136
PROJECT MANUAL FOR USF PROJECT NUMBER PF155214600301 CAMPUS RECREATION RENOVATIONS SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS ITN 14-15-MH UNIVERSITY OF SOUTH FLORIDA TAMPA CAMPUS DATE ISSUED: JANUARY 27, 2014

BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

PROJECT MANUAL FOR

USF PROJECT NUMBER PF155214600301 CAMPUS RECREATION RENOVATIONS

SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS ITN 14-15-MH

UNIVERSITY OF SOUTH FLORIDA

TAMPA CAMPUS

DATE ISSUED: JANUARY 27, 2014

Page 2: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 2 OF 69

USF PROJECT MANUAL USF PROJECT MANUAL INDEX

I. PROCUREMENT Section A ......... NOT USED Section B ........ NOT USED Section C ........ Proposal Form Exhibit C .......... Proposal Form Section D ........ NOT USED

II. GENERAL CONDITIONS

Section E ........ General Conditions Exhibit E .......... General Conditions of the Contract for Construction Section F ........ Performance and Payment Bonds Exhibit F-1 ....... Payment Bond (for Labor and Material) Exhibit F-2 ....... Performance Bond Section G ....... Agreement Exhibit G .......... Owner-Contractor Agreement for Construction Section H ........ Forms Exhibit H-1 ....... Certificate of Substantial Completion Exhibit H-2 ....... Certificates of Contract Completion – Contractor’s Affidavit Exhibit H-3 ....... Certificates of Contract Completion – Architect/Engineer Certification Exhibit H-4 ....... NOT USED Exhibit H-5 ....... NOT USED Exhibit H-6 ....... Construction Contract Change Order Exhibit H-7 ....... NOT USED by Contractor Exhibit H-8 ....... Construction Change Directive Exhibit H-9 ....... NOT USED Exhibit H-10 ..... Certificate of Partial Payment Exhibit H-11 ..... Contract Change Order Summary Exhibit H-12 ..... Schedule of Contract Values Exhibit H-13 ..... NOT USED Exhibit H-14 ..... MBE Report

III. TECHNICAL SPECIFICATIONS

01 10 00 ........... Summary of Work 01 78 39 ........... USF CAD Standards 02 40 00 ........... Selective Demolition and Removal of Materials 03 30 00 ........... Misc Cast-in-Place Concrete & Concrete Repair 07 92 00 ........... Joint Sealants 10 14 00 ........... Signage 13 11 00 ........... Swimming Pool & Pool Equipment 22 51 00 ........... Swimming Pool Plumbing Systems 26 00 00 ........... Electrical - General

Page 3: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 3 OF 69

USF PROJECT MANUAL REFERENCES

2013 F.S. Chapter 47 .................. Venue. 2013 F.S. Section 55/03(1) ......... Judgments; rate of interest, generally. 2013 F.S. Chapter 119 ................ Public Records 2013 F.S. Chapter 120 ................ Administrative Procedures Act. 2013 F.S. Section 120.53(5) ....... Rules for implementing indexing and making final orders available for

public inspection. 2013 F.S. Section 120.57 ............ Additional procedures for particular cases. 2013 F.S. Section 215.422.......... Payments, Warrants, & Invoices; Processing Time Limits; Dispute

Resolution; Compliance. 2013 F.S. Section 255.04 ............ Preference to Home Industries in Building Public Buildings 2013 F.S. Section 255.05 ............ Bond of contractor constructing public buildings; form; action by

claimants. 2013 F.S. Section 255.052.......... Substitution of securities for amounts retained on public contracts. 2013 F.S. Section 287.058.......... Contract Document 2013 F.S. Section 287.0585 ....... Late payments by contractors to subcontractors and suppliers; penalty. 2013 F.S. Section 287.132.......... Legislative intent with respect to integrity of public contracting and

purchasing process. 2013 F.S. Section 287.133.......... Public entity crime; denial or revocation of the right to transact business

with public entities. 2013 F.S. Chapter 440 ................ Worker’s Compensation 2013 F.S. Chapter 489 ................ Contracting. 2013 F.S. Chapter 533 ................ Building Construction Standards 2013 F.S. Chapter 533.79(8) ...... Permits; applications; issuance; inspections. 2013 F.S. Chapter 558 ................ Construction Defects 2013 F.S. Chapter 607 ................ Corporations. 2013 F.S. Chapter 624 ................ Insurance Article I, Section 6 ....................... Florida Constitution: Right to Work. Title 18 USC Chapter 47, 1001 ... US Code: Fraud and False Statements. Title 31 USC 9304-9308 .............. US Code: Surety Corporations. Executive Orders 11246 .............. 1965 US Federal Executive Order: Equal Employment Opportunity

Page 4: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 4 OF 69

B-13 BID GUARANTEE Proposals shall be accompanied by a bid guarantee of not less than five (5) percent of the amount of the base bid. This bid guarantee may be a certified check; cashier’s check, treasurer’s check or bank draft of any national or state bank; or bid bond made payable to the Owner. Such check or bid bond shall be submitted with the understanding that it shall guarantee that the Bidder will not withdraw the bid for a period of forty-five (45) days after the scheduled closing time for the receipt of bids; that if the Proposal is accepted, the Bidder will enter into a written contract with the Owner in accordance with the Agreement included as a part of the Contract Documents, and that the required Labor and Materials Payment Bond and Performance Bond will be given; and that in the event of failure to execute said Agreement and give said bonds within ten (10) days after receipt of the form of Agreement and bonds from the Owner, the Bidder shall be liable to the Owner for the full amount of the bid guarantee as representing the damage to the Owner on account of the default of the Bidder in any particular hereof. The bid guarantees shall be returned to all Bidders after execution of the Agreement and the Labor and Materials Payment Bond and the Performance Bond have been approved by the Owner. If the required Agreement and bonds have not been executed within forty-five (45) days after the date of the opening of the bids, then the bid bond or check of any Bidder will be returned upon request, provided the Bidder has not been notified of the acceptance of the Bidder’s Proposal prior to the date of such request. B-14 SURETY COMPANIES ACCEPTABLE TO THE OWNER The Surety for the Bid Bond does not necessarily have to be the same as for the Labor and Material Payment and Performance Bonds. 1. Bid Bonds.

To be acceptable to the Owner as Surety for Bid Bonds, a Surety Company must meet the following requirements at the time the invitation to bid is issued: a. Be in good standing with the Florida Department of Insurance. b. Be authorized or approved to do business in the State of Florida. c. Be authorized to write Surety Bonds in the State of Florida. d. The Bid Bond must be signed by a Florida Licensed Resident Agent who holds a current Power

of Attorney from the Surety Company issuing the Bid Bond. e. Have twice the minimum surplus and capital required by the Florida Insurance Code. f. Be in compliance with all other provisions of Florida Insurance Code (no violation). g. Hold a current valid certificate of authority issued by the United States Department of Treasury

under Sections 31 USC 9304-9308 (Surety Corporations).

2. Performance Bonds and Labor and Material Payment Bonds. The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials Payment Bond and a Performance Bond written by a Surety Company acceptable to the Owner and authorized to do business in the State of Florida and signed or countersigned by a Florida Licensed Resident Agent who holds a current Power of Attorney from the Surety issuing the Bond. The required forms of the Labor and Material Payment Bond, and the Performance Bond are included in the Project Manual.

The cost of the Bonds shall be borne by the Contractor. The Bonds shall be accompanied by a duly authenticated or certified document, evidencing that the person executing the Bonds in behalf of the Surety had the authority to do so on the date of the Bonds. In the usual case the conferring of that authority has occurred prior to the date of the Bonds, and the document showing the date of appointment and enumeration of powers of the person executing the Bonds is accompanied by a certification that the appointment and powers have not been revoked and remain in effect. The date of that certification cannot be earlier than the date of the Bonds. The Bonds shall not be dated earlier than the Agreement.

To be acceptable to the Owner as Surety for Performance and Labor and Materials Payment Bonds, a Surety Company must meet the following requirements at the time the invitation to bid is issued:

a. Be in good standing with the Florida Department of Insurance. b. Authorized or approved to do business in the State of Florida. c. Authorized to write Surety Bonds in the State of Florida. d. For projects for which the contract amount is $500,000 or less:

(1) Have twice the minimum surplus and capital required by the Florida Insurance Code,

Page 5: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 5 OF 69

Chapter 624 (Insurance), Florida Statues. (2) Be in compliance with all other provisions of Florida Insurance Code (no violation). (3) Hold a current valid certificate of authority issued by the United States Department of

Treasury under Sections 31 USC 9304-9308 (Surety Corporations).

e. For projects for which the contract amount is $500,000 or greater: (1) The Surety Company shall have been in business and have a record of successful

continuous operation for at least five years, unless this provision is expressly deleted by addendum or by the Special Conditions to this Project Manual; and

(2) Except for asbestos contracts, for which a B rating is acceptable, the Surety Company shall have at least the following minimum ratings:

Contract Amount Best Ratings Required Financial Size $500,000 to 749,999 A Class V $750,000 to 999,999 A Class VI $1,000,000 to 1,499,999 A Class VII $1,500,000 to 9,999,999 A Class VIII $10,000,000 or more A Class IX

B-27 PARTIAL SETS OF BIDDING DOCUMENTS Familiarity with the full set of Bidding Documents is recommended to assure that the interface among trades is fully identified. The sale of a partial set of Bidding Documents is predicated upon the buyer having had the opportunity to examine a full set, and having accepted the full responsibility for determining that the purchased partial set provides the information necessary to convey the full requirements as revealed by the complete set. Neither the Owner nor the Architect/Engineer shall be liable for the information revealed on less than complete sets of Bidding Documents.

Page 6: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 6 OF 69

USF PROJECT MANUAL EXHIBIT C PROPOSAL FORM

FROM:

(Bidder’s Name) (Address) (FL Corporate I.D. Number)

TO: Mike Hernandez, Purchasing,

University of South Florida, Purchasing 4202 East Fowler Avenue, AOC 200 Tampa, Florida 33620-7550

DATE: 02/20/2014 BIDS TO BE OPENED AT: TIME 00:00, PM PLACE: USF Purchasing

If the Bidder wishes to make last minute modifications to the Proposal, the following spaces may be used. See B-17 (Bid Modifications) of the Instruction to Bidders:

To the Base Bid, Add $ Deduct $ To Alternate No. Add $ Deduct $ To Alternate No. Add $ Deduct $ To Alternate No. Add $ Deduct $

The undersigned, hereinafter called “Bidder,” having visited the site of the proposed Project and having become familiar with the local conditions, nature and extent of the Work, and having examined carefully the drawings and the Project Manual dated Month 00, 0000 proposes to furnish all labor, materials, equipment and other items, facilities, and services for the proper execution and completion of

Project Name & Address: Campus Recreation Renovations - Swimming Pool and Pool Equipment Renovations

Project Number: USF – PF15521460031 in full accordance with the Contract Documents prepared by the firm of Name & Address of A/E in full accordance with the Call for Bids, Instructions to Bidders, Agreement and all other documents relating thereto on file in the Office of the Architect/Engineer and if awarded the Contract, to complete said Work within the time limits specified for the following bid price:

Base Bid: Dollars Dollars ($ 000.00) With the foregoing as a Base Bid, the following costs of alternate proposals are submitted in accordance with the drawings and specifications. All alternates must be quoted. See Section B-8 (Alternates) in the Instruction to Bidders. Unless the Bidder specifically indicates on the Proposal Form that the quotation for the alternate is deductive, all quotations will be considered as additive to the Base Bid.

Alternate No. 1 Add (Deduct) $ Provide:

Alternate No. 2 Add (Deduct) $ Provide:

Alternate No. 3 Add (Deduct) $ Provide:

Page 7: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 7 OF 69

Alternate No. 4 Add (Deduct) $ Provide:

Alternate No. 5 Add (Deduct) $ Provide:

Alternate No. 6 Add (Deduct) $ Provide:

ACKNOWLEDGEMENTS BIDDER INITIAL There is enclosed a cashier’s check, bank draft, or Bid Bond in the amount of not less than five (5) percent of the Base Bid payable to the University of South Florida, as a guarantee for the purpose set out in the Instructions to Bidders.

There is enclosed a list of subcontractors as prescribed by Article B-15 (Listing of Subcontractors) of the Instructions to Bidders.

The Bidder hereby agrees that: The above Proposal shall remain in full force and effect for a period of forty-five (45) calendar days after the time of the opening of this Proposal and that the Bidder will not revoke or cancel this Proposal or withdraw from the competition within the said forty-five (45) calendar days.

In the event the contract is awarded to this Bidder, the Bidder will enter into a formal written Agreement with the Owner in accordance with the accepted bid within ten (10) calendar days after said Agreement is submitted to the Bidder and will furnish to the Owner a Performance Bond and a Labor and Materials Payment Bond with good and sufficient sureties, satisfactory to the Owner, in the amount of 100% of the accepted bid, on the forms and terms comprising Section F (Performance & Payment Bonds) of the Project Manual. The Bidder further agrees that in the event of the Bidder’s default or breach of any of the agreements of this Proposal, the bid deposit shall be forfeited as liquidated damages.

Acknowledgment is hereby made of receipt of the following Addenda issued during the bidding period.

Addendum No. 00 Dated: Month 00, 0000 Addendum No. 00 Dated: Month 00, 0000 Addendum No. 00 Dated: Month 00, 0000 Addendum No. 00 Dated: Month 00, 0000 Addendum No. 00 Dated: Month 00, 0000

Florida Construction Industries Licensing Board Certification: Name Certification No. (Name of Holder) (Certification Number) SIGNED AND SEALED THIS, 00 DAY OF Month, 0000. ( (Signature) Name Title (Name) (Title)

Page 8: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 8 OF 69

USF PROJECT MANUAL EXHIBIT E GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION

GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION

TABLE OF CONTENTS

ARTICLE TITLE Article 1 ........... General Provisions Article 2 ........... Owner Article 3 ........... Contractor Article 4 ........... Administration of the Contract Article 5 ........... Subcontractors Article 6 ........... Construction by Owner by Separate Contractors Article 7 ........... Changes in the Work Article 8 ........... Time Article 9 ........... Payments and Completion Article 10 ......... Protection of Persons and Property Article 11 ......... Insurance and Bonds Article 12 ......... Uncovering and Correction of Work Article 13 ......... Miscellaneous Provisions Article 14 ......... Termination or Suspension of the Contract

ARTICLE 1 GENERAL PROVISIONS 1.1 BASIC DEFINITIONS 1.1.1 THE CONTRACT DOCUMENTS The Contract Documents consist of the Agreement between Owner and Contractor (herein after the Agreement), Conditions of the Contract (General, Supplementary, Special and other Conditions), Drawings, Specifications, addenda issued prior to execution of the Contract, other (documents listed e Agreement and Modifications issued after execution of the Contract. A Modification is: (1) a written amendment to the Contract signed by both parties, (2) a Change Order, (3) a Construction Change Directive, or (4) a written order for a minor change in the Work issued by the Architect/Engineer. Unless specifically enumerated in the Agreement, the Contract Documents do not include other documents such as bidding requirements (advertisement or invitation to bid, Instructions to Bidders, sample forms, the Contractor's bid or portions of addenda relating to bidding requirements). 1.1.2 THE CONTRACT The Contract Documents form the Contract for Construction. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations or agreements, either written or oral. The Contract may be amended or modified only by a Modification. The Contract Documents shall not be construed to create a contractual relationship of any kind between: (1). the Architect/Engineer and Contractor, (2) the Owner and a Subcontractor or Sub-subcontractor or (3) any persons or entities other than the Owner and Contractor. The Architect/Engineer shall, however, be entitled to performance and enforcement of obligations under the Contract intended to facilitate performance of the Architect/Engineer’s duties. 1.1.3 THE WORK The term "Work” means the construction services required by the Contract Documents, whether completed or partially completed, and includes all other labor, materials, equipment· and services provided or to be provided by the Contractor to fulfill ·the Contractor’s obligations. The Work may constitute the whole or a part of the Project. 1.1.4 THE PROJECT The Project is the total construction of which the Work performed under the Contract Documents may be the whole or a part and which may include construction by the Owner or by separate contractors.

Page 9: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 9 OF 69

1.1.5 THE DRAWINGS The Drawings are Ute graphic and pictorial portions of the Contract Documents, wherever located and whenever issued, showing the design, location and dimensions of the Work, generally including plans, elevations, sections, details, schedule and diagrams. 1.1.6 THE SPECIFICATIONS The Specifications are that portion of the Contract Documents consisting of the written requirements for materials, equipment, construction systems, standards and workmanship for the Work, and performance of related services. 1.1.7 THE PROJECT MANUAL The Project Manuel is the volume usually assembled for the Work which may include the bidding requirements, sample forms, Conditions of the Contract and Specifications. 1.2 EXECUTION, CORRELATION AND INTENT 1.2.1 Execution of the documents shall be accomplished by: signing six (6) copies of the Agreement within which the Conditions of the Contract, the Drawings and the date of their latest revisions, the Specifications, and all Addenda issued prior to signing of the Agreement are identified. The Contractor shall execute and return all required forms of the Agreement within 10 days of their receipt. Failure to return all forms correctly executed within 10 days of receipt without written extension by the Owner otherwise, shall constitute an irregularity and shall constitute grounds, at the Owner’s option, either for rejection and forfeiture of Bid Bond or for the deduction on a day for day basis from the time allotted for completion of the Work under Paragraph 4.1 (Time of Commencement and Completion) of the Agreement. If the Contractor is a firm or company owned by an individual, the Agreement shall be executed in the name of the firm or company by the manual signature of the owner. If the Contractor is a partnership, the Agreement shall be executed in the name of the partnership by the manual signature of the partner or partners. If· the Contractor is a corporation, the Agreement shall be executed in the name of the corporation and shall bear the corporate seal. It may be signed for the corporation by the president attested by the secretary; if signed for the corporation by other officer than the president, the signature of such officer signing shall be attested by the secretary, and the executed Agreement shall be accompanied by a duly authenticated document bearing the seal of the corporation, quoting the section of the by-laws of the corporation authorizing the board of directors to designate such officer and copy of the resolution designating and authorizing him to execute on behalf of the corporation. That document must contain a statement that the authority is in effect on the date of the execution of the Contract, and may not be dated earlier than the date of the execution of the Contract. The same officer may not execute the Contract and authenticate the document of authority. 1.2.1.1 Performance and Payment bonds shall be executed on behalf of the Contractor in the same manner and by the same person who executed the Agreement. 1.2.2 Execution of the Contract by the Contractor is a representation that the Contractor has visited the site, become familiar with local conditions under which the Work is to be performed and correlated personal observations with requirement of the Contract Documents. 1.2.3 The intent of the. Contract Documents is to include all items necessary for the proper execution and completion of the Work by the Contractor. The Contract Documents are complementary and what is required by one shall be as binding as if required by all; ·performance by the Contractor shall be required only· to the extent consistent with the Contract Documents and reasonably inferable from them as being necessary to produce the intended results. 1.2.3.1 Where reference is made to the Standard Specifications of the American Society for Testing and Materials (ASTM) or other standard specifications in connection with the required quality of materials, methods, etc., then the applicable specifications shall be of the latest revised edition effective as of the date the bids are opened by the Owner, unless otherwise expressly provided the technical specifications. 1.2.4 Organization of the Specifications into divisions, sections and articles, and arrangement of Drawings shall not control the Contractor in dividing the Work among Subcontractors or in establishing the extent of Work to be performed by any trade.

Page 10: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 10 OF 69

1.2.5 Unless otherwise stated in the Contract Documents, words which have well-known technical or construction industry meanings are used in the Contract Documents in accordance with such recognized meanings. 1.3 OWNERSHIP AND USE OF ARCHITECT/ENGINEER’S DRAWINGS, SPECIFICATIONS AND

OTHER DOCUMENTS 1.3.1 The Drawings, Specifications and other documents prepared by the Architect/Engineer are instruments of the Architect/Engineer’s service through which the Work to be executed by the Contractor is described. The Contractor may retain one contract record set, and the Owner may retain two contract record sets. Neither the Contractor nor any Subcontractor, Sub-subcontractor or material or equipment supplier shall own or claim a copyright of the Drawings, Specifications and other documents prepared by the Architect/Engineer, and unless otherwise indicated the Architect/Engineer shall be deemed the author of them and will retain all common law, statutory and other reserved rights, in addition to the copyright. All copies of them, except the Contractor’s record set and the Owner’s record set, shall be returned or suitably accounted for to the Architect/Engineer, and copies thereof furnished to the Contractor, are for use sorely with respect to this Project. They are not to be used by the Contractor or any Subcontractor, Sub-subcontractor or material or equipment supplier on other Projects or for addition to this project outside the scope of the Work without the specific written consent of the Owner and Architect/Engineer. The Contractor, Subcontractor, Sub-contractors and material or equipment suppliers are granted a limited license to use and reproduce applicable portions of the Drawings, Specifications and other documents prepared by the Architect/Engineer appropriate to and for use in the execution of their Work under the Contract Documents. All copies made under this license shall bear the statutory copyright notice, if any shown in the Drawings, Specifications and other documents prepared by the Architect/Engineer. Submittal or distribution to meet official regulatory requirements or for other purposes in connection with this Project is not to be construed as publication in derogation of the Architect/Engineer’s or other reserved rights. 1.4 CAPITALIZATION 1.4.1 Terms capitalized in these General Conditions include those are: (1) specifically defined, (2) the titles of numbered articles and identified references to Paragraphs and Subparagraphs in the document or (3) the titles of other documents published by other professional organizations or public entity. 1.5 INTERPRETATION 1.5.1 In the interest of brevity the Contract Documents frequently omit modifying words such as "all” and “any” and articles “the” and “an,” but the fact that a modifier or an article is absent form statement and appears in another is not intended to affect the interpretation of either statement. ARTICLE 2 OWNER 2.1 DEFINITION 2.1 1 The Owner is the person or entity identified as such in the Agreement and is referred to throughout the Contract Documents as if: singular in number. The term “Owner” means the Owner or Owner’s authorized representative. 2.2 NFORMATION AND SERVICES REQUIRED OF THE OWNER 2.2.1 The Owner shall, at the request of the Contractor, prior to execution of the Agreement furnish to the Contractor reasonable evidence that financial arrangements have been made to fulfill the Owner's obligations under the Contract. (Note: unless such reasonable evidence were furnished or request prior to the execution of the Agreement, the prospective contractor would not be required to execute the Agreement or to commence the Work) 2.2.2 The Owner shall furnish through the Architect/Engineer, necessary surveys, describing physical characteristics, legal limitations and utility locations for the site of the Project, and a legal description of the site. 2.2.3 Except for permits and fees which are the responsibility of the Contractor under the, Contract Documents, the Owner shall secure and pay for necessary approvals, easements, assessments and

Page 11: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 11 OF 69

charges required for construction, use, or occupancy of permanent structures or for permanent changes in existing facilities. 2.2.4 Information or services under the Owner's control shall be furnished by the Owner with reasonable promptness to avoid delay in orderly progress of the Work. 2.2.5 Unless otherwise provided in the Contract Documents, the Contractor will be furnished, free of charge, such copies of Drawings and Project Manuals for execution of the Work as established in the Special Conditions. If additional sets are required by the Contractor, they will be furnished upon request for the cost of printing and handling. 2.2.6 The foregoing are in addition to other duties and responsibilities of the Owner enumerated herein and especially those in respect to Article 6 (Construction by Owner or by Separate Contractors) and Article 9 (Payments and Completion) herein. 2.3 OWNER’S RIGHT TO STOP THE WORK 2.3.1 If the Contractor fails to correct Work which is not in accordance with the requirements of the Contract Documents as required by Paragraph 12.2 (Correction of Work) herein, the Owner by written order signed personally or an agent specifically so empowered by the Owner in writing may order the Contractor to stop the Work, or any portion thereof; until the cause for such order has been eliminated; however, the right of the Owner to stop the shall not give rise to a duty on the part of the Owner to exercise this right for the benefit of any other person or entity, except to the extent required by Subparagraph 6.1.3 (Coordination of Work by Separate Contractors) herein. 2.4 OWNER'S·RIGHT TO CARRY OUT THE WORK 2.4.1 If the Contractor defaults or neglects to carry out the Work in accordance with the Contract Documents and fails within a seven day period after receipt of written notice from the Owner to commence and continue correction of such defects or neglect with diligence and promptness, the Owner may after such seven day period give the Contractor a second written notice to correct such deficiencies within a second seven day period. If the Contractor within such second seven day period after receipt of such second notice fails to commence and continue correct any deficiencies, the Owner may without prejudice to other remedies, the Owner may have, correct such deficiencies. In such case an appropriate Change Order or Construction Change Directive shall be issued deducting from payments then or thereafter due to Contractor the cost of correcting such deficiencies, including compensation for the Architect/Engineer’s additional services expenses made· necessary by such default, neglect or failure. Such action by the Owner and amounts charged to the Contractor are both subject to prior approval of the Architect/Engineer. If payment then or thereafter due the Contractor are not sufficient to cover such amounts, the Contractor shall pay the difference to the Owner. 2.5 OWNER’S PROJECT REPRESENTATIVES 2.5.1 The Owner shall provide a Project Manager to represent the Owner in administration and management of the Contract on the Owner’s behalf. 2.5.2 The Owner shall provide a construction coordinator inspector to represent the Owner in the Construction of the project on the Owner’s behalf. 2.5.3 The Owner’s Project Manager and/or Construction Coordinator/Inspector are not the Owner’s Authorized Designee. ARTICLE 3 CONTRACTOR 3.1 DEFINITION 3.1.1 The Contractor is the person or entity identified as such in the Agreement and is referred to throughout the Contract Documents as if singular in number. The term “Contractor” means the Contractor or ·the Contractor's authorized representative. 3.2 REVIEW OF CONTRACT DOCUMENTS AND FIELD CONDITIONS BY CONTRACTOR 3.2.1 The Contractor shall carefully study and .compare the Contract Documents with each other and with information furnished by the Owner pursuant to Subparagraph 2.2.2 (Owner furnished Surveys) herein, and shall at once report to the Architect/Engineer errors, inconsistencies or omissions discovered.

Page 12: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 12 OF 69

The Contractor shall not be liable to the Owner or Architect/Engineer for damage resulting from errors, inconsistency or omissions in the Contract Documents unless the Contractor recognized such error, inconsistency or omission and knowingly failed to report to the Architect/Engineer. If the Contractor performs any construction activity knowing it involves a recognized error, inconsistency or omission in the Contract Documents without such notice to the Architect/Engineer, the Contractor shall assume appropriate responsibility for such performance and shall bear an appropriate amount of the attributable costs for correction. 3.2.2 The Contractor shall take field measurements and verify field conditions and shall carefully compare such field measurements and conditions and other information known to the Contractor with the Contract Documents before commencing activities. Errors, inconsistencies, or omissions discovered shall be reported to the Architect/Engineer at once. 3.2.3 The Contractor shall perform the Work in accordance with the Contract Documents and submittals approved pursuant to Paragraph 3.12 (Shop Drawings, Product Data and Samples) herein. 3.3. SUPERVISION AND CONSTRUCTION PROCEDURES 3.3.1 The Contractor shall supervise and direct the Work, using the Contractor’s skill and attention. The Contractor shall be solely responsible for and have control over construction means, methods, techniques, sequences and procedures and for coordinating all portions of the Work and the Contract, unless Contract Documents give other specific instructions concerning these matters. 3.3.2 The Contractor shall be responsible to the Owner for acts and omissions of the Contractor’s employees, Subcontractors and their agents and employees, and other persons performing portions of the Work ·under a contract with to the Contractor. 3.3.3 The Contractor shall not be relieved of obligations to perform the Work in accordance with the Contract Documents either by activities or duties of the Architect/Engineer in the Architect/Engineer's administration of the Contract, or by tests, inspections or approvals required or performed by persons other than the Contractor. 3.3.4 The Contractor shall be responsible for inspection of portions of Work already performed under this Contract to determine that such portions are in proper condition to receive subsequent Work. 3.3.5 The Architect/Engineer will schedule periodic construction meetings; which the Contractor shall be required to attend. 3.3.6 The Contractor shall be responsible for coordinating the work with the A/E and the Owner’s Representatives to assure performance of the work in a manner that is safe, and protects the health and well-being of the University occupants, without unacceptable interruptions or impacts on the University. The Contractor shall obtain prior approval and provide advance notification to the University for coordination and approval prior to implementing work that would impact the University including delivery of materials, staging, power or telecommunications interruptions, etc. 3.4 LABOR AND MATERIALS 3.4.1 Unless otherwise provided in the Contract Documents, the Contractor shall provide and pay for labor, materials, equipment, tools, construction equipment and machinery, water, heat, utilities, transportation, and other facilities and services necessary for proper execution and completion of the Work, whether temporary or permanent and whether or not incorporated or to be incorporated in the Work. 3.4.1.1 It shall be the responsibility of the Contractor to provide at the Contractor’s expense, the power, fuel and equipment necessary to maintain climate conditions including humidity and specified or necessary for Work in progress. 3.4.2 The Contractor shall enforce strict discipline and good order among the Contractor’s employees and other persons carrying out the Contract. The Contractor shall not permit employment of unfit person or persons not skilled in tasks assigned to them.

Page 13: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 13 OF 69

3.5 WARRANTY 3.5.1 The Contractor warrants to the Owner and the Architect/Engineer that materials and equipment furnished under the Contract will be of good quality and new unless otherwise required or permitted by the Contract Documents, that the Work will be free from defects not inherent in the quality required or permitted, and the Work will conform with the requirements of the Contract Documents. Work not conforming to these requirements, including substitutions not properly approved and authorized, may be considered defective. The Contactor’s warranty excludes remedy for damage or defect caused by abuse, modifications not executed by the Contractor, improper or insufficient maintenance, improper operation, or normal wear and tear under oral usage. lf required by the Architect/Engineer, the Contractor shall furnish satisfactory evidence as to the kind and quality of materials and equipment. 3.5.2 As required in Subparagraph 12.2.2 (Correction of Work) herein, the Contractor shall warrant all materials and equipment in accordance with the conditions of the contract. The Contractor shall correct all work found to be defective, or not in accordance with the requirements of the contract documents, for a period of one year from the date of Substantial Completion, or for such longer periods of time for specific warranties required by the contract documents and for the list of items to be completed or corrected at Substantial Completion, unless otherwise agreed to in writing, at no additional cost to the Owner. The Contractor shall conduct, jointly with the Architect and Owner, a warranty inspection forty-five (45) days prior to the end of the warranty periods to address completion of warranty obligations. The Owner shall provide notice to the Contractor of work that requires correction during the warranty periods. 3.5.3 The Contractor shall be responsible to assure that Asbestos Containing Materials (ACM) are not incorporated in the scope of work for the project. The Contractor shall provide Material Safety Data Sheets for all products and materials for the project and shall certify that Asbestos Containing Materials have not been incorporated in the scope of work. 3.6 TAXES 3.6.1 The Contractor shall pay sales, consumer, use and similar taxes for the Work or portions thereof provided by the Contractor which are legally enacted when bids are received or negotiations concluded, whether or not yet effective or merely scheduled to go into effect. 3.6.2 The Owner reserves the right to require the Contractor to develop, manage and administer a sales tax exempt purchasing program by Change Order to this contact if it is determined to be in the best interest of the University, in accordance with the requirements of the Department of Revenue and in adherence with the Facilities Planning & Construction Policies for Sales Tax Exempt Purchasing Procedures. If Implemented, the Contractor shall name the Owner as an additional insured on the Contractor’s Builder’s Risk Insurance to continue to cover the direct purchase materials and the Owner shall pay for the cost of such insurance. 3.7 PERMITS, FEES AND NOTICES 3.7.1 Unless otherwise provided in the Contract Documents, the Contractor shall secure and pay for the building permit and other permits and governmental fees, licenses and inspections necessary for proper execution and completion of the Work, including any connection permits required which are customarily secured after execution of the contract and which are legally required when bids are received or negotiations concluded. 3.7.2 The Contractor shall comply with and give notices required by laws, ordinances, rules, regulations and lawful orders of public authorities bearing on performance of the Work. 3.7.3 It is not the Contractor’s responsibility to ascertain that the Contract Documents are in accordance with applicable laws, statutes, ordinances, building codes, and rules and regulations. However, if the Contractor observes that portions of the Contract Documents are at variance therewith, the Contractor shall promptly notify the Architect/Engineer and Owner in writing, and necessary changes shall be accomplished by appropriate Modification. 3.7.4 If the Contractor performs Work knowing it to be contrary to laws, statutes, ordinances, building codes, and rules and regulations without such notice to the Architect/Engineer and Owner, the Contractor shall assume full responsibility for such Work and shall bear the attributable costs.

