Booster Bias Supply Upgrade April 2, 2014. First prototype was started in December The back half of the supply was totally gutted Transformer Interphase
First prototype was started in December The back half of the
supply was totally gutted Transformer Interphase reactor SCR/heat
sink assemblies All water hoses Relocated various chassis and
supplies A few need re-wiring Assembled as much as possible to
finalize layout Huge relief when it was verified that everything
was going to fit without a major overhaul
Slide 3
Slide 4
Slide 5
Slide 6
Slide 7
Slide 8
Slide 9
Slide 10
Slow going on first supply Not worked on full time Many delays
with materials and parts Many discussions and decisions on final
layout High priority on ease of future maintenance Second gutting
for final hole drilling, documenting and installation of plated
parts. Made doubles of many parts
Slide 11
Slide 12
Slide 13
Slide 14
Slide 15
Slide 16
Slide 17
Slide 18
Slide 19
Now have two techs from EE Support (80%) High current copper
bus bars Need 10 of these which are very labor intensive Flexible
copper straps Need 120 of these Fairly tedious to assemble, solder
and drill SCR/heat sink assemblies Need 20 of these
Slide 20
Slide 21
Slide 22
Slide 23
Slide 24
Slide 25
Slide 26
Next bias supply rehab: Much faster! Layout is finalized and
documented. Have 80% of parts and material on hand Few more
in-house machine shop jobs Off-the-shelf electrical parts EE
Support techs working on labor intensive assemblies ~2 month
turn-around on next supply Training full-time worker Ordering
remaining parts Remaining supplies have solid wall separating front
and back, possibly creating a few problems ~1 month turn-around
thereafter