Upload
matana
View
51
Download
1
Tags:
Embed Size (px)
DESCRIPTION
BSC Panel 202. 13 September 2012. Report on Progress of Modification Proposals. Dean Riddell. 13 September 2012. National Grid Update on Energisation Issues. Duncan Burt. 13 September 2012. Transmission Company Update. Update on the rectification plan - January and June ’12 - PowerPoint PPT Presentation
Citation preview
BSC Panel 202
13 September 2012
Report on Progress of Modification
Proposals
Dean Riddell
13 September 2012
National Grid Update on Energisation
Issues
Duncan Burt
13 September 2012
Transmission Company Update Update on the rectification plan - January and June ’12
No further failures Oversight team embedded Process aligned with generation connections Improved liaison between Transmission Company /
Elexon Workshop Planned on 26th October 2012
Transmission Company Update Established ‘Tracker’ of Registrations
Principle of “No surprises” Annual Review in Jan/Feb when plan handed over Regular updates from construction / operational teams Weekly teleconferences to review and coordinate actions Improved data submission - e.g. draft submissions, forms
with accompanying Single Line Diagrams
Transmission Company Update Improved awareness and training
Engineering bulletin issued on 19th June to raise awareness and proposed changes to working practices
Two Transmission Procedures affected TP131 (Settlement Metering) revised and updated TP106 (Equipment Commissioning) consequential updates Both updates to the TPs are currently in draft form for final
review meeting on 18th September If no significant issues raised both will be issued formally
within weeks
Transmission Company Update Working Better
Oversight team is key Single point of contact and escalation route
Improved awareness across the Transmission Company Senior Management committed to review for continuous
improvement Further improvements
Change in policy to simplify installations Propose to introduce unique code into ‘TOGA’ to simplify
automated monitoring of outages
Minutes of Meeting 201 & Actions Arising
Adam Richardson
13 September 2012
Chairman’s ReportBSC Panel
Andrew Pinder
13 September 2012
202/01ELEXON Report
Peter Haigh
13 September 2012
202/01ELEXON Report
Smart Update
Chris Rowell13 September 2012
12
Expected in the Autumn
• Smart Energy Code (initial sections legally drafted)
• DCC Licence (final version)
Smart Metering: Consultations
Smart Metering Equipment Technical Specifications (SMETS) v2• Home Area Networking (HAN) solution• the communications hub requirements • responsibilities• equipment assurance
8 Oc
t
Consequential Changes (SVG Paper)
13
Smart Metering: DCC Licence Award
Draft PQQ issued on 31 Aug• Information regarding the DCC, the
licence application process & evaluation process for the stage.
• Draft Qualification Questionnaire
Draft PQQ issued on 31 Aug• Information regarding the DCC, the
licence application process, & evaluation process for the stage.
• Draft Qualification Questionnaire
Expected Timetable (dependent on Prohibition Order & Licence Application Regulations) ~ 3 month deferral of
startshort formal PQQ processBUT early sight of draft~ 3 month deferral in grantD+1 SP signingno change to start of roll out
14
Smarter Markets: The Policy Reviews
2011-12
Q. When we have smart metering,
how do we improve the consumer
experience?
Change Programme
4 Policy
Reviews8
Propositions2012-13 2014 +
Scoping ReportApproach & Plan
Review of Policy not Process
Impact on 2013/14 Business Plan?