Page 14: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 14 OF 69

3.8 ALLOWANCES 3.8.1 The Contractor shall include in the Contract Sum all allowances stated in the Contract Documents. Items covered by allowances shall be supplied for such amounts and by such persons or entities as the Owner may direct, but the Contractor shall not be required to employ persons or entities against which the Contractors makes reasonable objection. 3.8.2 Unless otherwise provided in the Contract Documents:

.1 materials and equipment under an allowance shall be selected promptly by the Owner to avoid delay in the Work;

.2 allowances shall cover the cost to the Contractor of materials and equipment delivered at the site and all required taxes, less applicable trade discounts;

.3 Contractor’s costs for unloading and handling at the site, labor, installation costs, overhead, profit and other expenses contemplated for stated allowance amounts shall be included in the Contract Sum and not in the allowances;

.4 whenever costs are more than or less than allowances, the Contract Sum shall be adjusted accordingly by Change Order. The amount of the Change Order shall reflect (1) the difference between actual costs and the allowances under Subparagraph 3.8.2.2 (Contractor’s Cost) and (2) changes in Contractor’s costs under Subparagraph 3.8.2.3 (Unloading and Handling) herein;

.5 the Contractor shall solicit from information provided by the Architect/Engineer at least three bids for all allowance items from Subcontractors or material suppliers acceptable to the Owner, the Contractor and the Architect/Engineer. The Architect/Engineer shall review the bids and recommend to the Owner the acceptance or rejection of the lowest bid. If accepted the Architect/Engineer shall issue a change order to the Contractor as provided in Subparagraph 3.8.2.4 (Adjustment of Contract Sum) herein.

3.9 PROJECT STAFF 3.9.1 The Contractor shall employ a competent Field Staff including a Project Manager, a Superintendent, a Secretary/Assistant, and if necessary due to the needs of the Project, additional assistants, all to be acceptable to the Owner, who shall be in attendance at the Project site during performance of the Work. The Contractor shall provide required resources at the Project site to assist the Field Staff to meet the requirements of the Contract Documents. The Field Staff shall represent the Contractor, and communications given to the Field Staff shall be as binding as if given to the Contractor. Important communications shall be confirmed in writing. Other communications shall be similarly confirmed on written request in each case. The Field Staff qualifications shall meet or exceed the experience, expertise and ability required for this project. 3.9.2 The Contractor shall employ Home or Branch office employees and provide required resources to support the project and the Field Staff to meet the requirements or the Contract Documents. 3.10 CONTRACTOR’S CONSTRUCTION SCHEDULES 3.10.1 The Contractor, promptly after being awarded the Contract, shall prepare and submit for the Owner’s and Architect/Engineer’s information a Contractor’s construction schedule for the Work. The schedule shall not exceed time limits current under the Contract Documents, shall be revised at appropriate intervals as required by the conditions of the Work and Project, shall be related to the entire Project to the extent required by the Contract Documents, and shall provide for expeditious and practicable execution of the Work. 3.10.2 The Contractor shall prepare and keep current, for the Architect/Engineer’s approval, a schedule of submittals which is coordinated with the Contractor’s construction schedule and allows the Architect/Engineer reasonable time to review submittals. The schedule of submittals shall indicate the dates by which the Architect/Engineer must notify the Contractor of the outcome of the review in order to avoid extension of the Contract Time. 3.10.3 The Contractor shall conform to the most recent schedules. 3.10.4 Within thirty (30) days after the date of the Owner’s issuance of a Notice to Proceed with performance of the Work, the Contractor shall prepare and submit to the Architect/Engineer a

Page 15: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 15 OF 69

construction schedule in quadruplicate. This schedule shall graphically depict the contemplated activities which are necessary incidents to performance of the Work, showing the sequence the Contractor proposes for each activity to occur and the duration (dates of commencement and completion, respectively) of each such activity.

The Construction schedule shall be a critical path schedule that identifies, in detail, the start dates, end dates and critical dates of each subcontract activity and work requirement within the overall project development. The Construction schedule shall include milestone dates, dates to coordinate utility, road, etc. work that impacts the Owner for interruptions, shutdowns, etc. and benchmark dates to assure that the work is being performed to meet Contract Document requirements. 3.10.5 Following development and submittal of the construction schedule as aforesaid, the Contractor shall, at the end of each calendar month occurring thereafter during the period of time required to finally complete the subject Work or at such earlier intervals as circumstances may require, update and/or revise the construction schedule to show the actual progress of the Work performed and the occurrence of all events which have affected the progress of performance of the Work already performed or which will affect the progress of performance of the Work yet to be performed. Each such update and/or revision to the construction schedule shall be submitted to the Architect/Engineer in quadruplicate. Failure of the Contractor to update, revise and submit the construction schedule as aforesaid shall be sufficient grounds for the Architect/Engineer to find the Contractor in substantial default and certify to the Owner that sufficient cause exists to terminate the Contract or to withhold payment to the Contractor until a schedule or schedule update acceptable to the Architect/Engineer is submitted. 3.10.6 The Contractor shall have the option of scheduling a Substantial Completion date occurring earlier than the date established by the Contract Documents for Substantial Completion; provided, however, in such event, such earlier Substantial Completion date will be recognized by the Owner only as a matter of convenience to the Contractor and shall not change the date for Substantial Completion established by the Contract Documents or be otherwise binding on the Owner or anyone under the Owner’s control; and provided further, however, in such event, should events occur during performance of the Work which would justify the granting to the Contractor of an extension of the Contract Time pursuant to the provisions of Article 8 (Time) herein, the Contractor shall be entitled to receive only such an extension of Contract Time as is determined by the Architect/Engineer to be due the Contract or as follows: herein

.1 In the event the current Contractor’s construction schedule indicates completion ahead of the contractually established date for Substantial Completion, the revised Substantial Completion date shall be determined by adding the total time directly affecting the critical path of the schedule to the end date of the current schedule. No extension of time beyond the contractually established date shall be granted until the aggregate of the current Contractor’s construction schedule plus approved extension exceeds the date established by the Contract Documents, at which time the time extension granted will be the net difference between the contractually established date and the aggregate of the current Contractor’s construction schedule plus approved extensions thereto.

.2 In the event the current Contractor’s construction schedule indicates completion at or after the contractually established date for Substantial Completion, the time extension shall only be added to the contractually established date for Substantial Completion.

.3 The Owner will not grant time extensions based on improper scheduling of the Work. 3.11 DOCUMENTS AND SAMPLES AT THE SITE 3.11.1 The Contractor shall maintain at the site for the Owner one record copy of the Drawings, Specifications, addenda, Change Orders and other Modifications, in good order and marked currently to record changes and selections made during construction, and in addition approved Shop Drawings, Product Data, Samples and similar required submittals. These Drawings, Product Data, Samples and similar required submittals shall be available to the Architect/Engineer and shall be delivered to the Architect/Engineer for submittal to the Owner upon completion of the Work. 3.11.2 The Contractor shall provide a record copy of the drawings that reflect as-built conditions for the Project for use in developing record drawings to facilitate the University’s Space Management Program, in addition to use for maintenance and future renovation work. The Owner may withhold payments due and/or reject payment requests for failure of the Contractor to submit a record copy of the drawings.

Page 16: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 16 OF 69

3.12 SHOP DRAWINGS, PRODUCT DATA AND SAMPLES 3.12.1 Shop Drawings are drawings, diagrams, schedules and other data specially prepared for the Work by the Contractor or a Subcontractor, Sub-subcontractor, manufacturer, supplier or distributor to illustrate some portion of the Work. 3.12.2 Product Data are illustrations, standard schedules, performance charts, instructions, brochures, diagrams and other information furnished by the Contractor to illustrate materials or equipment for some portion of the Work. 3.12.3 Samples are physical examples which illustrate materials, equipment or workmanship and establish standards by which the Work will be judged. 3.12.4 Shop Drawings, Project Data, Samples and similar submittals are not Contract Documents. The purpose of their submittal is to demonstrate for those portions of the Work for which submittals are required the way the Contractor proposes to conform to the information given and the design concept expressed in the Contract Documents. Review by the Architect/Engineer is subject to the limitations of Subparagraph 4.2.7 (Architect/Engineer Review) herein. 3.12.4.1 Information submitted shall show the capacity, operating conditions and all engineering data and descriptive information necessary for comparison and to enable the Architect/Engineer to determine compliance with the specifications. 3.12.5 The Contractor shall review, approve and submit to the Architect/Engineer Shop Drawings, Product Data, Samples and similar submittals required by the Contract Documents with reasonable promptness and in such sequence as to cause no delay in the Work or in the activities of the Owner or of separate contractors. Submittals made by the Contractor which are not required by the Contract Documents may be returned without action. 3.12.5.1 Shop Drawings shall be fully identified by Project Name, location, supplier’s name, date, drawing number and specifications section reference. The Contractor shall submit four (4) copies (in addition to those copies necessary for the Contractor’s own requirements) of all Shop Drawings and schedules, or any required resubmission thereof required for the Work of the various trades, to the Architect/Engineer for approval. The Contractor shall make no deviation from the approved drawings, and the changes made thereto by the Architect/Engineer, if any. 3.12.5.2 It shall be the responsibility of the Contractor to properly schedule the submission of Shop Drawings for approval to allow adequate time for checking of drawings, manufacture and shipment of items to job site in sufficient time to prevent delay in the construction schedule. 3.12.5.3 It shall also be the responsibility of the Contractor to coordinate the preparation of Shop Drawings of items which will be furnished by more than one manufacturer but are designed to interface when installed. 3.12.5.4 If and when required by the Architect/Engineer, the Contractor shall prepare and submit in triplicate to the Architect/Engineer a completely itemized Schedule of Shop Drawings, brochures and other descriptive literature, listing each and all such items as required under these specifications, which schedule shall indicate for each required item:

.1 Identification as to pertinent Specification Division.

.2 Item(s) involved.

.3 Name of pertinent Subcontractor or supplier and the name of pertinent manufacturer.

.4 Scheduled date of delivery of pertinent items to the project.

3.12.5.5 The Contractor shall require all Subcontractors to submit to the Architect/Engineer through the Contractor complete brochures covering all materials and/or equipment proposed for use in the execution of the Work as required by their respective Divisions of the Specifications. These brochures shall be indexed and properly cross-referenced to the plans and specifications for easy identification.

Page 17: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 17 OF 69

3.12.5.6 A list of all materials and equipment, together with manufacturers’ drawings and catalog information shall be submitted to the Architect/Engineer for approval prior to ordering material or equipment but not later than 45 days after the date of the Notice to Proceed. Information submitted shall show the capacity, operating conditions and all engineering data and descriptive information. The Architect/Engineer’s approval will not relieve the Contractor of the responsibility for performance of any terms of the Contract Documents. 3.12.6 The Contractor shall perform no portion of the Work requiring submittal and review of Shop Drawings, Product Data, Samples or similar submittals until the respective submittal has been approved by the Architect/Engineer. Such Work shall be in accordance with approved submittals. 3.12.7 By approving and submitting Shop Drawings, Product Data, Samples and similar submittals, the Contractor represents that the Contractor has determined and verified materials, field measurements and field construction criteria related thereto, or will do so, and has checked and coordinated the information contained within such submittals with the requirements of the Work and of the Contract Documents. 3.12.7.1 Shop Drawings submitted to the Architect/Engineer for approval shall first be checked and approved by the Contractor, the evidence of which shall be a “checked” stamp marked “Approved”, or “Approved as Noted” on each copy of each Shop Drawing, placed thereon by the Contractor. Shop Drawings received without the Contractor’s “checked” stamp will be cause for immediate return without further action. Each drawing correctly submitted will be checked by the Architect/Engineer and marked “Approved” or “Not Approved”. 3.12.7.2 Resubmittals necessitated by required corrections due to Contractor’s errors or omissions shall not be cause for extension of Contract Time. 3.12.7.3 At no time shall Shop Drawings which have not been approved by the Architect/Engineer be allowed on the site. 3.12.8 The Contractor shall not be relieved of responsibility for deviations from requirements of the Contract Documents by the Architect/Engineer’s approval of Shop Drawings, Project Data, Samples or similar submittals unless the Contractor has specifically informed the Architect/Engineer in writing of such deviation at the time of submittal and the Architect/Engineer has given written approval to the specific deviation. The Contractor shall not be relieved of responsibility for errors or omissions in Shop Drawings, Product Data, Samples or similar submittals by the Architect/Engineer’s approval thereof. 3.12.9 The Contractor shall direct specific attention, in writing or on resubmitted Shop Drawings, Product Data, Samples or similar submittals, to revisions other than those requested by the Architect/Engineer on previous submittals. 3.12.10 Informational submittals upon which the Architect/Engineer is not expected to take responsive action may be so identified in the Contract Documents. 3.13 USE OF SITE 3.13.1 The Contractor shall confine operations at the site to areas permitted by law, ordinances, permits and the Contract Documents and shall not unreasonably encumber the site with materials or equipment. 3.14 CUTTING AND PATCHING 3.14.1 The Contractor shall by responsible for cutting, fitting or patching required to complete the Work or to make its parts fit together properly. 3.14.2 The Contractor shall not damage or endanger a portion of the Work or fully or partially completed construction of the Owner or separate contractors by cutting, patching or otherwise altering such construction, or by excavation. The Contractor shall not cut or otherwise alter such construction by the Owner or a separate contractor except with written consent of the Owner and of such separate contractor; such consent shall not be unreasonably withheld. The Contractor shall not unreasonably withhold from the Owner or a separate contractor the Contractor’s consent to cutting or otherwise altering the Work.

Page 18: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 18 OF 69

3.14.3 Existing structures and facilities, including but not limited to buildings, utilities, topography, streets, curbs, walks, landscape materials, and other improvements that are damaged or removed due to required excavations or Contractor’s Work, shall be patched, repaired, or replaced by the Contractor to the satisfaction of the Architect/Engineer, the owner of such structures and facilities, and authorities having jurisdiction. In the event that local authorities having jurisdiction require that such repairing and patching be done with their own labor and materials, the Contractor shall abide by such regulations and pay for such work. 3.15 CLEANING UP 3.15.1 The Contractor shall keep the premises and surrounding area free from accumulation of waste materials or rubbish caused by operations under the Contract. At completion of the Work the Contractor shall remove from and about the Project waste materials, rubbish, the Contractor’s tools, construction equipment, machinery and surplus materials.

Removal and disposal of all debris, waste materials, or rubbish due to demolition and construction, including clean up and trash removal is required to comply with all applicable ordinances, in the County where the construction site is located, that effect the disposal of solid wastes in the County including use of County franchise collection companies. 3.15.2 If the Contractor fails to clean up as provided in the Contract Documents, the Owner may do so and the cost thereof shall be charged to the Contractor. 3.16 ACCESS TO WORK 3.16.1 The Contractor shall provide the Owner and Architect/Engineer access to the Work in preparation and progress wherever located. 3.17 ROYALTIES AND PATENTS 3.17.1 The Contractor shall pay all royalties and license fees. The Contractor shall defend suits or claims for infringement of patent rights and shall hold the Owner and Architect/Engineer harmless from loss on account thereof, but shall not be responsible for such defense or loss when a particular design, process or product of a particular manufacturer or manufacturers is required by the Contractor Documents. However, if the Contractor has reason to believe that the required design, process or product is an infringement of a patent, the Contractor shall be responsible for such loss unless such information is promptly furnished to the Architect/Engineer. 3.18 INDEMNIFICATION 3.18.1 To the fullest extent permitted by law, the Contractor shall indemnify and hold harmless the Owner, Architect/Engineer, Architect/Engineer’s consultants, and agents and employees of any of them from and against claims, damages, losses and expenses, including but not limited to attorneys’ fees and court costs, arising out of or resulting from performance or non-performance of the Work, provided that such claim, damage, loss or expense is attributable to bodily injury, sickness, disease or death, or to injury to or destruction of tangible property (other than the Work itself) including loss of use resulting therefrom, but only to the extent caused in whole or in part by negligent acts or omissions of the Contractor, a Subcontractor, anyone directly or indirectly employed by them or anyone for whose acts they may be liable. Such obligation shall not be construed to negate, abridge, or reduce other rights or obligations of indemnity which would otherwise exist as to a party or person described in this Paragraph 3.18 (Indemnification) herein. 3.18.2 In claims against any person or entity indemnified under this Paragraph 3.18 (Indemnification) by an employee of the Contractor, a Subcontractor, anyone directly or indirectly employed by them or anyone for whose acts they may be liable, the indemnification obligation under this Paragraph 3.18 (Indemnification) shall not be limited by a limitation on amount or type of damages, compensation or benefits payable by or for the Contractor or a Subcontractor under workers’ or workmen’s compensation acts, disability benefit acts or other employee benefit acts. 3.18.3 The obligations of the Contractor under this Paragraph 3.18 (Indemnification) shall not extend to the liability of the Architect/Engineer, the Architect/Engineer’s consultants, and agents and employees of any of them arising out of: (1) the preparation or approval of maps, drawings, opinions, reports, surveys,

Page 19: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 19 OF 69

Change Orders, designs or specifications, or (2) the giving of or the failure to give directions or instructions by the Architect/Engineer, the Architect/Engineer’s consultants, and agents and employees of any of them provided such giving or failure to give is the primary cause of the injury or damage. 3.18.4 Prior to commencing any excavation or grading the Contractor shall become satisfied as to the accuracy of all survey data as indicated in the Contract Documents and/or as provided by the Owner. Should the Contractor discover any inaccuracies, errors, or omissions in the survey data, the Contractor shall immediately notify the Architect/Engineer in writing in order that proper adjustments can be made. Commencement by the Contractor of any excavation or grading shall be held as an acceptance of the survey data by the Contractor after which time the Contractor has no claims against the Owner resulting from alleged errors, omissions or inaccuracies of the said survey data except for conditions as described in Subparagraph 4.3.6 (Claims for Concealed or Unknown Conditions) herein. 3.18.5 The Contractor acknowledges that ten dollars has been included in the Contractor’s base bid, which represents the cost to the Owner for the provision of the indemnification required in accordance with this Paragraph 3.18 (Indemnification) herein. 3.18.6 The Contractor agrees that, upon receiving award of the Contract for construction, the Contractor will execute and deliver to the Owner an Assignment of Antitrust Claims as set forth in Section H of the Project Manual. 3.18.7 The Contractor also agrees that prior to final payment, the Contractor will cause each of his suppliers and Subcontractors who have furnished services, goods or materials in connection with the performance of the Work to execute and deliver to the Owner an Assignment of Antitrust Claims in the same form as specified above. 3.19 SUBSTITUTIONS 3.19.1 Substitutions for a specified system, product or material may be requested of the Architect/Engineer, and the Architect/Engineer’s written approval must be issued as an addendum before substitutions will be allowed. All requests for substitutions must be submitted prior to the opening of bids, and approvals shall be granted no less than seven (7) days prior to the bid date. Substitutions requested after that date will receive no consideration. Substitutions are changes in materials, equipment, methods or sequences or construction, design, structural systems, mechanical, electrical, air conditioning controls, or other requirements of the Drawings or the Specifications. 3.19.2 In substituting materials or equipment, the Contractor assumes responsibility for any changes in systems or for modifications required in adjacent or related work to accommodate such substitution, despite the Architect/Engineer approval, and all costs growing out of the approval shall be the responsibility of the Contractor. None of the extra costs resulting from such approval shall devolve upon the Owner, the Architect/Engineer or other contractors. The Architect/Engineer will be responsible for all architectural or engineering revisions to the drawings and shall be reimbursed by the Contractor for the costs of effecting such revisions. 3.19.3 In making requests for substitutions the Contractor shall list the particular system, product, or material for which a substitution is requested and the justification for such request. Requests submitted shall include any and all adjustments required by the substitution and any other Work affected thereby. The Architect/Engineer may reject a substitution for material reasons or the rejections may be based on aesthetics for which the Architect/Engineer shall be the sole judge. ARTICLE 4 ADMINISTRATION OF THE CONTRACT 4.1 ARCHITECT/ENGINEER 4.1.1 The Architect is the person lawfully licensed to practice architecture or an entity lawfully practicing architecture identified as such in the Agreement and is referred to throughout the Contract Documents as if singular in number. The Engineer is the person lawfully licensed to practice engineering or an entity lawfully practicing engineering identified as such in the Agreement and is referred to throughout the Contract Documents as if singular in number. The term “Architect/Engineer” means the Architect or the Engineer or the authorized representative of either.

Page 20: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 20 OF 69

4.1.2 In case of termination of employment of the Architect/Engineer, the Owner shall appoint an architect or an engineer whose status under the Contract Documents shall be that of the former Architect/Engineer. 4.2 ARCHITECT/ENGINEER’S ADMINISTRATION OF THE CONTRACT 4.2.1 The Architect/Engineer will provide administration of the Contract as described in the Contract Documents, and will be the Owner’s representative (1) during construction, (2) until final payment is made and (3) with the Owner’s concurrence, from time to time during the correction period described in Paragraph 12.2 (Correction of Work) herein. The Architect/Engineer will advise and consult with the Owner. The Architect/Engineer will have authority to act on behalf of the Owner only to the extent provided in the Contract Documents, unless otherwise modified by written instrument in accordance with other provisions of the Contract. 4.2.2 The Architect/Engineer will visit the site at intervals appropriate to the stage of construction to become generally familiar with the progress and quality of the completed Work and to determine in general if the Work is being performed in a manner indicating that the Work, when completed, will be in accordance with the Contract Documents. However, the Architect/Engineer will not be required to make exhaustive or continuous on-site inspections to check quality or quantity of the Work. On the basis of on-site observations as an architect or as an engineer, the Architect/Engineer will keep the Owner informed of progress of the Work, and will endeavor to guard the Owner against defects and deficiencies in the Work. 4.2.3 The Architect/Engineer will not have control over or charge of and will not be responsible for construction means, methods, techniques, sequences or procedures, or for safety precautions and programs in connection with the Work, since these are solely the Contractor’s responsibility as provided in Paragraph 3.3 (Supervision and Construction Procedures) herein. The Architect/Engineer will not be responsible for the Contractor’s failure to carry out the Work in accordance with the Contract Documents. The Architect/Engineer will not have control over or charge of and will not be responsible for acts or omissions of the Contractor, Subcontractors, or their agents or employees, or of any other persons performing portions of the Work. 4.2.4 Communications Facilitating Contract Administration. Except as otherwise provided in the Contract Documents or when direct communications have been specially authorized, the Owner and Contractor shall endeavor to communicate through the Architect/Engineer. Communications by and with the Architect/Engineer’s consultants shall be through the Architect/Engineer. Communications by and with Subcontractors and material suppliers shall be through the Contractor. Communications by and with separate contractors shall be through the Owner. 4.2.5 Based on the Architect/Engineer’s observations and evaluations of the Contractor’s Applications for Payment, the Architect/Engineer, will review and certify the amounts due the Contractor and will issue Certificates for Payment in such amounts. 4.2.5.1 The authorized representatives and agents of the Architect/Engineer, Owner, and such other persons as the Owner may designate shall have access to and be permitted to inspect all Work, subcontracts, materials, payrolls, records of personnel, invoices of materials and other relevant data and records wherever they are in preparation and progress. The Contractor shall provide proper facilities for such access and inspection and, when required, exact duplicate copies of the aforementioned data shall be furnished. 4.2.6 The Architect/Engineer will have authority to reject Work which does not conform to the Contract Documents. Whenever the Architect/Engineer considers it necessary or advisable for implementation of the intent of the Contract Documents, the Architect/Engineer will have authority to require additional inspection or testing of the Work in accordance with Subparagraphs 13.5.2 (Additional Testing and Inspections) and 13.5.3 (Contractor’s Costs) herein, whether or not such Work is fabricated, installed or completed. However, neither this authority of the Architect/Engineer nor a decision made in good faith either to exercise or not to exercise such authority shall give rise to a duty or responsibility of the Architect/Engineer to the Contractor, Subcontractors, material and equipment suppliers, their agents or employees, or other persons performing portions of the Work.

Page 21: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 21 OF 69

4.2.7 The Architect/Engineer will review and approve or take other appropriate action upon the Contractor’s submittals such as Shop Drawings, Product Data and Samples, but only for the limited purpose of checking for conformance with information given and the design concept expressed in the Contract Documents. The Architect/Engineer’s action will be taken with such reasonable promptness as to cause no delay in the Work, or in the activities of the Owner, Contractor or separate contractors, while allowing sufficient time in the Architect/Engineer’s professional judgment to permit adequate review. Review of such submittals is not conducted for the purpose of determining the accuracy and completeness of other details such as dimensions and quantities, or for substantiating instructions for installation or performance of equipment or systems, all of which remain the responsibility of the Contractor as required by the Contract Documents. The Architect/Engineer’s review of the Contractor’s submittals shall not relieve the Contractor of the obligations under Paragraphs 3.3 (Supervision and Constriction Procedures), 3.5 (Warranty) and 3.12 (Shop Drawings and Samples at the Site) herein. The Architect/Engineer’s review shall not constitute approval of safety precautions or, unless otherwise specifically stated by the Architect/Engineer, of any construction means, methods, techniques, sequences or procedures. The Architect/Engineer’s approval of a specific item shall not indicate approval of an assembly of which the item is a component. 4.2.8 The Architect/Engineer will prepare Change Orders and Construction Change Directives, and may authorize minor changes in the Work as provided in Paragraph 7.4 (Minor Changes in the Work) herein. 4.2.9 The Architect/Engineer will conduct inspections to determine the date or dates of Substantial Completion and the date of final completion, will receive and forward to the Owner for the Owner’s review and records written warranties and related documents required by the Contract and assembled by the Contractor, and will issue a final Certificate for Payment upon compliance with the requirements of the Contract Documents. 4.2.10 If the Owner and Architect/Engineer agree, the Architect/Engineer will provide one or more project representatives to assist in carrying out the Architect/Engineer’s responsibilities at the site. The duties, responsibilities and limitations of authority of such project representatives shall be as set forth in Subparagraphs 4.2.10.1 and 4.2.10.2 (Project Representative) herein. 4.2.10.1 The Architect/Engineer’s Project Representative(s) will:

.1 Assist the Contractor in obtaining interpretation of the Contract Documents from the Architect/Engineer.

.2 Conduct daily on-site observations for determining conformance to the Contract Documents in regard to Work, materials and equipment, etc.

.3 Request additional detail and/or information from the Architect/Engineer when needed by the Contractor.

.4 Evaluate suggestions and/or modifications submitted by the Contractor and transmit these to the Architect/Engineer with recommendations.

.5 Observe problems which may create delays in construction and report these to the Architect/Engineer.

.6 Maintain official relationship only with the Contractor and his job superintendent(s) regardless of which Subcontractor’s Work is involved.

.7 Attend all required construction conferences and participate in discussions of the Work.

.8 Maintain a daily log of Work activity including but not limited to: hours on the job site, weather conditions, daily construction activity, number of men in each trade on the site, with specific identification of ongoing MBE activities, general observations, written directives to the Contractor, and visitors.

.9 If, upon inspections or observations, Work is found not to be in accordance with Contract Documents, advise Contractor verbally and in writing, that the Work is not in accordance with the Contract Documents. Consult with Architect/Engineer for further directions if the Contractor refuses to correct the Work.

.10 Observe and record that tests and inspections required to be performed by others, in addition to those performed by Architect/Engineer’s representative and/or the Architect/Engineer, are actually performed, in accordance with the Contract Documents.

Page 22: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 22 OF 69

.11 When requested by the Owner, accompany all state and federal officials on inspections of construction and record the inspection in the log.

.12 Cooperate with university’s authorized representative and provide the representative with all required information about the Work.

.13 Accept no directions or instructions from anyone other than the Architect/Engineer.

.14 Maintain in an orderly manner, files of correspondence, reports of job conferences, shop drawings and samples, copies of Contract Documents, change orders, addenda, supplemental drawings, and job log.

.15 Review Applications for Payment submitted by Contractor and recommend to the Architect/Engineer for appropriate action.

.16 Participate in the observations of construction with the Architect/Engineer and the university’s authorized representative at regular intervals and at Substantial Completion.

.17 Refer all communications from university’s authorized representative to the Architect/Engineer.

.18 Copy university’s authorized representative on all correspondence related to the Project.

.19 Review plans, specifications and approved shop drawings on a regular basis. Advise the Architect/Engineer immediately upon discovery of any errors and omissions in the Contract Documents, or of construction problems.

.20 Advise Contractor and Architect/Engineer of Work being performed without approved shop drawings when such shop drawings are required by specifications.

.21 Check materials and equipment delivered to the job site against specifications, approved samples, shop drawings and related correspondence. When observed to be in conflict, advise Contractor and Architect/Engineer.

.22 Check that Contractor is maintaining record drawings of as-built conditions, from which contract record sets are to be developed.

.23 Act as liaison between the Contractor and the university’s authorized representative in the coordination of the Contractor’s schedule and the University’s requirements.

.24 Provide such other services as may be required in the Owner’s or Architect/Engineer’s interests or in the advancement of the Work.

4.2.10.2 The Architect/Engineer’s Project Representative is not authorized to do the following:

.1 Authorize deviations from the Contractor Documents (unless approved in writing by Architect/Engineer).

.2 Expedite the Work for the Contractor.

.3 Advise the Contractor on building techniques or scheduling.

.4 Approve Shop Drawings.

.5 Issue Certifications for Payment.

.6 Approve Substitutions.

.7 Get involved in disputes or problems between Subcontractor and Sub-subcontractor.

.8 Get involved in disputes or problems between Contractor and Subcontractor.

.9 Offer advice to Contractor or Subcontractors on how to perform the Work whether solicited from the Contractor or not.

