73
P-3218 Vantaa Systems training steam boiler Operating personnel training Edition 04.06.2013

Boiler_Operation Personnel Training

  • Upload
    zombos

  • View
    222

  • Download
    0

Embed Size (px)

DESCRIPTION

Instructions of how a high pressure boiler in a typical powerplant works. Detailed explanations of circulation of water and steam through the whole complex of tubes and pipes.

Citation preview

Page 1: Boiler_Operation Personnel Training

P-3218 VantaaSystems training steam boiler

Operating personnel trainingEdition 04.06.2013

Page 2: Boiler_Operation Personnel Training

2Name of Presentation

Introduction

The purpose of this training is to familiarise operating staff with the plant equipment and how to use it. It is a good idea for staff to visit the plant while the equipment is being fitted, in order to be able to see where the equipment is located on the plant, especially the connecting pipelines. Once the insulation has been installed the plant will look quite different.

Training will cover the following basic topics:

Theoretical classroom training

Practical training at the boiler plant

Page 3: Boiler_Operation Personnel Training

3Name of Presentation

Table of Contents

Process

Configuration Vantaa

I&CO functions

Plant operation

Safety at work

Fault rectification

Maintenance

Page 4: Boiler_Operation Personnel Training

Table of contents

Process

Configuration Vantaa

I&CO functions

Plant operation

Safety at work

Fault rectification

Maintenance

Page 5: Boiler_Operation Personnel Training

5Name of Presentation

Process

Fundamental of waste incineration steam generators

The following slides are not related to a specific plant.

For simplification, the expression „boiler“ is used for „steam generator“

Page 6: Boiler_Operation Personnel Training

Main Components of Boiler

Page 7: Boiler_Operation Personnel Training

Principle of Natural Circulation in Evaporators

saturated steam to superheaters

water from eco(below boiling temperature)

downcomer(not heated)

risers = evaporators(heat exchanger tubes)

heat input

saturated steam

boiling water

steam drum

Circulation caused by difference in density in risers and downcomers

Steam content in risers: at inlet: 0 % (water at boiling temperature) at outlet: ca. 5 mass -% (> 50 volume-%)

circ

ulat

ion

Page 8: Boiler_Operation Personnel Training

Main Control Loops

Life steam flow → waste input, combustion air flow (control within Combustion Control System (CCS)

Life steam pressure → turbine inlet valve (control turbine, no control within boiler)

Drum water level → feed water input (control of constant level)

Steam temperature → throughput water injection attemperators (control constant steam temperature)

Page 9: Boiler_Operation Personnel Training

Arrangement of Heating Surfaces (Heat Exchangers)Example: 2-Pass Horizontal Boiler

superheated steam

feed water

steam

water

SH 1SH 3 SH 2 Eco

saturated steam

Ev

ap

ora

tor

Evaporator(membrane walls)

Note:• Each heat exchanger may consist of several bundles (banks) e.g.: Eco = Eco 1.1 + Eco 1.2 + Eco 1.3 + Eco 1.4 + Eco 1.5 + Eco 2

+ Eco 3 , SH 1 = SH 1.1 + SH 1.2

• Additional heat exchangers may be installed, e.g.: evaporator between SH and Eco

Page 10: Boiler_Operation Personnel Training

Control of Flue Gas Temperatureat Boiler Outlet with preheater (External economiser)

10Name of Presentation

Minimum flue gas temperature maybe required by flue gas cleaning system.

Note: max. flue gas temperature can not be controlled (results from boiler fouling).

Page 11: Boiler_Operation Personnel Training

Control of Flue Gas Temperatureat Boiler Outlet with preheater (External economiser)

Page 12: Boiler_Operation Personnel Training

Control of Flue Gas Temperatureat Boiler Outlet with Eco-Bypass (1)

3-way valve

eco

no

mis

er

flue gas

T FG out

steam drum

bypass

Minimum flue gas temperature maybe required by flue gas cleaning system.

Note: max. flue gas temperature can not be controlled (results from boiler fouling).

