Bond Construction Bond Construction Update Update Citizens Oversight Citizens Oversight Committee Committee Long Beach Community College District April 25, 2012 EDUCATE ENGAGE EMPOWER 1

Bond Construction Update Citizens Oversight Committee

Embed Size (px)

DESCRIPTION

Bond Construction Update Citizens Oversight Committee. Long Beach Community College District April 25, 2012. EDUCATE  ENGAGE  EMPOWER. Agenda. Completed Construction Projects LAC Building I (Bookstore) Current Construction Projects LAC Building A – Student Services Retrofit - PowerPoint PPT Presentation

Citation preview

Page 1: Bond Construction Update  Citizens Oversight Committee

Bond Construction Bond Construction UpdateUpdate

Citizens Oversight Citizens Oversight CommitteeCommittee

Bond Construction Bond Construction UpdateUpdate

Citizens Oversight Citizens Oversight CommitteeCommittee

Long Beach Community College District April 25, 2012

EDUCATE ENGAGE EMPOWER 1

Page 2: Bond Construction Update  Citizens Oversight Committee

Agenda

Completed Construction Projects LAC Building I (Bookstore)

Current Construction Projects LAC Building A – Student Services Retrofit LAC Building I (Landscape) LAC Master Landscape LAC Veterans Stadium Lights PCC MDAB (Multi-Disciplinary Academic Building) PCC Building CC Retrofit

Upcoming Construction Projects LAC Math Technology Building PCC Building GG LAC Building C Retrofit

Q & A

2

Page 3: Bond Construction Update  Citizens Oversight Committee

Completed Construction Projects

3

Building construction complete Move in complete Bookstore is open for business

LAC Building I - Measure E 2008LAC Building I - Measure E 2008

Page 4: Bond Construction Update  Citizens Oversight Committee

Current Construction ProjectsLAC Building A – Student Services RetrofitLAC Building A – Student Services Retrofit

Measure E 2008Measure E 2008

4

Progress on sheeting the roof Interior wall framing in progress Subfloor and utility installation in progress Estimated completion date late fall 2012

Page 5: Bond Construction Update  Citizens Oversight Committee

Current Construction ProjectsLAC Building A – Student Services RetrofitLAC Building A – Student Services Retrofit

Measure E 2008Measure E 2008

5

Structural walls complete on new addition Roof structure to follow

Page 6: Bond Construction Update  Citizens Oversight Committee

Current Construction Projects

6

Exterior Landscape has started Privacy wall started, planting to follow Project expected to be complete in May 2012

LAC Building I Landscape - Measure E 2008LAC Building I Landscape - Measure E 2008

Page 7: Bond Construction Update  Citizens Oversight Committee

Current Construction Projects

7

Phase 1, South of Building A Bid opening date 5/22/2012

Construction to start in summer 2012

Passive Storm water retention system

Low water use Plants and trees

Pedestrian pathway alignment

LAC Master Landscape - Measure E 2008LAC Master Landscape - Measure E 2008

Page 8: Bond Construction Update  Citizens Oversight Committee

Current Construction Projects

8

Phase 2, North of Building A will bid Spring 2013

Construction to start in summer 2013

Active Storm water retention system

Low water use Plants and trees

Pedestrian pathway alignment

LAC Master Landscape - Measure E 2008LAC Master Landscape - Measure E 2008

Page 9: Bond Construction Update  Citizens Oversight Committee

9

Veteran’s Stadium Lighting Measure E 2008Veteran’s Stadium Lighting Measure E 2008Current Construction Projects

Stadium lighting retrofit Awaiting final DSA approval Construction includes demo of old fixtures and installation of energy

efficient fixtures.

Page 10: Bond Construction Update  Citizens Oversight Committee

Current Construction ProjectsPCC MDAB PCC MDAB

(Multi-Disciplinary Academic Building)(Multi-Disciplinary Academic Building)Measure E 2008Measure E 2008

10

MDAB building remodel project Phase 1 of 2 currently under construction Exterior envelope 90% constructed Roof Membrane 100% complete

Page 11: Bond Construction Update  Citizens Oversight Committee

Current Construction ProjectsPCC MDAB PCC MDAB

(Multi-Disciplinary Academic Building)(Multi-Disciplinary Academic Building)Measure E 2008Measure E 2008

11

South side exterior curtain wall Electrical distribution transformer complete Phase 1 Project to be completed Summer 2012

Page 12: Bond Construction Update  Citizens Oversight Committee

Upcoming Construction ProjectsPCC Building CC Retrofit - Measure E 2008PCC Building CC Retrofit - Measure E 2008

12

Building CC Fitness Center, offices and restrooms Demolition complete, exterior walls in progress Duration of project approximately 12 months Anticipated end of construction Fall 2012

Page 13: Bond Construction Update  Citizens Oversight Committee

Upcoming Construction Projects

Math and Culinary Arts instructional program as well as Reprographics

Contract awarded to Harper/Sillman Design Build Team Currently in design development phase (DD) Construction documents to DSA Fall of 2012 Anticipated start of construction 2013

LAC Math Technology Building – Measure E 2008LAC Math Technology Building – Measure E 2008

13

Page 14: Bond Construction Update  Citizens Oversight Committee

Upcoming Construction ProjectsPCC Building GG - Measure E 2008PCC Building GG - Measure E 2008

14

16 Design Build Entities (DBE) short listed to 5Interviews with 5 short listed DBE teams complete in January 3 Teams selected for proposals, Balfour Beatty, C.W. Driver, Bernards

Estimated start of construction December 2013

Page 15: Bond Construction Update  Citizens Oversight Committee

Upcoming Construction ProjectsLAC Building C Retrofit - Measure E 2008LAC Building C Retrofit - Measure E 2008

15

Hired Architect to do design work Program phase is currently ongoing Work includes modernization of structure, classrooms spaces, and

office areas

Page 16: Bond Construction Update  Citizens Oversight Committee

l i b

e r

a l

a r

t s

Liberal Arts CampusSite Plan

Page 17: Bond Construction Update  Citizens Oversight Committee

p a

c i f

i c

c

o a

s t

Pacific Coast CampusSite Plan

Page 18: Bond Construction Update  Citizens Oversight Committee

QUESTIONS&

ANSWERS

EDUCATE ENGAGE EMPOWER 18