Upload
dotram
View
219
Download
0
Embed Size (px)
Citation preview
Bond ReferendaTown Hall Meeting
Potential Mobility Bond Projects
Ricardo Canizales - DirectorDepartment of Transportation
|3|
Devlin Road Widening
n Description: Widen to 4-lanes from Linton Hall Rd to Wellington Rd with a sidewalk and shared use path. Total project length of 1.8 miles.
n Approximate Project Cost: $50,000,000
n Project Duration: 4 to 6 years
n Existing Funding: $12.5 million RSTP (Federal) funding. Eligible for other funding.
Purpose: Four-lane widening of Devlin Road, which will connect to the Balls Ford Road Interchange and improves access to Prince William Parkway and I-66
|4|
University Boulevard Extension
n Description: Extends University Boulevard (2-lanes) from Devlin Road to Progress Court and a possible pedestrian facility. Total project length of 1.7 miles.
n Approximate Project Cost: $30,000,000
n Project Duration: 4 to 6 years
n Existing Funding: $3.9 million in RSTP (Federal) funding. Eligible for other funding.
Purpose: Two-lane (half-section) extension of University Boulevard to connect Devlin Road to Wellington Road. Completes last segment of University Boulevard, which will connect Route 29 to Prince William Parkway/Godwin Drive
|5|
Route 28 Bypass
n Description: 4-lane limited access road, extending from Flat Branch to Route 28 near the Fairfax/Prince William County Line and one bike/ped facility. Total project length of 3.5 miles.
n Approximate Project Cost: $300,000,000
n Proposed Project Funding: $100,000,000
n Existing Funding: $95 million in NVTA funds. $100,000,000 more needed from other sources.
n Project Duration: 5 to 7 years
Purpose: Construction of a bypass to relieve congestion between the City of Manassas and Fairfax County
|6|
Sudley Road Corridor Intersection Improvements
n Description: Roundabouts at the Catharpin Road/Sudley Road intersection and the Pageland Lane/Sanders Lane/Sudley Road intersection (Includes Pageland Lane Realignment).
n Approximate Project Cost: $12,500,000
n Project Duration: 3 to 5 years
n Existing Funding: None. Unlikely to receive other funding.
Purpose: Improve intersection safety and flow along Route 234 - Sudley Road
|7|
Route 55 Widening and Catharpin Road Intersection Improvements
n Description: 4-lane widening of Route 55 from Gillis Way to Catharpin Road, and intersection improvements at the intersection of Route 55 at Catharpin Road, includes bike/pedestrian facilities. Total project length of 0.8 miles
n Approximate Project Cost: $40,000,000
n Project Duration: 4 to 6 years
n Existing Funding: None. Unlikely to receive other funding.
Purpose: Eliminate bottleneck between two proposed developer projects and improve the intersection of Catharpin Road at Route 55
|8|
Minnieville Road at Prince William Pkwy Interchange
n Description: Grade separated intersection at Minnieville Road and Prince William Parkway.
n Approximate Project Cost: $70,000,000
n Project Duration: 4 to 6 years
n Existing Funding: None. Eligible for other funding.
Purpose: To provide improved operations at the intersection of Minnieville Road and Prince William Parkway
Concept Only*
|9|
Old Bridge Road at Gordon Boulevard Intersection Improvements
n Description: Construction of a flyover ramp from Route 123/I-95 to Old Bridge Road.
n Approximate Project Cost: $15,000,000
n Project Duration: 3 to 5 years
n Existing Funding: None. Eligible for other funding.
Purpose: To create safer traffic flow from I-95 to Old Bridge Road
Old Bridge Road at Prince William Parkway Intersection Improvements
n Description: Addition of a lane to the ramp that connects eastbound Prince William Parkway traffic at Old Bridge Road.
n Approximate Project Cost:$15,000,000
n Project Duration: 3 to 5 years
n Existing Funding: None. Eligible for other funding
Purpose: To promote use of Prince William Parkway to access I-95 by adding capacity and providing safety improvements to the eastbound direction
|10|
|11|
Summit School Road Extension
n Description: 4-lane extension of Summit School Road to Caton Hill Road (through Telegraph Road).
n Approximate Project Cost: $20,000,000
n Project Duration: 3 to 4 years
n Existing Funding: $11 million in NVTA Funds. Eligible for other funding.