Page 13: Boiler_Operation Personnel Training

Continuous Boiler Blow Down

Steam generation =„distillation“

→ impurities are accumulated in boiler water (evaporators)

Continuous blow down from drumis adjusted in order to maintain boiler water qualitiy within acceptable limits.

Typical continuous blow down:0.5 % of life steam flow

steamconductivity < 0.2 μS/cm

feed water from ecoconductivity 0.2 < μS/cm << 50(downstream chemical dosing)

circulating boiler water (evaporators)conductivity < 50 μS/cm

blow down valve

expansion vessel

steam vent

drain

steam drum

Page 14: Boiler_Operation Personnel Training

Effect of Boiler Fouling on Flue Gas Temperature

Flue Gas Temperature in Clean and Fouled Boiler

100

200

300

400

500

600

700

800

900

1000

1100

1200

flue gas path (-)

flu

e g

as

te

mp

era

ture

(°C

)

economiserssuperheaters

radiationpasses

190

163

fouled

clean

inlet boiler exit boiler

• Fouling increases with boiler operation time

• Fouling = „insulation“ of boiler tubes

• Assuming same flue gas and water/steam temperatures in heat exchanger:

heat flux can be reduced by up to ca. 50 % due to fouling

• Due to higher flue gas temperature in case of fouled boiler: heat flux in whole boiler is reduced only by few % and results in an increase of flue gas temperature at boiler exit of ca. 30 °C within 8000 h

Page 15: Boiler_Operation Personnel Training

Minimizing Corrosion: Final Superheater (SH 4) with Co-Flow

• Steam temperature and therefore tube surface temperature is highest in final superheater• Highest risk of corrosion in final superheater (SH3 = SH3.1 + SH3.2)• Co-flow: reduction of corrosion rate, but

reduction of heat flux compared to counter-flow

Final Superheater with Co-Flow

300

350

400

450

500

550

600

650

700

Ste

am

- a

nd

Flu

e G

as

Tem

per

atu

re (

°C)

flue gas flow diection

steam flow direction

steam temperature

flue gas temperatureavoid combinationof high flue gas and high steam temperature

inlet outlet

Page 16: Boiler_Operation Personnel Training

Table of contents

Process

Configuration Vantaa

I&CO functions

Plant operation

Safety at work

Fault rectification

Maintenance

Page 17: Boiler_Operation Personnel Training

17Name of Presentation

Natural circulation boiler

Most common type of boiler (used in industry, combined heat and power stations)

Uneconomical for larger plants (> 500 t/h steam)

Simple evaporator design

Part loads and changes in load are easily possible

Changes in load: require control through injection, variation of live steam temperature

Sensitive to rapid pressure drops (profuse steam generation)

Reduced output of feed water pumps required

Lower feed water quality required (due to blow-down)

Page 18: Boiler_Operation Personnel Training

18Name of Presentation

Boiler operating principle

The feed water pump (6) conveys the feed water through the economiser (1) into the boiler drum (2). The difference in density between the water/steam mixture in the heated riser pipes (3) and the water in the non-heated downpipes (5) causes a natural circulation to occur. The saturated steam, which is ultimately superheated in the superheater (4), accumulates in the top part of the boiler drum (2).

No. Description

1 Economiser(pre-heater)

2 Boiler drum

3 Evaporators (heated risers)

4 Superheaters

5 Non-heated downpipes

6 Feed water pump

Page 19: Boiler_Operation Personnel Training

19Name of Presentation

Boiler plant assembly method

Description of the boiler assembly process:

Pipes with 21.3 to 219.1 mm diameter are welded together

The diaphragm walls are made with longitudinal welding of pipes and steel strips

Method of transporting the parts from the workshop to the site and final assembly.

When the boiler is assembled, further procedures are to be carried out, such as:

Rinsing the boiler

Cleaning the water side of the boiler chemically

Drying the refractory lining

Steam cleaning of superheating surfaces.