.10 Shut down the job except in extreme emergencies and except under certain conditions as authorized by the Architect/Engineer.

4.2.11 The Architect/Engineer will interpret and decide matters concerning performance under and requirements of the Contract Documents on written request of either the Owner or Contractor. The Architect/Engineer’s response to such requests will be made within 15 days after written request is made for them. 4.2.12 Interpretations and decisions of the Architect/Engineer will be consistent with the intent of and reasonably inferable from the Contract Documents and will be in writing or in the form of drawings. When making such interpretations and decisions, the Architect/Engineer will endeavor to secure faithful performance by both Owner and Contractor, will not show partiality to either and will not be liable for results of interpretations or decisions so rendered in good faith. 4.2.13 The Architect/Engineer’s decisions on matters relating to aesthetic effect will be final if consistent with the intent expressed in the Contract Documents.

Page 23: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 23 OF 69

4.3 CLAIMS AND DISPUTES 4.3.1 Definition. A Claim is a demand or assertion by one of the parties seeking, as a matter of right, adjustment or interpretation of Contract terms, payment of money, extension of time or other relief with respect to the terms of the Contract. The term “Claim” also includes other disputes and matters in question between the Owner and Contractor arising out of or relating to the Contract. Claims must be made by written notice. The responsibility to substantiate Claims shall rest with the party making the Claim. 4.3.2 Decision of Architect/Engineer. Claims, including those alleging an error or omission by the Architect/Engineer, shall be referred initially to the Architect/Engineer for action as provided in Paragraph 4.4 (Resolution of Claims and Disputes) herein. A decision by the Architect/Engineer, as provided in Subparagraph 4.4.4 herein, shall be required as a condition precedent to litigation of a Claim between the Contractor and Owner as to all such matters arising prior to the date final payment is due, regardless of (1) whether such matters relate to execution and progress of the Work or (2) the extent to which the Work has been completed. The decision by the Architect/Engineer in response to a Claim shall not be a condition precedent to litigation in the event (1) the position of Architect/Engineer is vacant, (2) the Architect/Engineer has not received evidence or has failed to render a decision within agreed time limits, (3) the Architect/Engineer has failed to take action required under Subparagraph 4.4.4 herein, within 30 days after the Claim is made, or ( 4) 45 days have passed after the Claim has been referred to the Architect/Engineer. 4.3.3 Time Limits on Claims. Claims by either party must be made within 21 days after occurrence of the event giving rise to such Claim or within 21 days after the claimant first recognizes the condition giving rise to the Claim, whichever is later. Claims must be made by written notice. An additional Claim made after the initial Claim has been implemented by Charge Order will not be considered unless submitted within the time limits provided in this Subparagraph 4.3.3 (Time Limits on Claims) herein. 4.3.4 Continuing Contract Performance. Pending final resolution of a Claim including litigation, unless otherwise agreed in writing the Contractor shall proceed diligently with performance of the Contract and the Owner shall continue to make payments in accordance with the Contract Documents. 4.3.5 Waiver of Claims: Final Payment. The making of final payment shall constitute a waiver of Claims by the Owner except those arising from:

.1 Claims, security interest or encumbrances arising out of the Contract and unsettled;

.2 failure of the Work to comply with the requirements of the Contract Documents; or

.3 terms of special warranties required by the Contract Documents.

.4 damages including attorneys’ fees and costs incurred by the Owner resulting from lawsuits brought against the Owner, the Architect/Engineer or their agents, employees or representatives because of acts or omissions on the part of the Contractor, any Subcontractor, or any of their employees, agents or representatives.

4.3.6 Claims for Concealed or Unknown Conditions. If conditions are encountered at the site which are (1) subsurface or otherwise concealed physical conditions which differ materially from those indicated in the Contract Documents or (2) unknown physical conditions of an unusual nature, which differ materially from those ordinarily found to exist and generally recognized as inherent in construction activities of the character provided for in the Contract Documents, then notice by the observing party shall be given to the other party promptly before conditions are disturbed and in no event later than 21 days after first observance of the conditions. The Architect/Engineer will promptly investigate such conditions and, if they differ materially and cause an increase or decrease in the Contractor’s cost of, or time required for, performance of any part of the Work, will recommend an equitable adjustment in the Contract Sum or Contract Time, or both. If the Architect/Engineer determines that the conditions at the site are not materially different from those indicated in the Contract Documents and that no change in the terms of the Contract is justified, the Architect/Engineer shall so notify the Owner and Contractor in writing, stating the reasons. Claims by either party in opposition to such determination must be made within 21 days after the Architect/Engineer has given notice of the decision. If the Owner and Contractor cannot agree on an adjustment in the Contract Sum or Contract Time, the adjustment shall be referred to

Page 24: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 24 OF 69

the Architect/Engineer for initial determination, subject to further proceedings pursuant to Paragraph 4.4 (Resolution of Claims and Disputes) herein. 4.3.7 Claims for Additional Cost. If the Contractor wishes to make Claim for an increase in the Contract Sum, written notice as provided herein shall be given before proceeding to execute the Work. Prior notice is not required for Claims relating to an emergency endangering life or property arising under Paragraph 10.3 (Emergencies) herein. If the Contractor believes additional cost is involved for reasons including but not limited to (1) a written interpretation from the Architect/Engineer, (2) an order by the Owner to stop the Work where the Contractor was not at fault, (3) a written order for a minor change in the Work issued by the Architect/Engineer, (4) failure of payment by the Owner, (5) termination of the Contract by the Owner, (6) Owner’s suspension or (7) other reasonable grounds, Claim shall be filed in accordance with the procedure established herein. 4.3.8 Claims for Additional Time 4.3.8.1 If the Contractor wishes to make Claim for an increase in the Contract Time, written notice as provided herein shall be given. The Contractor’s Claim shall include an estimate of cost and of probable effect of delay on progress of the Work. In the case of a continuing delay only one Claim is necessary. 4.3.8.2 If adverse weather conditions are the basis for a Claim for additional time, such Claim shall be documented by data substantiating that weather conditions were abnormal for the period of time and could not have been reasonably anticipated, and that weather conditions had an adverse effect on the scheduled construction. 4.3.9 Injury or Damage to Person or Property. If either party to the Contract suffers injury or damage to person or property because of an act or omission of the other party, of any of the other party’s employees or agents, or of others for whose acts such party is legally liable, written notice of such injury or damage, whether or not insured, shall be given to the other party within a reasonable time not exceeding 21 days after first observance. The notice shall provide sufficient detail to enable the other party to investigate the matter. If a Claim for additional cost or time related to this Claim is to be asserted, it shall be filed as provided in Subparagraphs 4.3.7 (Claims for Additional Costs) or 4.3.8 (Claims for Additional Time) herein. 4.4 RESOLUTION OF CLAIMS AND DISPUTES 4.4.1 The Architect/Engineer will review Claims and take one or more of the following preliminary actions within ten days of receipt of a Claim: (1) request additional supporting data from the claimant, (2) submit a schedule to the parties indicating when the Architect/Engineer expects to take actions, (3) reject the Claim in whole or in part, stating reasons for rejection, (4) recommend approval of the Claim by the other party or (5) suggest a compromise. The Architect/Engineer may also, but is not obligated to, notify the surety, if any, of the nature and amount of the Claim. 4.4.2 If a Claim has been resolved, the Architect/Engineer will prepare or obtain appropriate documentation. 4.4.3 If a Claim has not been resolved, the party making the Claim shall, within ten days after the Architect/Engineer’s preliminary response, take one or more of the following actions: (1) submit additional supporting data requested by the Architect/Engineer, (2) modify the initial Claim or (3) notify the Architect/Engineer that the initial Claim stands. 4.4.4 If a Claim has not been resolved after consideration of the foregoing and of further evidence presented by the parties or requested by the Architect/Engineer, the Architect/Engineer will notify the parties in writing that the Architect/Engineer’s decision will be made within seven days, which decision shall be final and binding on the parties but subject to resolution as provided in Paragraph 4.5, (Legal Recourses) herein. Upon expiration of such time period, the Architect/Engineer will render to the parties the Architect/Engineer’s written decision relative to the Claim, including any change in the Contract Sum or Contract Time or both. If there is a surety and there appears to be a possibility of a Contractor’s default, the Architect/Engineer may, but is not obligated to, notify the surety and request the surety’s assistance in resolving the controversy.

Page 25: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 25 OF 69

4.5 LEGAL RECOURSE 4.5.1 The finding of the Architect/Engineer shall be a required condition precedent to further action by the Owner or Contractor as follows:

.1 Claims of $100,000 or less in value shall be conducted pursuant to and under the procedures of the Chapter 120 (Administrative Procedures Act), Florida Statutes;

.2 All other claims, disputes and other matters not governed by the foregoing shall be determined under the judiciary system of the State of Florida.

The Chapter 558 (Construction Defects), Florida Statutes, contains important requirements you must follow before you may bring any legal action for an alleged construction defect. Sixty days before you bring any legal action, you must deliver to the other party to this contract a written notice, referring to Chapter 558, of any construction conditions you allege are defective and provide such person the opportunity to inspect the alleged construction defects and to consider making an offer to repair or pay for the alleged construction defects. You are not obligated to accept any offer which may be made. There are strict deadlines and procedures under this Florida law which must be met and followed to protect your interests. ARTICLE 5 SUBCONTRACTORS 5.1 DEFINITIONS 5.1.1 A Subcontractor is a person or entity who has a direct contract with the Contractor to perform a portion of the Work at the site. The term “Subcontractor” is referred to throughout the Contract Documents as if singular in number and means a Subcontractor or an authorized representative of the Subcontractor. The term “Subcontractor” does not include a separate contractor or subcontractors of a separate contractor. 5.1.2 A Sub-subcontractor is a person or entity who has a direct or indirect contract with a Subcontractor to perform a portion of the Work at the site. The term “Sub-subcontractor” is referred to throughout the Contract Documents as if singular in number and means a Sub-subcontractor or an authorized representative of the Sub-subcontractor. 5.2 AWARD OF SUBCONTRACTS AND OTHER CONTRACTS FOR PORTIONS OF THE WORK 5.2.1 Within thirty (30) days after the date of the Notice to Proceed, the Contractor, in compliance with the requirements of the Contract Documents, shall furnish in writing to the Owner and through the Architect/Engineer the names of persons or entities (including those who are to furnish materials or equipment fabricated to a special design) proposed for each principal portion of the Work. The Architect/Engineer will promptly reply to the Contractor in writing stating whether or not the Owner or the Architect/Engineer, after due investigation, has reasonable objection to any such proposed person or entity. Failure of the Architect/Engineer to reply promptly shall constitute notice of no reasonable objection. 5.2.2 The Contractor shall not contract with a proposed person or entity to whom the Owner or Architect/Engineer has made reasonable and timely objection. The Contractor shall not contract with any subcontractor which does not hold the proper contractor’s license as required by the State of Florida. Inclusion of the Subcontractor’s name in the list provided in accordance with Subparagraph 5.2.1 shall constitute a certification by the Contractor that the Subcontractor is properly licensed. Thereafter, by signing the monthly University of South Florida’s Certificate of Partial Payment, the Contractor will certify that all Subcontractors providing services for the Work are properly licensed. The Contractor shall not be required to contract with anyone to whom the Contractor has made reasonable objection. 5.2.3 If the Owner or Architect/Engineer has reasonable objection to a person or entity proposed by the Contractor, the Contractor shall propose another to whom the Owner or Architect/Engineer has no reasonable objection. The Contract Sum shall be increased or decreased by the difference in cost occasioned by such change and an appropriate Change Order shall be issued. However, no increase in the Contract Sum shall be allowed for such change unless the Contractor has acted promptly and responsively in submitting names as required. 5.2.4 The Contractor shall not change a Subcontractor, person or entity previously selected if the Owner or Architect/Engineer makes reasonable objection to such change including, but not limited to, objections related to MBE participation.

Page 26: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 26 OF 69

5.2.5 The Contractor and the Subcontractors shall, within 10 days of the date of the Notice to Proceed, provide the names of all major Sub-subcontractors and/or material and equipment manufacturers. The following list is suggested but can be reduced or expanded at the discretion of the Architect/Engineer or as directed by the Owner.

.1 concrete supplier

.2 major specialties

.3 major equipment

.4 special construction

.5 plumbing fixtures, special piping, traps, sumps, etc., mechanical equipment, monitoring and automation controls, etc.

.6 electrical equipment, controllers, switchgears, devices, etc.

5.2.6 The Contractor understands and agrees that the Contractor alone is responsible to the Owner for all of the Work under the Contract and that any review of Subcontractors or Sub-subcontractors by the Owner or Architect/Engineer will not in any way make the Owner responsible to any Subcontractor or Sub-subcontractor, nor will it make the Owner responsible for the actions or omissions of any Subcontractor or Sub-subcontractor. 5.3 SUBCONTRACTUAL RELATIONS 5.3.1 By appropriate agreement, written where legally required for validity, the Contractor shall require each Subcontractor, to the extent of the Work to be performed by the Subcontractor, to be bound to the Contractor by terms of the Contract Documents, and to assume toward the Contractor all the obligations and responsibilities which the Contractor, by these Documents, assumes toward the Owner and Architect/Engineer. Each subcontract agreement shall preserve and protect the rights of the Owner and Architect/Engineer under the Contract Documents with respect to the Work to be performed by the Subcontractor so that subcontracting thereof will not prejudice such rights, and shall allow to the Subcontractor, unless specifically provided otherwise in the subcontract agreement, the benefit of all rights, remedies and redress against the Contractor that the Contractor, by the Contract Documents, has against the Owner. Where appropriate, the Contractor shall require each Subcontractor to enter into similar agreements with Sub-subcontractors. The Contractor shall make available to each proposed Subcontractor, prior to the execution of the subcontract agreement, copies of the Contract Documents to which the Subcontractor will be bound, and, upon written request of the Subcontractor, identify to the Subcontractor terms and conditions of the proposed subcontract agreement which may be at variance with the Contract Documents. Subcontractors shall similarly make copies of applicable portions of such documents available to their respective proposed Sub-Subcontractors. 5.4 CONTINGENT ASSIGNMENT OF SUBCONTRACTS 5.4.1 Each subcontract agreement for a portion of the Work is assigned by the Contractor to the Owner provided that:

.1 assignment is effective only after termination of the Contract by the Owner for cause pursuant to Paragraph 14.2 (Termination by the Owner for Cause) herein, and only for those subcontract agreements which the Owner accepts by notifying the Subcontractor in writing; and

.2 Assignment is subject to the prior rights of the surety, if any, obligated under bond relating to the Contract.

ARTICLE 6 CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS 6.1 OWNER’S RIGHT TO PERFORM CONSTRUCTION AND TO AWARD SEPARATE

CONTRACTS 6.1.1 The Owner reserves the right to perform construction or operations related to the Project with the Owner’s own forces, and to award separate contracts in connection with other portions of the Project or other construction or operations on the site under Conditions of the Contract identical or substantially similar to these including those portions related to insurance and waiver of subrogation. If the Contractor claims that delay or additional cost is involved because of such action by the Owner, the Contractor shall make such Claim as provided elsewhere in the Contract Documents.

Page 27: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 27 OF 69

6.1.2 When separate contracts are awarded for different portions of the Project or other construction or operations on the site, the term “Contractor” in the Contract Documents in each case shall mean the Contractor who executes each separate Owner-Contractor Agreement. 6.1.3 The Owner shall provide for coordination of the activities of the Owner’s own forces and of each separate contractor with the Work of the Contractor, who shall cooperate with them. The Contractor shall participate with other separate contractors and the Owner in reviewing their construction schedules when directed to do so. The Contractor shall make any revisions to the construction schedule and Contract Sum deemed necessary after a joint review and mutual agreement. The construction schedules shall then constitute the schedules to be used by the Contractor, separate contractors and the Owner until subsequently revised. 6.2 Mutual Responsibility 6.2.1 The Contractor shall afford the Owner and separate contractors reasonable opportunity for introduction and storage of their materials and equipment and performance of their activities and shall connect and coordinate the Contractor’s construction and operations with theirs as required by the Contract Documents. 6.2.2 If part of the Contractor’s Work depends for proper execution or results upon construction or operations by the Owner or a separate contractor, the Contractor shall, prior to proceeding with that portion of the Work, promptly report to the Architect/Engineer apparent discrepancies or defects in such other construction that would render it unsuitable for such proper execution and results. Failure of the Contractor so to report shall constitute an acknowledgment that the Owner’s or separate contractors’ completed or partially completed construction is fit and proper to receive the Contractor’s Work, except as to defects not then reasonably discoverable. 6.2.3 Costs caused by delays or by improperly timed activities or defective construction shall be borne by the party responsible therefor. 6.2.4 The Contractor shall promptly remedy damage wrongfully caused by the Contractor to completed or partially completed construction or to property of the Owner or separate contractors as provided in Subparagraph 10.2.5 (Prompt Remedy) herein. 6.2.5 Claims and other disputes and matters in question between the Contractor and a separate contractor shall be subject to the provisions of Paragraph 4.3 (Claims and Disputes) herein, provided the separate contractor has reciprocal obligations. 6.2.6 The Owner and each separate contractor shall have the same responsibilities for cutting and patching as are described for the Contractor in Paragraph 3.14 (Cutting and Patching) herein. 6.3 OWNER’S RIGHT TO CLEAN UP 6.3.1 If a dispute arises among the Contractor, separate contractors and the Owner as to the responsibility under their respective contracts for maintaining the premises and surrounding area free from waste materials and rubbish as described in Paragraph 3.15 (Cleaning Up) herein, the Owner may clean up and allocate the cost among those responsible as the Architect/Engineer determines to be just. ARTICLE 7 CHANGES IN THE WORK 7.1 CHANGES 7.1.1 Changes in the Work may be accomplished after execution of the Contract, and without invalidating the Contract, by Change Order, Construction Change Directive or order for a minor change in the Work, subject to the limitations stated in this Article 7 (Changes in the Work) herein, and elsewhere in the Contract Documents. 7.1.2 A Change Order shall be based upon agreement among the Owner, Contractor and Architect/Engineer; a Construction Change Directive requires agreement by the Owner and Architect/Engineer and may or may not be agreed to be the Contractor; an order for a minor change in

Page 28: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 28 OF 69

the Work may be issued by the Architect/Engineer as provided in Paragraph 7.4 (Minor Changes in the Work) herein. 7.1.3 Changes in the Work shall be performed under applicable provisions of the Contract Documents, and the Contractor shall proceed promptly, unless otherwise provided in the Change Order, Construction Change Directive or order for a minor change in the Work. 7.1.4 If unit prices are stated in the Contract Documents or subsequently agreed upon, and if quantities originally contemplated are so changed in a proposed Change Order or Construction Change Directive that application of such unit prices to quantities of Work proposed will cause substantial inequity to the Owner or Contractor, the applicable unit prices shall be equitably adjusted. 7.2 CHANGE ORDERS 7.2.1 A Change Order is a written instrument prepared by the Architect/Engineer and signed by the Owner, Contractor and Architect/Engineer, stating their agreement upon all of the following:

.1 a change in the Work;

.2 the amount of the adjustment in the Contract Sum, if any; and

.3 the extent of the adjustment in the Contract Time, if any. 7.2.2 Methods used in determining adjustments to the Contract Sum may include those listed in Subparagraph 7.3.3 (Change Directive) herein. 7.2.3 All Change Orders must be on the University of South Florida Change Order form, included in Section H of the Project Manual. 7.3 CONSTRUCTION CHANGE DIRECTIVES 7.3.1 A Construction Change Directive is a written order prepared by the Architect/Engineer and signed by the Owner and Architect/Engineer, directing a change in the Work and stating a proposed basis for adjustment, if any, in the Contract Sum or Contract Time, or both. The Owner may by Construction Change Directive, without invalidating the Contract, order changes in the Work within the general scope of the Contract consisting of additions, deletions or other revisions, the Contract Sum and Contract Time being adjusted accordingly. The Construction Change Order Directive form is provided in Section H of the Project Manual. 7.3.2 If the Construction Change Directive shall be used in the absence of total agreement on the terms of a Change Order. 7.3.3 If the Construction Change Directive provides for an adjustment to the Contract Sum, the adjustment shall be based on one of the following methods:

.1 mutual acceptance of a lump sum properly itemized and supported by sufficient substantiating data to permit evaluation;

.2 a not-to-exceed amount based on unit prices stated in the Contract Documents or subsequently agreed upon;

.3 cost to be determined in a manner agreed upon by the parties and a percentage fee as provided in Subparagraph 7.3.12 (Overhead & Profit); or

.4 as provided in Subparagraph 7.3.6 (Adjustment to Contract Sum) herein. 7.3.4 Upon receipt of a Construction Change Directive, the Contractor shall promptly proceed with the change in the Work involved and advise the Architect/Engineer of the Contractor’s agreement or disagreement with the method, if any, provided in the Construction Change Directive for determining the proposed adjustment in the Contract Sum or Contract Time. 7.3.5 A Construction Change Directive signed by the Contractor indicates the agreement of the Contractor therewith, including adjustment in Contract Sum and Contract Time or the method for determining them. Such agreement shall be effective immediately and shall be recorded as a Change Order.

Page 29: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 29 OF 69

7.3.6 If the Contractor does not respond promptly or disagrees with the method for adjustment in the Contract Sum, the method and the adjustment and the not-to-exceed amount shall be determined by the Architect/Engineer on the basis of reasonable expenditures and savings of those performing the Work attributable to the change, including, in case of an increase in the Contract Sum, the stipulated allowance for overhead and profit as stated in Subparagraph 7.3.12 (Overhead and Profit) herein. In such case, and also under Subparagraph 7.3.3.3 (Determining Costs) herein, the Contractor shall keep and present, in such form as the Architect/Engineer may prescribe, an itemized accounting together with appropriate supporting data. Unless otherwise provided in the Contract Documents, costs for the purposes of this Subparagraph 7.3.6 (Adjustments to Contract Sum) herein, shall be limited to the following:

.1 costs of labor, including social security, old age and unemployment insurance, fringe benefits required by agreement or custom, and workers’ or workmen’s compensation insurance;

.2 costs of materials, supplies and equipment, including sales tax and cost of transportation, whether incorporated or consumed;

.3 rental costs of machinery and equipment, exclusive of hand tools, whether rented from the Contractor or others;

.4 costs of premiums for all bonds and insurance, permit fees, and sales, use or similar taxes related to the Work; and

.5 additional costs of supervision and field office personnel directly attributable to the change. 7.3.7 Pending final determination of cost to the Owner, amounts not in dispute may be included in Applications for Payment. The amount of credit to be allowed by the Contractor to the Owner for a deletion or change which results in a net decrease in the Contract Sum shall be actual net cost as confirmed by the Architect/Engineer. When both additions and credits covering related Work or substitutions are involved in a change, the allowance for overhead and profit shall be figured on the basis of net increase, if any, with respect to that change. 7.3.8 If the Owner and Contractor do not agree with the adjustment in Contract Time or the method for determining it, the adjustment or the method shall be referred to the Architect/Engineer for determination. 7.3.9 When the Owner and Contractor agree with the determination made by the Architect/Engineer concerning the adjustments in the Contract Sum and Contract Time, or otherwise reach agreement upon the adjustments, such agreement shall be effective immediately and shall be recorded by preparation and execution of an appropriate Change Order. 7.3.10 The Cost of the Change shall not include any of the following items:

.1 Salaries or other compensation of the Contractor’s personnel at the Contractor’s offices, including the field office, unless direct additional expense has been incurred exclusively because of the change;

.2 Expenses of the Contractor’s offices, including the field office;

.3 Any part of the Contractor’s capital expenses, including interest on the Contractor’s capital;

.4 Costs due to the negligence of the Contractor, any Subcontractor, and Sub-subcontractor, anyone directly or indirectly employed by any of them, or for whose acts any of them may be liable, including, but not limited to, the correction of defective or nonconforming Work, disposal of materials and equipment wrongly supplied, or making good any damage to property; or,

.5 Overhead, general expense, and the cost of any item not specifically or reasonably inferable as included in the items described in Subparagraph 7.3.6 (Adjustments to Contract Sum) herein.

7.3.11 The Contractor shall check all materials, equipment and labor entering into the Work as a result of changes in the Work and shall keep such full and detailed accounts as may be necessary for proper financial management under the Contract, and the system shall be satisfactory to the Owner. The Owner shall be afforded access to all the Contractor’s records, books, correspondence, instructions, drawings, receipts, vouchers, memoranda and similar data relating to changes in the Contract. 7.3.12 The percentage fee for overhead and profit combined, to be added to the cost of the change in determining the total cost to the Owner, shall be negotiated based upon the following schedule:

Page 30: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 30 OF 69

.1 For any work performed by the Contractor’s own forces, a maximum of 15% of the cost of the change;

.2 For any work performed by a Subcontractor or forces under the Subcontractor including any Sub-subcontractors or other persons not in the direct employ of the Subcontractor, a maximum total of 22½% of the cost of the change, with a maximum of 15% to be assigned to the Subcontractor and any forces under him and a maximum of 7½% to be assigned to the Contractor.

7.3.13 If a change in the Work results in a credit to the Owner, the credit shall be the net Cost of the Charge as defined in Subparagraphs 7.3.6 Adjustments to Contract Sum) and 7.3.10 (Cost of Change) herein, and shall not include any allowance for the Contractor’s or Subcontractors’ overhead and profit. 7.4 MINOR CHANGES IN THE WORK 7.4.1 The Architect/Engineer will have authority, after receiving the Owner’s approval, to order minor changes in the Work not involving adjustment in the Contract Sum or extension of the Contract Time and not inconsistent with the intent of the Contract Documents. Such changes shall be effected by written order and shall be binding on the Owner and Contractor. The Contractor shall carry out such written orders promptly. ARTICLE 8 TIME 8.1 DEFINITIONS 8.1.1 Unless otherwise provided, Contract Time is the Period of time, including authorized adjustments, allotted in the Contract Documents for Substantial Completion of the Work. 8.1.2 The date of commencement of the Work is the date established in the notice to proceed. The date shall not be postponed by the failure to act of the Contractor or of persons or entities for whom the Contractor is responsible. 8.1.3 The date of Substantial Completion is the date certified by the Architect/Engineer in accordance with Paragraph 9.8 (Substantial Completion) herein. 8.1.4 The term “day” as used in the Contract Documents shall mean calendar day unless otherwise specifically defined. 8.2 PROGRESS AND COMPLETION 8.2.1 Time limits stated in the Contract Documents are of the essence of the Contract. By executing the Agreement the Contractor confirms that the Contract Time is a reasonable period for performing the Work. 8.2.2 The Contractor shall not knowingly, except by agreement or instruction of the Owner in writing, prematurely commence operations on the site or elsewhere prior to the effective date of insurance required by Article 11 (Insurance and Bonds) herein, to be furnished by the Contractor. The date of commencement of the Work shall not be changed by the effective date of such insurance. 8.2.3 The Contractor shall proceed expeditiously with adequate forces and shall achieve Substantial Completion within the Contract Time. 8.3 DELAYS AND EXTENSIONS OF TIME 8.3.1 If the Contractor is delayed at any time in progress of the Work by an act or neglect of the Owner or Architect/Engineer, or of an employee of either, or of a separate contractor employed by the Owner, or by changes ordered in the Work, or by labor disputes, fire, unusual delay in deliveries, unavoidable casualties or other causes beyond the Contractor’s control, or by delay authorized by the Owner pending resolution of Claims or other matters in question, or by other causes which the Architect/Engineer determines may justify delay, then the Contract Time shall be extended by Change Order for such reasonable time as the Architect/Engineer may determine. 8.3.2 Claims relating to time shall be made in accordance with applicable provisions of Paragraph 4.3 (Claims and Deputes) herein.

Page 31: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 31 OF 69

8.3.3 This Paragraph 8.3 herein does not preclude recovery of damages for delay by either party under other provisions of the Contract Documents, except that in instances of delays due to adverse weather conditions and labor disputes, Claims for extended overhead costs will not be allowed. ARTICLE 9 PAYMENTS AND COMPLETION 9.1 CONTRACT SUM 9.1.1 The Contract Sum is stated in the Agreement and, including authorized adjustments, is the total amount payable by the Owner to the Contractor for performance of the Work under the Contract Documents. 9.2 SCHEDULE OF VALUES 9.2.1 Before the first Application for Payment, the Contractor shall submit to the Architect/Engineer a schedule of values allocated to various portions of the Work, prepared in the form as provided in Section H of the Project Manual, and supported by such data to substantiate its accuracy as the Architect/Engineer may require. This schedule, unless objected to by the Architect/Engineer, shall be used as a basis for reviewing the Contractor’s Applications for Payment. 9.3 APPLICATIONS FOR PAYMENT 9.3.1 At least ten days before the date established for each progress payment, the Contractor shall submit to the Architect/Engineer an itemized preliminary draft of the Application for Payment with complete supporting data on the University of South Florida Certificate of Partial Payment form. Upon approval of the preliminary draft, the Contractor shall submit to the Architect/Engineer the Application for Payment for operations completed in accordance with the schedule of values. Such application shall be notarized and supported by such data substantiating the Contractor’s right to payment as the Owner or Architect/Engineer may require, such as copies of requisitions from Subcontractors and materials suppliers, and reflecting retainage. Applications for payments shall be made monthly beginning within 30 days after the notice to proceed. 9.3.1.1 With the exception of Work which may be exempted from this requirement by a provision in the Special Conditions of this Project Manual, retainage shall be withheld from each monthly payment request, in an amount not to exceed 10% of the approved payment until 50% of construction payments are made. After the Work is considered to be 50% complete, retainage thereafter not to exceed 10% of the request, may or may not be withheld at the discretion of the Owner.

Withholding of the retainage shall be subject to the provisions of the Paragraph 6.3 (Payments Withheld) and Subparagraph 6.3.1.2 of the Owner Contractor Agreement. 9.3.1.2 If securities are substituted in lieu of retainage as permitted by Section 255.052 (Substitution of Securities for Retainage), Florida Statues, the securities must be free of all encumbrances, and the Contractor must assign all its rights to the securities to the Owner, enabling the Owner to use those securities as it would retainage. 9.3.2 Unless otherwise provided in the Contract Documents, payments shall be made on account of materials and equipment delivered and suitably stored at the site for subsequent incorporation in the Work. If approved in advance by the Owner, payment may similarly be made for materials and equipment suitably stored off the site at a location agreed upon in writing. Payment for materials and equipment stored on or off the site shall be conditioned upon compliance by the Contractor with procedures satisfactory to the Owner to establish the Owner’s title to such materials and equipment or otherwise protect the Owner’s interest, and shall include applicable insurance, storage and transportation to the site for such materials and equipment stored off the site. 9.3.3 The Contractor warrants that title to all Work covered by an Application for Payment will pass to the Owner no later than the time of payment. The Contractor further warrants that upon submittal of an Application for Payment all Work for which Certificates for Payment have been previously issued and payments received from the Owner shall, to the best of the Contractor’s knowledge, information and belief, be free and clear of liens, claims, security interests or encumbrances in favor of the Contractor, Subcontractors, material suppliers, or other persons or entities making a claim by reason of having provided labor, materials and equipment relating to the Work.