Senior Advisory Group
P202/06:Scope for review of settlement
15
Smart Grids: LCNF Projects
LCNF: Low Carbon Network Fund
Running from 2010 to 2015 - up to £500m - support to DNO sponsored projects - addressing new technology, operating & commercial arrangements – sharing findings
First Tier
Small projects - partial recovery of funding – up to £16m per year
Second TierFlagship projects - annual competition - up to £64m per year
Discretionary Award
successful completion & exceptional projects - up to £100m over the 5 years
Technologies & equipmentSystems operationConsumer behaviourData monitoring & analysisMarket models
16
Smart Budget
M J J A S OA N D J F MO
Backfill MembershipsConferences(Analysis)
£ 300K £ 131K
£ 1,200 K
Distribution Report
David Lane
13 September 2012
Transmission Report
Ian Pashley
13 September 2012
Ofgem Report
Dora Ianora
13 September 2012
Report from the PAB(Quarterly Update)
Andrew Colley
13 September 2012
202/04Proposal to hold the
2013 ISG & SVG meetings on the
same day
Kathryn Coffin
13 September 2012
22
• Hold 2013 ISG and SVG meetings on same dates
• Start with ISG, then shared business, then SVG
• Use indicative timed agendas to help members plan travel
• Provide room for SVG Members to work, in case ISG overruns
• If bumper agenda, start with shared business and then split into different rooms
• Will still be separate Committees – existing Terms of Reference continue to apply
Suggestion
23
Why?
ISG 13121/12
13224/01
13321/02
13427/03
-24/04
13529/05
13626/06
-24/07
13728/08
Decision papers
6 (+ 1)
2 4 2 0 2 (+ 3)
3 0 6 (+ 1)
Shared business
14% Zero 25% 50% - 40% 33% - 57%
SVG 13103/01
13231/01
13328/02
13403/04
13501/05
13606/06
13703/07
13831/07
13904/09
Decision papers
3 8 6 4 4 6 (+ 1)
2 2 12
Shared business
33% Zero 17% 25% Zero 43% Zero 50% 50%
Papers in brackets were ex-committeeExamples of shared business: CPs or Metering Dispensations with both CVA/SVA impacts
24
Committee views
ISG – Against (unanimous) SVG – For (unanimous)
• Some confidential Committee items
• Volume of business is variable• Future workload could increase• No clear start time for SVG• Difficult to manage meeting• Potential late finish and travel
issues for SVG (more time away from office)
• Already use teleconferencing if low volume of business
• Little apparent benefit for Parties• Parties who monitor/support both
Committees prefer spacing out papers
• No issue with joint business – defer to SVG if SVA; few disagreements
• Could constrain ability to discuss wider industry matters
• Supportive of suggestion in principle, subject to practicalities
• Enthusiastic about bringing Committees together – encourage Panel to explore all options
• Unless causes excessively late finish, would be more efficient
• Benefits in discussing joint business together
• Reduces uncertainty for Parties on whether a joint Change Proposal or Metering Dispensation approved
25
The BSC Panel is invited to:
• NOTE ELEXON’s paper on the suggested benefits and practicalities;
• NOTE the views expressed by Committee Members for and against;
• AGREE whether the 2013 ISG meetings should be held a week later than currently, on the same dates as SVG; and
• NOTE that, if the Panel adopts this approach, the ISG and SVG can review in 12 months (or sooner if needed)
Recommendations
202/05Panel and Panel
Committee Dates for 2013
Nicola Dempsey
13 September 2012
27
The BSC Panel is invited to:
• APPROVE the proposed dates; and
• APPROVE their publication on the ELEXON website.
Recommendations
202/06 Scope for Review of
Settlement
David Jones / Justin Andrews
13 September 2012
Smarter Markets – review of Settlement Reform
»Panel agreed to provide a report to Ofgem – how it would undertake a review of Settlement in a smart world
»Establish an advisory group:»Settlement Reform Scoping Group (SRSG)»Membership drawn from existing committees
with varied industry backgrounds»Terms of Reference (includes outline of report
content)
30
Timetable
31
The BSC Panel is invited to:
• AGREE to the creation of the Settlement Reform Scoping Group (SRSG) and the group Terms of Reference (Attachment 1);
• AGREE to the chairmanship and membership of SRSG (Appendix A); and
• AGREE the plan for delivering the scoping report (Appendix B).
Recommendations
Summary of Consultation on BSC
Service Manager Contract Principles
Adam Richardson
13 September 2012
33
Appointing a BSC Service Manager
Work Stream Responsibility
1. Modification P284: Enables BSCCo to outsource work to a BSC Service Manager.
The Authority makes a determination following a BSC Panel recommendation.
