BSB JOP Project BSBEEP Black Sea Buildings Energy Efficiency Plan GA 1 Status Report: “ Knowledge and Information collection and dissemination - Analysis of external current situation” 2nd Meeting, Yerevan, 2013. Georgios GAIDAJIS, Komninos ANGELAKOGLOU - PowerPoint PPT Presentation
Citation preview
BSB JOP Project BSBEEPBlack Sea Buildings Energy Efficiency PlanGA 1 Status Report: “Knowledge and Information collection and dissemination - Analysis of external current situation”
2nd Meeting, Yerevan, 2013
Georgios GAIDAJIS, Komninos ANGELAKOGLOULaboratory of Environmental Management and Industrial Ecology (LEMIE)Department of Production Engineering & ManagementDemocritus University of Thrace, School of EngineeringXanthi, Greece
1. GA1 quick review2. Plan versus actual3. Work scheduled and done4. Work to be done5. Main bottlenecks and constraints6. Discussion
Structure of presentation
2/27
Basic outputs – Reminder!
GA1 outputs will provide the basis for a solid understanding of the current situation and potential regarding energy efficiency for buildings in the examined areas.
3/27
GA1.1 - Collection of building guidelines (legislation) concerning energy efficiency issues
Basic Output: Legal framework corpus, concerning the legal framework at EU, national and local level.
Basic Output: Guide for funding, political initiatives at EU, national and local level.
GA 1.2 - Collection funding opportunities and programs, political initiatives at EU, national and local level.
1. GA1 quick review
GA1.3 - Collection of applied best practices concerning energy efficiency issues and study visits at participating municipalities areas.
Basic Output: Best practices collection, from EU, national and local experience.
Basic outputs – Reminder!
4/27
GA1.4 - Collection of a pool of active bodies and experts that are involved on energy efficiency matters - BSBEEP POOL
GA1.5 - Collection of building materials and systems concerning energy efficiency issues - BSBEEP AGORA
Basic Output: Index of actors (institutions and bodies) at EU, national and local level.
Basic Output: Guide of building materials concerning energy efficiency issues.
1. GA1 quick review
Summary of participants in GA1 activity
ParticipantsGA1
Activity1.1 1.2 1.3 1.4 1.5
Municipality of Kavala-GR Municipality of Galati-RO Municipality of Cahul-MD Municipality of Mykolayiv-UA Municipality of Samsun-TR Municipality of Tekirdag-TR Democritus University of Thrace (Leader)University “DUNĂREA" Galaţi-RO American University of Armenia-AM RR & Energy Efficiency Fund-AM
Municipalities of Cahul, Mykolayiv, Samsun and Tekirdag will participate in all 5 GAs
5/27
1. GA1 quick review
Description
Year 1Semester 1
(Month)Semester 2
(Month)1 2 3 4 5 6 Dec Jan Feb Mar Apr May
GA1.1 - Collection of building guidelines (legislation) concerning energy efficiency issues GA 1.2 - Collection of funding, including funding opportunities and programs, political initiatives at EU, national and local level. GA1.3 Collection of applied best practices concerning energy efficiency issues and study visits at participating municipalities areas. GA1.4 Collection of a pool of active bodies and experts that are involved on energy efficiency matters - BSBEEP POOL GA1.5 Collection of building materials and systems concerning energy efficiency issues - BSBEEP AGORA
6 Months have passed!!Mostly administrative and preparatory activities…
No major work regarding GA1!