Page 32: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 32 OF 69

9.4 CERTIFICATES FOR PAYMENT 9.4.1 The Architect/Engineer will, within seven days after receipt of the Contractor’s Application for Payment, either issue to the Owner a Certificate for Payment, with a copy to the Contractor, for such amount as the Architect/Engineer determines is properly due, or notify the Contractor and Owner in writing of the Architect/Engineer’s reasons for withholding certification in whole or in part as provided in Subparagraph 9.5.1 (Withholding Certification) herein. 9.4.2 The issuance of a Certificate for Payment will constitute a representation by the Architect/Engineer to the Owner, based on the Architect/Engineer’s observations at the site and the data comprising the Application for Payment, that the Work has progressed to the point indicated and that, to the best of the Architect/Engineer’s knowledge, information and belief, quality of the Work is in accordance with the Contract Documents. The foregoing representations are subject to an evaluation of the Work for conformance with the Contract Documents upon Substantial Completion, to results of subsequent tests and inspections, to minor deviations from the Contract Documents correctable prior to completion and to specific qualifications expressed by the Architect/Engineer. The issuance of a Certificate for Payment will further constitute a representation that the Contractor is entitled to payment in the amount certified. However, the issuance of a Certificate for Payment will not be a representation that the Architect/Engineer has (1) made exhaustive or continuous on-site inspections to check the quality or quantity of the Work, (2) reviewed construction means, methods, techniques, sequences or procedures, (3) reviewed copies of requisitions received from Subcontractors and materials suppliers and other data requested by the Owner to substantiate the Contractor’s right to payment or (4) made examination to ascertain how or for what purpose the Contractor has used money previously paid on account of the Contract Sum. 9.5 DECISIONS TO WITHHOLD CERTIFICATION 9.5.1 The Architect/Engineer may decide not to certify payment and may withhold a Certificate for Payment in whole or in part, to the extent reasonably necessary to protect the Owner, if in the Architect/Engineer’s opinion the representations to the Owner required by Subparagraph 9.4.2 (Certificate for Payment) herein cannot be made. If the Architect/Engineer is unable to certify payment in the amount of the Application, the Architect/Engineer will notify the Contractor and Owner as provided in Subparagraph 9.4.1 herein. If the Contractor and Architect/Engineer cannot agree on a revised amount, the Architect/Engineer will promptly issue a Certificate for Payment for the amount for which the Architect/Engineer is able to make such representations to the Owner. The Architect/Engineer may also decide not to certify payment or, because of subsequently discovered evidence or subsequent observations, may nullify the whole or a part of a Certificate for Payment previously issued, to such extent as may be necessary in the Architect/Engineer’s opinion to protect the Owner from loss because of, but not limited to:

.1 defective Work not remedied;

.2 third party claims filed or reasonable evidence indicating probable filing of such claims;

.3 failure of the Contractor to make payments properly to Subcontractors or for labor, materials or equipment;

.4 reasonable evidence that the Work cannot be completed for the unpaid balance of the Contract Sum;

.5 damage to the Owner or another contractor;

.6 reasonable evidence that the Work will not be completed within the Contract Time, and that the unpaid balance would not be adequate to cover actual or liquidated damages for the anticipated delay; or

.7 persistent failure to carry out the Work in accordance with the Contract Documents. 9.5.2 When the above reasons for withholding certification are removed, certification will be made for amounts previously withheld. 9.6 PROGRESS PAYMENTS 9.6.1 After the Architect/Engineer has issued a Certificate for Payment, the Owner shall make payment in the manner and within the time provided in the Contract Documents, and may so notify the Architect/Engineer.

Page 33: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 33 OF 69

9.6.2 The Contractor shall promptly pay each Subcontractor, upon receipt of payment from the Owner, out of the amount paid to the Contractor on account of such Subcontractor’s portion of the Work, the amount to which said Subcontractor is entitled, reflecting percentages actually retained from payments to the Contractor on account of such Subcontractor’s portion of the Work. When the Contractor receives payment from the Owner for labor, services or materials furnished by subcontractors and suppliers hired by the Contractor for the project, the Contractor shall remit payment due to those subcontractors and suppliers, less the value of any item contested in accordance with the Contract, within ten (10) days after the Contractor’s receipt of payment from the Owner. When the payment due the subcontractor is for final payment, including retainage, the subcontractor must include with the invoice for final payment a conditional release of lien and all appropriate warranties and closeout documentation. When the subcontractor receives payment from the Contractor for labor, services or materials furnished by subcontractors and suppliers hired by the subcontractor, the subcontractor shall remit payment due to those subcontractors and suppliers, less the value of any item contested in accordance with the Contract, within ten (10) days after the subcontractor’s receipt of payment. 9.6.3 The Architect/Engineer will, on request, furnish to a Subcontractor, if practicable, information regarding percentages of completion or amounts applied for by the Contractor and action taken thereon by the Architect/Engineer and Owner on account of portions of the Work done by such Subcontractors. 9.6.4 Neither the Owner nor Architect/Engineer shall have an obligation to pay or to see to the payment of money to a Subcontractor except as may otherwise be required by law. 9.6.5 Payment to material suppliers shall be treated in a manner similar to that provided in Subparagraphs 9.6.2, 9.6.3 and 9.6.4 herein. 9.6.6 A Certificate for Payment, a progress payment, or partial or entire use or occupancy of the Project by the Owner shall not constitute acceptance of Work not in accordance with the Contract Documents. 9.7 FAILURE OF PAYMENT 9.7.1 If the Architect/Engineer does not issue a Certificate for Payment, through no fault of the Contractor, within seven days after receipt of the Contractor’s Application for Payment, or if the Owner does not pay the Contractor within seven days after the date established in the Contract Documents the amount certified by the Architect/Engineer or awarded by litigation then the Contractor may, upon seven additional days’ written notice to the Owner and Architect/Engineer, stop the Work until payment of the amount owing has been received. The Contract Time shall be extended appropriately and the Contract Sum shall be increased by the amount of the Contractor’s reasonable costs of shut-down, delay and start-up, which shall be accomplished as provided in Article 7 (Changes in the Work) herein. 9.8 SUBSTANTIAL COMPLETION 9.8.1 Substantial Completion is the stage in the progress of the Work when the Work or designated portion thereof is sufficiently complete in accordance with the Contract Documents so the Owner can occupy or utilize the Work for its intended use. 9.8.2 When the Contractor considers that the Work, or a portion thereof which the Owner agrees to accept separately, is substantially complete, the Contractor shall prepare and submit to the Architect/Engineer a comprehensive list of items to be completed or corrected. The Contractor shall proceed promptly to complete and correct items on the list. Failure to include an item on such list does not alter the responsibility of the Contractor to complete all Work in accordance with the Contract Documents. Upon receipt of the Contractor’s list, the Architect/Engineer will make an inspection to determine whether the Work or designated portion thereof is substantially complete. If the Architect/Engineer’s inspection discloses any item, whether or not included on the Contractor’s list, which is not in accordance with the requirements of the Contract Documents, the Contractor shall, before issuance of the Certificate of Substantial Completion, complete or correct such item upon notification by the Architect/Engineer. The Contractor shall then submit a request for another inspection by the Architect/Engineer to determine Substantial Completion. When the Work or designated portion thereof is substantially complete, the Architect/Engineer will prepare a Certificate of Substantial Completion which shall establish the date of Substantial Completion, shall establish responsibilities of the Owner and Contractor for security, maintenance, heat, utilities, damage to the Work and insurance, and shall fix the

Page 34: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 34 OF 69

time within which the Contractor shall finish all items on the list accompanying the Certificate. Warranties required by the Contract Documents shall commence on the date of Substantial Completion of the Work or designated portion thereof unless otherwise provided in the Certificate of Substantial Completion. The Certificate of Substantial Completion shall be submitted to the Owner and Contractor for their written acceptance of responsibilities assigned to them in such Certificate. 9.8.3 Upon Substantial Completion of the Work or designated portion thereof and upon application by the Contractor and certification by the Architect/Engineer, the Owner shall make payment, reflecting adjustment in retainage, if any, for such Work or portion thereof as provided in the Contract Documents. Liquidated damages to the date of Substantial Completion shall be deducted by Construction Change Directive from the Contract Sum and from the Substantial Completion payment. 9.8.4 The acceptance of Substantial Completion payment shall constitute a waiver of all claims by the Contractor except those previously made in writing and identified by the Contractor as unsettled at the time of the Application for Payment for Substantial Completion, and except for the retainage sums due at final acceptance. 9.8.5 The Contractor shall be responsible for collecting, identifying, indexing and collating the following materials from the Subcontractors, and will deliver four copies of the finished document to the Architect/Engineer to verify completeness. The Architect/Engineer will deliver three copies of the following to the Owner:

.1 Complete equipment diagrams, operating instructions, maintenance manuals, parts lists, wiring diagrams, pneumatic and/or electrical control diagrams, test and balance reports, inspection reports, guarantees and warranties, as applicable, for each and every piece of fixed equipment furnished under this Contract to be supplied in a ring binder, hard-cover book, properly indexed for ready reference. Also, specific information regarding manufacturer’s names, addresses, office and home phone numbers, make and model numbers, operating design and characteristics, etc., will be required. All information submitted shall be current as of the time of submission.

9.8.6 Subsequent to the time of Substantial Completion and receipt of contract record sets and operations and maintenance books, but prior to the date of final acceptance, the Contractor and/or Subcontractor shall provide a competent and experienced person (or persons) thoroughly familiar with the Work for a reasonable period of time but not less than 40 hours to instruct the Owner’s personnel in operation and maintenance of equipment and control systems. This instruction will include normal start-up, run, stop, and emergency operations, location and operation of all controls, alarms and alarm systems, etc. This instruction will include tracing the system in the field and on the diagrams in the instruction booklets so that operating personnel will be thoroughly familiar with both the system and the data supplied. 9.9 PARTIAL OCCUPANCY OR USE 9.9.1 The Owner may occupy or use any completed or partially completed portion of the Work at any stage when such portion is designated by separate agreement with the Contractor, provided such occupancy or use is consented to by the insurer as required under Paragraph 11.3 (Property Insurance) herein, and authorized by public authorities having jurisdiction over the Work. Such partial occupancy or use may commence whether or not the portion is substantially complete, provided the Owner and Contractor have accepted in writing the responsibilities assigned to each of them for payments, retainage if any, security, maintenance, heat, utilities, damage to the Work and insurance, and have agreed in writing concerning the period for correction of the Work and commencement of warranties required by the Contract Documents. When the Contractor considers a portion substantially complete, the Contractor shall prepare and submit a list to the Architect/Engineer as provided under Subparagraph 9.8.2 (Substantial Completion) herein. Consent of the Contractor to partial occupancy or use shall not be unreasonably withheld. The stage of the progress of the Work shall be determined by written agreement between the Owner and Contractor or, if no agreement is reached, by decision of the Architect/Engineer. 9.9.2 Immediately prior to such partial occupancy or use, the Owner, Contractor and Architect/Engineer shall jointly inspect the area to be occupied or portion of the Work to be used in order to determine and record the condition of the Work.

Page 35: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 35 OF 69

9.9.3 Unless otherwise agreed upon, partial occupancy or use of a portion or portions of the Work shall not constitute acceptance of Work not complying with the requirements of the Contract Documents. 9.10 FINAL COMPLETION AND FINAL PAYMENT 9.10.1 Upon receipt of written notice that the Work is ready for final inspection and acceptance and upon receipt of a final Application for Payment, the Architect/Engineer will promptly make such inspection and, when the Architect/Engineer finds the Work acceptable under the Contract Documents and the Contract fully performed, the Architect/Engineer will promptly issue a final Certificate for Payment stating that to the best of the Architect/Engineer’s knowledge, information and belief, and on the basis of the Architect/Engineer’s observations and inspections, the Work has been completed in accordance with terms and conditions of the Contract Documents and that the entire balance found to be due the Contractor and noted in said final Certificate is due and payable. The Architect/Engineer’s final Certificate for Payment will constitute a further representation that conditions listed in Subparagraph 9.10.2 herein, as precedent to the Contractor’s being entitled to final payment have been fulfilled. Liquidated damages assessed subsequent to Substantial Completion shall be deducted by Construction Change Directive from the Contract Sum and from the final payment. 9.10.2 Neither final payment nor any remaining retained percentage shall become due until the Contractor submits to the Architect/Engineer (1) an affidavit that payrolls, bills for materials and equipment, and other indebtedness connected with the Work for which the Owner or the Owner’s property might be responsible or encumbered (less amounts withheld by Owner) have been paid or otherwise satisfied, (2) a certificate evidencing that insurance required by the Contract Documents to remain in force after final payment is currently in effect and will not be cancelled or allowed to expire until at least 30 days’ prior written notice has been given to the Owner, (3) a written statement that the Contractor knows of no substantial reason that the insurance will not be renewable to cover the period required by the Contract Documents, (4) consent of surety, if any, to final payment and (5) if required by the Owner, other data establishing payment or satisfaction of obligations, such as receipts, releases and waivers of claims, security interests, or encumbrances arising out of the Contract, to the extent and in such form as may be designated by the Owner. If a Subcontractor refuses to furnish a release or waiver required by the Owner, the Contractor may furnish a bond satisfactory to the Owner to indemnify the Owner against such claim. If such claim remains unsatisfied after payments are made, the Contractor shall refund to the Owner all money that the Owner may be compelled to pay in discharging such claim, including all costs and reasonable attorneys’ fees. 9.10.3 If, after Substantial Completion of the Work, final completion thereof is materially delayed through no fault of the Contractor or by issuance of Change Orders affecting final completion, and the Architect/Engineer so confirms, the Owner shall, upon application by the Contractor and certification by the Architect/Engineer, and without terminating the Contract, make payment of the balance due for that portion of the Work fully completed and accepted. If the remaining balance for Work not fully completed or corrected is less than retainage stipulated in the Contract Documents, and if bonds have been furnished, the written consent of surety to payment of the balance due for that portion of the Work fully completed and accepted shall be submitted by the Contractor to the Architect/Engineer prior to certification of such payment. Such payment shall be made under terms and conditions governing final payment, except that it shall not constitute a waiver of claims. The making of final payment shall constitute a waiver of claims by the Owner as provided in Subparagraph 4.3.5 (Waiver of Claims) herein. 9.10.4 Acceptance of final payment by the Contractor, a Subcontractor or material supplier shall constitute a waiver of claims by that payee except those previously made in writing and identified by that payee as unsettled at the time of final Application for Payment. Such waivers shall be in addition to the waiver described in Subparagraph 4.3.5 herein. 9.10.5 The Contractor’s application for final payment shall be accompanied by a completed and notarized “Certificate of Contract Completion” as provided in Section H of the Project Manual. Any items required by the Contract Documents not previously submitted shall accompany the application for final payment.

Page 36: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 36 OF 69

ARTICLE 10 PROTECTION OF PERSONS AND PROPERTY 10.1 SAFETY PRECAUTIONS AND PROGRAMS 10.1.1 The Contractor shall be responsible for initiating, maintaining and supervising all safety precautions and programs in connection with the performance of the Contract.

10.1.2 Unless asbestos abatement is specifically included as part of the Work elsewhere in the Contract Documents, then in the event the Contractor encounters on the site material reasonably believed to be asbestos or polychlorinated biphenyl (PCB) which has not been rendered harmless, the Contractor shall immediately stop Work in the area affected and report the condition to the Owner and Architect/Engineer in writing. The Work in the affected area shall not thereafter be resumed except by written agreement of the Owner and Contractor if in fact the material is asbestos or polychlorinated biphenyl (PCB) and has not been rendered harmless. The Work in the affected area shall be resumed in the absence of asbestos or polychlorinated biphenyl (PCB), or when it has been rendered harmless, by written agreement of the Owner and Contractor, or in accordance with final determination by the Architect/Engineer on which legal recourse has not been demanded, or by legal recourse under Article 4 (Administration of the Contract) herein. 10.1.2.1 The Contractor shall be responsible to insure that Asbestos Containing Materials (ACM) are not incorporated in the scope of work for the project. The Contractor shall provide Material Safety Data Sheets for all products and materials for the project and shall certify that Asbestos Containing Materials have not been incorporated in the scope of work. 10.1.2.2 The Contractor shall be responsible for notification of the proper agencies, and for the cost of the removal, encapsulation, transportation and disposal of any hazardous material, including, without limitation, any asbestos or asbestos-related products as substitutions per paragraph 3.19 in connection with the Work. Hazardous material, described by Federal guidelines brought by bthe Contractor or the Subcontractors shall remain their responsibility for proper disposal. Any hazardous material on the site prior to proceeding with the work and not specifically shown on the documents shall be considered a concealed condition. 10.1.2.3 Any hazardous material removal including asbestos abatement Work required in connection with the Work shall only be performed by an approved Contractor for asbestos, etc., which has been pre-qualified by the Owner. 10.1.3 The Contractor shall not be required pursuant to Article 7 (Changes in the Work) herein, to perform without consent any Work relating to asbestos or polychlorinated biphenyl (PCB). 10.2 SAFETY OF PERSONS AND PROPERTY 10.2.1 The Contractor shall take reasonable precautions for safety of, and shall provide reasonable protection to prevent damage, injury or loss to:

.1 employees on the Work and other persons who may be affected thereby;

.2 The Work and materials and equipment to be incorporated therein, whether in storage on or off the site, under care, custody or control of the Contractor or the Contractor’s Subcontractors or Sub-subcontractors; and

.3 other property at the site or adjacent thereto, such as trees, shrubs, lawns, walks, pavements, roadways, structures and utilities not designated for removal, relocation or replacement in the course of construction.

10.2.2 The Contractor shall give notices and comply with applicable laws, ordinances, rules, regulations and lawful orders of public authorities bearing on safety of persons or property or their protection from damage, injury or loss. 10.2.3 The Contractor shall erect and maintain, as required by existing conditions and performance of the Contract, reasonable safeguards for safety and protection, including posting danger signs and other warnings against hazards, promulgating safety regulations and notifying owners and users of adjacent sites and utilities.

Page 37: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 37 OF 69

10.2.4 When use or storage of explosives or other hazardous materials or equipment or unusual methods are necessary for execution of the Work, the Contractor shall exercise utmost care and carry on such activities under supervision of properly qualified personnel. 10.2.5 The Contractor shall promptly remedy damage and loss (other than damage or loss insured under property insurance required by the Contract Documents) to property referred to in Subparagraphs 10.2.1 (Safety of Persons and Property) and 10.2.1.2 herein, caused in whole or in part by the Contractor, a Subcontractor, a Sub-subcontractor, or anyone directly or indirectly employed by any of them, or by anyone for whose acts they may be liable and for which the Contractor is responsible under Subparagraphs 10.2.1.2 and 10.2.1.3 herein. except damage or loss attributable to acts or omissions of the Owner or Architect/Engineer or anyone directly or indirectly employed by either of them, or by anyone for whose act either of them may be liable, and not attributable to the fault or negligence of the Contractor. The foregoing obligations of the Contractor are in addition to the Contractor’s obligation under Paragraph 3.18 (Indemnification) herein. 10.2.6 The Contractor shall designate a responsible member of the Contractor’s organization at the site whose duty shall be the prevention of accidents. This person shall be the Contractor’s superintendent unless otherwise designated by the Contractor in writing to the Owner and Architect/Engineer. 10.2.7 The Contractor shall not load or permit any part of the construction or site to be loaded so as to endanger its safety. 10.3 EMERGENCIES 10.3.1 In an emergency affecting safety of persons or property, the Contractor shall act, at the Contractor’s discretion, to prevent threatened damage, injury or loss. Additional compensation or extension of time claimed by the Contractor on account of an emergency shall be determined as provided in Paragraph 4.3 (Claims and Disputes) and Article 7 (Changes in the Work) herein. ARTICLE 11 INSURANCE AND BONDS 11.1 CONTRACTOR’S LIABILITY INSURANCE 11.1.1 The Contractor shall purchase from and maintain in a company or companies lawfully authorized to do business in Florida such insurance as will protect the Contractor from claims set forth below which may arise out of or result from the Contractor’s operations under the Contract and for which the Contractor may be legally liable, whether such operations be by the Contractor or by a Subcontractor or by anyone directly or indirectly employed by any of them, or by anyone for whose acts any of them may be liable:. All insurance policies shall be issued and countersigned by representatives of such companies duly authorized for the State of Florida and shall be written on ISO standard forms or their equivalents. The Contractor shall provide the ISO Commercial General Liability policy for general liability coverages. All liability policies shall provide that the Owner is a named additional insured as to the operations of the Contractor under the Agreement and shall provide the Severability of Insured’s Provision. The Owner shall be exempt from, and in no way liable for, any sums of money which may represent a deductible in any insurance policy. The payment of such deductible shall be the responsibility solely of the Contractor and/or Subcontractor providing such insurance. This insurance shall protect the Contractor from the following claims:

.1 claims under workers’ or workmen’s compensation, disability benefit and other similar employee benefit acts which are applicable to the Work to be performed;

.2 claims for damages because of bodily injury, occupational sickness or disease, or death of the Contractor’s employees;

.3 claims for damages because of bodily injury, sickness or disease, or death of any person other than the Contractor’s employees;

.4 claims for damages insured by usual personal injury liability coverage including claims which are sustained (1) by a person as a result of an offense directly or indirectly related to employment of such person by the Contractor, or (2) by another person;

.5 claims for damages, other than to the Work itself, because of injury to or destruction of tangible property, including loss of use resulting therefrom;

.6 claims for damages because of bodily injury, death of a person or property damage arising out of ownership, maintenance or use of a motor vehicle; and

Page 38: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 38 OF 69

.7 claims involving contractual liability insurance applicable to the Contractor’s obligations under Paragraph 3.18 (Indemnification) herein.

11.1.2 The insurance required by Subparagraph 11.1.1 herein, shall be written for not less than limits of $500,000 per person, $1,000,000 per occurrence or a minimum of $1,000,000 combined single limit. Coverages, whether written on an occurrence or claims-made basis, shall be maintained without interruption from date of commencement of the Work until date of final payment and termination of any coverage required to be maintained after final payment. The insurance required by Subparagraph 11.1.1 herein, shall include contractual liability insurance applicable to the Contractor’s obligations under Paragraph 3.18 (Indemnification) herein, and coverage for the “XCU” exposure.

The University of South Florida, Board of Trustees shall be named as an additional insured and a waiver of subrogation in favor of the Owner shall be included in all liability policies. 11.1.2.1 Worker’s Compensation: The Contractor shall secure and maintain for the life of this Agreement, valid Worker’s Compensation Insurance as required by Chapter 440 (Worker’s Compensation), Florida Statutes. Copies of the insurance policy shall be filed with the Owner no later than 60 days after execution of the Owner-Contractor Agreement. 11.1.2.2 Automobile Liability: The Contractor shall secure and maintain, during the life of this Agreement, Automobile Liability insurance on all vehicles against bodily injury and property damage in at least the amounts of $500,000 per person, $1,000,000 per occurrence and property damage in at least the amount of $500,000; or combined single limit of $1,000,000 for bodily injury and property damage. The University of South Florida, Board of Trustees shall be named as an additional insured and a waiver of subrogation in favor of the Owner shall be included in all liability policies. 11.1.3 Certificates of Insurance acceptable to the Owner shall be filed with the Owner prior to commencement of the Work. These Certificates and the insurance policies required by this Paragraph 11.1 (Contractor’s Liability Insurance) herein, shall contain a provision that coverages afforded under the policies will not be cancelled or allowed to expire until at least 30 days’ prior to written notice has been given to the Owner. If any of the foregoing insurance coverages are required to remain in force after final payment, an additional certificate evidencing continuation of such coverage shall be submitted with the final Application for Payment as required by Subparagraph 9.10.2 (Final Payment) herein. The Contractor shall furnish one copy each of Certificates of Insurance for each copy of the Agreement which shall specifically set forth evidence of all insurance coverage required by the Contract Documents. The Certificate of Insurance shall be dated and show the name of the insured Contractor, the specific job by name and job number, the name of the insurer, the number of the policy, its effective date, and its termination date. The Contractor shall furnish a copy of the insurance policy to the Owner within 60 days following execution of the Agreement. 11.2 OWNER’S LIABILITY INSURANCE 11.3 PROPERTY INSURANCE 11.3.1 The Contractor shall purchase and maintain, with an admitted carrier in the State of Florida, property insurance in the amount of the initial Contract Sum as well as subsequent modifications thereto for the entire Work at the site on a replacement cost basis, including, where applicable, the existing structure. Coverage for existing structures shall include all perils described in Subparagraph 11.3.1.1 below. Such property insurance (builder’s risk) shall be maintained, unless otherwise provided in the Contract Documents or otherwise agreed in writing by all persons and entities who are beneficiaries of such insurance, until final payment has been made as provided in Paragraph 9.10 or until no person or entity other than the Owner has an insurable interest in the property required by this Paragraph 11.3 (Property Insurance), herein to be covered, whichever is earlier. This insurance shall include interests of the Owner, the Contractor, Subcontractors and Sub-subcontractors in the Work. 11.3.1.1 Property insurance shall be written on a Builder’s Risk form or its equivalent and shall include coverage on a replacement value basis. Property covered by this insurance shall include property of the Owner, Contractor, Subcontractors and Sub-subcontractors, consisting of materials, supplies, machinery, equipment and fixtures which will become a permanent part of the Work at the project site. Property covered by this insurance shall also include temporary building(s) or structure(s) at the site other

Page 39: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 39 OF 69

than office trailer(s). The perils insured under this insurance shall be at least equivalent to the insured perils of the Causes of Loss – Special form as published by the Insurance Services Office, Inc. including reasonable compensation for Architect/Engineer’s services and expenses required as a result of such insured loss. 11.3.1.2 Any special insurance requirements will be addressed in the Special Conditions or in Supplementary Conditions. 11.3.1.3 If the property insurance provides deductibles, the Contractor shall pay costs not covered because of such deductibles, unless otherwise provided in the Contract Documents or otherwise agreed in writing by the Owner and the Contractor. 11.3.1.4 Unless otherwise provided in the Contract Documents, this property insurance shall cover portions of the Work stored off the site after written approval of the Owner at the value established in the approval, and also portions of the Work in transit. 11.3.2 Boiler and Machinery Insurance. When the Work includes the repair, removal, installation and/or testing of live steam boilers, valves, pipes or lines, then this insurance shall include coverage at least equivalent to the Boiler and Machinery Coverage Form as published by the Insurance Services Office, Inc. This insurance shall include interests of the Owner, Contractor, Subcontractors and Sub-subcontractors in the Work, and the Owner and Contractor shall be named insured’s. 11.3.3 Prior to commencement of the Work, the Contractor shall provide the Owner with a Certificate of Insurance which evidences the property insurance (builder’s risk) provided by the Contractor. This Certificate of Insurance shall include an Additional Named Insured Provision and a Waiver of Subrogation Provision in favor of the Owner to protect the interests of the Owner. Upon receipt of the policy, the Contractor shall file with the Owner a copy of each policy that includes insurance coverages required by this Paragraph 11.3 (Property Insurance) herein. Each policy shall contain all generally applicable conditions, definitions, exclusions and endorsements related to this Project. Each policy shall contain a provision that the policy will not be cancelled or allowed to expire until at least 30 days’ prior written notice has been given to the Owner. 11.3.4 A loss or losses insured under this insurance shall be adjusted by the Contractor and its insurance company. The Contractor shall repair or replace the damaged property with the proceeds from the builder’s risk policy. The Contractor shall be responsible for all damages and necessary repairs whether or not the loss is covered by the builder’s risk policy. 11.3.5 Partial occupancy or use in accordance with Paragraph 9.9 (Partial Occupancy or Use) herein, shall not commence until the insurance company or companies providing property insurance have consented to such partial occupancy or use by endorsement or otherwise. The Owner and the Contractor shall take reasonable steps to obtain consent of the insurance company or companies and shall, without mutual written consent, take no action with respect to partial occupancy or use that would cause cancellation, lapse or reduction of insurance. 11.4 PERFORMANCE BOND AND PAYMENT BOND 11.4.1 The Contractor shall furnish bonds covering faithful performance of the Contract and payment of obligations arising thereunder as stipulated in bidding requirements or specifically required in the Contract Documents on the date of execution of the Contract. 11.4.2 Upon the request of any person or entity appearing to be a potential beneficiary of bonds covering payment of obligations arising under the Contract, the Contractor shall promptly furnish a copy of the bonds or shall permit a copy to be made. ARTICLE 12 UNCOVERING AND CORRECTION OF WORK 12.1 UNCOVERING OF WORK 12.1.1 If a portion of the Work is covered contrary to the Architect/Engineer’s request or to requirements specifically expressed in the Contract Documents, it must, if required in writing by the Architect/Engineer,

Page 40: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 40 OF 69

be uncovered for the Architect/Engineer’s observation and be replaced at the Contractor’s expense without change in the Contract Time. 12.1.2 If a portion of the Work has been covered which the Architect/Engineer has not specifically requested to observe prior to its being covered, the Architect/Engineer may request to see such Work and it shall be uncovered by the Contractor. If such Work is in accordance with the Contract Documents, costs of uncovering and replacement shall, by appropriate Change Order, be charged to the Owner. If such Work is not in accordance with the Contract Documents, the Contractor shall pay such costs unless the condition was caused by the Owner or a separate contractor in which event the Owner shall be responsible for payment of such costs. 12.2 CORRECTION OF WORK 12.2.1 The Contractor shall promptly correct Work rejected by the Architect/Engineer or failing to conform to the requirements of the Contract Documents, whether observed before or after Substantial Completion and whether or not fabricated, installed or completed. The Contractor shall bear costs of correcting such rejected Work, including additional testing and inspections and compensation for the Architect/Engineer’s services and expenses made necessary thereby. The Contractor shall commence correction of the Work within seven days after the date of written notice from the Architect/Engineer. 12.2.2 If, within one year after the date of Substantial Completion of the Work or designated portion thereof, or after the date for commencement of warranties established under Subparagraph 9.9.1 (Owner Occupancy) herein, or by terms of an applicable special warranty required by the Contract Documents, any of the Work is found to be not in accordance with the requirements of the Contract Documents, the Contractor shall correct it promptly after receipt of written notice from the Owner to do so unless the Owner has previously given the Contractor a written acceptance of such condition. This period of one year shall be extended with respect to portions of Work first performed after Substantial Completion by the period of time between Substantial Completion and the actual performance of the Work. This obligation under this Subparagraph 12.2.2 herein, shall survive acceptance of the Work under the Contract and termination of the Contract. The Owner shall give such notice promptly after discovery of the condition. 12.2.3 The Contractor shall remove from the site portions of the Work which are not in accordance with the requirements of the Contract Documents and are neither corrected by the Contractor nor accepted by the Owner. 12.2.4 If the Contractor fails to correct nonconforming Work within a reasonable time, the Owner may correct it in accordance with Paragraph 2.4 (Owner’s right to Carry Out the Work) herein. If the Contractor does not proceed with correction of such nonconforming Work within a reasonable time fixed by written notice from the Architect/Engineer, the Owner may remove it and store the salvable materials or equipment at the Contractor’s expense. If the Contractor does not pay costs of such removal and storage within ten days after written notice, the Owner may upon ten additional days’ written notice sell such materials and equipment at auction or at private sale and shall account for the proceeds thereof, after deducting costs and damages that should have been borne by the Contractor, including compensation for the Architect/Engineer’s services and expenses made necessary thereby. If such proceeds of sale do not cover costs which the Contractor should have borne, the Contract Sum shall be reduced by the deficiency. If payments then or thereafter due the Contractor are not sufficient to cover such amount, the Contractor shall pay the difference to the Owner. 12.2.5 The Contractor shall bear the cost of correcting destroyed or damaged construction, whether completed or partially completed, of the Owner or separate contractors caused by the Contractor’s correction or removal of Work which is not in accordance with the requirements of the Contract Documents. 12.2.6 Nothing contained in this Paragraph 12.2 (Correction of Work) herein, shall be construed to establish a period of limitation with respect to other obligations which the Contractor might have under the Contract Documents. Establishment of the time period of one year as described in Subparagraph 12.2.2 herein, relates only to the specific obligation of the Contractor to correct the Work, and has no relationship to the time within which the obligation to comply with the Contract Documents may be sought to be

Page 41: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 41 OF 69

enforced, nor to the time within which proceedings may be commenced to establish the Contractor’s liability with respect to the Contractor’s obligations other than specifically to correct the Work. 12.3 ACCEPTANCE OF NONCONFORMING WORK 12.3.1 If the Owner prefers to accept Work which is not in accordance with the requirements of the Contract Documents, the Owner may do so instead of requiring its removal and correction, in which case the Contract Sum will be reduced as appropriate and equitable. Such adjustment shall be effected whether or not final payment has been made. ARTICLE 13 MISCELLANEOUS PROVISIONS 13.1 GOVERNING LAW 13.1.1 The Contract shall be governed by the law of the State of Florida. 13.2 SUCCESSORS AND ASSIGNS 13.2.1 The Owner and Contractor respectively bind themselves, their partners, successors, assigns and legal representatives to the other party hereto and to partners, successors, assigns and legal representatives of such other party in respect to covenants, agreements and obligations contained in the Contract Documents. Neither party to the Contract shall assign the Contract as a whole without written consent of the other. In case the Contractor, on written consent of the Owner, assigns all or any part of any money due or to become due under this Contract, the instrument of assignment shall contain a Subparagraph substantially to the effect that it is agreed that the right of the assignee to any money due or to become due to the Contractor shall be subject to prior claims of all persons, firms and corporations for services rendered or materials supplied for the performance of the Work called for in this Contract. 13.3 WRITTEN NOTICE 13.3.1 Written notice shall be deemed to have been duly served if delivered in person to the individual or a member of the firm or entity or to an officer of the corporation for which it was intended, or if delivered at or sent by registered or certified mail to the last business address known to the party giving notice. 13.4 RIGHTS AND REMEDIES 13.4.1 Duties and obligations imposed by the Contract Documents and rights and remedies available thereunder shall be in addition to and not a limitation of duties, obligations, rights and remedies otherwise imposed or available by law. 13.4.2 No action or failure to act by the Owner, Architect/Engineer or Contractor shall constitute a waiver of a right or duty afforded them under the Contract, nor shall such action or failure to act constitute approval of or acquiescence in a breach thereunder, except as may be specifically agreed in writing. 13.5 TESTS AND INSPECTIONS 13.5.1 Tests, inspections and approvals of portions of the Work required by the Contract Documents or by laws, ordinances, rules, regulations or order of public authorities having jurisdiction shall be made at an appropriate time. Unless otherwise provided, the Contractor shall make arrangements for such tests, inspections and approvals with an independent testing laboratory or entity acceptable to the Owner, or with the appropriate public authority, and shall bear all related costs of tests, inspections and approvals. The Contractor shall give the Architect/Engineer timely notice of when and where tests and inspections are to be made so the Architect/Engineer may observe such procedures. The Owner shall bear costs of tests, inspections or approvals which do not become requirements until after bids are received or negotiations concluded. 13.5.2 If the Architect/Engineer, Owner or public authorities having jurisdiction determine that portions of the Work require additional testing, inspection or approval not included under Subparagraph 13.5.1 herein, the Architect/Engineer will, upon written authorization from the Owner, instruct the Contractor to make arrangements for such additional testing, inspection or approval by an entity acceptable to the Owner, and the Contractor shall give timely notice to the Architect/Engineer of when and where tests and inspections are to be made so the Architect/Engineer may observe such procedures. The Owner shall bear such costs except as provided in Subparagraph 13.5.3 herein.

