48
BSC Panel 202 13 September 2012

BSC Panel 202

  • Upload
    matana

  • View
    51

  • Download
    1

Embed Size (px)

DESCRIPTION

BSC Panel 202. 13 September 2012. Report on Progress of Modification Proposals. Dean Riddell. 13 September 2012. National Grid Update on Energisation Issues. Duncan Burt. 13 September 2012. Transmission Company Update. Update on the rectification plan - January and June ’12 - PowerPoint PPT Presentation

Citation preview

Page 1: BSC Panel 202

BSC Panel 202

13 September 2012

Page 2: BSC Panel 202

Report on Progress of Modification

Proposals

Dean Riddell

13 September 2012

Page 3: BSC Panel 202

National Grid Update on Energisation

Issues

Duncan Burt

13 September 2012

Page 4: BSC Panel 202

Transmission Company Update Update on the rectification plan - January and June ’12

No further failures Oversight team embedded Process aligned with generation connections Improved liaison between Transmission Company /

Elexon Workshop Planned on 26th October 2012

Page 5: BSC Panel 202

Transmission Company Update Established ‘Tracker’ of Registrations

Principle of “No surprises” Annual Review in Jan/Feb when plan handed over Regular updates from construction / operational teams Weekly teleconferences to review and coordinate actions Improved data submission - e.g. draft submissions, forms

with accompanying Single Line Diagrams

Page 6: BSC Panel 202

Transmission Company Update Improved awareness and training

Engineering bulletin issued on 19th June to raise awareness and proposed changes to working practices

Two Transmission Procedures affected TP131 (Settlement Metering) revised and updated TP106 (Equipment Commissioning) consequential updates Both updates to the TPs are currently in draft form for final

review meeting on 18th September If no significant issues raised both will be issued formally

within weeks

Page 7: BSC Panel 202

Transmission Company Update Working Better

Oversight team is key Single point of contact and escalation route

Improved awareness across the Transmission Company Senior Management committed to review for continuous

improvement Further improvements

Change in policy to simplify installations Propose to introduce unique code into ‘TOGA’ to simplify

automated monitoring of outages

Page 8: BSC Panel 202

Minutes of Meeting 201 & Actions Arising

Adam Richardson

13 September 2012

Page 9: BSC Panel 202

Chairman’s ReportBSC Panel

Andrew Pinder

13 September 2012

Page 10: BSC Panel 202

202/01ELEXON Report

Peter Haigh

13 September 2012

Page 11: BSC Panel 202

202/01ELEXON Report

Smart Update

Chris Rowell13 September 2012

Page 12: BSC Panel 202

12

Expected in the Autumn

• Smart Energy Code (initial sections legally drafted)

• DCC Licence (final version)

Smart Metering: Consultations

Smart Metering Equipment Technical Specifications (SMETS) v2• Home Area Networking (HAN) solution• the communications hub requirements • responsibilities• equipment assurance

8 Oc

t

Consequential Changes (SVG Paper)

Page 13: BSC Panel 202

13

Smart Metering: DCC Licence Award

Draft PQQ issued on 31 Aug• Information regarding the DCC, the

licence application process & evaluation process for the stage.

• Draft Qualification Questionnaire

Draft PQQ issued on 31 Aug• Information regarding the DCC, the

licence application process, & evaluation process for the stage.

• Draft Qualification Questionnaire

Expected Timetable (dependent on Prohibition Order & Licence Application Regulations) ~ 3 month deferral of

startshort formal PQQ processBUT early sight of draft~ 3 month deferral in grantD+1 SP signingno change to start of roll out

Page 14: BSC Panel 202

14

Smarter Markets: The Policy Reviews

2011-12

Q. When we have smart metering,

how do we improve the consumer

experience?

Change Programme

4 Policy

Reviews8

Propositions2012-13 2014 +

Scoping ReportApproach & Plan

Review of Policy not Process

Impact on 2013/14 Business Plan?

Senior Advisory Group

P202/06:Scope for review of settlement

Page 15: BSC Panel 202

15

Smart Grids: LCNF Projects

LCNF: Low Carbon Network Fund

Running from 2010 to 2015 - up to £500m - support to DNO sponsored projects - addressing new technology, operating & commercial arrangements – sharing findings

First Tier

Small projects - partial recovery of funding – up to £16m per year

Second TierFlagship projects - annual competition - up to £64m per year

Discretionary Award

successful completion & exceptional projects - up to £100m over the 5 years

Technologies & equipmentSystems operationConsumer behaviourData monitoring & analysisMarket models

Page 16: BSC Panel 202

16

Smart Budget

M J J A S OA N D J F MO

Backfill MembershipsConferences(Analysis)