6/27
2. Plan versus actual
Description
Year 1Semester 1
(Month)Semester 2
(Month)1 2 3 4 5 6 Dec Jan Feb Mar Apr May
GA1.1 - Collection of building guidelines (legislation) concerning energy efficiency issues GA 1.2 - Collection of funding, including funding opportunities and programs, political initiatives at EU, national and local level. GA1.3 Collection of applied best practices concerning energy efficiency issues and study visits at participating municipalities areas. GA1.4 Collection of a pool of active bodies and experts that are involved on energy efficiency matters - BSBEEP POOL GA1.5 Collection of building materials and systems concerning energy efficiency issues - BSBEEP AGORA
GA1.1 and GA1.2 activities must end until end of December –That’s 23 days from now! (including Christmas…)
7/27
2. Plan versus actual
Description
Year 1Semester 1
(Month)Semester 2
(Month)1 2 3 4 5 6 Dec Jan Feb Mar Apr May
GA1.1 - Collection of building guidelines (legislation) concerning energy efficiency issues GA 1.2 - Collection of funding, including funding opportunities and programs, political initiatives at EU, national and local level. GA1.3 Collection of applied best practices concerning energy efficiency issues and study visits at participating municipalities areas. GA1.4 Collection of a pool of active bodies and experts that are involved on energy efficiency matters - BSBEEP POOL GA1.5 Collection of building materials and systems concerning energy efficiency issues - BSBEEP AGORA
8/27
2. Plan versus actual
GA1.3 and GA1.4 activities are estimated to have ended until February
GA1.5 activities are estimated to have ended until April
GAYear 1
Semester 1 (Month)
Semester 2 (Month)
1 2 3 4 5 6 7 8 9 10 11 12GA1.1 GA 1.2 GA1.3 GA1.4 GA1.5
Months 1-4 Until 1st Progress Report
What we had to do:• Specifications for five (5) studies
9/27
3. Work scheduled and done
What we have done: Specifications for all five GA1 studies have been prepared.
Moreover: An analytical timetable and a template including specific instructions and timeframe were
elaborated and were distributed to all partners (12/9/2013).
A questionnaire regarding the analytical profile of all municipalities has been developed and distributed.
Screening evaluation and collection of relative literature, preliminary analysis, summary lists.
Adaptation of GA1 internal structure
One (1) introductory chapter General information regarding
activity’s subject and notions.
Seven (7) chapters (one for each municipality and one for Armenia).
Focus on local national and EU level.
One (1) comparative final chapter
Identify common approaches, pros and cons, evaluate data adequacy etc.
Structure flexibility-adaptation since many municipalities fall under common legislative framework (i.e. EU, Turkish, etc.)
Avoidance of effort duplication (ensure the that participants will not work on identical subjects thus losing valuable time, i.e. EU and Turkish legislation should not be described in each EU and Turkish municipality respectively)
Indicative example GA1.3
10/27
3. Work scheduled and done
Initial structure
New structure
& contents
Activity 1 (legislation)
11/27
3. Work scheduled and done
GA1.1
1.Introduction2. EU Level 2.1 Legal Framework 2.2 Administrative Framework 2.3 Challenges and Opportunities 2.4 Problems and Constraints3. National and Local Level 3.1 Armenia & Yerevan 3.2 Greece & Kavala 3.3 Moldova & Cahul 3.4 Romania & Galati 3.5 Turkey & Samsun & Tekirdag 3.6 Ukaraine & Mykolayiv4. Comparison and Conclusions
General information regarding activity’s subject and notions. Issues such as significance of accomplishing the specific activity, references to similar work, definitions et al. may be included.
2.1 & 2.2: Mention the temporal evolution of the legislation and the reasoning behind that evolution. Provide an exhaustive list with all the EU legislation related with Buildings and Energy Efficiency, and a brief summary of each legislation.
2.3 & 2.4: Mention and point out the challenges and/or the opportunities together with the problematic areas and any limitations, that may arise from the legislative framework.
Similar to EU Level.
Identify common approaches, pros and cons, evaluate data adequacy etc. Attempt to summarize, in a critical way the information collection.
Activity 2 (funding opportunities, political initiatives)
12/27
3. Work scheduled and done
GA1.2
1. Introduction2. EU Level 2.1 Funding Programs 2.2 Political Initiatives3. National and Local Level 3.1 Armenia & Yerevan 3.2 Greece & Kavala 3.3 Moldova & Cahul 3.4 Romania & Galati 3.5 Turkey & Samsun & Tekirdag 3.6 Ukaraine & Mykolayiv4. Evaluation
5. Comparison and Conclusions
General information regarding activity’s subject and notions. Issues such as significance of accomplishing the specific activity, references to similar work, definitions et al. may be included.
Analysis of funding programs and political initiatives available in EU.
Same as EU level – an international approach for non EU countries should also be reported.
Each partner-municipality should clarify a number of top priorities and needs regarding its energy related strategy. DUTH will elaborate those priorities according to the respective needs and will develop a dynamic Table for each municipality which will indicate which programs fit to its specific needs.
Identify common approaches, pros and cons, evaluate data adequacy etc. Report summary and conclusions..