Page 42: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 42 OF 69

13.5.3 If such procedures for testing, inspection or approval under Subparagraphs 13.5.1 and 13.5.2 herein reveal failure of the portions of the Work to comply with requirements established by the Contract Documents, the Contractor shall bear all costs made necessary by such failure including those of repeated procedures and compensation for the Architect/Engineer’s services and expenses. 13.5.4 Required certificates of testing, inspection or approval shall, unless otherwise required by the Contract Documents, be secured by the Contractor and promptly delivered to the Architect/Engineer. 13.5.5 If the Architect/Engineer is to observe tests, inspections or approvals required by the Contract Documents, the Architect/Engineer will do so promptly and, where practicable, at the normal place of testing. 13.5.6 Test or inspections conducted pursuant to the Contract Documents shall be made promptly to avoid unreasonable delay in the Work. 13.5.7 Where tests are required by the technical specifications for materials, methods or equipment, the Contractor shall pay the cost of initial tests to prove qualities and determine conformance with specification requirements, e.g., mill tests on cement and steel; load testing of piling; sieve analysis and colorimetric tests on sand; strength tests for determining proportions of materials for concrete, moisture content and sound transmission tests of concrete blocks, etc. 13.5.8 If substitute materials or equipment are proposed by the Contractor, he shall pay the cost of all tests which may be necessary to satisfy the Architect/Engineer that specification requirements are met. 13.5.9 The Contractor shall pay for all testing costs, including but not limited to, power, fuel, and equipment costs which may be required for complete testing of all equipment and systems for proper operation such as plumbing, heating, ventilation, air conditioning, electrical, elevator, dumbwaiters and conveyors, etc. 13.6 INTEREST 13.6.1 Interest shall be paid in certain cases as provided by Section 215.422 (Payments), Florida Statues. 13.6.2 The Contractor shall be required to pay interest to Subcontractors and suppliers in certain cases where payments are not within the time constraints of Section 287.0585 (late Payments), Florida Statues. 13.7 COMMENCEMENT OF STATUTORY LIMITATION PERIOD 13.7.1 As between the Owner and Contractor:

.1 Before Substantial Completion. As to acts or failures to act occurring prior to the relevant date of Substantial Completion, any applicable statute of limitations shall commence to run and any alleged cause of action shall be deemed to have accrued in any and all events not later than such date of Substantial Completion;

.2 Between Substantial Completion and Final Certificate for Payment. As to acts or failures to act occurring subsequent to the relevant date of Substantial Completion and prior to issuance of the final Certificate for Payment, any applicable statute of limitations shall commence to run and any alleged cause of action shall be deemed to have accrued in any and all events not later than the date of issuance of the final Certificate for Payment; and

.3 After Final Certificate for Payment. As to acts or failures to act occurring after the relevant date of issuance of the final Certificate for Payment, any applicable statute of limitations shall commence to run and any alleged cause of action shall be deemed to have accrued in any and all events not later than the date of any act or failure to act by the Contractor pursuant to any warranty provided under Paragraph 3.5 (Warranty) herein, the date of any correction of the Work or failure to correct the Work by the Contractor under Paragraph 12.2 (Correction of Work) herein, or the date of actual commission of any other act or failure to perform any duty or obligation by the Contractor or Owner, whichever occurs last.

13.8 HARMONY

Page 43: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 43 OF 69

13.8.1 The Contractor shall exert every reasonable and diligent effort to assure that all labor employed by the Contractor and the Subcontractors for Work on the Project shall Work in harmony with and be compatible with all other labor being used on the site of the Project, and representative of the Architect/Engineer and the Owner. 13.8.2 The Contractor shall include this provision in all contracts with Subcontractors, and the Contractor shall require that such a provision be included in the contracts between the Subcontractors and the Sub-subcontractors, provided, however, that this provision shall not be interpreted or enforced so as to deny or abridge, on account of membership or non-membership in any labor union or labor organization, the right of any person to work as guaranteed by Article I, Section 6 (Right to Work) of the Florida Constitution. 13.9 CHANGE OF ADDRESS 13.9.1 If the address of the Contractor changes, the Contractor shall provide written notice to that effect to both the Owner and the Architect/Engineer. 13.10 DISCOVERY OF VALUABLE ITEMS OR ITEMS OF HISTORICAL SIGNIFICANCE 13.10 If in the execution of the Work any items of historical significance or any valuable items or materials of any kind are discovered buried or hidden within the Work, such items or materials shall be the property of the Owner. The Contractor shall immediately upon discovery of such items or materials, and before removal thereof, acquaint the Architect/Engineer with such discovery and carry out by Change Order, at the expense of the Owner, the Architect/Engineer’s orders as to the disposal of the items or materials. ARTICLE 14 TERMINATION OR SUSPENSION OF THE CONTRACT 14.1 TERMINATION BY THE CONTRACTOR 14.1.1 The Contractor may terminate the Contract if the Work is stopped for a period of 30 days through no act or fault of the Contractor or a Subcontractor, Sub-subcontractor or their agents or employees or any other persons performing portions of the Work under contract with the Contractor, for any of the following reasons:

.1 issuance of an order of a court or other public authority having jurisdiction;

.2 an act of government, such as a declaration of national emergency, making material unavailable;

.3 because the Architect/Engineer has not issued a Certificate for Payment and has not notified the Contractor of the reason for withholding certification as provided in Subparagraph 9.4.1 (Certification for Payment) herein, or because the Owner has not made payment on a Certificate for Payment within the time stated in the Contract Documents;

.4 if repeated suspensions, delays or interruptions by the Owner as described in Paragraph 14.3 (Suspension of Work for Owner Convenience) herein, constitute in the aggregate more than 100 percent of the total number of days scheduled for completion, or 120 days in any 365-day period, whichever is less; or

.5 the Owner has failed to furnish to the Contractor promptly, upon the Contractor’s request, reasonable evidence as required by Subparagraph 2.2.1 (Review by Contractor) herein.

14.1.2 If one of the above reasons exists, the Contractor may, upon seven additional day’s written notice to the Owner and Architect/Engineer, terminate the Contract and recover from the Owner payment for Work executed and for proven loss with respect to materials, equipment, tools, and construction equipment and machinery, including reasonable overhead, profit and damages. 14.2 TERMINATION BY THE OWNER FOR CAUSE 14.2.1 The Owner may terminate the Contract if the Contractor:

.1 persistently or repeatedly refuses or fails to supply enough properly skilled workers or proper materials;

.2 fails to make payment to Subcontractors for materials or labor in accordance with the respective agreements between the Contractor and the Subcontractor;

.3 persistently disregards laws, ordinances, or rules, regulations or orders of a public authority having jurisdiction; or

.4 otherwise is guilty of substantial breach of a provision of the Contract Documents.

Page 44: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 44 OF 69

14.2.2 When any of the above reasons exist, the Owner, upon certification by the Architect/Engineer that sufficient cause exists to justify such action, may without prejudice to any other rights or remedies of the Owner and after giving the Contractor and the Contractor’s surety, if any, seven days’ written notice, terminate employment of the Contractor and may direct the surety to:

.1 take possession of the site and of all materials, equipment, tools, and construction equipment and machinery thereon owned by the Contractor;

.2 accept assignments of subcontracts pursuant to Paragraph 5.4 (Contingent Assignment of Subcontractors) herein; and

.3 finish the Work by whatever reasonable method the Owner may deem expedient. 14.2.3 When the Owner terminates the Contract for one of the reasons stated in Subparagraph 14.2.1 (Termination) herein, the Contractor shall not be entitled to receive further payment until the Work is finished. 14.2.4 If the Contractor’s surety is directed to complete the Work, then all payments made after termination shall be made to the Surety until the Work is finished and the Contract Sum has been expended. The surety shall then be responsible for all of the obligations and duties of the Contractor under the Contract and shall be bound by the conditions of the Contract to fulfill all obligations of the Contract for the Contract Sum therein. The Surety may not assign those obligations without the written consent of the Owner. The surety shall be responsible for the payment of all costs relating to the termination of the employment of the Contractor, including compensation for the Architect/Engineer’s services and expenses made necessary thereby. The amount to be paid to the surety or Owner, as the case may be, shall be certified by the Architect/Engineer, upon application, and this obligation for payment shall survive termination of the employment of the Contractor. 14.3 SUSPENSION BY THE OWNER FOR CONVENIENCE 14.3.1 The Owner may, without cause, order the Contractor in writing to suspend, delay or interrupt the Work in whole or in part for such period of time as the Owner may determine. 14.3.2 An adjustment shall be made for increases in the cost of performance of the Contract including profit on the increased cost of performance, caused by suspension, delay or interruption. No adjustment shall be made to the extent:

.1 that performance is, was or would have been so suspended, delayed or interrupted by another cause for which the Contractor is responsible; or

.2 that an equitable adjustment is made or denied under another provision of the Contract. 14.3.3 Adjustments made in the cost of performance may have a mutually agreed fixed or percentage fee.

END OF EXHIBIT F GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION

Page 45: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 45 OF 69

USF PROJECT MANUAL EXHIBIT F-1 PAYMENT BOND

(FOR LABOR AND MATERIALS)

THIS BOND IS ISSUED SIMULTANEOUSLY WITH PERFORMANCE BOND IN FAVOR OF THE OWNER CONDITIONED ON THE FULL AND FAITHFUL PERFORMANCE OF THE CONTRACT AS PROVIDE BY SECTION 255.05, F.S.

BY THIS BOND WE: Contractor Name, Contrcator Address, City, State, 00000, as Principal, hereinafter called Contractor and Surety Name, Surety Address, City, State, 00000, as Surety, hereinafter called Surety, are held and firmly bound unto the University of South Florida Board of Trustees, a public body corporate, hereinafter called Owner, for the use and benefit of claimants as herein below defined, in the amount [Total Construction Contract Amount] of $ 0,000,000.00, for the payment whereof Contractor and Surety bind themselves, their heirs, executors, administrators, successors and assigns, jointly and severally. WHEREAS: Contractor has by written agreement dated Month 00, 0000, entered into a contract with Owner for construction of USF Project Name, University of South Florida, Project Number USF 000, in accordance with Drawings and Specifications prepared by A/E Name, A/E Address, which Owner-Contractor Agreement is by reference made a part hereof, and is hereinafter referred to as the Agreement. [If property is not on University campus include a legal property description or street address and identity of the property owner] THE CONDITIONS OF THIS BOND are such that: 1. If Contractor shall promptly make all payments owing when due to all persons who are defined in

Section 713.01, Florida Statutes, whose claims derive directly or indirectly from the prosecution of the Work provided for in the Agreement, then this bond is void; otherwise, it remains in full force and effect.

2. Each said claimant shall have a right of action against the Contractor and Surety for the amount due the claimant. No such action shall subject the Owner to any cost, expense, loss or damage, and Contractor shall promptly pay Owner for the full measure of all cost, expense, loss, damage, and attorney's fees sustained by Owner as a result of any default by Contractor under the Agreement.

3. A claimant, except a laborer, who is not in privity with the Contractor shall, before commencing or not later than forty five (45) days after commencing to furnish labor, materials, equipment or supplies for the prosecution of the Work, furnish the Contractor with a notice that the claimant intends to look to the bond for protection. A claimant who is not in privity with the Contractor and who has not received payment for labor, materials, equipment or supplies shall deliver to the Contractor and to the Surety written notice of the performance of the labor or delivery of the materials, equipment or supplies and of the nonpayment. The notice of nonpayment may be served at any time during the progress of the work or thereafter, but before 45 days after the first furnishing of labor, services or materials and not later than 90 days after the final furnishing of the labor, services or materials by the claimant or, with respect to rental equipment, not later than 90 days after the date that the rental equipment was last on the jobsite available for use. No action for the labor, materials, equipment or supplies may be instituted against the Contractor or the Surety unless both notices have been given. No action shall be instituted against the Contractor or the Surety after one year from the performance of the labor or completion of the delivery of the materials, equipment or supplies is completed.

4. An action against the Surety or the Contractor, or both, may be brought in the county in which the public building or public work is being constructed or repaired or in any other place authorized by the provisions of Chapter 47 (Venue), Florida Statutes.

5. The amount of this bond shall be changed only to the extent that the Contract Sum is changed in accord with applicable provisions of the Contract For Construction.

6. Neither any change in or under the Contract Documents, nor any compliance or noncompliance with any formalities provided in the Agreement or the change shall relieve the Surety of its obligations under this Bond.

Page 46: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 46 OF 69

SIGNED AND SEALED THIS 00 DAY OF Month, 0000 For the CONTRACTOR AS WITNESSED BY: (SEAL)

BY: OFFICER NAME: Name

OFFICE TITLE: Title For the SURETY AS WITNESSED BY: Surety Name: Surety (SEAL)

BY: OFFICER NAME: Name

OFFICE TITLE: Title

AGENT’S NAME: Name AGENT’S TITLE: Title

AGENT’S COMPANY: Company AGENT’S ADDRESS: Address

AGENT’S CITY, STATE, ZIP: City State Zip

Page 47: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 47 OF 69

USF PROJECT MANUAL EXHIBIT F-2 PERFORMANCE BOND

THIS BOND IS ISSUED SIMULTANEOUSLY WITH PAYMENT BOND (FOR LABOR & MATERIALS) IN FAVOR OF THE OWNER CONDITIONED ON THE FULL AND FAITHFUL PERFORMANCE

OF THE CONTRACT AS PROVIDED BY SECTION 255.05, F.S. BY THIS BOND WE: Contractor Name, Contrcator Address, City, State, 00000, as Principal, hereinafter called Contractor and Surety Name, Surety Address, City, State, 00000, as Surety, hereinafter called Surety, are held and firmly bound unto the University of South Florida Board of Trustees, a public body corporate, hereinafter called Owner, for the use and benefit of claimants as herein below defined, in the amount [Total Construction Contract Amount] of $ 0,000,000.00, for the payment whereof Contractor and Surety bind themselves, their heirs, executors, administrators, successors and assigns, jointly and severally. WHEREAS, Contractor has by written agreement dated Month 00, 0000, entered into a contract with Owner for construction of USF Project Name, University of South Florida, Project Number USF 000, in accordance with Drawings and Specifications prepared by A/E Name, A/E Address, which Owner-Contractor Agreement is by reference made a part hereof, and is hereinafter referred to as the Agreement. NOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that, if Contractor shall promptly and faithfully perform said Agreement, then this obligation shall be null and void; otherwise, it shall remain in full force and effect.

The Surety hereby waives notice of any alteration or extension of time made by the Owner.

Whenever Contractor is in default under the Agreement, and the Owner has performed its obligations thereunder, the Surety shall promptly remedy the default, in accordance with Section 255.05 (Bond of Contractor), Florida Statutes, or shall promptly obtain a bid or bids for completing the Agreement in accordance with its terms and conditions, and arrange for a contract between such bidder and the Surety, and pay as work progresses (even though there should be a default or a succession of defaults under the contract or contracts of completion arranged under this paragraph) the cost of completion less the balance of the Contract Sum; but not exceeding, including other costs and damages for which the Surety may be liable hereunder, the amount set forth in the first paragraph hereof. The term "balance of the Contract Sum", as used in this paragraph, shall mean the total amount payable by Owner to Contractor under the Agreement and any amendments thereto, less the amount properly paid by Owner to Contractor.

No right of action shall accrue on this bond to or for the use of any person or corporation other than the Owner named herein or the heirs, executors, administrator or successors of the Owner.

CONTINUED ON FOLLOWING PAGE

Page 48: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 48 OF 69

SIGNED AND SEALED THIS 00 DAY OF Month, 0000 FOR THE CONTRACTOR

AS WITNESSED BY: CONTRACTOR: Contractor Name (SEAL)

BY: OFFICER NAME: Name

OFFICE TITLE: Title FOR THE SURETY AS WITNESSED BY: SURETY NAME: Surety Name (SEAL)

BY: OFFICER NAME: Name

OFFICE TITLE: Title

AGENT’S NAME: Name AGENT’S TITLE: Title

AGENT’S COMPANY: Company AGENT’S ADDRESS: Address

AGENT’S CITY, STATE, ZIP: City State Zip

(POWER OF ATTORNEY ATTACHED HERETO)

Page 49: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 49 OF 69

USF PROJECT MANUAL EXHIBIT G OWNER-CONTRACTOR AGREEMENT FOR CONSTRUCTION

OWNER – CONTRACTOR AGREEMENT FOR CONSTRUCTION

INDEX ARTICLE TITLE Article 1 .... The Contract Document Article 2 .... The Work Article 3 .... The Architect/Engineer Article 4 .... Time of Commencement and Completion Article 5 .... Contract Sum Article 6 .... Payment and Contract Sum Article 7 .... Final Payment Article 8 .... Miscellaneous Provisions Article 9 .... Certificate of Contract Completion

THIS AGREEMENT made this 00 day of Month, 0000, by and between the University of South Florida Board of Trustees, a public body corporate, hereinafter called the Owner, and Contractor Name, Contractor Address a Florida corporation, Federal I.D. number Corporate ID Number, hereinafter called the Contractor. The Owner and the Contractor agree as set forth below. ARTICLE 1. THE CONTRACT DOCUMENTS 1.1 The Contract Documents consist of this Agreement, the Conditions of the Contract (General, Supplementary, Special and other Conditions), the Drawings, the Specifications, the Project Manual dated Month 00, 0000, and all Addenda issued prior to execution of this Agreement and all Modifications issued subsequent thereto. These form the Contract, and all are as fully a part of the Contract as if attached to this Agreement or repeated herein. An enumeration of the Contract Documents appears in Article 8 of this Agreement. 1.2 If any portion of the Contract Documents is in conflict with any other portion, the various documents comprising the Contract Documents shall govern in the following order of precedence: The Owner-Contractor Agreement; Modifications; Addenda; any Special Conditions; Supplementary Conditions; the General Conditions; the Specifications; the Drawings; as between schedules and information given on Drawings, the schedules shall govern; as between figures given on Drawings and the scaled measurements, the figures shall govern; as between large-scale Drawings and small-scale Drawings, the larger scale shall govern. ARTICLE 2. THE WORK 2.1 The Contractor shall perform all the Work required by the Contract Documents for Project Name, University of South Florida, USF Project No. USF 000. ARTICLE 3. THE ARCHITECT/ENGINEER 3.1 The Architect/Engineer for this project is A/E Name, A/E Address. ARTICLE 4. TIME OF COMMENCEMENT AND COMPLETION 4.1 The Work to be performed under this contract shall be commenced within ten (10) calendar days after the date indicated on the Notice to Proceed, shall be substantially completed within Number (00) calendar days after the date indicated on the Notice to Proceed, and shall be finally completed within thirty (30) calendar days after the date of Substantial Completion or within such other time as identified on the Certificate of Substantial Completion. 4.2 Liquidated Damages for Failure to Complete on Time 4.2.1 Inasmuch as failure to complete the project within the time fixed in Paragraph 4.1 (Commencement & Completion) herein will result in substantial injury to the Owner, and as damages

Page 50: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 50 OF 69

arising from such failure cannot be calculated with Any degree of certainty, it is hereby agreed that if the Work is not substantially completed, according to the definition of "Substantial Completion" in Paragraph 8.4 (Date of Substantial Completion) herein, or within such further time, if any, as shall be allowed for time extensions in accordance with the provisions of the Contract Documents, the Contractor shall pay to the Owner as liquidated damages for such delay, and not as a penalty, $ 0,000.00 for each and every calendar day elapsing between the date fixed for Substantial Completion in Paragraph 4.1 herein and the date such Substantial Completion shall have been fully accomplished. Said liquidated damages shall be payable in addition to any excess expenses or costs payable by the Contractor to the Owner under the provisions of Article 14 (Termination or Suspension of the Contract) of the General Conditions, and shall not preclude the recovery of damages by the Owner under other provisions of the Contract Documents, except for Contractor's delays. 4.2.2 This provision for liquidated damages for delay shall in no manner affect the Owner's right to terminate the Contract as provided in Article 14 of the General Conditions or elsewhere in the Contract Documents. The Owner's exercise of the right to terminate shall not release the Contractor from the obligation to pay said liquidated damages in the amount set out in Subparagraph 4.2.1 herein. 4.2.3 It is further agreed that the Owner may deduct from the balance retained by the Owner under the provisions of Subparagraph 6.3.1 (Payment Withheld) herein the liquidated damages stipulated herein or in Paragraph 4.3 herein, as the case may be, or such portion thereof as the retained balance will cover. 4.3 Liquidated Damages When Owner Terminates Contract. The Owner is entitled to completion of the project within the time fixed in Paragraph 4.1 herein or within such further time, if any, as may be allowed in accordance with the provisions of the Contract. In the event of termination of the Contract by the Owner prior to completion as provided in Paragraph 14.2 (Termination by the Owner for Cause) of the General Conditions or elsewhere in the Contract Documents, the Contractor shall be liable to the Owner for the expenses for additional managerial and administrative services provided in said Article 14 and also for the per diem liquidated damages agreed upon in Paragraph 4.2 herein. 4.3.1 for each day the Contractor is in arrears in the Work at the time of said termination as determined by the Architect/Engineer, and 4.3.2 for each day of thirty (30) additional calendar days hereby stipulated and agreed to be the time it will require the Surety to effect another contract for completion of the Work, including resumption of Work thereon, 4.3.3 Provided, however, that the sum of Subparagraphs 4.3.1 and 4.3.2 herein shall not exceed the number of days beyond the original agreed completion date, or any extension thereof as herein provided, reasonably required for completion of the Work. ARTICLE 5. CONTRACT SUM 5.1 The Owner shall pay the Contractor for the performance of the Work, subject to additions and deductions by Change Order or Construction Change Directive as provided in the Conditions of the Contract, the Contract Sum of Dollars Dollars ($ 0,000.00), for the Base Bid only OR the Base Bid and Alternates 1 through 00. ARTICLE 6. PAYMENTS OF CONTRACT SUM 6.1 Indemnification Rider. Upon receipt of the Notice to Proceed, the Contractor shall begin providing the indemnification described in Paragraph 3.18 (Indemnification) of the General Conditions. The Contractor shall include the Sum of Ten Dollars for provision of the indemnification on the Schedule of Values accompanying the first application for payment. 6.2 Progress Payments. The Contractor shall provide to the Owner a projection of invoice amounts for the duration of the project, based upon the project schedule, to facilitate the Owner’s need to manage the cash flow requirements for the project. The projection shall be updated as required. Based upon Applications for Payment submitted to the Architect/Engineer by the Contractor and Certificates of Payment issued by the

Page 51: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 51 OF 69

Architect/Engineer and approved by the Owner, the Owner shall make progress payments to the Contractor against the account of the Contract Sum, as provided in the Conditions of the Contract in accordance with the following: 6.2.1 Within thirty (30) days from the Owner's receipt of any Application for Payment submitted by the Contractor, the Owner shall pay or cause to be paid to the Contractor that portion of the Contract Sum previously unpaid, properly allocable to labor, materials, and equipment already incorporated in Work that has been satisfactorily performed in accordance with the requirements of the Contract Documents, as determined by the Architect/Engineer, together with that portion of the Contract Sum properly allocable to materials and equipment suitably stored by the last day of the preceding calendar month at the Project site or at some other location(s) mutually agreed upon in writing by the parties, as determined by the Architect/Engineer.

.1 The Contractor shall pay each Subcontractor out of the amount paid to the Contractor on account of such Subcontractor’s Work, the amount to which said Subcontractor is entitled reflecting the percentage actually retained, if any, from payments to the Contractor on account of said Subcontractor’s Work. The Contractor shall, by appropriate agreement with each Subcontractor, require each Subcontractor to make payments to its subcontractors in a similar manner. When the Contractor receives payment from the Owner for labor, services, or materials furnished by subcontractors and suppliers hired by the Contractor for the project, the Contractor shall remit payment due to those subcontractors and suppliers, less the value of any item contested in accordance with the Contract, within ten (10) days after the Contractor’s receipt of payment from the Owner. When the payment due the subcontractor is for final payment, including retainage, the subcontractor must include with the invoice for final payment a conditional release of lien and all appropriate warranties and closeout documentation. When the subcontractor receives payment from the Contractor for labor, services, or materials furnished by the subcontractors and suppliers hired by the subcontractor, the subcontractor shall remit payment due to those subcontractors and suppliers, less value of any item contested in accordance with the Contract, within ten (10) days after the subcontractor’s receipt of payment.

.2 The Architect/Engineer may, at the Architect/Engineer's discretion, furnish to a Subcontractor, if practicable, information regarding the percentages of completion of the amounts applied for by the Contractor and the action taken thereon by the Architect/Engineer on account of Work done by such Subcontractor.

.3 Neither the Owner nor the Architect/Engineer shall have any obligation to pay or to see to the payment of any moneys to any Subcontractor except as may otherwise be required by law.

.4 No Certificate for a progress payment, nor any progress payment, nor any partial or entire use of occupancy of the Project by the Owner, shall constitute an acceptance of any Work not in accordance with the Contract Documents.

6.2.2 As provided by Section 215.422 (Public Inspection), Florida Statues, if a warrant in payment of an invoice is not mailed by the Owner within 40 days after the receipt of the invoice and receipt, inspection and approval of the services, the Owner shall pay to the Contractor, in addition to the amount of the invoice, interest at the rate established by Section 55.03(1) (Rate of Interest), Florida Statues on the unpaid balance from the expiration of such 40-day period until such time as the warrant is mailed to the Contractor. These provisions apply only to undisputed amounts for which payment has been authorized. Invoices or pay requests returned to the Contractor due to preparation errors will result in a payment delay. Payment requirements do not start until a properly completed invoice or pay request is provided to the Owner. A Vendor Ombudsman has been established within the Department of Financial Services. The duties of this individual include acting as an advocate for vendors who may be experiencing problems in obtaining timely payment(s) from a state agency. The Vendor Ombudsman may be contacted at (850) 413-5516, or by calling the Department of Financial Services Consumer Hotline at 1-800-342-2762. 6.3 Payments Withheld 6.3.1 With the exception of Work which may be exempted from this requirement by a provision in the Special or Supplementary Conditions in the Project Manual, retainage shall be withheld from each monthly payment request, in an amount not to exceed 10% of the request, until 50% of construction

Page 52: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 52 OF 69

payments are made. After the Work is considered to be 50% complete, retainage not to exceed 10% of the request, may or may not be withheld at the discretion of the Architect/Engineer, subject to the following:

.1 If securities are substituted in lieu of retainage as permitted by Section 255.052, Florida Statutes, the securities must be free of all encumbrances, enabling the Owner to use those securities as it would retainage, and the Contractor must assign all its rights to the securities to the Owner.

