Upload
john-latilla
View
352
Download
6
Embed Size (px)
Citation preview
Targeted buffer blasting to control
movement along bedding plane shears
John Latilla – Thiess (Formerly – AMC Consultants)
Batdelger Tumur-Ochir – Energy Resources, Mongolia
Coal 2016
University of Wollongong, 10-12 February 2016
Ukhaa Khudag Coking Coal Mine, Mongolia
Locality
Infrastructure
CHPP (annual washing capacity of 15 million tonnes coal)
Power plant (18 MW)
250 km Road to Gants Mod on the Chinese border
Camp and Aimag
Airfield
Planned rail link
Infrastructure
Tavantolgoi coal basin and UHG infrastructure map (proposed railway line is in red)
CHPP (with 3 modules)
Power plant
Central office at mine site
Workshops
Camp
Residential village for workers
Coal seams – qualities and dips
High quality hard coking coal plus thermal
Multiple seams dipping generally 3° to 17° into highwall
Flanks (endwalls) dipping 5° to 40° out of pit wall
Production rate
Mining contractor Thiess (Asia)
Terrace mining (truck and shovel)
Ex-pit waste dumping
Coal – 4.6Mt (2014) capacity of 15M Tonnes per annum
Overburden removal – 26.3M BCM per annum (2014)
Production fleet capable of meeting the demands of 15Mtpa CHPP
Pit dimensions (end 2015) ±2.2km E-W, ±2.0km N-S and ±170m deep
Overview of structure and major stability
issues
Mine plan (current pit shell with faults)
E-W structure
Strata generally dipping into highwall along the main direction of advance
(±3 times vertical exaggeration on cross section)
W E
N-S structure
Generally dipping into the pit. There has been a significant amount for
folding and thrust faulting resulting in bedding shears
Bedding plane shears are common in coal seams and more common
in higher quality seams
Other shear zones are also present and can be up to tens of metres
wide, they often cut through bedding and are associated mainly with
thrust faulting. Not part of this presentation.
N-S structure (LOM pit design with current pit shell)
S N
N-S structure (LOM pit design with current pit shell)
NS
Geological structure summary
Complex structure with multiple major disturbance phases, faulting,
folding, and shearing. Dominant environment is compression.
Main northern and southern fault zones (boundary faults) plus
numerous other faulted zones (fault corridors) which still contain coal
seams but where it is difficult to model and predict their structure
Influence of bedding plane shears
Major driver of significant sliding failures
Structure rather than rock strength defines slope behaviour
Approx. 90% of all significant failures are classified as sliding failures
along bedding shears
Zero cohesion and friction angle (13°) assumed – confirmed by back
analysis and very similar to quoted values in literature
Recorded instances of nearby production blasts initiating failure as well
as re-mobilising failures along bedding shears
Failures along faults – have occurred but not common
South endwall slope failure (July 2013)
Buffer blast strip overrun by the leading edge of the failure by between around 10 and 15m
10m wide by 6m high waste buttress proposed for on top of the buffer blast but not placed
Overall about 20m of displacement – the entire section of slope moved as one unit along beddingplane shear 2m below roof of 0C seam (Large areas moved as solid blocks with only occasionalcracks visible)
Site geotechs measured accelerating opening of cracks (monitored crack meters) and gave warning
Failure triggered by confined, high energy production blast in box cut sited on SW corner of failure(Shot # 547 maximum instantaneous charge 4,604kg)
Long straight major tensile crack along sub-vertical shear visible after failure. An earlier blast (left inplace) lay along the line of the shear
Considerable work done on site to quantify slope damage due to blast vibrations (not the subject ofthis presentation). Intact rock expected to be damaged for a distance of up to 150 m from blast edgeand single blast estimated to be enough to cause failure up to about 60 m away
South endwall slope failure (July 2013)
Approx. position
of major tensile
crack
South endwall slope failure (July 2013)
South endwall slope failure (July 2013)
Toe position with reference to buffer blast
strip after failure
Bedding shear
Failed section of slope
Buffer blast strip
No heave evident down
dip of buffer blasted strip
Galena analysis – static FOS
Galena analysis – pseudo static earthquake
option
North endwall detached slope (August 2013)
Cracking first observed near crest at dispatch office
Crack monitoring indicated opening up associated with production
blasting
Crest was unloaded 10m high by 50m wide in mid Sept. This assisted
the longer term stability
Coal was recovered from beneath the failure and buffer blasting was
frequently used to anchor the toe to enable coal extraction
North endwall detached slope (August 2013)
0C coal recovery below north endwall
detached slope
Buffer blast &
waste buttress
at toe
Potential solutions
Buffer
blast
Waste
buttress
Managing bedding plane shears
Annual external assessment of proposed pit wall designs. Low FOS
slopes identified (may be the entire slope, or more commonly, a portion
of the slope or an individual batter stack)
Options:
• Mine coal out following dip – slope angle same as dip or shallower. In many
cases this is not optimal for coal recovery especially in tough financial times
(targeting most advantageous stripping ratio)
• Waste buttressing – issues with in-pit dumping at present so not used
routinely
• Targeted buffer blasting – relatively light charges to “rough-up” zones
containing bedding plane shears. Increasing cohesion and friction angle.