Activity 3 (Best Available Practices)
13/27
3. Work scheduled and done
GA1.3
1. Introduction2. Best Available Practices 2.1 Bioclimatic design (AUA) 2.2 RES integration (Samsun) 2.3 Insulation (Cahul) 2.4 Energy efficiency lighting (Tekirdag) 2.5 Automation systems (DUTH) 2.6 Frame replacement (Mykolaiv) 2.7 Update electro/mech syst. (DUNAREA)3. Proposals for Application 3.1 Yerevan 3.2 Kavala 3.3 Cahul 3.4 Galati 3.5 Samsun 3.6 Tekirdag 3.7 Mykolayiv
4. Comparison and Conclusions
Introductory text on the best available practices (BAP) regarding energy efficiency in building sector.
Analytical description and presentation of BAPs related with the specific category..
At least one (1), maximum two (2) application-case study per participant according to the practice chosen before (Chapter 2).
Comparative summary of the BAPs and the case studies. Point out common applicable BAPs, highlight and evaluate BAPs with similar cases within the EU. Conclusive remarks.
Activity 4 (BSBEEP POOL)
14/27
3. Work scheduled and done
GA1.4
1. Introduction2. EU Level 2.1 Public bodies 2.2 Institution 2.3 Private agents/experts3. National and Local Level 3.1 Armenia & Yerevan 3.2 Greece & Kavala 3.3 Moldova & Cahul 3.4 Romania & Galati 3.5 Turkey & Samsun & Tekirdag 3.6 Ukaraine & Mykolayiv
4. Comparison and Conclusions
Introductory text on bodies and experts involved on energy efficiency issues..
List of active bodies and experts in EU level (aim and scope of the body, brief description, service provided and contact details).
List of active bodies and experts (aim and scope of the body, brief description, service provided and contact details) for local.
Comparisons, Evaluation and separation of the mentioned bodies and agents according to the service they provide, Concluding remarks
Activity 5 (BSBEEP AGORA)
15/27
3. Work scheduled and done
GA1.5
1. Introduction2. Building Product List 2.1 Armenia 2.2 Greece 2.3 Moldova 2.4 Romania 2.5 Turkey 2.6 Ukraine
3. Comparison and Conclusions
Introductory text and general information regarding materials and systems related with energy efficiency issues.
Separate various products, materials and services according to their functionality. Each participant will be responsible for product identification in National level.
Summarize, in a critical way the information collected.
Municipalities’ profile(Questionnaire)
16/27
3. Work scheduled and done
Why?
Help the participants in terms of comprehension of the spatial and special characteristics, thus enabling efficient benchmarking.
Provide an initial assessment of the current situation regarding data availability and readiness of your municipality.
Very useful for GA2.
Municipalities’ profile (Questionnaire)
17/27
3. Work scheduled and done
GAYear 1
Semester 1 (Month)
Semester 2 (Month)
1 2 3 4 5 6 7 8 9 10 11 12GA1.1 GA 1.2 GA1.3 GA1.4 GA1.5
Months 5-8 Until 2nd Progress Report – February 2014
What we have to do:
• Four (4) studies collecting information and producing knowledge (from act. 1,2,3,4).
• Each study (approx. 200 pages in average) will be published in seven languages (English, Greek, Romanian, Turkish, Ukrainian, Armenian and Moldavian). [4 studies*200 pages=800 pages]
18/27
4. Work to be done
19/27
4. Work to be done
GA1.1
X: Deliverable is expected X: Deliverable is expected (deadline expired) √: Deliverable sent (revision needed) √: Deliverable sent (final)
Kavala
Galati
Cahul
Mykolayiv
Samsun
Tekirdag
AUA
DUNAREA
DUTH
R2E2 Deadline
1.Introduction (Leader: Cahul) X X 30/11/20132. EU Level (Leader: Kavala)
30/11/2013 2.1 Legal Framework X √ X 2.2 Administrative Framework X √ X 2.3 Challenges and Opportunities X √ X 2.4 Problems and Constraints X √ X 3. National and Local Level
30/11/2013