.2 Subcontractors, forty-five (45) days after satisfactory completion of their work on the project, can invoice the Contractor for the remainder of unpaid work, including the full value of the retainage related to their work, less the value of any item contested in accordance with the terms and conditions of the Construction Contract. The subcontractor shall include a conditional release of lien and all appropriate warranties and closeout documentation with this final payment invoice to the Contractor. The Contractor must include this subcontractor payment request in the next Application for Payment in the pay application cycle to the Architect following the receipt of the subcontractor payment request, if deemed to be complete and in compliance with this section. The Owner shall process the payment request within twenty (20) days of receipt of the Certificate for payment from the Architect, in accordance with Section 215.422(1) (Payments), Florida Statues and shall include payment of the retainage, less the value of any contested item, in its next payment to the Contractor.

.3 Payments made under Subparagraph 6.3.1.2 herein do not change General Warranty period requirements or Specific Warranty period requirements, both of which begin at the date of Substantial Completion for the project, unless otherwise agreed to in writing.

.4 Payments made under Subparagraph 6.3.1.2 herein do not change contract requirements regarding project closeout, including list of items to be completed or corrected, documentation, instructions, etc.

.5 Determination of satisfactory completion of the work under Subparagraph 6.3.1.2 herein shall not change the warranty and project closeout requirements of the Contractor, and shall be subject to the Owner’s approval.

6.3.2 The Architect/Engineer may decline to certify payment or, because of subsequently discovered evidence or subsequent observations, he may nullify the whole or any part of any Certificate for Payment previously issued, to such extent as may be necessary, in the Architect/Engineer's opinion, to protect the Owner from loss because of:

.1 defective work not remedied,

.2 third party claims filed or reasonable evidence indicating probable filing of such claims,

.3 reasonable evidence that the Work cannot be completed for the unpaid balance of the Contract Sum,

.4 damage to the Owner or another contractor,

.5 reasonable evidence that the Work will not be completed within the Contract Time, or

.6 persistent failure to carry out the Work in accordance with the Contract Documents. 6.3.3 When the above grounds in Subparagraph 6.3.2 herein are removed, payment shall be made for the amount withheld because of them. ARTICLE 7. FINAL PAYMENT 7.1 Within forty (40) days from the date of Contract Completion the Owner shall pay or cause to be paid to the Contractor, the entire unpaid balance of the Contract Sum, less the amount of any sums which continue to be retained to satisfy the cost of performing any change in the Work which is the subject of any claim or dispute and which has not yet been satisfactorily performed by the Contractor, and less any amount being withheld for liquidated damages, provided that the parties have not otherwise stipulated in the Certificate of Substantial Completion, and provided further that the Work has been satisfactorily completed, the Contractor's obligations under the Contract have been fully performed, and a final Certificate for Payment has been issued by the Architect/Engineer.

Page 53: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 53 OF 69

ARTICLE 8. MISCELLANEOUS PROVISIONS 8.1 Terms used in the Agreement which are defined in the Conditions of the Contract shall have the meaning designated in those Conditions. 8.2 The Contract Documents, which constitute the entire Contract between the Owner and Contractor, are listed in Article 1 and, except for Modifications issued after execution of this Agreement, are enumerated as follows:

8.2.1 Project Manual: Entitled: “University of South Florida, Tampa Campus, USF Project Name: USF Project Name, USF Project No. USF 000” dated Month 00, 0000,” consisting of I. Procurement, II. General Conditions, and III. Technical Specifications. 8.2.2 Construction Drawings: Entitled “USF Project Name, University of South Florida, Tampa Campus, USF Project No. USF 000”, dated Month 00, 0000, See attached Index of Drawings. 8.2.3 Addenda 1 – 00: 8.3 As required by Section 287.058 (Contract Documents), Florida Statutes, this Contract may be unilaterally canceled by the Owner for refusal by the Contractor to allow public access to all documents, papers, letters, or other material subject to the provisions of Chapter 119 (Public Records), Florida Statues and made or received by the Contractor in conjunction with the Contract. 8.4 The Date of Substantial Completion of the Work or designated portion thereof is the date certified by the Architect/Engineer when construction is sufficiently complete, in accordance with the Contract Documents, so the Owner can occupy or utilize the Work or designated portion thereof for the use for which it is intended. The term "Substantial Completion" shall not mean the inclusion of such minor alterations and patching as the final inspection shall disclose. 8.5 Claims 8.5.1 Under this Contract the Contractor shall not have the right to compensation to satisfy any claim for costs, liabilities, or debts of any kind whatever from any act or omission attributable to the Owner unless the Contractor has provided notice to the Architect/Engineer and the Owner within 21 days of the event giving rise to the claim(s) as required by Article 4 (Administration of the Contract) of the General Conditions of the Contract and unless the detailed claim therefor is delivered to the Architect/Engineer and the Owner within 30 days following the notice. The detailed claim shall include:

.1 The date of the occurrence of the event giving rise to the claim and the date and manner of the Contractor's compliance with the notice requirements of Article 4 of the General Conditions of the Contract.

.2 The reasons upon which the Contractor bases the claim, demonstrating thereby that the costs, liabilities or debts reflected in the claim are not already a part of the Contract and the Contractor's compensation under the Contract; and that specific relief is due the Contractor for the claim.

8.5.2 The Architect/Engineer shall make a recommendation to the Owner within the time from provided in Paragraph 4.4 of the General Conditions after receipt of a claim. Copies of the Architect/Engineer's recommendation will be presented to the Contractor as well as the Owner. Unless the Architect/Engineer's recommendation is accepted by the Contractor, the Owner, the Architect/Engineer and the Contractor shall attempt to resolve the claim by following the procedures set forth in Article 4 of the General Conditions. 8.5.3 The Contractor shall carry on the Work and maintain the progress schedule during any administrative hearing or judicial proceeding unless otherwise agreed by the Contractor and the Owner in writing, and the Owner shall continue to make payments to the Contractor in accordance with the Contract Documents. 8.6 Harmony 8.6.1 The Contractor shall exert every reasonable and diligent effort to assure that all labor employed by the Contractor and the Subcontractors for Work on the Project shall work in harmony with and be

Page 54: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 54 OF 69

compatible with all other labor being used on the site of the Project, representatives of the Architect/Engineer, and the Owner. 8.6.2 Contractor further agrees that this provision will be included in all subcontracts of the Subcontractor as well as in the Contractor's own contract; provided, however, that this provision shall not be interpreted or enforced so as to deny or abridge, on account of membership or non-membership in any labor union or labor organization, the right of any person to work as guaranteed by Article 1, Section 6 (Right to Work) of the Florida Constitution. 8.7 Assignment of Antitrust Claims 8.7.1 The Contractor agrees that, after completion of all Work under this Contract and all amendments thereto and prior to final payment, the Contractor will execute and deliver to the Owner an Assignment of Antitrust Claims in the form provided in Section H of the Project Manual. 8.7.2 The Contractor also agrees that prior to final payment, the Contractor will cause each of the suppliers and Subcontractors who have furnished services, goods or materials in connection with the performance of this Contract to execute and deliver to the Owner an Assignment of Antitrust Claims in the same form as specified in Subparagraph 8.7.1 herein. 8.8 Public Entity Crime Warranty 8.8.1 As required by Section 287.133 (Public Entity Crime), Florida Statutes, the Contractor warrants that it is not on the convicted vendor list for a public entity crime committed within the past 36 months. The Contractor further warrants that it will neither utilize the services of, nor contract with, any supplier, subcontractor, or consultant in excess of $25,000 in connection with this Project for a period of 36 months from the date of their being placed on the convicted vendor list. ARTICLE 9. CERTIFICATE OF CONTRACT COMPLETION 9.1 The Contractor's application for final payment shall be accompanied by a completed and notarized "Certificate of Contract Completion". IN WITNESS WHEREOF, the parties have affixed their signatures, effective on the date first written above.

CONTINUED ON NEXT PAGE

Page 55: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 55 OF 69

FOR THE CONTRACTOR Contractor Name ATTEST:

BY: (NAME, TITLE AND CORPORATE SEAL) Name

Title

AS WITNESSED BY: DATE:

FOR THE OWNER University of South Florida Board of Trustees A Public Body Corporate

BY: Name

Title University of South Florida

AS WITNESSED BY: DATE: APPROVED AS TO FORM AND LEGALITY: APPROVED:

BY:

BY: Name General Counsel University of South Florida

Name Title University of South Florida

DATE: DATE:

Page 56: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 56 OF 69

USF PROJECT MANUAL EXHIBIT H-1 CERTIFICATE OF SUBSTANTIAL COMPLETION

CERTIFICATE OF SUBSTANTIAL COMPLETION Project: USF Project Name USF Project No.: USF 000 Date of Substantial Completion: Month 00, 0000 The Work, or portion of the Work identified on an attachment hereto, performed under the Contract, dated Month 00, 0000 between the University of South Florida Board of Trustees, a public body corporate, Owner, and Name of GC or CM, Contractor, for the construction of Project Name, was inspected and found to be substantially completed as of Month 00, 0000.

The Date of Substantial Completion of the Work or designated portion thereof is the date certified by the Architect/Engineer when construction is sufficiently complete, in accordance with the Contract Documents, so that the Owner can take beneficial occupancy or utilize the Work or designated portion thereof for the use for which it was intended.

A list of items to be completed or corrected is appended hereto. This list may not be exhaustive and the failure to include an item on it does not alter the responsibility of the Contractor to complete all the Work in accordance with the Contract Documents, including authorized changes thereto.

The Contractor shall complete or correct the Work on the list of items appended hereto within Contract Number of Days (00) calendar days from the Date of Substantial Completion.

Owner assumed or will assume full possession and responsibility for security of the facility above described on Month 00, 0000.

The responsibility of the Contractor to provide utilities shall cease on the date the Architect/Engineer determines the Work to have been substantially completed in accordance with the requirements of the Contract Documents. On the date so established by the Architect/Engineer as the date of Substantial Completion of the project, or beneficial occupancy, whichever comes first, the one-year warranty shall commence running. All insurance coverage shall continue in force as provided by the Contract Documents. FOR THE ARCHITECT/ENGINEER Firm Name

AUTHORIZED REPRESENTATIVE FOR THE CONTRACTOR Firm Name

AUTHORIZED REPRESENTATIVE FOR THE OWNER RECOMMENDED FOR APPROVAL: APPROVED:

Name

Name, University of South Florida

Page 57: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 57 OF 69

USF PROJECT MANUAL EXHIBIT H-2 CERTIFICATE OF CONTRACT COMPLETION – CONTRACTOR’S AFFIDAVIT

CERTIFICATE OF CONTRACT COMPLETION Project: USF Project Name USF Project No.: USF 000 Contract Date: Month 00, 0000 Contract Amount: $ 0,000,000.00 CONTRACTOR’S AFFIDAVIT I solemnly swear and affirm: That the Work under the above named Contract has been completed in accordance with the requirements of said Contract; that all costs incurred for equipment, materials, labor, and services against the Project have been paid; that no liens have been attached against the Project; that no suits are pending by reason of Work on the Project under the Contract; that all Workers’ Compensation claims are covered by Workers’ Compensation insurance as required by law; that all public liability claims are adequately covered by insurance, and that the Contractor shall save, protect, defend, indemnify, and hold the Owner harmless from and against any and all claims which arise as a direct or indirect result of any transaction, event, occurrence, or omission related to performance of the Work contemplated under said Contract.

FOR THE CONTRACTOR:

(SEAL TITLE: DATE:

STATE OF: COUNTY OF: Personally appeared before me this ______ day of ________________, _______, known (or made known) to me to be the Name, Title of Name of Firm, who, being by me duly sworn, subscribed to the forgoing affidavit in my presence.

BY: (NOTARY PUBLIC) (Type Name) MY COMMISSION EXPIRES:

Page 58: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 58 OF 69

USF PROJECT MANUAL EXHIBIT H-3 CERTIFICATE OF CONTRACT COMPLETION – CERTIFICATE OF ARCHITECT/ENGINEER

CERTIFICATE OF CONTRACT COMPLETION Project: USF Project Name USF Project No.: USF 000 Contract Date: Month 00, 0000 Contract Amount: $ 0,000,000.00 CERTIFICATE OF ARCHITECT/ENGINEER I CERTIFY: That, to the best of my knowledge and belief, the Work under the Owner-Contractor Agreement by and between the University of South Florida Board of Trustees, a public body corporate, Owner, and Contrcator Firm, dated Month 00, 0000, has been satisfactorily completed under the terms of the Contract; that the Work is recommended for occupancy by the Owner; and that the Contractor has submitted a sworn affidavit as evidence that the Contractor has paid all labor, materials and other charges against the Project in accordance with the terms of the Contract.

FOR THE ARCHITECT/ENGINEER: A/E FIRM NAME:

TITLE: DATE:

CERTIFICATE OF ACCEPTANCE BY UNIVERSITY OF SOUTH FLORIDA THIS IS TO CERTIFY: That, based upon the statements made in the above affidavit and certificate, the Work is hereby accepted as completed for occupancy, operation and maintenance. FOR THE OWNER RECOMMENDED FOR APPROVAL: APPROVED:

Name

Name, University of South Florida

Page 59: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 59 OF 69

USF PROJECT MANUAL EXHIBIT H-6

CONSTRUCTION CONTRACT CHANGE ORDER DATE: Click here to enter a date. CHANGE NO: 00 ARCHITECT/ENGINEER: A/E Firm Name TO (CONTRACTOR): GC/CM Firm Name

GC/CM Firm Address PROJECT: USF-000, Project Name A/E JOB NO:

YOUR PROPOSAL HAS BEEN ACCEPTED FOR MAKING FOLLOWING CHANGES:

PROPOSED CHANGE: (ATTACH ADDITIONAL SHEETS IF REQUIRED) CONSTRUCTION CONTRACT CO REQUEST NO. DESCRIPTION DECREASE INCREASE

COR-000 ($0,000.00) $0,000.00

NOTICE TO PROCEED DATE: 00/00/0000 SUBTOTAL SUBTOTAL ORIGINAL CONTRACT SUM: $0,000.00

($0,000.00) $0,000.00 CONTRACT TIME: DAYS: SC Date: PRESENT CONTRACT: 000 00/00/0000 PRESENT SUM: $0,000.00 THIS CHANGE: 000

ADD / (DEDUCT): $0,000.00

NEW CONTRACT TIME: 000 00/00/0000 NEW SUM: $0,000.00

THIS CHANGE ORDER IS AN AMENDMENT TO THE OWNER-CONTRACTOR AGREEMENT, AND ALL CONTRACT PROVISIONS SHALL APPLY UNLESS SPECIFICALLY EXEMPTED. THE AMOUNT AND TIME CHANGE DESIGNATED ARE THE MAXIMUM AGREED TO BY BOTH THE OWNER AND THE CONTRACTOR FOR THIS CHANGE. IN CONSIDERATION OF THE FOREGOING ADJUSTMENTS IN CONTRACT TIME AND CONTRACT SUM, THE CONTRACTOR HEREBY RELEASES OWNER FROM ALL CLAIMS, DEMANDS, OR CAUSES OF ACTION ARISING OUT OF THE TRANSACTIONS, EVENTS AND OCCURRENCES GIVING RISE TO THIS CHANGE ORDER. THIS WRITTEN CHANGE ORDER IS THE ENTIRE AGREEMENT BETWEEN OWNER AND CONTRACTOR WITH RESPECT TO THIS CHANGE ORDER. NO OTHER AGREEMENT OR MODIFICATION SHALL APPLY TO THIS CONTRACT AMENDMENT UNLESS EXPRESSLY PROVIDED HEREIN. AGREED: FOR THE ARCHITECT/ENGINEER: FOR THE CONTRACTOR (GC/CM):

ARCHITECT/ENGINEER DATE CONTRACTOR DATE

FOR THE OWNER:

USF FPC Fiscal DATE

USF President or Designee DATE

Page 60: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 60 OF 69

USF PROJECT MANUAL EXHIBIT H-8 CONSTRUCTION CHANGE DIRECTIVE

DATE: Click here to enter a date. CHANGE NO: 00 ARCHITECT/ENGINEER: A/E Firm Name TO (CONTRACTOR): GC/CM Firm Name

GC/CM Firm Address PROJECT: USF-000, Project Name A/E JOB NO:

YOUR PROPOSAL HAS BEEN ACCEPTED FOR MAKING FOLLOWING CHANGES:

PROPOSED CHANGE: (ATTACH ADDITIONAL SHEETS IF REQUIRED) CONSTRUCTION CONTRACT CO REQUEST NO. DESCRIPTION DECREASE INCREASE

COR-000 ($0,000.00) $0,000.00

NOTICE TO PROCEED DATE: 00/00/0000 SUBTOTAL SUBTOTAL ORIGINAL CONTRACT SUM: $0,000.00

($0,000.00) $0,000.00 CONTRACT TIME: DAYS: SC Date: PRESENT CONTRACT: 000 00/00/0000 PRESENT SUM: $0,000.00 THIS CHANGE: 000

ADD / (DEDUCT): $0,000.00

NEW CONTRACT TIME: 000 00/00/0000 NEW SUM: $0,000.00

WHEN SIGNED BY THE OWNER AND ARCHITECT/ENGINEER AND RECEIVED BY THE CONTRACTOR, THIS DOCUMENT BECOMES EFFECTIVE IMMEDIATELY AS A CONSTRUCTION CHANGE DIRECTIVE (CCD), AND THE CONTRACTOR SHALL PROCEED WITH THE CHANGE(S) DESCRIBED

AGREED: FOR THE ARCHITECT/ENGINEER:

ARCHITECT/ENGINEER DATE FOR THE OWNER:

USF FPC Fiscal DATE USF President or Designee DATE

SIGNATURE BY THE CONTRACTOR INDICATES THE CONTRACTOR’S AGREEMENT WITH THE PROPOSED ADJUSTMENTS IN CONTRACT SUM AND CONTRACT TIME SET FORTH IN THIS CONSTRUCTION CHANGE DIRECTIVE, AND THIS CONSTRUCTION CHANGE DIRECTIVE BECOMES A CHANGE ORDER TO THE OWNER-CONTRACTOR AGREEMENT. (ARCHITECT/ENGINEER REVIEW AND SIGNATURE IS NOT REQUIRED FOR CHANGE DIRECTIVES ISSUED IN SUPPORT OF THE OWNER DIRECT PURCHASE PROGRAM)

CONTRACTOR DATE

Page 61: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 61 OF 69

USF PROJECT MANUAL EXHIBIT H-10 CERTIFICATE OF PARTIAL PAYMENT

CONTRACTOR APPLICATION AND CERTIFICATION OF PARTIAL PAYMENT Application No.: 00 00 of 00 Pages Date: USF-000

Contractor: GC/CM Firm Name /Address NTP Date: 00/00/0000 A/E Job Number: 000 No. of Days Elapsed: 000 Calendar Days USF Project No: USF-000 Prev. Pay Period Ending: 00/00/0000

USF Project Name: USF Project Name This Pay Period Ending: 00/00/0000

SOV

Reference Schedule of Values No. of Days Progress Payment

Calculation* Contract Accounting

C ORIGINAL CONTRACT (Sum / Days) 000 $0,000.00 $0,000.00

Net Amount of CHANGE ORDERS Scope of Work 000 $0,000.00 $0,000.00

Net Amount of CHANGE ORDERS Owner Direct Purchase* $0,000.00

CURRENT CONTRACT (Sum / Days) 000 $0,000.00 $0,000.00

H

BALANCE TO FINISH (Sum / Days) 000 $0,000.00 D

COMPLETED TO DATE (Previous G) From Previous Cert. $0,000.00 $0,000.00

E

COMPLETED TO DATE From This Cert. $0,000.00 $0,000.00 F

MATERIALS STORED $0,000.00 $0,000.00

G

TOTAL COMPLETED & STORED 000 $0,000.00 $0,000.00

I LESS RETAINAGE Minimum 10% $0,000.00

LESS RETAINAGE Retainage Exceptions $0,000.00

TOTAL $0,000.00

LESS PREVIOUS PAYMENTS $0,000.00

AMOUNT THIS CERTIFICATE $0,000.00

00.0% 00.0% 00.0%

* % completed calculation for progress payments adjusted to reflect ODP Program intended for both Contractor Fee and the A/E Construction Administration Phase services fee. Required Documents for Pay Application (CM Initial): Current Contract Progress Report

Current Cost / Budget Summaries Submittal to Office of Vendor Diversity

CERTIFICATION BY CONTRACTOR: According to the best of my knowledge and belief, I certify that all items and amounts shown on the face of this Application are correct, that all Work has been performed and material supplied in full accordance with the terms and conditions of the Contract, and that all just and lawful bills against me and my Subcontractors for labor and equipment employed in the performance of this Contract have been paid in full in accordance with the terms and conditions. I further certify that all Subcontractors providing service for the Work are licensed according to the requirements of the State of Florida. Contractor Signature

State of Florida, County of Hillsborough

Subscribed and sworn before me this ___ day of ______, ______.

Notary Public:

Commissions Expire:

CERTIFICATION OF ARCHITECT/ENGINEER: I certify that I have checked and verified this Progress Payment Application; that to the best of my knowledge and belief the above application is a true statement of the value of the Work performed and the materials suitably stored on the site; and that the Work and materials included in this Certificate has been formed and materials supplied in accordance with the requirements of the Construction Documents and this Contract, and I approve for payment the Contractor's certified amount noted above.

A/E Firm Name

Architect/Engineer Firm Architect/Engineer Signature/Date

Reviewed and recommended for payment by Owner's representative: (Signature / Date) University Project Manager *verified receipt of required reports. University FPC Fiscal Approval (receipt No: ) Approved by the Owner: (Signature / Date) University Approval

Page 62: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 62 OF 69

CHANGE ORDER SUMMARY USF PROJECT MANUAL EXHIBIT H-11

CHANGE ORDER SUMMARY

0 Date:USF-000 Contractor:

CO No. No. of Days Additions Deductions Additions Deductions Additions DeductionsCO 1 0 -$ -$ -$ -$ -$ -$ -$ CD 2 0 -$ -$ -$ -$ -$ -$ -$

0 -$ -$ -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ -$ -$ -$

-$ -$ -$ -$ -$ -$ 0 -$

OwnerDirect

Net Amount of Change Orders

Change Orders Approved to Date Scope of WorkDescription

Pay App No.:

UF Project No:

* All change order / change directive numbers shall be used consecutively and only once. CM shall prepare a Change Directive for the ODP (Owner Direct Purchase) program submitted with the initial requisition. -$

Bid / Tax Savings CM Contingency

-$ -$ Sub-Total

Page 63: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 63 OF 69

USF PROJECT MANUAL EXHIBIT H-12 SCHEDULE OF CONTRACT VALUES

CONSTRUCTION

Payment Application No.: Date:USF Project Number: Contractor:

A B D E F G HMATERIALS

OWNERCHANGE

OWNER DIRECT PURCHASE

BID/TAXSAVINGS*

CMCONTINGENCY

Construction01.000 General Requirements $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 #DIV/0! $0.00 $0.00 $0.0002.000 Existing Condtions $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 #DIV/0! $0.00 $0.00 $0.0002.100 Sub-Contractor A $100,000.00 $0.00 $0.00 $0.00 $0.00 $100,000.00 $0.00 $0.00 $0.00 $0.00 0.00% $0.00 $0.00 $0.0002.200 Sub-Contractor B $100,000.00 $0.00 $0.00 ($60.00) $0.00 $100,000.00 $0.00 $0.00 $0.00 $0.00 0.00% $0.00 $0.00 $0.0003.000 Concrete $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 #DIV/0! $0.00 $0.00 $0.0003.100 Sub-Contractor C $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 #DIV/0! $0.00 $0.00 $0.0004.000 Masonry $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 #DIV/0! $0.00 $0.00 $0.0005.000 Metals $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 #DIV/0! $0.00 $0.00 $0.0006.000 Wood, Plastics & Composites $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 #DIV/0! $0.00 $0.00 $0.0007.000 Thermal & Moisture Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 #DIV/0! $0.00 $0.00 $0.0008.000 Openings $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 #DIV/0! $0.00 $0.00 $0.0009.000 Finishes $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 #DIV/0! $0.00 $0.00 $0.0010.000 Specialties $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 #DIV/0! $0.00 $0.00 $0.0011.000 Equipment $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 #DIV/0! $0.00 $0.00 $0.0012.000 Furnishings $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 #DIV/0! $0.00 $0.00 $0.0013.000 Special Construction $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 #DIV/0! $0.00 $0.00 $0.0014.000 Conveying System $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 #DIV/0! $0.00 $0.00 $0.0021.000 Fire Suppression $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 #DIV/0! $0.00 $0.00 $0.0022.000 Plumbing $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 #DIV/0! $1.00 $0.00 $1.0023.000 Heating, Ventilating and AC $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 #DIV/0! $2.00 $0.00 $2.0026.000 Electrical $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 #DIV/0! $3.00 $0.00 $3.0027.000 Communications $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 #DIV/0! $4.00 $0.00 $4.0031.000 Earthwork $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 #DIV/0! $5.00 $0.00 $5.0032.000 Exterior Improvements $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 #DIV/0! $6.00 $0.00 $6.0033.000 Utiltities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 #DIV/0! $7.00 $0.00 $7.0034.000 Transportation $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 #DIV/0! $8.00 $0.00 $8.0035.000 Waterway & Marine $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 #DIV/0! $9.00 $0.00 $9.0044.000 Pollutiuon Control Equipement $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 #DIV/0! $10.00 $0.00 $10.0048.000 Electrical Power Generation $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 #DIV/0! $11.00 $0.00 $11.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 #DIV/0! $0.00 $0.00 $0.00Sub Total - Construction $200,000.00 $0.00 $0.00 ($60.00) $0.00 $200,000.00 $0.00 $0.00 $0.00 $0.00 0.00% $66.00 $0.00 $66.00Contingency (for CM Agreements)Sub Total-CM Contingency $100,000.00 $0.00 $0.00 $100,000.00General ConditionsSub Total from Gen Cond Cost Worksheet $100,000.00 $0.00 $100,000.00 $0.00 $0.00 $0.00 0.00% $100,000.00 $0.00 $0.00CM Fees (for CM Agreements)Sub Total from CM Fee Worksheet $427,598.00 $0.00 $427,598.00 $0.00 $0.00 $0.00 0.00% $427,598.00 $0.00 $0.00Sub-Total (less CM P&OH) $827,598.00 $0.00 $827,598.00 $0.00 $0.00 $0.00 $0.00 0.00% $527,664.00 $0.00 $66.00

CM Profit & Overhead (for CM Agreements)P&OH $100,000.00 $0.00 100,000.00$ -$ -$ -$ 0.00% $100,000.00 $0.00 $0.00

TOTAL (GMP for CM Agreements) $927,598.00 $0.00 $0.00 $60.00 $0.00 $927,598.00 $0.00 $0.00 $0.00 $0.00 0.00% $627,664.00 $0.00 $66.00*The Tax Savings accrue under the GMP for Owner 's discretionary use.

SCHEDULE OF VALUESC

ORIGINAL CONTRACT

CURRENT CONTRACT

CHANGE ORDERS % COMPLETE(G / Current)

FROM PREVIOUS

CERT.THIS PERIOD

IWORK COMPLETED

PRESENTLY STORED

(Not in D or E)

RETAINAGE

Minimum 10%

0USF-000

ExceptionsDESCRIPTION OF WORK

Trade Contractor Name & Scope of Work

BALANCE TO FINISH

(Current - G)

ITEM NO.(CM's Cost

Codes)

TOTAL COMPLETED &

STORED (D + E + F)

Page 64: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 64 OF 69

USF PROJECT MANUAL EXHIBIT H-12A SCHEDULE OF CONTRACT VALUES

CM FEE REIMBURSABLE (FOR CM PROJECTS)

Payment Application No:

USF Project No:

A B

TOTAL UNITS LABOR MATERIAL TO DATE PREVIOUS THIS PERIOD BALANCE Project PersonnelHome/branch office employees Project Director/Executive 50 Hours 58.00$ 2,900.00$ -$ 2,900.00$ 0 -$ -$ -$ 2,900.00$ Project Manager 2000 Hours 38.00$ 76,000.00$ -$ 76,000.00$ 0 -$ -$ -$ 76,000.00$ Accountant 250 Hours 20.00$ 5,000.00$ -$ 5,000.00$ 0 -$ -$ -$ 5,000.00$ Accounting Clerk 500 Hours 10.00$ 5,000.00$ -$ 5,000.00$ 0 -$ -$ -$ 5,000.00$ Safety Director 100 Hours 20.00$ 2,000.00$ -$ 2,000.00$ 0 -$ -$ -$ 2,000.00$ Secretarial 50 Hours 10.00$ 500.00$ -$ 500.00$ 0 -$ -$ -$ 500.00$ Field employees Project Superintendent 2000 Hours 24.00$ 48,000.00$ -$ 48,000.00$ 0 -$ -$ -$ 48,000.00$ Project Assistant Superintendent 2000 Hours 19.00$ 38,000.00$ -$ 38,000.00$ 0 -$ -$ -$ 38,000.00$ MEP Superintendent 800 Hours 36.00$ 28,800.00$ -$ 28,800.00$ 0 -$ -$ -$ 28,800.00$ Project Engineer 2000 Hours 20.00$ 40,000.00$ -$ 40,000.00$ 0 -$ -$ -$ 40,000.00$ Project Secretarial 2000 Hours 12.00$ 24,000.00$ -$ 24,000.00$ 0 -$ -$ -$ 24,000.00$ Labor Burden for Project Staff 49% 132,398.00$ -$ 132,398.00$ 0 -$ -$ -$ 132,398.00$ Sub-Total Project Personnel 402,598.00$ -$ 402,598.00$ -$ -$ -$ 402,598.00$ Project Site CostGeneral operating expenses home office expenses 12 Months 500.00$ 6,000.00$ -$ 6,000.00$ 0 -$ -$ -$ 6,000.00$ Capital expenses -$ -$ -$ -$ -$ -$ -$ field office expenses 0 -$ -$ -$ -$ -$ -$ -$ -$ home office expenses 0 -$ -$ -$ -$ -$ -$ -$ -$ Travel / per diem costs -$ -$ -$ -$ -$ -$ -$ field office personnel 0 -$ -$ -$ -$ -$ -$ -$ -$ home office personnel 0 -$ -$ -$ -$ -$ -$ -$ -$ Cost estimating service 12 Months 800.00$ 9,600.00$ -$ 9,600.00$ -$ -$ -$ 9,600.00$ Minor expenses -$ -$ -$ -$ -$ -$ -$ long distance telephone -$ -$ -$ -$ -$ -$ -$ site telephone service -$ -$ -$ -$ -$ -$ -$ cellular phone service -$ -$ -$ -$ -$ -$ -$ postage -$ -$ -$ -$ -$ -$ -$ express delivery -$ -$ -$ -$ -$ -$ -$ office supplies -$ -$ -$ -$ -$ -$ -$ Cost of equipment -$ -$ -$ -$ -$ -$ -$ typewriters / computers 1 Allowance 1,000.00$ 1,000.00$ -$ 1,000.00$ -$ -$ -$ 1,000.00$ cameras / video recorders -$ -$ -$ -$ -$ -$ -$ radios / pagers / phones -$ -$ -$ -$ -$ -$ -$ copiers / printers / fax -$ -$ -$ -$ -$ -$ -$ construction trailers -$ -$ -$ -$ -$ -$ -$ construction vehicles 12 Months 500.00$ 6,000.00$ -$ 6,000.00$ -$ -$ -$ 6,000.00$ construction vehicle fuel/repair/maint. 12 Months 200.00$ 2,400.00$ -$ 2,400.00$ -$ -$ -$ 2,400.00$ construction office furniture -$ -$ -$ -$ -$ -$ -$ Sub-Total Project Site Cost 25,000.00$ -$ 25,000.00$ -$ -$ -$ 25,000.00$ TOTAL- CM FEE REIMBURSABLES 427,598.00$ -$ 427,598.00$ -$ -$ -$ 427,598.00$

Note: Adjustments to the Schedule of Values under CM Fees Reimbursable allowances are permitted only when documented through the Change Order process.

