum Efficiency Fuel is the major cost Minimize fuel consumption and maximize steamgeneration Boiler efficiency depends on design It can be maintained by reducing loss in stackand ash pit
Stack Loss: Heat loss depends on mass flow rate and temperature of
flue gas Mass flow rate depends on mass of fuel+ excess air Excess air should be controlled efficiency Temperature of the flue gas affected by cleanliness ofboiler and heat transfer
surfaces Pro er o eration of soot blower and air heater
A Course on Thermal Power PlantA Course on Thermal Power Plant
8/2/2019 Boiler Operations and Control
26/41
Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
A Course on Thermal Power PlantA Course on Thermal Power Plant
26
Pressure and Temperatures: Pressure and temperatures are unique parameters for the
turbine output or process requirement Deviation from set point indicate loss of efficiency
For Power generation, modern controllers adjust the supplytemperature to turbine within 60C
Each 280
C reduction in temperature reduces plant efficiencyby 1% in supercritical units
Variable pressure operation is another option forincreasing efficiency Can improve cycle efficiency at low loads Boiler pressure can be varied to meet the turbinerequirements- slow dynamics
For fast response throttle valve control is used. Boilerpressure is increased in the next instant.
Emission Requirements:
A Course on Thermal Power PlantA Course on Thermal Power Plant
8/2/2019 Boiler Operations and Control
27/41
Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
A Course on Thermal Power PlantA Course on Thermal Power Plant
27
To ensure minimum ammonia usage, thegeneration of NO
xby combustion should be
controlled.Trade off between NO
xgeneration and
increase in CO and un-burnt carbon in ash to bemadeCombustion operation
Modern distributed control systemrequires more information and analysis.Closed loop neural network and other intelligentcontrol techniques are used.
Special attention to be paid to the followingpoints
A Course on Thermal Power PlantA Course on Thermal Power Plant
8/2/2019 Boiler Operations and Control
28/41
Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
A Course on Thermal Power PlantA Course on Thermal Power Plant
28
Burner adjustmentsBurner adjustments not only affect the
performance of the said unit but also theperformance of the other burners.
All the burners should be identical. All the burners should be equallyadjusted.
Burners should be adjusted toincrease turbulence Increased air-fuel mixing Increased combustion intensity
Faster heat release Lesser demand for excess air Lesser un-burned carbon But it also amounts to
Increased NOx formation
Higher fan power requirement
A Course on Thermal Power PlantA Course on Thermal Power Plant
8/2/2019 Boiler Operations and Control
29/41
Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
A Course on Thermal Power Plant
29
Overfire air (OFA) port adjustment
For NOx reduction burners are usuallyoperated with less than theoretical air forcomplete combustion.The remaining air needed for completingcombustion is introduced separately abovehighest burner zone. The OFA is typicallyvaried as a function of load based on testsconducted during commissioning.Adjustment is needed if type of fuel is
altered.
Excess Air Total combustion air by adjusting FD and ID fan dampers
Excess air gives combustion intensity, reduced carbon loss and COformation
Reduced slag formation Increased fan power Increased stack loss Increased tube erosion and possibly increased NOx formation
A Course on Thermal Power PlantA Course on Thermal Power Plant
8/2/2019 Boiler Operations and Control
30/41
Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur 30
Abnormal Operations: Low Water
In case water level falls below the prescribed minimum,fuel firing should be stopped Caution should be taken while adding water to avoidtemperature shock Water should be added periodically with soak timesprovided to allow drum temperature to equalize Thermocouple readings from the top and bottom of thedrum should be taken time to time to control the process ofcleaningTube Failure: Operating a boiler with a known tube leak is not
recommended Steam or water escaping from a small leak can cut othertubes by impingement and set up a chain reaction of tubefailures Loss of water and steam alters boiler circulations- over
heating For this furnace risers of once throu h t e of boilers
A Course on Thermal Power PlantA Course on Thermal Power Plant
8/2/2019 Boiler Operations and Control
31/41
Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur 31
Detection of Tube failures:
Unusual rise in temperature of furnacerisers Abnormal loss of water from the system Loss of chemical from a drum type boiler Sound made by the leak Boilers should be shut down as soon asnormal operating procedures permit after aleak A leak is then detect by hydrostatic
testing
A thorough inspection is needed after a tubefailure is located. It includes
