Brown Middle School Weekly Construction Report May 6, 2016 Page 1 Brown Middle School Weekly Progress Report 5/6/2016 Picture 1: Paving at track Picture 2: Backstop fence at softball field Picture 3: Finish grading at North elevation Picture 4: Sidewalk at lower level classroom building

Brown Middle School Weekly Construction Report · Weekly Construction Report May 6 , 2016 Page 2 Brown Middle School Weekly Progress Report 5/6/2016 Picture 5: Sheathing at the mechanical

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Brown Middle School Weekly Construction Report · Weekly Construction Report May 6 , 2016 Page 2 Brown Middle School Weekly Progress Report 5/6/2016 Picture 5: Sheathing at the mechanical

Brown Middle School

Weekly Construction Report May 6, 2016

Page 1

Brown Middle School Weekly Progress Report 5/6/2016

Picture 1: Paving at track

Picture 2: Backstop fence at softball field

Picture 3: Finish grading at North elevation

Picture 4: Sidewalk at lower level classroom building

Page 2: Brown Middle School Weekly Construction Report · Weekly Construction Report May 6 , 2016 Page 2 Brown Middle School Weekly Progress Report 5/6/2016 Picture 5: Sheathing at the mechanical

Brown Middle School

Weekly Construction Report May 6, 2016

Page 2

Brown Middle School Weekly Progress Report 5/6/2016

Picture 5: Sheathing at the mechanical yard screen wall Picture 6: Installing interior overhead coiling doors in kitchen

Picture 7: Installing ceiling tile in new addition

Picture 8: Installing light fixtures in corridor of new

addition

Page 3: Brown Middle School Weekly Construction Report · Weekly Construction Report May 6 , 2016 Page 2 Brown Middle School Weekly Progress Report 5/6/2016 Picture 5: Sheathing at the mechanical

Brown Middle School

Weekly Construction Report May 6, 2016

Page 3

Brown Middle School Weekly Progress Report 5/6/2016

Picture 9: Hanging light fixtures in media center

Picture 10: Installing the kiln in the art room

Picture 11: Toilets and fixtures in new addition gang restrooms

Picture 12: Epoxy flooring in the kitchen

Page 4: Brown Middle School Weekly Construction Report · Weekly Construction Report May 6 , 2016 Page 2 Brown Middle School Weekly Progress Report 5/6/2016 Picture 5: Sheathing at the mechanical

Brown Middle School

Weekly Construction Report May 6, 2016

Page 4

Brown Middle School Weekly Progress Report 5/6/2016

Upcoming: Site:

Gym entrance stairs

Paving at north parking lot

Sod at fields Addition:

Toilet partitions and accessories

VCT & carpet

Device trim out

Schedule Status: Base contract – June 29, 2016

On schedule *Basement Scope Schedule - TBD

Courtyard Exterior Lighting

Ongoing: Site:

Sidewalks

Trees

Addition:

Brick and cast stone

Storefront

Light fixtures

Painting

Budget Status: Project Budget - $19,500,000

Spent to Date - $16,074,145

On budget *Basement Scope Budget – TBD