ITEM NO. DESCRIPTION OF WORK QUANTITY UNIT COST COSTSCURRENT CONTRACT

QUANTITY TO DATE

CHANGEORDERS

ORIGINAL CONTRACT

C

0

D

Date:

Contractor:USF-000

Page 65: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 65 OF 69

USF PROJECT MANUAL EXHIBIT H-12B SCHEDULE OF CONTRACT VALUES

GENERAL CONDITIONS

Payment Application No.:USF Project No.:

A B

TOTAL UNITS LABOR MATERIAL TO DATE PREVIOUS THIS PERIOD BALANCE Credits to OwnerDiscounts/Credits to Owner Trade discount, rebates, refunds -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ Revenue from sale of surplus -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ Revenue from recycled material -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ Sub-Total Credits to Owner* -$ -$ -$ -$ -$ -$ -$ Project ReimbursableInsurance and bonds builder's risk insurance 1 Lump Sum -$ 100,000.00$ 100,000.00$ -$ 100,000.00$ 0 -$ -$ -$ 100,000.00$ payment & performance bonds -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ Sales, use and gross receipt taxes -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ Building & permit fee building & operating permit fees -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ inspection & filing fee -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ sewer & water fees -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ royalties and patent costs -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ Trash Removal/Dump Fees trash removal / dump fee -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ daily clean-up -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ Site emergency costs Safety/ First Aid -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ Legal costs -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ Temporary site utilities temporary electric power & lighting -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ temporary telephone & telecomm -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ temporary water -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ temporary steam & hot water -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ temporary chilled water -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ temporary gas service -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ temporary weather protection -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ Temporary safety costs barricades & safety equipment -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ temporary roads & parking -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ dust control -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ pest & varmint control -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ temporary hoists, scaffolds, ladders -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ temporary work protection -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ temporary project signs -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ temporary fire protection -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ Site security & watchmen -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ Surveying & Layout surveys -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ layout -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ Construction Dwgs./Specs shop drawing preparation -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ coordination plan / as-built records -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ photographs & digital image record -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ Construction Testing -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ Reproduction of documents -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ Other costs -$ self-performed work -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ Hand tools -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ Rented equipment -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ Mobilization / demobilization costs tool shed setup -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ field office setup -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ temporary fences -$ -$ -$ -$ -$ 0 -$ -$ -$ -$ Sub-Total Reimbursable 100,000.00$ -$ 100,000.00$ -$ -$ -$ 100,000.00$ TOTAL- GENERAL CONDITIONS COSTS 100,000.00$ -$ 100,000.00$ -$ -$ -$ 100,000.00$

Note: Adjustments to the Schedule of Values under General Conditions allowances are permitted only when documented through the Change Order process.

CHANGE ORDERS

ORIGINAL CONTRACT

DCOSTS

USF-000

0

CURRENT CONTRACT

QUANTITY TO DATE

Date:Contractor:

ITEM NO. DESCRIPTION OF WORK QUANTITY UNIT COSTC

Page 66: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 66 OF 69

USF PROJECT MANUAL EXHIBIT H-14 MINORITY BUSINESS ENTERPRISE PAYMENT STATUS REPORT

Date: January 1, 2000

Trade Services or Supplies /Materials Provided by CMBE*

OriginalSubcontract

Amount

Total amount paidto CMBE Firm Unpaid Balance

$ 0.00 $ 0.00 $ 0.00$ 0.00 $ 0.00 $ 0.00$ 0.00 $ 0.00 $ 0.00$ 0.00 $ 0.00 $ 0.00$ 0.00 $ 0.00 $ 0.00$ 0.00 $ 0.00 $ 0.00$ 0.00 $ 0.00 $ 0.00$ 0.00 $ 0.00 $ 0.00$ 0.00 $ 0.00 $ 0.00$ 0.00 $ 0.00 $ 0.00$ 0.00 $ 0.00 $ 0.00$ 0.00 $ 0.00 $ 0.00$ 0.00 $ 0.00 $ 0.00$ 0.00 $ 0.00 $ 0.00$ 0.00 $ 0.00 $ 0.00$ 0.00 $ 0.00 $ 0.00$ 0.00 $ 0.00 $ 0.00

*CMBE - Certified Minority Business Enterprises Totals $ 0.00 $ 0.00 $ 0.00

SUBMIT to: Supplier Diversity Program 4202 E Fowler Aveneue / AOC 200 Phone: [email protected] Univeristy of South Florida Tampa, FL 33620-9000 Website: www.usf.edu/supplierdiversity

SUPPLEMENT TO CONTRACTOR’S PARTIAL PAYMENT REQUEST

Construction Manager:USF Project No. / Name:

SUPPLEMENT TO CONTRACTOR’S FINAL PAYMENT REQUEST 0Pay Application No.:

Name of Certified Small, Minority and Women-owned Firms (Certified by the State of Florida’s Office of Supplier Diversity)

USF-000, Project Name

Page 67: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 67 OF 69

USF PROJECT MANUAL EXHIBIT I

SPECIAL CONDITIONS SPECIAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION

(Note to Architect/Engineer – This section is established for the inclusion of non-typical, non-technical items which, in the opinion of the Architect/Engineer, will require written clarification or instruction in connection with a specific project. If one of more of the following items are totally, partially or not at all applicable to a particular project, it/they may be included, modified or deleted by the Architect/Engineer.) TABLE OF ARTICLES

Article 1 .......... Minority Business Enterprise Report Article 2 .......... Special Requirements for Threshold Buildings Article 3 .......... USF Building Code Administration Program Article 4 .......... Special Pre-qualification Requirements Article 5 .......... Construction Facilities Article 6 .......... Telephone Article 7 .......... Water Article 8 .......... Electricity Article 9 .......... Project Sign Article 10 ........ Pre-construction Conference Article 11 ........ Building Permits Article 12 ........ Project Drawings – Copies Furnished to Contractors Article 13 ........ Building Plaque

ARTICLE 1 MINORITY BUSINESS ENTERPRISE REPORT 1.1 The University of South Florida is an equal opportunity institution, and, as such, strongly encourages the lawful use of certified Minority and Women-owned Business Enterprises (“MBEs”) in the provision of design and construction-related services by providing a fair and equal opportunity to compete for, or for participation in, design and/or construction-related services. 1.2 MBE participation information for this project shall be provided by the Contractor in response to a request from the University’s Supplier Diversity Program Office. The amount of MBE participation is required to be reported by USF to verify payments made to certified and non-certified Minority Business Enterprises each fiscal year. 1.3 The USF Supplier Diversity Program (www.usf.edu/supplierdiversity), USF Purchasing and Financial Services, Telephone: (813) 974-2481, Email: [email protected], may be contacted to obtain information on the Small, Minority and Women-owned Business Enterprises. ARTICLE 2 SPECIAL REQUIREMENTS FOR THRESHOLD BUILDINGS 2.1 STRUCTURAL INSPECTION PLAN Chapter 553 (Building Construction Standards), Florida Statutes, defines a “Threshold Building” as “any building which is greater than three stories or 50 feet in height, or which has an assembly occupancy classification that exceeds 5,000 square feet in area and an occupant content greater than 500 persons.” For such buildings the Contractor shall request from the Owner a structural inspection plan prepared by the Architect/Engineer prior to proceeding with the requirements of a Notice to Proceed, and issuance of a building permit. Usually this structural inspection plan will accompany the Notice to Proceed from the Owner. The structural inspection plan shall provide specific inspection procedures and schedules to assure compliance with the permitted plans. 2.2 SHORING AND RESHORING AND INSPECTION For a threshold building the Contractor shall provide or shall require his Subcontractor to provide, plans prepared by an engineer licensed to practice in Florida and retained by the Contractor or his Subcontractor for the preparation of plans for the shoring and the reshoring of the Work. These plans shall be filed with the Owner prior to the shoring or reshoring of the Work. The Section 553.79(8) (Permits) Florida Statutes identifies the Contractor’s responsibilities as: “The named contractor to whom the building permit is issued shall have the responsibility for supervision, direction, management, and control of the construction activities on the project for which the building permit was issued.” The

Page 68: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 68 OF 69

Contractor shall notify the special inspector when the shoring is ready for inspection for conformance with the shoring and reshoring plans submitted to the Owner; however, such inspection shall not relieve the Contractor from responsibilities under Section 553.79(8), Florida Statutes. ARTICLE 3 USF BUILDING CODE ADMINISTRATION PROGRAM 3.1 USF BUILDING CODE ADMINISTRATION PROGRAM 3.1.1 The Contractor shall comply with, and adhere to, the requirements of the USF Building Code Administration Program. The following is the USF Building Code Administration Program Policies and Procedures Manual. The cost of the building permit fee and the State Fire Marshal permit fee shall be paid by the University. ARTICLE 4 SPEICAL PREQUALIFICATION REQUIREMENTS The Contractor and his field staff shall have experience on previous projects similar in scope, complexity, and construction value. Evidence of experience shall be provided upon request of the Owner, and/or the Architect/Engineer. ARTICLE 5 CONSTRUCTION FACILITIES 5.1 FIELD OFFICES 5.1.1 Contractor’s Field Office: Trailers may be used for field offices. The Contractor shall have a telephone installed in the Contractor’s office and shall permit business use of it to Subcontractors and other trades who shall reimburse the Contractor for such use if so directed by the Contractor. Trades or Subcontractors wishing to install their own telephone service may do so at their own expense. The Architect/Engineer shall be informed of the job telephone numbers and a directory of all trades shall be installed adjacent to the phone in the Contractor’s field office.

The Contractor’s field office shall provide a meeting room space suitable to conduct the weekly progress meetings, including, but not limited to, a conference table, seating for a minimum of twelve (12) people, heated and air conditioned, and restroom facilities. 5.2 STORAGE AND WORK AREAS At the start of the operations the Contractor shall make arrangements with the Architect/Engineer’s Project Representative and the Owner’s authorized representative for the assignment of storage and work areas. During construction the Contractor shall maintain the areas in a neat condition. 5.3 SANITARY PROVISIONS The Contractor shall provide and maintain in a neat and sanitary condition such accommodations for the use of the Contractor’s and Architect/Engineer’s employees as may be necessary to comply with regulations of the State Board of Health, and the University requirements. ARTICLE 6 TELEPHONE 6.1 The Contractor shall be responsible for the installation of a telephone in the Contractor’s field office, and it shall remain until the full completion of the Work. Charges for long distance calls shall be paid for by the persons making the calls. All other charges in connection with the telephone shall be paid for by the Contractor. ARTICLE 7 WATER 7.1 Water necessary to carry out the Work and for testing its plumbing and mechanical systems shall be provided by the Owner. The Contractor shall make all connections, install a meter, take out and pay for all permits necessary, do all piping and clear away all evidence of same after the Work is completed. The Contractor shall assure that the water usage is utilized in a responsible manner with water conservation as a primary goal. ARTICLE 8 ELECTRICITY 8.1 All electricity for light and power necessary to carry out the Work and to test its electrical and mechanical systems shall be provided by the Owner. The Contractor shall make all connections, install the meter, obtain all necessary permits, and provide all work to provide the required electrical service for the construction of the project. The Contractor shall assure that use of electricity is in a responsible manner, with energy conservation as a primary goal.

Page 69: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

UNIVERSITY OF SOUTH FLORIDA USF CAMPUS RECREATION RENOVATIONS FACILITIES PLANNING AND CONSTRUCTION SWIMMING POOL AND POOL EQUIPMENT RENOVATIONS

USF PROJECT MANUAL – PF 155214600301 PAGE 69 OF 69

8.2 TEMPORARY WIRING Wiring shall meet all safety requirements of the National Electric Code and local requirements. In addition, all wire shall be so sized that it is not overloaded according to the National Electric Code and O.S.H.A. Standards, and any wire used shall be fused to adequately protect that wire according to the most restrictive applicable Code. The Contractor shall have an adequate number of outlets and each outlet shall be properly and clearly labeled with the maximum voltage and fuse protection. Where temporary lighting is used, outlets shall consist of weatherproof sockets insulated and provided with a locking type wire guard. All devices shall be provided with ground-fault protection. ARTICLE 9 PROJECT SIGN 9.1 A sign shall be erected at the site by the Contractor and shall be ¾” x 4’-0” x 8’-0” exterior grade plywood, mounted on 4”’ x 4” wood posts (p.t.), located in a prominent location approved by the Architect/Engineer and Owner. The sign shall be painted in a professional manner and conform to the size, colors and design as illustrated in Section H of the Project Manual. ARTICLE 10 PRE-CONSTRUCTION CONFERENCE 10.1 Before beginning Work at the site the Contractor shall attend a pre-construction conference and be accompanied by the field staff employed for the Work. This conference will be scheduled by the Owner’s representative who will arrange for the Architect/Engineer, and other interested parties to be present. At this time all parties concerned will discuss the Work and prepare a program of procedure in keeping with requirements of the Contract Documents. The field staff shall thereafter make every effort to expeditiously coordinate all segments of the Work, including the required reporting procedure, to obtain the end result within the full purpose and intent of the plans and specifications for the Work. ARTICLE 11 BUILDING PERMITS 11.1 The Contractor shall comply with, and adhere to, the requirements of the USF Building Code Administration Program in obtaining Building Permits for the project. The cost of the building permit and the State Fire Marshal permit fee shall be paid by the University. The forms provided included as a part of the USF Building Code Administration Program requirements must be utilized. ARTICLE 12 PROJECT DRAWINGS – COPIES FURNISHED TO CONTRACTORS 12.1 The Architect/Engineer will provide the Contractor 1 set of reproducible drawings and 1 set of specifications upon Contract award. If additional sets are required by the Contractor, they shall be provided by the Contractor and included within the Cost of the Project. ARTICLE 13 BUILDING PLAQUE 13.1 If a building plaque is to be provided, the Architect/Engineer shall include the specification requirements here. The area of the plaque shall not exceed 432 square inches. It shall contain only lettered information, and a border (if specified by the Architect/Engineer).

13.2 Information to be provided on the plaque will be limited to the following: .1 Chairperson of the Board of Trustees, .2 Vice Chairperson of the Board of Trustees, .3 Members of the Board of Trustees, .4 University President, .5 Contractor, .6 Architect/Engineer, and .7 Date (Year of Completion).

All individuals listed shall be those who were in their positions on the date of construction contract award.

Page 70: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

SUMMARY 011000 - 1

SECTION 01 10 00 - SUMMARY

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Project information. 2. Work covered by Contract Documents. 3. Phased construction. 4. Work under separate contracts. 5. Access to site. 6. Coordination with occupants. 7. Work restrictions. 8. Specification and drawing conventions. 9. Miscellaneous provisions.

B. Related Requirements:

1. Division 01 Section "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.

1.2 PROJECT INFORMATION A. Project Identification: Campus Recreation Renovations

Swimming Pool and Pool Equipment Renovations USF Project Number PF155214600301 1. Project Location: 12902 USF Magnolia Drive Tampa, FL 33620 2. Owner: University of South Florida

4202 Fowler Avenue, FPC110 Tampa, FL 33620

3. Owner's Representative: Facilities Planning & Construction Address (Same as Owner listed above)

B. Design-Builder: .

1. Design-Builder shall be engaged for this Project to provide engineering services and to serve as Project's constructor. In Divisions 01 through 33 Sections, the terms "Design-Builder" and "Contractor" are synonymous.

Page 71: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

SUMMARY 011000 - 2

1.3 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of Project to renew the life of an existing 25-yard x 20-meter indoor swimming pool (293,000 gallons with depths from 3’-6” to 12’-0”) and replace the filtration system is defined by the Contract Documents and shall include, but not be limited to the following Scope Of Work:

1. Remove D.E. Filtration and Refurbish Collector Tank: a. Remove existing Vacuum D. E. Filtration system and associated equipment and dispose

of same, b. Clean, Re-seal and re-coat existing Collector Tank with same material as is to be applied

on pool interior, 2. Repair existing broken Main Drain piping:

a. Drain existing water from the pool INTO STORM DRAINAGE SYSTEM (NOT SANITARY SEWER SYSTEM). Neutralize pool chemicals prior to discharge into the environment,

b. Perform dewatering as required to ensure no damage to pool occurs as it is empty, c. Remove and dispose of existing diving board and framing; recycle metal where possible, d. Cut and remove existing Pool Deck Slab and excavate, with shoring and dewatering as

required to access Main Drain piping repair, e. Remove existing Diving Board, associated structure and elevated concrete pad. f. Repair existing broken 8” Main Drain piping (reportedly located approximately 10’ from

the north wall of the pool filter room) g. Replace and compact soil and re-install concrete at pool deck,

3. Install New Filtration System: a. Install new High-Rate Sand Filtration System, including all filtration tanks, valves, pip-

ing, piping supports and hangers, backwash controls and drains, connections, housekeep-ing pads, sight glasses and guages ,

b. Install (2) new high-efficiency 10 HP Pumps and Variable Frequency Drives, c. Install new butterfly valves at existing gutter lines, main drain lines, return lines and

flanged union(s), d. Integrate new Pumps, VFD’s and control valves with existing DCM5 Automated Control

System, e. Connect piping for new Pumps and Filtration system with existing Heat Exchanger and

Control Valves, f. Provide and Install new Ozone Treatment System, g. Provide Add Alternate Pricing to provide and install new Salt Saline Chlorine Genera-

tion System, with all necessary additional control systems, valves, piping and integration with other control systems,

h. Install new Drain Covers to meet Code, i. Install new Return Outlets on pool floor,

4. Refinish Existing Pool and upgrade Markings to meet Codes: a. Remove existing interior pool surface containing fiberglass, b. Coordinate with Owner-Contracted Asbestos Abatement Contractor to remove Asbestos-

Containing Sealant around existing underwater observation window, c. Repair existing Perimeter Beam,

Page 72: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

SUMMARY 011000 - 3

d. Repair existing Gutter Edge to provide a clean, true, even edge, within ¼” variation around pool perimeter,

e. Recoat pool interior surface with Hydrazzo marble-cement plaster system, Pebble-Tec quartz-cement plaster system or equivalent,

f. Recoat interior of Gutters with same material as pool interior, g. Re-seal existing underwater window perimeter sealant, h. Replace existing, non-functioning Underwater Lighting fixtures with LED fixtures, i. Clean and re-coat Lane Lines and Targets (or remove existing and install new tile flush

with new interior finish), j. Remove existing Depth Markers and install new, Code-compliant Depth Markers, k. Remove existing “No Diving” Markers and install new, Code-compliant “No Diving”

Markers where required by Codes, l. Install new Upper Tile, Cap Tile and Lower Tile around Gutter to meet Codes, m. Ensure all lane line anchors and warning flag anchors are sealed and solidly anchored in

place, n. Ensure all ladders are structurally stable and mountings are secure; remove any surface

rust and polish stainless steel, 5. Provide Engineering Design and Drawings as required to obtain a Building Permit and necessary

Health Department approvals, a. Include costs of obtaining a Building Permit from the USF Building Code Administration

and from the Hillsborough County Health Department, b. All Design and Work to comply with Florida Building Codes and Florida Administrative

Code 64-E9, 6. Cooperate and coordinate with other Owner-Directed Contractors performing additional renova-

tions in the Pool Equipment Rooms and Natatorium, 7. Provide Comprehensive Project Close-out, System Start-up and Stabilization,

a. Provide Owner Training for new systems, b. Provide As-Built Documentation and Record Drawings to meet the USF Facilities Plan-

ning & Construction CAD Guidelines, c. Provide Contractor’s Guarantee for Labor and materials for a minimum of 1-year after

Completion, d. Provide Manufacturer’s Warranties on all applicable products and installation,

8. Provide Bid Guarantee and Performance and Payment Bond, 9. Commence Project on March 7, 2014, 10. Attain Substantial Completion on or before May 1, 2014.

B. Type of Contract.

1. Project will be constructed under a single prime contract.

2. The Owner-Contractor Agreement is included as an Exhibit to the Project Manual.

Page 73: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

SUMMARY 011000 - 4

1.4 WORK UNDER SEPARATE CONTRACTS

A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract or other contracts. Coordinate the Work of this Contract with work performed under separate contracts.

B. Preceding Work: Owner has awarded a separate contract for the renovation of the Locker Rooms serving the Swimming Pool. Those operations are scheduled to be substantially complete concurrently with this Contract.

C. Concurrent Work: Owner will award separate contract(s) for the following construction operations at Project site. Those operations will be conducted simultaneously with work under this Contract.

1. Tile and Pool Deck a. The pool deck surrounding the pool shall be resurfaced with floor tile, including

drain modifications.

2. Painting a. The interior walls and ceiling of the Natatorium shall be cleaned and painted. b. The interior walls and ceilings of the Pool Equipment Room shall be cleaned and

painted. 1) Exposed reinforcing and deteriorated concrete at the slab above the Pool

Equipment Room shall be repaired. 2) Deteriorated wall surfaces shall be painted.

c. The floor of the Pool Equipment Room shall be cleaned and coated.

3. Lighting and Electrical Repairs a. The lighting in the Natatorium shall be replaced. b. Miscellaneous repairs to electrical systems within the Natatorium shall be

undertaken. c. All Electrical repairs or replacement of electrical systems in the Pool Equipment

Room shall be included within the Swimming Pool and Pool Equipment Renovation Project.

4. Ventilation a. An Exhaust Fan and associated Electrical and Controls shall be installed in the

Natatorium.

1.5 ACCESS TO SITE

A. General: Contractor shall have full use of Project site for construction operations during construction period. Contractor's use of Project site is limited only by Owner's right to perform work or to retain other contractors on portions of Project. 1. The use of the University’s premises by Contractor shall be limited to the Area identified

within the “Project Limits” as established for this Project, in additional the temporary facilities and reasonable access thereto. Space for staging work and related operations of Contracto rand Contractor’s employees will be provided, subject ot availablilty. Coordinate use of premises with the Owner. Develop a plan for staging of work, locations of storage areas, layout areas and temporary facilities with the Owner, in

Page 74: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

SUMMARY 011000 - 5

conjunction with other Contractors working on site simultaneously. Submit plan for approval within seven (7) calendar days of Notice To Proceed.

2. Contractor will have limited use of the premises during the course of work during designated times (7:00am – 8:00pm, Monday through Friday) and must coordinate use of surrounding areas with the FP&C Owner’s Representative. Use of other nearby site or floor areas or buildings for staging or other purposes must be pre-approved by the FP&C Representative and other University Representatives. All week-end and after hours Work shall be approved by the Owner’s Representative a minimum of 72-hours in advance.

3. The Contractor is advised that the Project site is an active University and within a very active Student Recreation Center, and that all necessary provisions shall be taken to assure the safety of the students, University employees, visitors and other contractors during both day and night, when the Work Area is occupied and when it is not occupied.

4. Provide and erect before any Work begins, and maintain during the progress of the work, all necessary protective barriers, warning devices and lights. The extent of this Work and the details of construction shall be in accordance with the requirements of all Federal, state, University and local ordinances, codes, and shall be subject to the approval of Authorities Having Jurisdiction over the project site.

5. Exercise the utmost care to protect from damage existing landscaping, equipment, furniture, building finishes, etc.

6. Any portion of the existing building or existing utility services not included as a part of the work of this Contract, or any portion of the work damaged because of failure to provide the protection required shall be removed and replaced with new materials and construction at the Contractor’s expense.

7. ALL areas within the Project are designated as NO SMOKING areas. The Contractor shall not allow any workers to smoke within University buildings or on campus, except in designated Smoking Areas.

8. The Contractor shall at all times guard against damage or loss to the property of the University of other Contractors or Vendors working at the University, and shall be held responsible for replacing or repairing any such loss or damage. The University may withhold payment or make such deductions as deemed necessary to insure reimbursement or replacement for loss or damage property through negligence of the Contractor or its agents.

9. Retain "Use of Site" Paragraph below if Project site is accessible to other parties or if parts of a building being renovated are occupied during construction. Revise to suit Project. See Evaluations for model text.

10. "Driveways, Walkways and Entrances" Subparagraph below is an example of a special requirement appropriate to many projects. Revise to suit Project or delete.

11. Driveways, Walkways and Entrances: Keep driveways, loading areas, and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. a. Schedule deliveries to minimize use of driveways and entrances by construction

operations. b. Schedule deliveries to minimize space and time requirements for storage of

materials and equipment on-site.

B. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weather tight condition throughout construction period. Repair damage caused by construction operations.

Page 75: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

SUMMARY 011000 - 6

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:

1. Notify Owner not less than 72 hours in advance of proposed utility interruptions.

D. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with Owner.

1. Notify Owner not less than 72 hours in advance of proposed disruptive operations.

1.6 SPECIFICATION AND DRAWING CONVENTIONS

A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:

1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.

B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.

C. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:

1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.

2. Abbreviations: Materials and products are identified by abbreviations published as part of the U.S. National CAD Standard and scheduled on Drawings.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

- END OF SECTION 011000 -

Page 76: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

AutoCAD Standards 01 78 39 - 2

Table of Contents PART 1: WORKING WITH THE CAD STANDARDS ............................................................................... 5 SECTION 1: THE PURPOSE OF USING USF CAD STANDARDS ............................................................................ 5

1.1 Why the University has Data Standards ............................................................................................................ 5

1.2 Scope of the CAD Data Standards .................................................................................................................... 6

1.3 Who Must Use the Standards? .......................................................................................................................... 6

SECTION 2: CAD ENVIRONMENT ...................................................................................................................... 6 2.1 Basic CAD Software .......................................................................................................................................... 6

2.2 CAD Application Software .................................................................................................................................. 6

SECTION 3: REQUESTING CAD DATA FROM THE UNIVERSITY ............................................................................. 7 3.1 How to Request Data ......................................................................................................................................... 7

SECTION 4: DELIVERABLES REQUIRED BY THE UNIVERSITY ............................................................................... 7 4.1 Delivery of a Hardcopy Set ................................................................................................................................ 7

4.2 Delivery of CAD Files (Vector Files)................................................................................................................... 7

4.3 Delivery of PDF Files (Raster Files) ................................................................................................................... 8

4.4 Completed Electronic Submission Checklist ...................................................................................................... 8

4.5 Digital Media Labeling ........................................................................................................................................ 8

4.6 Validation of Delivered Materials ....................................................................................................................... 8

SECTION 5: COMMUNICATION ABOUT THE CAD STANDARDS .............................................................................. 9 5.1 Suggestions for the Standards ........................................................................................................................... 9

PART 2: TECHNICAL REQUIREMENTS FOR CAD DATA .................................................................... 10 SECTION 6: MASTER CAMPUS DRAWINGS .......................................................................................................10

6.1 Files Translation and Submission .................................................................................................................... 10

6.2 New Construction and Renovation Documents ................................................................................................ 11

SECTION 7: TYPES OF CAD FILES ..................................................................................................................12 7.1 Model Files ...................................................................................................................................................... 12

7.2 Sheet Files ....................................................................................................................................................... 12

SECTION 8: DRAWING FILE NAMES & SHEET NUMERATION ..............................................................................13 8.1 Drawing File Names ......................................................................................................................................... 13

8.2 Sheet Numeration Method ............................................................................................................................... 13

SECTION 9: DRAWING :LAYER DESCRIPTION ...................................................................................................16 9.1 Layer Standards .............................................................................................................................................. 16

9.2 Layer Formats .................................................................................................................................................. 16

SECTION 10: DRAWING SETUP .......................................................................................................................20 10.1 Drawing Units ................................................................................................................................................ 20

10.2 Accuracy ........................................................................................................................................................ 20

10.3 Scale .............................................................................................................................................................. 20

10.4 Origins and Registration of CAD Data Files ................................................................................................... 21

10.5 Entities and Graphic Representation ............................................................................................................. 21

Page 77: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

AutoCAD Standards 01 78 39 - 3

10.6 Saved State of CAD Model Files ................................................................................................................... 21

10.7 Plotting ........................................................................................................................................................... 21

10.8 Title Blocks / Borders ..................................................................................................................................... 21

10.9 Room Numbering Standards ......................................................................................................................... 22

10.10 Room Numbering Standards ........................................................................................................................ 23

SECTION 11: SYMBOLOGY AND COMPOSITION .................................................................................................26 11.1 Line Types ..................................................................................................................................................... 26

11.2 Line Type Scale ............................................................................................................................................. 26

11.3 Line Weight and Color ................................................................................................................................... 26

11.4 Text and Fonts ............................................................................................................................................... 26

11.5 Annotation ...................................................................................................................................................... 27

11.6 Dimensions .................................................................................................................................................... 27

11.7 XREF (External Reference) Files ................................................................................................................... 27

11.8 Blocks ............................................................................................................................................................ 27

11.9 Hatching ......................................................................................................................................................... 27

EXHIBIT A: MASTER CAMPUS DRAWING ........................................................................................ 28 EXHIBIT B: ELECTRONIC FILE SUBMISSION CHECKLIST .................................................................. 33

Page 78: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

AutoCAD Standards 01 78 39 - 4

PART 1: WORKING WITH THE CAD STANDARDS Part 1 of this manual describes how to conform to these standards: the purpose and scope of the standards, receipt and delivery of data, and communication. SECTION 1: THE PURPOSE OF USING USF CAD STANDARDS

Computer-Aided Design (CAD) is an accepted tool for producing the documentation required for construction and management of facilities; it also provides for a common medium of information exchange. In fact, the true power and potential of CAD is the ability to re-use and share the information contained within the CAD document. The key to realizing this potential is common organizing principles and standards for the production and dissemination of CAD information. The standard organization of files, layers and entities, as well as standardized software applications is essential for effective work and communication. Standards are necessary to ensure that:

CAD drawings and data created in one phase (e.g., design) are readily usable in subsequent phases (e.g., facility management, space management).

Drawings and data are applicable for their intended use. Drawings and data are compatible with the available CAD equipment and software. Drawings and data created for one project or project discipline are compatible with those

created for others. Drawings and data can be transferred and integrated with other applications, such as facility

management and space management. Drawings and data created in one department of the University are consistent with those

developed by the other departments. The compatibility of the University CAD drawings and data with pertinent national,

international and industry standards is maintained. Because CAD guidelines relate to an area of technology that continues to change, it is important that they evolve and improve. To ensure that the University of South Florida and its consultants conform to the broader scope of the proposed National CADD Standard sponsored by the National Institute of Building Sciences (NIBS) CADD Council, these Standards partially incorporate recommended guidelines from the following:

American Institute of Architects (AIA), CAD Layer Guidelines The Construction Specifications Institute (CSI), Uniform Drawing System (UDS)

1.1 Why the University has Data Standards

These CAD data standards are part of the University's comprehensive facilities and space management strategies. Much of the CAD data created for the University of South Florida will be brought into the University's Information Management System, and this data must follow these CAD data standards to be readily useful within that system.