a visual inspection of the failed tube laboratory analysis Background information like locations offailure, length of time the unit is in operation,
load conditions start up and shut down
A Course on Thermal Power PlantA Course on Thermal Power Plant
8/2/2019 Boiler Operations and Control
32/41
Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur 32
Shut Down Operations:Boiler shut down is less complicated than start upEmphasis is on safety and protection of equipment
Two shut down situations: Control shut down shut down in an emergency
Control shut down: Firing rate is gradually reduced. Fuel is shut off when combustion equipments at itsminimum capacity
Boiler is purged with afresh air If some pressure is to be maintained, the fans areshut down and the dampers are closed Drum pressures are gradually lower as heat is loss
from the boiler setting Minimal amount of air drifts out of the stack
A Course on Thermal Power PlantA Course on Thermal Power Plant
8/2/2019 Boiler Operations and Control
33/41
Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur 33
Emergency Shut Down:
Fuel is immediately shut offBoiler is purged of combustible gases
Additional procedure may apply to the fuel feed
equipment
Boiler may be held at a reduced pressure or may becompletely cooled as described above
A Course on Thermal Power PlantA Course on Thermal Power Plant
8/2/2019 Boiler Operations and Control
34/41
Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
Different Control Strategies for Steam Generation
Boiler following control system
Boiler follows the turbine response
MW load control is the responsibility
of the turbine-generator
Boiler is assigned the secondary
responsibility of throttle control
Load change repositions turbine
control valve
Boiler control modifies firing rate and
restores throttle pressure
It has a rapid load response storedenergy in the boiler provides the initial
change in load
Less stable throttle control
A Course on Thermal Power PlantA Course on Thermal Power Plant
8/2/2019 Boiler Operations and Control
35/41
Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
Turbine follows the boiler response
MW load control is the responsibility of
the boiler
T-G is assigned the secondary
responsibility of throttle control
With load change boiler control
increases the firing rate, this increases
the throttle pressure.
To maintain the throttle pressure,turbine control valve open increasing
Megawatt output.It provides minimal steam pressure and
temperature fluctuations during a load
change
Turbine following control system
A Course on Thermal Power PlantA Course on Thermal Power Plant
8/2/2019 Boiler Operations and Control
36/41
Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
Coordinated-boiler turbine generator control system
A Course on Thermal Power PlantA Course on Thermal Power Plant
8/2/2019 Boiler Operations and Control
37/41
Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
Coordinated boiler turbine control
Both of the above systems can provide satisfactorily control the boiler
operations but have inherent disadvantages
None of them can fully exploit the capabilities of both the boiler and
turbine generators
The two control options can be combined to do so
boiler is not capable of producing rapid changes in steam generationat constant pressure
Turbine is used to provide the initial load response
For a change in load throttle pressure set point is modified using MW
error (demand)
Turbine control valve responds to this change in set point and give the
new load quickly
Boiler modifies the firing rate to reach new load and restore throttle
pressure
A Course on Thermal Power PlantA Course on Thermal Power Plant
8/2/2019 Boiler Operations and Control
38/41
Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
The throttle pressure set point returns to its normal value
The result is fast and efficient production of electric power by a proper
coordination between the boiler and turbine
The response is much faster than turbine following system
But not as fast as boiler following system because the effect of MW error is
limited to maintain a balance between boiler response and stability
Wider limits would provide a faster response but a narrower limit will give
more stability
A Course on Thermal Power PlantA Course on Thermal Power Plant
8/2/2019 Boiler Operations and Control
39/41
Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
A Course on Thermal Power PlantA Course on Thermal Power Plant
Turbine3000 rpm
8/2/2019 Boiler Operations and Control
40/41
Prof. P. K. Das; Dept. of Mechanical Engineering; IIT KharagpurProf. P. K. Das; Dept. of Mechanical Engineering; IIT Kharagpur
Pl
S
H
R
H
R
H
F
S
H
Eco
PSH
147Kg/cm25400C
Generator
TransformerGenerator
Boiler
Coal Bunkers
Primary Air Fans
Coal
Mills
Raw
Coal Fdr
Chimne
y
Flue Gas Duct
Induced Draft Fan
Coal
Conveyer
SECL
Coal
Bunker
CSEB Crusher
House
400/220 KV
15.75KV
Condenser
Coal Handling Plant
Boiler
Drum
3000 rpm
210MW
ESPESP
AH
A Course on Thermal Power PlantA Course on Thermal Power Plant
8/2/2019 Boiler Operations and Control
41/41