This approach is analysed in this presentation
How does buffer blasting work?
FOS=1.13
FOS=1.22
What happens
Blasting disturbs the bedding plane shears and results in disrupted
continuity along the bedding shear planes
This results in an increase of cohesion and friction angle
To achieve best results, the blast must only be strong enough to disturb
the ground and not completely pulverise it
Note – this is not a new idea:
• Earliest identified example Civils in Tennessee “shot in place buttress” late
1960’s (Moore 1986)
• Softwall blasting is a similar concept with the aim being to obliterate
structure (Kelso 2011)
Buffer blasts for different purposes
Targeted buffer blast strip ( the subject of this presentation):
• Utilised where a target zone (typically a coal seam containing
bedding plane shears) has been identified
• The intention is to disrupt the bedding plane shears at the seam
level and then displace the rest of the overlying strata without
completely fragmenting it
• Strata dip generally 5° to 20°
• Also referred to as shot-in-place buttressing (Moore 1986)
Buffer blasts for different purposes
Bench buffer blast (not covered here):
• Entire batter, plus the bench behind, it is identified as being so
structurally disturbed that it is better to blast it and obliterate all
structure
• The entire batter and bench are blasted with a similar charge weight
as a normal production blast and the blasted material is then
excavated at a slope angle of between 40° and 45°
• Also referred to as softwall blasting (Kelso 2011)
• Strata dip generally >20°
Material properties of buffer blasted rock?
For UHG the following Mohr Coulomb material properties have evolved with
time: Unit weight 21.4 kN/m3, c=60 kPa and ϕ=33°
Based on:
• Unsaturated Cat 4 Spoil (Simmons and McManus, 2004) c=50 kPa and ϕ=35°
• Softwall paper: (Kelso) ϕ=30°
• Bowen Basin softwall: c= 50 to 100 kPa and ϕ=35°
• Tennessee, in jointed sandstone with shale bands, application - civils for road
(Moore 1986 - in Xanthakos 1994) ϕ=38°, unit weight 22kN/m3
Phreatic surface
Assumed the buffer blast material acts as a “drain” thereby dropping the
phreatic surface
Current UHG phreatic surface model derived from dipping water levels in blast
holes prior to charging up
The following simplified model for the depth of the average in-pit water level is
suggested:
At surface 23m
Below bench / batter crests 15m
Below bench / batter toes 6 m
Below overall slope toe and under pit floor 1m
Below buffer blast areas Surface conforms to base of buffer blast
Limit equilibrium analyses of buffer blasting
potential
FOS=1.48
FOS=0.94
Limit equilibrium
Galena is the preferred software used for LE analyses – site geotechs
also use Galena
Models usually built by tracing cross sections from the geological
model – some are fairly complex and a few have used up the
50 allowed material profiles
Buffer blasts are limited to max 40 m in design stage due to drilling
constraints – aim is to intersect known zones of bedding plane shears
Buffer blast width is arrived at iteratively with target FOS of 1.2. In
some cases a supplementary waste buttress is needed to achieve the
target FOS
Limit equilibrium
Targeted buffer blasting to control movement along bedding plane
shears is considered a practical option within a strata dip range of
5° to 20°
Minimum – no sliding along bedding plane shears is expected where
the dip is less than 5°
Maximum – practical limitation indicates that targeted BB will be
difficult at dip >20°. At steeper dip it is considered best to extract coal
along dip mining from the top down
Alternatively, BB the entire slope in a series of 50m batters (bench
buffer blasting)
Practical implementation
Identification of areas requiring buffer
blasting
Bench or targeted buffer blast required?
Galena analysis of selected cross sections as supplied by mine
geotech team.
If FOS <1.2 then:
• Reduce slope angle
• Place buttress
• Carry out buffer blast at toe
Depth, width and length of buffer blast block
Depth depends on locality of suspected bedding plane shear zones
and is also limited by drill capability (generally ≤ 40m but one BB of
50m has been blasted
Width determined by Galena analysis – incrementally increased in size
until FOS≥1.2
Length of buffer blast strip is derived by considering a set of cross
sections (Galena is a 2D code)
Buffer blast layout and design
Some issues:
• Drilling capacity
• Depth of bedding shear zones
• Slope of berm or bench must be suitable for safe drilling – wide
enough and flat enough
• Angled buffer holes have been considered but not yet used
• Sometimes it’s too late to buffer the area because the OB is
production blasted or there is no OB left on top of coal seam etc.
Buffer blast layout and design
Deep buffer
blast
example
Buffer blast layout and design
Targeted buffer blast charge weight typically around 40% of the normal charge
weight for a production blast of the same depth:
Burden normally 7.5m
Drill hole diameter usually 229mm
Average charge weight per blasthole
• Deep holes >= 40m 1010kg
• Intermediate holes 20-40m 332kg
• Shallow holes < 20m 316kg
Powder factor avg. 0.36kg/bcm (0.14 to 0.52)
Maximum instantaneous charge (MIC (8ms)) 2532kg
Buffer blast scheduling
The scheduling of the blast must be such that the buffer
strip is blasted before mining of the coal or other strata
down dip from it. In other words, while the planned buffer
blasted toe is still buttressed by solid rock or coal.