Purpose: Provides for improved and new connection between Minnieville Rd and Telegraph Rd
|12|
Van Buren Road Extension
n Description: 4-lane extension of Van Buren Road between Route 234 and Cardinal Drive. Includes bike/ped facilities. Total project length of 2.7 miles.
n Approximate Project Cost: $70,000,000
n Project Duration: 4 to 6 years
n Existing Funding: None. Eligible for other funding.
Purpose: Creates an internal parallel route to I-95 and Route 1 between Dale Boulevard and Route 234
|13|
North Woodbridge Mobility Improvements
n Description: Projects may consist of various mobility improvements adjacent to Route 1, Route 123, Horner Road, Annapolis Way and Marina Way.
n Approximate Project Cost: $165,000,000
n Proposed Project Funding: $55,000,000
n Existing Funding: $450,000 Local TRIP funds (Annapolis Way). Eligible for other funding,
n Project Duration: 5 to 10 years
Purpose: To improve the mobility network in the North Woodbridge Area
|14|
Other Safety/Operational and Bicycle/Pedestrian Projects
A separate line item is proposed for other safety/operational and bicycle/pedestrian projects Countywide for $35 million
|15|
Summary
n Number of projects: 11
n Total new lane miles: 50 miles
n Total length of bicycle and pedestrian facilities: 22 miles
n Total cost of all projects: $512,500,000
n Funding currently available: $27,850,000
n Total Bonding amount: $400,000,000
n Funding needed from other sources: $184,650,000 (Includes $100,000,000 additional for Route 28 Bypass Project)
Potential Park Bond Projects
Seth Hendler-Voss, DirectorDepartment of Parks, Recreation, and Tourism
Field House§ Description: Indoor multi-
sport practice facility for local leagues, high schools, and residents
§ Specs: 125,000+/- square feet, practice track, multi-use courts
§ Estimated Cost: $17.6 million
§ Project Duration: 36-48 months
§ Uses: Futsal, basketball, tennis, pickleball, field hockey, etc.
17
Howison Park Improvements§ Description: Functional and accessibility
improvements to existing community park
§ Specs: ADA improvements, trail, spectator seating, fitness equipment, comfort station expansion, additional parking
§ Estimated Cost: $6 million
§ Project Duration: 24 months
18
COMFORT STATION EXPANSION
OUTDOOR GYM
TRAIL
PERIMETER SIDEWALKSEATING
Indoor Turf Fieldhouse§ Description: Indoor multi-sport
practice field
§ Specs: 87,000+/- square feet
§ Estimated Cost: $4.0 million
§ Project Duration: 24 months
§ Uses: Soccer, football, lacrosse, rugby, cricket, ultimate frisbee, etc.
19
Long Park Improvements
§ Description: Upgrades and expansion to existing regional park
§ Specs: Road improvements, soccer field #1 and #2 lights and irrigation, addition of two baseball fields, comfort station, sewer line, parking expansion
§ Estimated Cost: $10.8 million
§ Project Duration: 36 months
20ADD 2 FIELDSAND COMFORT STATION
LIGHTS AND IRRIGATION
ADD LEFT TURN LANE
EXPAND PARKING
New Park Development§ Description: New amenity-rich
community park
§ Specs: Dynamic playground, climbing wall, hill slides, skating ribbon, pedal powered monorail, and amphitheater
§ Estimated Cost: $6 million
§ Project Duration: 36 months
21
Indoor Sports Complex
§ Description: Indoor competition and practice facility for local leagues, high schools, and residents
§ Specs: 230,000+/- square feet, hydraulic banked 200 meter/6 lane track, courts, 3,500 fixed seats, and turf
§ Estimated Cost: $84 million
§ Project Duration: 48 months
22
Field Hockey Basketball/Volleyball
Cheer Wrestling
Indoor Track
Pickle Ball
Graduations/Concerts
Turf Sports
Fuller Heights Expansion
§ Description: Expand existing community park
§ Specs: 2-230’ fields and parking
§ Estimated Cost: $6 million
§ Project Duration: 36 months
23
ADD 2 FIELDS
Aquatic and Fitness Center§ Description: Family-based aquatic and
fitness facility
§ Specs: 50,000+/- square feet, competition and leisure pool, weight/functional fitness room, fitness classrooms, basketball court, children/youth area, community space
§ Estimated Cost: $42 million
§ Project Duration: 48 months
24
§ Description: Advance numerous off-road trail projects in various stages of completion and open space acquisition
§ Allowance: $23.6 million
§ Project Duration: 120 months
25
Trails & Open Space
SPEAK UPBE HEARD!
pwcgov.org/speakup