2. BSC Service Description: Defines the services capable of being outsourced.
The BSC Panel is responsible for approving the BSC Service Description for use.
3. Contract: Negotiating and agreeing appropriate Contractual Provisions required for outsourced arrangement with a BSC Service Manager.
The BSCCo Board is responsible for putting in place appropriate commercial and contractual provisions.
34
• Should a case be made for outsourcing and appropriate commercial and contractual terms developed, the BSC Service Manager Contract will be provided to the BSCCo Board for review and approval prior to being agreed.
Or
• If a case is not made for outsourcing or if commercial and contractual terms cannot be agreed which satisfy the principles established by the BSCCo Board the BSC services will not be outsourced and will continue to be provided by BSCCo.
Ultimately
35
Consultation Respondents
• National Grid• Electricity North West Ltd• Scottish Power Group• Drax Power Ltd• EDF Energy• Centrica• E.ON• SmartestEnergy Ltd• RWE npower• Eggborough Power Ltd• TMA Data Management Ltd• EnAppSys Ltd
1 Aug 3 Sep
Consultation
6 SepWorkshop
• Peter Bolitho – E.ON • Andy Colley – SSE • David Lane – Clear
Energy• Ian Pashley – National
Grid• Colette Baldwin – E.ON • Tim Collins – Centrica • Gemma Hunt –
Smartest • Cem Sueyman – Drax • Mari Toda – EDF • Lisa Waters –
WatersWye
12 Responses49 Parties, 9 Non-Parties
36
Summary of Consultation Responses (1)
Question Yes No Other
1: Are there any specific discretions, judgements or services currently provided by ELEXON Ltd that you feel it would be inappropriate for BSCCo to subcontract to a service management company?
7 5 -
2: Are the principles set out in Section 4 appropriate for use in underpinning a decision whether to appointment a BSC Service Manager?
7 2 3
3: Do you believe the principles set out in section 4 are consistent with Ofgem’s conclusions and prerequisite conditions published in its letter of 30 April 2012? 8 2 2
4: Are there any additional principles which you believe the BSCCo Board should use to underpin any outsourcing decision?
7 5 -
5: Do you have any other comments? 7 5 -
37
• 3 New bullet points within Principles• Confidentiality and Data Protection• Conflict of Interest• Transition Arrangements
• Additional exclusions under paragraph 3.4 (related to
areas of potential conflict of interest)
• A number of clarifications to Contract Principles
Summary of Consultation Responses (2)
38
• Many responses identify elements that will flow through into:• BSC Service Manager Service Description• BSC Service Manager Contract• Some comments aimed at operating model and
resourcing • Comments on “zero Risk” & “all IPR irrespective of
commercial viability”• Desire for more information on KPIs and Service Levels (to
be detailed in contract) • Pension liability - avoid crystallising for as long as
possible• Contract term - preference for 5 years (recognising
incentive value in possible extenion options).
Summary of Consultation Responses (3)
Amendment Details
39
Subject to Approval of P284…
• Panel Invited to Appoint Panel Observer to: • review documentation; advise BSCCo team; and ensure
process followed
• Update the Contract Framework (Contract Principles)
• Develop Term Sheet
• Review Business Case against Contract Principles
Next Steps
Any Other Business
13 September 2012
Confidential Business Closed Session
13 September 2012
202/07ISG & SVG Membership
Changes
Adam Richardson
13 September 2012
43
The BSC Panel is invited to:
• NOTE the resignations of Bob Brown as ISG/SVG Industry Member and Mark Field as SVG Industry Alternate
• APPOINT Edward Hunter as SVG Industry Alternate
• APPOINT Colette Baldwin as SVG Industry Alternate
• NOTE that ELEXON has advertised the ISG/SVG Industry Member vacancy and will bring all applications to the October Panel
Recommendations
202/08Appointment of PAB
Industry Alternate
Adam Richardson
13 September 2012
45
The BSC Panel is invited to:
• APPROVE Hazel Ward as a Member of the PAB
Recommendations
Any Other Business
13 September 2012
Next Panel Meeting:11 October 2012
13 September 2012