Page 20: Boiler_Operation Personnel Training

20Name of Presentation

Steam boiler

Description Data

Nominal rating (saturated steam) 83 t/h

Live steam nominal pressure 91 bar (a)

Live steam nominal temperature 400 °C

Feed water temperature 132 °C

• Technical specifications

Page 21: Boiler_Operation Personnel Training

21Name of Presentation

Steam boiler

• Size of heating surfacesDescription Data KKS-No.

External economiser 1.1 451  m2 J1HAC05 AC011

External economiser 1.2 451  m2  J1HAC05 AC012

External economiser 1.3 451  m2  J1HAC05 AC013

External economiser 1.4 451  m2  J1HAC05 AC014

External economiser 1.5 451  m2  J1HAC05 AC015

Economiser 2L/2R 1438 m2  J1HAC10 AC021J1HAC10 AC022

Economiser 3L/3R 1438 m2  J1HAC10 AC031J1HAC10 AC032

Evaporator walls 2063 m2   J1HAD10 AC001

Evaporator 1 214 m2   J1HAD10 AC002

Superheater 1.1L/1.1R 902 m2   J1HAH10 AC111 J1HAH10 AC112

Superheater 1.2L/1.2R 902 m2   J1HAH10 AC121 J1HAH10 AC122

Superheater 2L/2R 867 m2   J1HAH20 AC201 J1HAH20 AC202

Superheater 3.1L/3.1R 366 m2   J1HAH30 AC311 J1HAH30 AC312

Superheater 3.2L/3.2R 523 m2   J1HAH30 AC321 J1HAH30 AC322

Total 7190 m2 -

Page 22: Boiler_Operation Personnel Training

22Name of Presentation

• Volume of the boiler pressure system

Steam boiler

Description Data KKS-No.

Boiler drum 22,908 m³ J1HAD10 BB001

Evaporator 1 2,193 m³ J1HAD10 AC002

Superheater 1.1L/1.1R8,528 m³

J1HAH10 AC111 J1HAH10 AC112

Superheater 1.2L/1.2R8,528 m³

J1HAH10 AC121 J1HAH10 AC122

Superheater 2L/2R7,118 m³

J1HAH20 AC201 J1HAH20 AC202

Superheater 3.1L/3.1R5,762 m³

J1HAH30 AC311 J1HAH30 AC312

Superheater 3.2L/3.2R4,104 m³

J1HAH30 AC321 J1HAH30 AC322

External economiser 1.1 2,435 m³J1HAC05 AC011

External economiser 1.2 2,325 m³J1HAC05 AC012

External economiser 1.3 2,325 m³J1HAC05 AC013

External economiser 1.4 2,325 m³J1HAC05 AC014

External economiser 1.5 2,435 m³J1HAC05 AC015

Economiser 2L/2R13,204 m³

J1HAC10 AC021J1HAC10 AC022

Economiser 3L/3R13,204 m³

J1HAC10 AC031J1HAC10 AC032

Membran walls - vertical part 35,816 m³ J1HAD10 AC001

Membran walls-horizontal part 16,547 m³ J1HAD10 AC001

Connecting pipings 18,969 m³  -

Total 168,73 m³  -

Page 23: Boiler_Operation Personnel Training

23Name of Presentation

Structure of the boiler

Page 24: Boiler_Operation Personnel Training

24Name of Presentation

Structure of the boiler

Page 25: Boiler_Operation Personnel Training

25Name of Presentation

Structure of the boiler

The steam is generated with a 5-pass horizontal boiler. This consists of the vertical 1st to 3rd pass the horizontal 4th pass, and vertical 5th pass

The lower part of the 1st pass forms the furnace. In the grate area, the side walls are fitted with refractory lining.

The side walls of passes 1 to 4 are designed as evaporator pipes with a gas-tight diaphragm construction and are connected to the natural circulation system.

The economiser, the evaporator and the superheater are arranged in the horizontal 4th pass. The boiler drum is arranged diagonally at the top, on the boiler.