Drilling and blasting the buffer strip at the slope toe after
the down dip material has been removed, would entail
drilling and charging up on a bench at the toe of a sub 1.0
FOS slope.Note that this slide was added after Coal 2016 in response to a question from a
delegate. The need to schedule the blast as outlined on this slide was implied but not
specified – this additional page rectifies that shortcoming.
Results
Blast
block
ID Pit sector Date Remarks
586a NEW1 3/09/2013
Unnecessary in retrospect - flat seam dip identified in subsequent (closer)
cross section. Indicated dip at time of design 6°
605 NEW1 25/09/2013 Successful (without subsequent placement of waste buttress)
397 ELW 3/12/2012 Successful (ramp operating on top of buffer block - no cracks observed)
433 NEW1 4/02/2013 Successful
480 NEW1 23/03/2013 Successful
512 SEW1A 6/05/2013
Unsuccessful (major endwall failure, triggered by box cut blast, overran
buffer strip). Waste buttress not placed on top. Buffer may have prevented
the failure from extending further down slope.
675 SEW1A 26/11/2013
Probably successful - slope behind buffer stable but narrow strip between
buffer and toe is unstable (where they overlap) - floor heave at toe. Part of
floor heave and toe instability area is not in front of the buffer blast.
343 SEW1 12/10/2012
Probably successful (slope stable but exposed buffer portion of slope does
not appear very disrupted)
Summary of results4 successful, 2 probably successful and 1 unsuccessful
Unsuccessful case
Shot# 512
Outcome - Probably helped but major south endwall failure overran (pushed?)
this buffered area. Crackmeter monitoring indicated that slope movement was
triggered by blast vibration
• Planned width 30m but using 7.5m burden spacing means outer rows of
holes were 15m apart. 7.5m burden may be optimistic for light BB charges
• Powder factor 17 kg/bcm
• Buffer blast overrun by ±15m by the front of the failure
• No floor heave observed on pit side of buffer strip
• 6m high by 10m wide waste buttress planned on top of buffer strip – not
placed
Other
Site personnel report that there were no cases where:
• A buffer blast was recommended but not implemented and then the
slope failed (failure due to not being buffer blasted)
• Recommended buffer blast not done but slope remained stable
(stable even though not buffer blasted)
Conclusions
successful
possibly successful
unsuccessful
Summary of conclusions
This is a relatively small sample of cases and as such the following
conclusions should be treated with caution:
• In 86% of cases studied the buffer blasts have been successful or
probably successful in stabilising the slope
• Blast vibration has triggered movement in some cases – this has
received significant attention on site and is far better controlled now
• It appears that, on average, a slope of up to 13° above the strata dip
can be held with the aid of buffer blasting
Also note that conditions at UHG are generally quite dry – low rainfall
and no really strong aquifers. Different outcomes possible in wetter
conditions.
FOS Design dimensions
Blast
block
ID
Pit
sector Seam dip
OSA of
slope above
buffer blast Before BB After BB Depth Width Remarks
(°) (°) (m) (m)
586a NEW1 2 to 6 15 1.25 1.42 40 10 Unnecessary
605 NEW1 8 20 0.88 1.14 / 1.22* 27 40 Successful
397 ELW 15 NA 0.64 1.23 22 38 Successful
433 NEW1 5 27 1.17 1.5 50 10 Successful
480 NEW1 5 16 1.01 1.36 15 30 Successful
512 SEW1A 5 to 11 18 1.14 1.25 / 1.21^ 10 30 Unsuccessful
675 SEW1A 12 to 9 13 0.62 1.03** 32 30 Probably successful
343 SEW1 5 to 10 24 0.81 1.1^^ 22 43 Probably successful
Summary of conclusions
Perceptions
Mining personnel think that buffer blasting helps the slope stability
because of the result of the successful buffered slopes, especially the
Northern Endwall ones
Room for improvement and future
developments
Planning, planning, planning…
A more pro-active method of designing buffer blast blocks. At times the
rate of mining is such that buffer blasts are not designed in time
Improved and quicker identification of areas requiring buffer blasting –
planning TARP implementation. To pre-identify Code Red zones
(where buffer blasting is most likely to be required)
Post blasting assessments
No photos of the previous buffer blasts once exposed. This will be
done in future
Buffer blast assessment data sheet to be developed to collect all
relevant data. Particularly aim at photographic record of bedding plane
shears after they have been disturbed.
Fully buffer blasted endwalls
In some areas the strata dip in endwalls is >20° and the final slope
angle is planned to be just less than the strata dip angle by 1 or 2° (to
accommodate ramps)
Limit equilibrium analyses indicates that it may be possible to steepen
the OSA by as much as 4° by bench buffer blasting all the batters. Fully
buffer blasted slope
Fully buffer blasted endwalls
OSA 20°
OSA 24°
Thank you
Energy Resources, Mongolia are thanked for their
assistance in preparing this presentation and for
permission to share this experience