£ 300K £ 131K

£ 1,200 K

Page 17: BSC Panel 202

Distribution Report

David Lane

13 September 2012

Page 18: BSC Panel 202

Transmission Report

Ian Pashley

13 September 2012

Page 19: BSC Panel 202

Ofgem Report

Dora Ianora

13 September 2012

Page 20: BSC Panel 202

Report from the PAB(Quarterly Update)

Andrew Colley

13 September 2012

Page 21: BSC Panel 202

202/04Proposal to hold the

2013 ISG & SVG meetings on the

same day

Kathryn Coffin

13 September 2012

Page 22: BSC Panel 202

22

• Hold 2013 ISG and SVG meetings on same dates

• Start with ISG, then shared business, then SVG

• Use indicative timed agendas to help members plan travel

• Provide room for SVG Members to work, in case ISG overruns

• If bumper agenda, start with shared business and then split into different rooms

• Will still be separate Committees – existing Terms of Reference continue to apply

Suggestion

Page 23: BSC Panel 202

23

Why?

ISG 13121/12

13224/01

13321/02

13427/03

-24/04

13529/05

13626/06

-24/07

13728/08

Decision papers

6 (+ 1)

2 4 2 0 2 (+ 3)

3 0 6 (+ 1)

Shared business

14% Zero 25% 50% - 40% 33% - 57%

SVG 13103/01

13231/01

13328/02

13403/04

13501/05

13606/06

13703/07

13831/07

13904/09

Decision papers

3 8 6 4 4 6 (+ 1)

2 2 12

Shared business

33% Zero 17% 25% Zero 43% Zero 50% 50%

Papers in brackets were ex-committeeExamples of shared business: CPs or Metering Dispensations with both CVA/SVA impacts

Page 24: BSC Panel 202

24

Committee views

ISG – Against (unanimous) SVG – For (unanimous)

• Some confidential Committee items

• Volume of business is variable• Future workload could increase• No clear start time for SVG• Difficult to manage meeting• Potential late finish and travel

issues for SVG (more time away from office)

• Already use teleconferencing if low volume of business

• Little apparent benefit for Parties• Parties who monitor/support both

Committees prefer spacing out papers

• No issue with joint business – defer to SVG if SVA; few disagreements

• Could constrain ability to discuss wider industry matters

• Supportive of suggestion in principle, subject to practicalities

• Enthusiastic about bringing Committees together – encourage Panel to explore all options

• Unless causes excessively late finish, would be more efficient

• Benefits in discussing joint business together

• Reduces uncertainty for Parties on whether a joint Change Proposal or Metering Dispensation approved

Page 25: BSC Panel 202

25

The BSC Panel is invited to:

• NOTE ELEXON’s paper on the suggested benefits and practicalities;

• NOTE the views expressed by Committee Members for and against;

• AGREE whether the 2013 ISG meetings should be held a week later than currently, on the same dates as SVG; and

• NOTE that, if the Panel adopts this approach, the ISG and SVG can review in 12 months (or sooner if needed)

Recommendations

Page 26: BSC Panel 202

202/05Panel and Panel

Committee Dates for 2013

Nicola Dempsey

13 September 2012

Page 27: BSC Panel 202

27

The BSC Panel is invited to:

• APPROVE the proposed dates; and

• APPROVE their publication on the ELEXON website.

Recommendations

Page 28: BSC Panel 202

202/06 Scope for Review of

Settlement

David Jones / Justin Andrews

13 September 2012

Page 29: BSC Panel 202

Smarter Markets – review of Settlement Reform

»Panel agreed to provide a report to Ofgem – how it would undertake a review of Settlement in a smart world

»Establish an advisory group:»Settlement Reform Scoping Group (SRSG)»Membership drawn from existing committees

with varied industry backgrounds»Terms of Reference (includes outline of report

content)

Page 30: BSC Panel 202

30

Timetable

Page 31: BSC Panel 202

31

The BSC Panel is invited to:

• AGREE to the creation of the Settlement Reform Scoping Group (SRSG) and the group Terms of Reference (Attachment 1);

• AGREE to the chairmanship and membership of SRSG (Appendix A); and

• AGREE the plan for delivering the scoping report (Appendix B).

Recommendations

Page 32: BSC Panel 202

Summary of Consultation on BSC

Service Manager Contract Principles

Adam Richardson

13 September 2012

Page 33: BSC Panel 202

33

Appointing a BSC Service Manager

Work Stream Responsibility

1. Modification P284: Enables BSCCo to outsource work to a BSC Service Manager.

The Authority makes a determination following a BSC Panel recommendation.