External vertical convection 5th pass with economiser heating surfaces and

sheet metal casing

Page 26: Boiler_Operation Personnel Training

26Name of Presentation

Boiler layout and internal circulation of all fluids

Passes (vertical and horizontal) including associated heating surfaces

are to be indicated as follows:

Superheating surfaces SH 1.1, SH 1.2, SH2, SH3.1, SH 3.2 with internal attemperators for outlet temperature control

Evaporating surfaces ECO1.1 – ECO1.5, ECO2, ECO3

Internal connecting pipelines; feed-water heater – drum – steam

Superheater 1.1. – steam superheaters 1.2 - Attemperator 1 – steam superheaters 2 - Attemperator 2 – steam superheaters 3.1 - steam superheaters and main steam line.

Location of draining and venting points

– evaporators

Feed-water heaters -

Directions of flue gas flow through the boiler are also to be indicated. Flue gases from domestic waste incineration boilers contain a high amount of ash that should be removed from heating surfaces by means of mechanical rapping devices.

Page 27: Boiler_Operation Personnel Training

27Name of Presentation

Superheater: final superheater co-flow 2 desuperheatersEconomiserEvaporator protection evaporator upstream SH

Page 28: Boiler_Operation Personnel Training

Inlet economiser:≥ 132 °C

Outlet economiser:≥ 15 °C belowboiling

Live steam:Typically402 °C, 41.5 bar

Page 29: Boiler_Operation Personnel Training

29Name of Presentation

Evaporator - Vantaa

Page 30: Boiler_Operation Personnel Training

30Name of Presentation

Economiser - Vantaa

Page 31: Boiler_Operation Personnel Training

31Name of Presentation

Superheater – Vantaa

Page 32: Boiler_Operation Personnel Training

External economiser - Vantaa

32Name of Presentation

Page 33: Boiler_Operation Personnel Training

33Name of Presentation

Associated components: refractory lining

Reference to the following training of J + G

Page 34: Boiler_Operation Personnel Training

34Name of Presentation

Safety equipment and control circuits overview

Installed safety equipment includes:

Safety transmitter of minimum and maximum level in the drum J1 HAD10 CP001, J1 HAD10 CP002, J1 HAD10 CP003.

Safety valve J1 LBA10 AA510 with control unit J1 HAD10 CG501

Thermometer J1 LBA10 CT002 – protection of maximum temperature of superheated steam

Transmitter J1 LBA10 CP002 – maximum steam pressure protection

The purpose of the installed safety equipment is to protect the plantagainst deviations from default values.

Page 35: Boiler_Operation Personnel Training

35Name of Presentation

Safety equipment and control circuits overview

Control circuits are:

Control of drum level consisting of feed-water control level transmitters, including water and steam flow meters

Control circuit to protect feed-water from dropping below minimum temperature

Control circuit of steam attemperation

Control circuit to protect against high drum level.

Other operating (auxiliary) systems are:

Chemicals dosing system in order to maintain pH values of steam and water within default values

System for collecting water from blow-down

Boiler warming system, i.e. maintaining standby condition.

Page 36: Boiler_Operation Personnel Training

36Name of Presentation

Presentation and description of operation of fitted equipment:

Safety valves

Cooling valves including associated attemperators

Valves for continuous water blow-down from the boiler drum

Water and steam quantity measurement – measuring orifices

Three-way control valve J1 HAC05 AA020 for protecting feed water against dropping below minimum temperature,

Water and steam sampling system

System for mechanical cleaning of heating surfaces

Wet cleaning.

Each part of the equipment should be provided

with the relevant suppliers’ brochure.

Fitted equipment overview

Page 37: Boiler_Operation Personnel Training

37Name of Presentation

Safety valve

Page 38: Boiler_Operation Personnel Training

Safety valve on main steam line

Flow area – 2827 mm2

Normal pressure – 91 bar (g)

Set pressure in main steam line 1 96 bar(g)

Set pressure in main steam line 2 97 bar(g)

Set pressure in drum 107,0 bar(g)

Page 39: Boiler_Operation Personnel Training

Pneumatic contol unit

M1 – 96 barg – main steam line

M1 – 96 barg – main steam line

M3 – 108 barg – boiler drum

Page 40: Boiler_Operation Personnel Training

40Name of Presentation

Instruments

Thermometer J1 LBA10 CT003 – protection of maximum temperature of superheated steam

Transmitter J1 LBA10 CP001 – maximum steam pressure protection

The purpose of the installed safety equipment is to protect the plant against deviations from default values.