3.1 Armenia & Yerevan X 3.2 Greece & Kavala X 3.3 Moldova & Cahul X 3.4 Romania & Galati √ 3.5 Turkey & Samsun & Tekirdag X X 3.6 Ukaraine & Mykolayiv X
4. Comparison and Conclusions X 30/11/2013
20/27
4. Work to be done
GA1.2
X: Deliverable is expected X: Deliverable is expected (deadline expired) √: Deliverable sent (revision needed) √: Deliverable sent (final)
Kavala
Galati
Cahul
Mykolayiv
Samsun
Tekirdag
AUA
DUNAREA
DUTH
R2E2 Deadline
1. Introduction (Leader: AUA) X √ X 30/11/20132. EU Level (Leader: DUNAREA)
30/11/2013 2.1 Funding Programs X √ 2.2 Political Initiatives X √ 3. National and Local Level
30/11/2013
3.1 Armenia & Yerevan X 3.2 Greece & Kavala X X 3.3 Moldova & Cahul X 3.4 Romania & Galati √ 3.5 Turkey & Samsun & Tekirdag X X 3.6 Ukaraine & Mykolayiv X 4. Evaluation X 31/12/2013
5. Comparison and Conclusions (Leader:DUTH) X X X 31/12/2013
21/27
4. Work to be done
GA1.3
X: Deliverable is expected X: Deliverable is expected (deadline expired) √: Deliverable sent (revision needed) √: Deliverable sent (final)
Kavala
Galati
Cahul
Mykolayiv
Samsun
Tekirdag
AUA
DUNAREA
DUTH
R2E2 Deadline
1. Introduction X 31/1/20142. Best Available Practices
31/1/2014
2.1 Bioclimatic design X 2.2 RES integration X 2.3 Insulation X 2.4 Energy efficiency lighting X 2.5 Automation systems X 2.6 Frame replacement X 2.7 Update electro/mechanical syst. X 3. Proposals for Application
31/1/2014
3.1 Yerevan X 3.2 Kavala X 3.3 Cahul X 3.4 Galati X 3.5 Samsun X 3.6 Tekirdag X 3.7 Mykolayiv X
4. Comparison and Conclusions X 28/2/2014
22/27
4. Work to be done
GA1.4
X: Deliverable is expected X: Deliverable is expected (deadline expired) √: Deliverable sent (revision needed) √: Deliverable sent (final)
Kavala
Galati
Cahul
Mykolayiv
Samsun
Tekirdag
AUA
DUNAREA
DUTH
R2E2 Deadline
1. Introduction X 31/1/2014
2. EU Level (Leader: Mykolayiv)
31/1/2014 2.1 Public bodies X X X 2.2 Institution X X X 2.3 Private agents/experts X X X 3. National and Local Level
31/1/2014
3.1 Armenia & Yerevan X 3.2 Greece & Kavala X X 3.3 Moldova & Cahul X 3.4 Romania & Galati X 3.5 Turkey & Samsun & Tekirdag X X 3.6 Ukaraine & Mykolayiv X
4. Comparison and Conclusions X 28/2/2014
23/27
4. Work to be done
GAYear 1
Semester 1 (Month)
Semester 2 (Month)
1 2 3 4 5 6 7 8 9 10 11 12GA1.1 GA 1.2 GA1.3 GA1.4 GA1.5
Months 9-12 Until Interim Report – May 2014
What we have to do:
• One (1) study collecting information and producing knowledge (from act.5).
• The study (approx. 200 pages) will be published in seven languages (English, Greek, Romanian, Turkish, Ukrainian, Armenian and Moldavian).
24/27
4. Work to be done
GA1.5
X: Deliverable is expected X: Deliverable is expected (deadline expired) √: Deliverable sent (revision needed) √: Deliverable sent (final)
Kavala
Galati
Cahul
Mykolayiv
Samsun
Tekirdag
AUA
DUNAREA
DUTH
R2E2 Deadline
1. Introduction X 31/1/2014
2. Building Product List
31/1/2014
2.1 Armenia X
2.2 Greece X
2.3 Moldova X
2.4 Romania X
2.5 Turkey X X
2.6 Ukraine X
3. Comparison and Conclusions (Leader: DUNAREA)
X X 15/2/2014
25/27
5. Main bottleneck and constraints
Preparatory activities took too long!Administrative problems! (e.g. contracts, budget and work
allocation). Too much work to do in January/February (11 parallel GA
activities!).
Absorbing the delay is possible BUT We need to follow the timeline!!
26/27
6. Conclusions - Discussion
January is critical for the project.Don’t forget – GA2 has started too and requires our time!!Honest commitment to provide deliverables – Justification of
delay in advance.A good chance to discuss who will work with whom here.
Thank you for your attention!Partner: Democritus University of ThraceContact Person: Ass. Prof. Georgios GAIDAJISPresenter: Komninos ANGELAKOGLOUE-mail: [email protected]. & Fax: +30 25420 79877Mobile Phone: +30 6945 395 119Skype address: geogai
http://www.lemie.gr/en/