2. BSC Service Description: Defines the services capable of being outsourced.

The BSC Panel is responsible for approving the BSC Service Description for use.

3. Contract: Negotiating and agreeing appropriate Contractual Provisions required for outsourced arrangement with a BSC Service Manager.

The BSCCo Board is responsible for putting in place appropriate commercial and contractual provisions.

Page 34: BSC Panel 202

34

• Should a case be made for outsourcing and appropriate commercial and contractual terms developed, the BSC Service Manager Contract will be provided to the BSCCo Board for review and approval prior to being agreed.

Or

• If a case is not made for outsourcing or if commercial and contractual terms cannot be agreed which satisfy the principles established by the BSCCo Board the BSC services will not be outsourced and will continue to be provided by BSCCo.

Ultimately

Page 35: BSC Panel 202

35

Consultation Respondents

• National Grid• Electricity North West Ltd• Scottish Power Group• Drax Power Ltd• EDF Energy• Centrica• E.ON• SmartestEnergy Ltd• RWE npower• Eggborough Power Ltd• TMA Data Management Ltd• EnAppSys Ltd

1 Aug 3 Sep

Consultation

6 SepWorkshop

• Peter Bolitho – E.ON • Andy Colley – SSE • David Lane – Clear

Energy• Ian Pashley – National

Grid• Colette Baldwin – E.ON • Tim Collins – Centrica • Gemma Hunt –

Smartest • Cem Sueyman – Drax • Mari Toda – EDF • Lisa Waters –

WatersWye

12 Responses49 Parties, 9 Non-Parties

Page 36: BSC Panel 202

36

Summary of Consultation Responses (1)

Question Yes No Other

1: Are there any specific discretions, judgements or services currently provided by ELEXON Ltd that you feel it would be inappropriate for BSCCo to subcontract to a service management company?

7 5 -

2: Are the principles set out in Section 4 appropriate for use in underpinning a decision whether to appointment a BSC Service Manager?

7 2 3

3: Do you believe the principles set out in section 4 are consistent with Ofgem’s conclusions and prerequisite conditions published in its letter of 30 April 2012? 8 2 2

4: Are there any additional principles which you believe the BSCCo Board should use to underpin any outsourcing decision?

7 5 -

5: Do you have any other comments? 7 5 -

Page 37: BSC Panel 202

37

• 3 New bullet points within Principles• Confidentiality and Data Protection• Conflict of Interest• Transition Arrangements

 • Additional exclusions under paragraph 3.4 (related to

areas of potential conflict of interest)

• A number of clarifications to Contract Principles

Summary of Consultation Responses (2)

Page 38: BSC Panel 202

38

• Many responses identify elements that will flow through into:• BSC Service Manager Service Description• BSC Service Manager Contract• Some comments aimed at operating model and

resourcing • Comments on “zero Risk” & “all IPR irrespective of

commercial viability”• Desire for more information on KPIs and Service Levels (to

be detailed in contract) • Pension liability - avoid crystallising for as long as

possible• Contract term - preference for 5 years (recognising

incentive value in possible extenion options).

Summary of Consultation Responses (3)

Amendment Details

Page 39: BSC Panel 202

39

Subject to Approval of P284…

• Panel Invited to Appoint Panel Observer to: • review documentation; advise BSCCo team; and ensure

process followed

• Update the Contract Framework (Contract Principles)

• Develop Term Sheet

• Review Business Case against Contract Principles

Next Steps

Page 40: BSC Panel 202

Any Other Business

13 September 2012

Page 41: BSC Panel 202

Confidential Business Closed Session

13 September 2012

Page 42: BSC Panel 202

202/07ISG & SVG Membership

Changes

Adam Richardson

13 September 2012

Page 43: BSC Panel 202

43

The BSC Panel is invited to:

• NOTE the resignations of Bob Brown as ISG/SVG Industry Member and Mark Field as SVG Industry Alternate

• APPOINT Edward Hunter as SVG Industry Alternate

• APPOINT Colette Baldwin as SVG Industry Alternate

• NOTE that ELEXON has advertised the ISG/SVG Industry Member vacancy and will bring all applications to the October Panel

Recommendations

Page 44: BSC Panel 202

202/08Appointment of PAB

Industry Alternate

Adam Richardson

13 September 2012

Page 45: BSC Panel 202

45

The BSC Panel is invited to:

• APPROVE Hazel Ward as a Member of the PAB

Recommendations

Page 46: BSC Panel 202

Any Other Business

13 September 2012

Page 47: BSC Panel 202

Next Panel Meeting:11 October 2012

13 September 2012

Page 48: BSC Panel 202