Page 41: Boiler_Operation Personnel Training

41Name of Presentation

Control circuits are

Control of drum level consisting of feed-water control valve, level transmitters including water and

steam flow meters.

The function of the transparent water level indicator J1 HAD10 CL502 is checked as follows:

No.

Description KKS-No.

1 Boiler Drum J1HAD10 BB001

2 Shut-off valve boiler drum measurement connection J1HAD10 AA654

3 Shut-off valve boiler drum measurement connection J1HAD10 AA653

4 Level measurement boiler drum J1HAD10 CL502

5 Shut-off valve boiler drum measurement connection J1HAD10 AA652

6 Shut-off valve boiler drum measurement connection J1HAD10 AA651

7 Shut-off valve measuring instrument drain boiler J1LCL90 AA830

Page 42: Boiler_Operation Personnel Training

42Name of Presentation

Drum level measuring

Bicolour level gauge

Page 43: Boiler_Operation Personnel Training

43Name of Presentation

Blow-down expansion tank level measuring

Blow-down expansion tank

Page 44: Boiler_Operation Personnel Training

44Name of Presentation

Cooling valves including associated attemperators

Page 45: Boiler_Operation Personnel Training

45Name of Presentation

AUMA actuator

Page 46: Boiler_Operation Personnel Training

46Name of Presentation

Water and steam quantity measuring

Orifice plate

Page 47: Boiler_Operation Personnel Training

47Name of Presentation

Pneumatic rapping device

The rapping system is an automatically working cleaning device that cleans off the bundle of pipes of a heating boiler through strikes against especially developed rapping points of the bundle of pipes. For this a rapping carriage moves between two travelling way supports on the outer wall of the heating boiler. The rapping carriage is moved via a rubber wheel on the travelling way by a geared motor. The rapping carriage is guided by curved rollers on ball bearings. Rams are built into the boiler wall at regular intervals and are situated at the rapping points of the bundles of pipes. If the rapping carriage reaches a ram an initiator is occupied by a positioning lug on the ram structural component. The rapping carriage stops in this position. The occupation of the initiator is a fundamental precondition for the rapping procedure. A further precondition is that compressed air is pending. These are arranged on both side walls.The dirty heating surfaces are caused to vibrate so that the resulting caking falls off.

Page 48: Boiler_Operation Personnel Training

48Name of Presentation

Pneumatic rapping device

Rapping device KKS-No.

Rapping device 1 1 HCE40 AW001

Rapping device 2 1 HCE40 AW002

Page 49: Boiler_Operation Personnel Training

Helical Soot Blowers

49Name of Presentation

Long retractable blower The long retractable blowers consist of a blow pipe and a nozzle head on theend of the blow pipe. They move in an axial direction past the heating surfacesto be cleaned. Live steam/MP steam is used as a blowing medium. The restposition of the lance-type screw blowers is outside of the combustion gas flow.

Scoot blower KKS-No.

Helical Soot Blowers 1 J1HCB05 AN001

Helical Soot Blowers 2 J1HCB05 AN002

Helical Soot Blowers 3 J1HCB05 AN003

Helical Soot Blowers 4 J1HCB05 AN004

Helical Soot Blowers 5 J1HCB05 AN005

Page 50: Boiler_Operation Personnel Training

Helical Soot Blowers

50Name of Presentation

Area of application: Cleaning of heating surface banks.The blowing tube is installed in the flue gas pass and it and is helically moved forward and backwards. The helical movement of the blowing tube / lance tube is effected by chain drive at the soot blower carriage which is driven by a geared motor. The blowing tube is on its entire length equipped with Venturi nozzles. A full cleaning effect over the whole blowing distance is ensured due to the conical expansion of the blowing jets and due to the arrangement of the nozzles.

Page 51: Boiler_Operation Personnel Training

Helical Soot Blowers

51Name of Presentation

Soot Blowes - parts

Page 52: Boiler_Operation Personnel Training

52Name of Presentation

Three-way control valve J1 HAC05 AA020

Page 53: Boiler_Operation Personnel Training

53Name of Presentation

P&I diagrams

All P&I diagrams and their functions are to be included:

P&I diagram of boiler drum eco

P&I diagram of boiler superheaters

P&I diagram of boiler blow-down

P&I diagram of boiler drains vents

P&I diagram of boiler FG-side 2

P&I diagram of primary air preheater

P&I diagram of external eco & soot blowers

Page 54: Boiler_Operation Personnel Training

54Name of Presentation

P&I diagram of boiler drum eco

Page 55: Boiler_Operation Personnel Training

55Name of Presentation

P&I diagram of boiler superheaters

Page 56: Boiler_Operation Personnel Training

56Name of Presentation

P&I diagram of boiler drains vents

Page 57: Boiler_Operation Personnel Training

57Name of Presentation

P&I diagram of boiler blow-down

Page 58: Boiler_Operation Personnel Training

58Name of Presentation

P&I diagram of boiler FG-side 2

Page 59: Boiler_Operation Personnel Training

P&I diagram of primary air preheater

59Name of Presentation

Page 60: Boiler_Operation Personnel Training

P&I diagram of external eco & soot blowers

60Name of Presentation

Page 61: Boiler_Operation Personnel Training

Table of contents

Process

Structure

I&CO functions

Plant operation

Safety at work

Fault rectification

Maintenance

Page 62: Boiler_Operation Personnel Training

62Name of Presentation

Description and preparation of plant start-up

This section contains a brief description of the plant preparation and start-up, its operation and shutdown.

Presentation of the preparation for starting up the plant:

Procedures for plant start-up preparations

Initial drum water level

Top up from the start-up pipeline and valve

Warming up the superheated steam pipeline from the main steam valve to the steam

Turbine by using the bypass valve for warming up

Description of work during regular boiler plant operation

Controlled shutdown procedure.

The "Operating instructions manual for boiler plant" should be used to describe the above-mentioned procedures, i.e. the most common plant operation scenarios.

Page 63: Boiler_Operation Personnel Training

63Name of Presentation

Associated components: scrubbing systems

The problem!

Page 64: Boiler_Operation Personnel Training

64Name of Presentation

Example: Shower Cleaning SystemOn-load boiler water cleaning

Spray nozzle

Page 65: Boiler_Operation Personnel Training

65Name of Presentation

Associated components: sampling station

Page 66: Boiler_Operation Personnel Training

Table of contents

Process

Structure

I&CO functions

Plant operation

Safety at work

Fault rectification

Maintenance

Page 67: Boiler_Operation Personnel Training

Safety

You have probably gone through hundreds of site

inductions and will probably go through hundreds more

The induction is important as all sites are different andhave a wide range of hazards which will

change as the site develops

This site induction is specific to this site and provides you with information on the current hazards of

the site and tells you about the site rules

Page 68: Boiler_Operation Personnel Training

Signs on Site

Always comply with safety signage

Read the labels on containers before using any substances

Use any safety precautions required

Page 69: Boiler_Operation Personnel Training

Personal Protective Equipment

Look after your P.P.E. and always wear it when required

Page 70: Boiler_Operation Personnel Training

Table of contents

Process

Structure

I&CO functions

Plant operation

Safety at work

Fault rectification

Maintenance

Page 71: Boiler_Operation Personnel Training

Table of contents

Process

Structure

I&CO functions

Plant operation

Safety at work

Fault rectification

Maintenance

Page 72: Boiler_Operation Personnel Training

Most important aspects of maintenance

InputB3.10 Chap.1.2 Maintenance work planB3.10 Chap.1.3 Lubrication schedule and products

Page 73: Boiler_Operation Personnel Training

Thank you very muchfor your attention