This document sets performance standards for CAD data delivered to the University. The University does not intend to influence the methods or means of practice of outside consultants.

The University is committed, however, to enforcing the standards of information delivery that insure predictability and the ability to easily reuse information. As a result, these standards will be included as part of the contractual requirements for delivery of electronic information to the University of South Florida Division of Facilities Planning and Construction.

Page 79: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

AutoCAD Standards 01 78 39 - 5

1.2 Scope of the CAD Data Standards

This data specification covers all construction documents prepared by or on behalf of the University of South Florida. The deliverables described in this document must be provided for each sheet that is issued for construction in a project and must include all supporting data files that are used to produce the finished sheets.

If additional electronic design drawings or 3-D models are provided, it is the responsibility of the consultant to initiate discussion with the University Owner's Representative to determine an acceptable format for those deliverables.

1.3 Who Must Use the Standards?

Anyone who is going to prepare CAD data for the University, including University Facilities Planning and Construction staff, contractors, and consultants, must read and become familiar with this document before proceeding with any work. (The term "consultant" used in these standards refers to the person or organization who is preparing the CAD data, whether the person or organization is part of the University or not.)

SECTION 2: CAD ENVIRONMENT

2.1 Basic CAD Software

The designated CAD software for the University is Autodesk AutoCAD Architecture 2011 or current release as stated on their website (www.autodesk.com). AutoCAD 2011 is acceptable however. Verify the current release with the CAD/GIS Operations Manager. All CAD drawings are required to be delivered in AutoCAD .dwg file format. If a consultant or vendor uses a program other than Autodesk AutoCAD Architecture 2011or Autodesk AutoCAD 2011, they must convert their files to Autodesk AutoCAD 2011 file format and fully adhere to these standards.

2.2 CAD Application Software

CAD application software packages operate on top of, or in conjunction with, the basic CAD software to extend its capabilities. The extensions enhance design, drafting and modeling productivity and link non-graphic attribute data to the graphic entities. All CAD application packages used by Facilities Planning and Construction, or its consultants, which modify or create CAD layers or other entities, must comply with these standards. All subsequent produced drawing files should be readable and usable in AutoCAD Version 2011. All complex objects and items created should be made to work in ACAD 2011. ex. Point objects, contour info etc.

Page 80: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

AutoCAD Standards 01 78 39 - 6

SECTION 3: REQUESTING CAD DATA FROM THE UNIVERSITY

Consultants may request copies of existing CAD data for University facilities. CAD data is provided for the convenience of the recipient only and is not to be shared with out USF approval. This data has been gathered from a variety of sources, and it may or may not conform to University CAD standards. The data may be incomplete, or may not accurately reflect current facility conditions.

The University makes no representation as to the data's completeness or accuracy. Consultants also should acknowledge that CAD data appears to be extremely accurate because it has been generated with a computer, and that the accurate appearance of drawings does not guarantee that they truly represent existing conditions. CAD data submitted by consultants to the University must be accurate and must conform to the current CAD standards, even if reference data provided by the University was inaccurate or did not conform to the standards. 3.1 How to Request Data

Requests should be made to the Project Manager at Facilities Planning & Construction. The Project Manager will review the request and forward it to the CAD/GIS Operations Manager, who will in turn have the requested files or materials copied and sent to the Project Manager for distribution.

SECTION 4: DELIVERABLES REQUIRED BY THE UNIVERSITY

The following applies to both New Construction/Renovation Documents. “New Construction Documents” are those drawings which are developed by USF consultants or vendors under contract to provide drawings which will be used by a General Contractor for the construction of a new USF facility. Conversely, “Renovation Documents” are those drawings which are developed by USF consultants or vendors under contract to provide drawings which will be used by a General Contractor for the construction of an extension or alteration to an existing USF facility. At the conclusion of a project, the consultants must submit to the CAD/GIS Operations Manager in the FPC Archive Department in a single letter of transmittal the following:

(1) Full size hardcopy set for both the 100% Documents & Final Record (As-Built) Documents (1) Full set of checked electronic files matching the hardcopy set delivered on CD or DVD of all

CAD Design and supporting files (i.e. e-transmits, fonts, xrefs & images etc.) that includes all disciplines.

(1) Full and matching set of .pdf files for both 100% and Final Record (As-Built) Documents as separate files of each sheet in the set matching the hardcopy exactly.

(1) Completed – “Electronic Submission Check List” (last page in these standards)

Each of these submittals is explained in more detail below. 4.1 Delivery of a Hardcopy Set

Submit a complete bound full-size hardcopy set of the final drawings plotted for construction using accepted line weights signed and sealed by responsible professionals.

4.2 Delivery of CAD Files (Vector Files)

All project files must be produced using these standards. When working with a CAD program other than AutoCAD, these standards must be adhered to and files must be submitted as an AutoCAD .dwg file. No other format will be accepted, .dxf files will not be accepted as the final translation.

Page 81: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

AutoCAD Standards 01 78 39 - 7

All submittal documents and digital files must include all supporting CAD and associated files and must be delivered as follows:

All deliverables must be submitted in the format supported by the current AutoCAD version in use within Facilities Planning and Construction. As indicated in section 2.1 of these standards.

On acceptable media, currently defined as CD-ROM or DVD Disks. File compression and disk spanning are allowable, if it is necessary to compress and/or span disks please use a program that produces files with the ZIP extension.

Submit a set of AutoCAD Drawing files at the 100% submittal which match exactly the final plotted drawings for construction. Do not draw any manual images on the final construction set of drawings.

Submit a set of conformed Final Record (As-Built) Documents in AutoCAD .dwg format at the completion of construction or certificate of occupancy and include any deviations, additions or corrections which were implemented during the construction process. Do not leave any revision “clouds” or revision marks on these drawings.

All drawings must be drawn “Life size” sometimes referred to as “Full size”. All raster images, shape files, and external references must be included in submission. Files submitted with external references must not contain other nested blocks or external

references. If submitting project files that have been combined (that once used xrefs) do not use the bind

option for external references, use the insert option instead. 4.3 Delivery of PDF Files (Raster Files)

Submit a set of full size Adobe PDF files that match exactly the final plotted submitted hardcopy. Submit individual PDF files for each sheet in the set as separate files using the sheet numbers / names for the files name. These files are to be created from the CAD 100% and Conformed Record drawings (As-Built) and are to be included and delivered at the same time as the above CAD files.

4.4 Completed Electronic Submission Checklist

Refer to and fill out the Electronic Submission Checklist at the end of this document. This signed checklist must accompany all documents.

4.5 Digital Media Labeling

Digital media labels should contain the following information as a minimum:

University project name and number Description of media content, ie: As-Builts, Conformed, Bid Documents, Shop Drawings, etc. Consultant name and telephone number Date of submittal Virus scanned (date and software used) Both the CD-ROM case and the CD-ROM itself shall be labeled.

4.6 Validation of Delivered Materials

The University of South Florida Facilities Planning & Construction Department will validate the CAD data and other materials submitted by consultants. If submittals do not conform to the data standards, the University may return the materials to the consultant, for corrections. The consultant is responsible for revising the materials to make them conform to the standards.

NOTE: If there are any conflicts, differences or lack of mention requiring CAD and deliverable standards between the consultant’s contract with USF and this AutoCAD Standards Manual, this manual supersedes and takes precedence.

Page 82: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

AutoCAD Standards 01 78 39 - 8

SECTION 5: COMMUNICATION ABOUT CAD STANDARDS

These Cad Standards will be most effective for the University and most usable for consultants if there is communication between consultants and the University's Representative.

Consultants should ask questions about the CAD data standards before beginning work. Direct questions to the FPC CAD/GIS Operations Manager, University of South Florida.

Concerns regarding the impact of the CAD standards on a particular project must be discussed with the Project Manager.

Consultants’ questions are valuable because they help the University understand the real-world conditions of each project's design and construction process. Questions will raise issues that will result in better CAD standards. 5.1 Suggestions for the Standards

The content of these standards are intended to be neither static nor all-inclusive and thus will be updated and enhanced as appropriate. Suggestions for improvements are encouraged so that subsequent updates reflect the needs of the University. Submit suggestions, as well as any pertinent new information which would enhance these standards, to the FPC CAD/GIS Operations Manager.

Page 83: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

AutoCAD Standards 01 78 39 - 9

PART 2: TECHNICAL REQUIREMENTS FOR CAD DATA The organization and format of the CAD deliverables should support the requirements of the University project for design, construction, bidding and archiving. The deliverable should also readily support the integration of information into other University management systems, such as facility maintenance management systems, with minimal additional effort.

The University's standards for CAD file types, file names, and sheet numbering are based on industry standards. The requirements of these standards are described below. SECTION 6: MASTER CAMPUS DRAWINGS

The following applies to both New Construction/Renovation Documents and Master Campus Drawings. All project files must be produced using these standards. When working with a CAD program other than AutoCAD, these standards must be adhered to and files must be submitted as an AutoCAD “DWG” file.

1. All drawings must be drawn “Life size” sometimes referred to as “Full size”. 2. Only one (1) linetype per layer and only one (1) color per layer are permitted. Set

linetype and color bylayer. (See layer descriptions and the prototype drawing for additional information).

3. Use only those linetypes provided with AutoCAD. Do not use third party linetypes. 4. Use only those hatch patterns provided with AutoCAD. Do not use third party hatch

patterns. 5. If fonts are used other than those provided with AutoCAD the font files must

accompany the drawing file when submitted. Restrict the use of third party fonts when possible.

6. Create all blocks on layer 0 during the process of developing the drawing whenever possible.

7. Do not draw any entities on layer 0. Leave this layer clean. 8. All raster images, shape files, and external references must be included in submission. 9. Files submitted with external references must not contain other nested blocks or

external references. 10. If submitting project files that have been combined (that once used xrefs) do not use

the bind option for external references, use the insert option instead. 6.1 File Translation and Submission

It is the responsibility of the consultant/vendor to provide all translations and/or submissions as requested in the current approved formats. The current format for submission is subject to change as new products and technologies become available. A revision to these standards will be issued when such changes are made. Please check the USF facilities planning web site for updates. Please contact FPC if you have any questions concerning the current submission standard.

Translations

All drawings are to be translated into the AutoCAD “DWG” file format and are to be compatible with the version of AutoCAD being used by Facilities Planning at the time of submission. The current version is subject to change and a revision to these standards will be issued on an as-needed basis. If the consultant / vendor is using CAD software other than AutoCAD the file must be translated into the AutoCAD DWG format. DXF files will not be accepted as the final translation.

Page 84: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

AutoCAD Standards 01 78 39 - 10

Submissions

CAD Files: (vector files)

Submit a set of AutoCAD Drawing files at the 100% submittal which match exactly the final plotted drawings for construction. Do not draw any manual images on the final construction set of drawings. Submit a set of “as - built” AutoCAD drawing files at the completion of construction or certificate of occupancy and include any deviations, additions or corrections which were implemented during the construction process. Do not leave any revision “clouds” or revision marks on these drawings.

All drawings are to be submitted on Compact Disk. File compression and disk spanning are allowable, if it is necessary to compress and/or span disks please use a program that produces files with the ZIP extension. Also, refer to the submission checklist at the end of this document. The signed submission checklist must accompany all documents.

PDF Files: (raster files)

Submit a set of full size Adobe PDF files that match exactly the final plotted drawings for construction. These files are to be created from the CAD 100% and “as – built” drawings and are to be included and delivered at the same time as the above CAD files.

6.2 New Construction and Renovation Documents

“New Construction Documents” are those drawings which are developed by USF consultants or vendors under contract to provide drawings which will be used by a General Contractor for the construction of a new USF facility. Conversely, renovation documents are those drawings which are developed by USF consultants or vendors under contract to provide drawings which will be used by a General Contractor for the construction of an extension or alteration to an existing USF facility.

NOTE: If there are any conflicts between the consultants or vendors’ contract with USF and this Drawings & CAD Standards manual, the contract supersedes and takes precedence.

Page 85: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

AutoCAD Standards 01 78 39 - 11

SECTION 7: TYPES OF CAD FILES

The University's CAD data will include two distinct types of CAD files, model files and sheet files. Model files contain the project's data, and sheet files are the vehicles used to present the data in different ways. 7.1 Model Files

A model file contains the graphics, which describes a subset of a building's geometry and its physical components: walls, doors, windows, columns, beams, outlets, ducts, etc. This information can be thought of as a computer "model" of the facilities involved in a project.

A model must be created at real size: 1=1. Most buildings are described by a series of two-dimensional models: plans, elevations, sections, and details.

Model files are usually referenced by other files. Models can contain other models referenced in those files.

7.2 Sheet Files

Sheet files are used to assemble model files, title blocks, and other information for plotting. A sheet file contains one or more scaled views of one or more models arranged within a border and title block. A sheet file is a 'ready-to-plot' CAD file. Each sheet file contains the parameters that will produce its corresponding plotted drawing, such as scale, layer visibility, and graphic appearance. Sheet files contain AutoCAD's paper space information. They are never referenced by other files.

By organizing information into model and sheet files, plans and other drawings can be developed without concern for layout of the construction document. Sheet files can also be developed later on in the project cycle. Sheet files allow for consistent plotting standards while also allowing different types of plots from the same CAD model. All AutoCAD viewports in sheet files must utilize a “per viewport” frozen or thawed state to reflect the extended view regardless of layer state in the drawing.

Page 86: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

AutoCAD Standards 01 78 39 - 12

SECTION 8: DRAWING FILE NAMES & SHEET NUMERATION

8.1 Drawing File Names

The following are suggested file naming guidelines. Files should be labeled in a format that creates organization.

File names contain the (B)uilding number, (S)heet number and drawing (T)ype. The example below shows how this information should be formatted.

(BBBB_SSS_T)

Building number should be obtained from your assigned project manager and should always contain four digits. For example, building 3 will be shown as 0003

The Sheet number should correspond to the drawing/sheet number. This field may contain as many characters as needed. Refer to the preferred sheet numeration chart in Section 7.2 for recommended practices. If a set of drawings will be divided into phases, which would result in similar file names, then a suffix may be added to the sheet number as follows:

(BBBB_SSS-PH#_T)

Drawing Type

Date of drawing should match the date of the latest revision. Please do not use dates that have been handwritten or stamped onto the drawing.

Example 1 0012_A1.0_R.dwg This would be the file name for sheet A1.0 in a set of renovation documents for building 12

Example 2 0311_E1-PH2_RA.dwg This would be the file name for sheet E-1 of phase 2 in a set of renovation as-built documents for building 311.

8.2 Sheet Numeration Method

The sheet numbering system shown in the chart below is USF’s preferred method of labeling sheets. The asterisk allows the addition of sheets within that description category without having to renumber multiple sheets.

Example C2.1 … Site Details If another sheet of Site Details is required then: C22 … Site Details

DRAWING TYPE DESCRIPTION

A = As Built Drawings showing changes that occurred during construction

R = Renovation / Remodeling Additions or changes after occupancy RA = Renovation As-Built (if needed) Changes during construction of renovation RO = Renovation Original (if needed) Original renovation drawings O = Original Original drawing to build the building P = Permit Permitted documents with stamp and signature PR = Permit Review Documents submitted for permit review

Page 87: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

AutoCAD Standards 01 78 39 - 13

NUMBER DESCRIPTION *Indicates wildcard / expandable field, i.e. E2.1

C0.* Civil information, notes, etc.

C1.* Topographic survey General survey Site grading & Paving

C2.* Site details C3.* Site Utilities & Site plan L0.* Landscape information, notes, etc. L1.* Landscape plan & Details LS0.* Life safety information, notes, etc. LS1.* Life safety plans

A0.* General information, notes, etc. Abbreviations, Symbols & Drawing Index

A1.* Site plan, floor plan & life safety plans A2.* Exterior elevations A3.* Reflected ceiling plan A4.* Roof plans and details

A5.* Building sections, wall sections Miscellaneous Sections & Details

A6.* Enlarged plans and details A7.* Schedules

A8.* Interior Elevations Interior Sections & Details

EQ0.* Equipment information, notes, etc. EQ1.* Equipment plans and Details S0.* Structural information, notes, etc. S1.* Foundation and framing plans S2.* Structural diagrams & shear walls S3.* Schedules S4.* Sections and details M0.* Mechanical information, notes, etc. M1.* Mechanical plans (site, 1st., 2nd. …) M2.* Mechanical room plans M3.* Details M4.* Schedules M5.* Isometrics and riser diagrams M6.* Controls P0.* Plumbing information, notes, etc. P1.* Plumbing plans (site, 1st., 2nd. …) P2.* Toilet room plans P3.* Schedules and details FP0.* Fire protection information, notes, etc. FP1.* Fire protection plans (site, 1st., 2nd.,…) FP2.* Fire alarm riser diagrams

Page 88: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

AutoCAD Standards 01 78 39 - 14

NUMBER DESCRIPTION *Indicates wildcard / expandable field, i.e. E2.1

E0.* Electrical information, notes, etc.

E1.* Electrical plans (site, 1st., 2nd., …) Legend and schedules

E2.* Electrical power plans (site, 1st., 2nd. …) E3.* Lightening protection

E4.* Low voltage electrical plans (communications, data, security)

E5.* Isometrics and riser diagrams

Page 89: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

AutoCAD Standards 01 78 39 - 15

SECTION 9: DRAWING LAYER DESCRIPTIONS

General Information

The Facilities Planning department at the University of South Florida has adopted a system of electronically cataloging information concerning the buildings on our campuses. The effective use of computer aided design (CAD) in architecture, engineering and facility management depends on sharing graphic information. These standards are intended to serve as a guideline on which an information sharing system can be built. The absence of a standard would result in unrealized potential for sharing graphic information. The standards strive for a balance, providing a general framework for practice while allowing expansion and modification.

The structure for these standards was derived in part from the AIA CAD LAYER GUIDELINES, and the U.S. National CAD Standard, both having major influence over the built-in layer naming structure utilized by Autodesk’s AutoCAD Architecture. Therefore, the following layer naming system is a direct derivation of the default layer naming system used by AutoCAD Architecture. 9.1 Layer Standards

The standard blocks (symbols) and smart objects in AutoCAD Architecture will automatically be placed on the appropriate layer.

The layering standards established in this document, as previously mentioned, are a direct derivation of the Autodesk Architecture 2011 default layering structure, which is based in the AIA 256 color standard. The USF derivative of this layering standard does not alter any layer name or established use, it does, however, simplify the AutoCAD Architecture layering standard by discouraging the use of the subcategories available in the discipline designator group. Likewise, USF also discourages the use of AutoCAD Architecture minor group 2 field; therefore it is not included in the drawing layer chart in Section 8.2. Because the layering system does not alter any established layer name or use, AutoCAD Architecture’s Layer Key Override functionality was not utilized and as such, for maximum compliance, consultants should not alter the default settings in this utility.

NOTE: Additional supplemental files to this document are available and are provided for convenience to all USF consultants. These supplemental files are to be used as part of these standards.

Supplemental files to this document are located on the FPC web site. USF layer template files contain all layers listed in the drawing layer chart in Section 8.2. These template files can be utilized by using the Layer States Manager feature in AutoCAD Architecture. Additionally the layer translator utility can be used after a drawing is complete (AutoCAD command: laytrans). The layer translator is a quick and easy way to comply with the USF layering standards.

9.2 Layer Formats

Do not draw any entities on layer 0 (Leave this layer clean and unused) Blocks should be created on Layer 0 and inserted onto the appropriate object layer

The layer guidelines are organized as a hierarchy. This structure makes the list easier to use and accommodates future expansion. Layer names are alphanumeric and use easy to remember abbreviations such as A_DOOR for architectural doors, A_WALL for architectural walls and E_POWR for electrical power.

Page 90: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

AutoCAD Standards 01 78 39 - 16

Drawing Layer Chart

DISCIPLINE DESIGNATOR A -- Architectural O -- Operations B -- Geotechnical P -- Plumbing C -- Civil Q -- Equipment D -- Process R -- Resource E -- Electrical S -- Structural F -- Fire Protection T -- Telecommunications G -- General U -- University H -- Hazardous Materials V -- Survey/Mapping I -- Interiors W -- Civil Works L -- Landscape X -- Other Disciplines M -- Mechanical Z -- Contractor / Shop Drawings

MAJOR DESIGNATOR Accs – Access Plan Flor – Floor Anno – Annotation Furn – Furnishings Area – Area Glaz – Glazing Beam – Beams HVAC – HVAC Clng – Ceiling Lite – Lighting Fixtures Code – Code Compliance Plan Plan – Key Plan (Floor Plan) Cols -- Columns Poly – Polygons Comm – Telecommunications Prop – Property Conv – Conveying Systems Prot – Fire Protection System Ctrl – Control Points Roof – Roof Detl – Detail Sect – Section Door – Doors Site – Site Plan Elec – Electrical Slab – Slabs Elev – Elevation Strm – Drainage Eqpm – Equipment Tinn – Triang. Irregular Network Evac – Evacuation Plan Topo – Topography Fire – Fire Protection Plan Wall – Walls

MINOR GROUP Abov – Elements Above Eqpm – Equipment Accs – Access Evtr – Elevator Cars and Equipment Adtv – Additive Elements Fasc – Fascias Appl – Appliances File – File Cabinets Assm – Assemblies Fine – Fine Weight Graphic Lines Bdry – Boundary Elements Fire – Fire Walls Blow – Below Fixd – Fixed Equipment Brce – Braces Fixt – Plumbing Fixtures Brng – Bearings & Distance Labels Fnsh – Finishes Case – Casework Free – Freestanding Cavi – Cavity Full – Full-Height Chas – Chase Grid – Grid Clng – Ceiling Grps – Groups Cntr – Centerline Head – Door and Window Headers Comm – Tele-Com Hevy – Heavy Graphic Lines

Page 91: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

AutoCAD Standards 01 78 39 - 17

MINOR GROUP Comp -- Internal Components Hide – Hidden Objects Conn – Connections Hide – Hidden Objects Curt – Curtain Wall Hral – Handrails / Guard Rails Demo – Demolition Iden – Identification Tags Dims – Dimensions Jamb – Door and Window Jambs Keyn – Keynotes Revc – Revision Clouds Labl – Labels Revs – Revisions Legn – Legends, Symbols Keys Risr – Stair Risers Levl – Lvl Chg, Ramps, Pits Schd – Schedules Line – Defining Line Scrn – Screened Backgrounds Lite – Lighting SDFF – Supply Diffusers Mark – Markers, Leaders Notes Seat – Seating Mask – ADT Masking Objects Sign – Signs Mass – Massing Elements Sill – Window Sills Matc – Match Lines Slab – Slabs Mcut – Main Cut Line Elements Slce – Slices Medm – Med Graphic Lines Spce – Space Move – Moveable Equipment Spcl – Specialties Nicn – Not in Contract Notes Stor – System Storage Components Nplt – No-plot Graphic Information Strs – Treads, Escalators, Ladders Occp – Occupant Names Subt – Subtractive Elements Open – Openings Susp – Suspended Elements Otln – Outline Swch – Switches Ovhd – Overhead Tabl – Data Tables Patt – Texture or Hatch Patterns Tees – Main Tees Pepl – People Text – Text Pkng – Parking Thin – Thin Weight Graphic Lines Pnls – Panels Thld – Thresholds Plnt – Plants Title – Drawing or Detail Titles Powr – System Panels Tptn – Toilet Partitions Prht – Power Ttlb – Border and Title Block Prof – Partial Height Util – Utilities Rais – Profiles Vhcl – Vehicles RDFF – Raised View – Viewport Definition Symb – Return Air Diffusers Wall – Wall Rdme – Symbols Wdwk– Architectural Woodwork Refl – Read-me-layer (no-plot) Wide – Wide Weight Graphic Lines Refr – Reflected Plan Wksf – System Work Surface

STATUS 1 -- Phase 1 9 -- Phase 9 2 -- Phase 2 D -- Existing to Demolish 3 -- Phase 3 E -- Existing to Remain 4 -- Phase 4 F -- Future Work 5 -- Phase 5 M -- Items to be moved 6 -- Phase 6 N-- New Work 7 -- Phase 7 T -- Temporary Work 8 -- Phase 8

Page 92: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

AutoCAD Standards 01 78 39 - 18

Discipline Designators:

The major groups correspond to the traditional discipline designations used in construction document sheet numbering; they are not intended to suggest which member of the design team draws which objects. For example, the column grid would be placed on layer S_COLS_GRID regardless of whether it was drawn by the architect or structural engineer.

Major Group Designators:

Major groups subdivide discipline groups on the basis of constructions or the type of information. For example, the architectural discipline group contains major groups for walls, doors, floors, ceilings, and furniture.

Minor Group Designators:

A modifier may be added to a layer name for further differentiation. For example, walls (A_WALL) may be categorized as full height (A_WALL_FULL), partial height (A_WALL_PRHT) or moveable (A_WALL_MOVE).

NOTE: Facilities Planning & Construction has provided an additional document entitled: USF Layer Guidelines This document contains more descriptive layer names by discipline to be used as a guide in the development of CAD Drawings that will be submitted to the University. This document can be found on the FPC web site.

Page 93: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

AutoCAD Standards 01 78 39 - 19

SECTION 10: DRAWING SETUP

This section describes how to organize and set up CAD drawings for the University. It has been prepared using the AIA CAD Layer Guidelines and the CSI Uniform Drawing System. It is recommended that University employees and consultants obtain copies of these materials to supplement this section. CAD Layer Guidelines American Institute of Architects 1735 New York Avenue, NW Washington, DC 20006-5292 Voice: (202) 626-7300 Orders: (800) 365-2724 Fax: (802) 864-7626 Email: [email protected] Internet: http://www.aia.org Uniform Drawing System The Construction Specifications Institute 601 Madison Street Alexandria, VA 22314-1791 Voice: (800) 689-2900 Fax: (703) 684-0465 Email: [email protected] Internet: http://www.csinet.org Consultants must obtain prior approval from the Project Manager for any exceptions to the drawing set up standards. Consultants must submit documentation that shows the files affected and how they deviate from the standards. 10.1 Drawing Units

Most CAD files should use the architectural (feet and inches) report format. Civil engineering CAD files may use the engineering (feet and tenths) or decimal report format.

10.2 Accuracy

All CAD drawings shall be drafted using precision input employing the most accurate source material available. For all drawing entities, zero tolerance is required, all lines meet at intersections, straight lines are straight, blocks are inserted properly without overlap, etc. Consultants are responsible for the accuracy of all CAD drawings delivered to the University, regardless of the accuracy of CAD drawings of previous projects furnished by the University as a convenience to the consultant.

10.3 Scale

Model Space objects shall be created at full size. 1 AutoCAD unit = 1 foot for civil or engineering general and 1 AutoCAD unit = 1 inch for architectural so therefore a 100-foot wall will be drawn to 100 feet and a 36-inch column will be drawn to 36 inches. The following types of CAD drawings may be drawn to any scale: schedules, riser diagrams, schematic diagrams and single line diagrams.

Page 94: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

AutoCAD Standards 01 78 39 - 20

10.4 Origins and Registration of CAD Data Files

The origins of CAD model files must be defined at coordinates 0, 0, 0, with the exception of Civil Engineering CAD model files. This is typically the lower left corner of the building. For non-rectilinear buildings a logical origin point shall be established.

The origin point must remain consistent between all model files in a project. This is critical for correct registration of different model files when referenced together, aligning the various views of the facility. Registration of electronic data must be maintained so the information will be usable in future applications.

The origin of each CAD sheet file should be at the lower left-hand corner of the sheet border and set to coordinates 0, 0, 0. Special Considerations for Site Plans

Civil Engineering CAD model files must use true geographic coordinates for their origins. The basis of coordinates used shall be clearly identified within the model space and listed in the notes of the printed sheets.

10.5 Entities and Graphic Representation

Curved Entities

Circles, arcs and ellipses shall be created as individual entities, not of line segments. Drawing Limits

Drawing and extents must be checked to ensure there are no objects outside the drawing limits. Objects outside the drawing limits will slow the regeneration and manipulation of the drawing. All drawings shall be submitted with the drawing display zoomed to the drawing extents. Entity Properties

Entity properties such as color and linetype shall be BYLAYER. For purposes of clarity, some symbol and block properties may not be set BYLAYER, but this should be avoided whenever possible.

10.6 Saved State of CAD Model Files

CAD files should be delivered in the state described below:

Blocks should not be exploded Drawings should be purged Drawings should be zoomed to extents Drawings should be left in paperspace if they use paperspace

10.7 Plotting

Each sheet drawing file generally represents a single plotted drawing. The sheet origin point is the lower left-hand corner of the sheet. The sheet border may be an xref file inserted at 0,0. No drawing entities should reside outside of the sheet's border. When saving a sheet file, make only the layers needed for correct plotting of the sheet visible. Plotting shall be set at a scale of 1"=1".

Page 95: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

AutoCAD Standards 01 78 39 - 21

10.8 Title Blocks/Borders

USF project title blocks are provided on the Facilities Planning web site and are to be used for All USF projects.

Title Block & Sheet Sizes

8.5” x 11” 11” x 17” 18” x 24” 24” x 36” 30” x 42” Sheets within a document set should include a title-block containing at minimum the following information: page/sheet number (see chart in Section 7.1-7.2 for suggested practice), approved project title (see your assigned USF project manager), building number and revision history. *USF Health projects have a different title block. This can also be found on the Facilities Planning Website: http://usfweb2.usf.edu/FacilitiesPlan/process/USF_CAD_STANDARDS.html

10.9 Title Block and Title Sheet Information

Required information on title blocks:

TITLE BLOCK INFORMATION Content: The following information shall be provided in the title block of each drawing Name of University Project location State Project Number State University System of Florida Sheet Title/Name

Phase of development (i.e. Conceptual Schematics, Advanced Schematics, Design Development, 50%, 100% Construction Documents)

Name of Architect/Engineer Address of Architect/engineer Telephone number of Architect/engineer Sheet number

Date of preparation Initials of preparer Signature of reviewer Date of review (On each sheet, as applicable)

Name of consultant Address of consultant Telephone number of consultant

Organization:

The basic organization of the title block shall be the same for each drawing, changing the information on each sheet as appropriate. The sheet number shall always appear either on the lower right hand corner or along the right margin of the drawing.

Seal & Signature:

Each drawing shall be signed, sealed and dated by the responsible professional.

Page 96: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

AutoCAD Standards 01 78 39 - 22

The title sheet for drawings should be made as simple as possible, and should contain the following information:

TITLE SHEETS, PAGES AND BINDINGS Project Title Project Location University Name: University of South Florida USF Project Number Name, Address, and Telephone Number of Architect/Engineer As appropriate: Name, Address, and Telephone Number of Consultants Date of Publication

The cover of the Project Manual may be of any style or format, as long as it is consistent with the above outline. The title page may be omitted if the cover provides the prescribed content.

The title sheet for the drawings may serve as the drawings cover or a plain sheet may be used for protection.

Project Manual and drawings shall be bound in such a manner as to discourage separation or removal of pages.

10.10 Room Numbering Standards

Room numbers should be assigned at the 50% Construction Document phase. Coordinate all room numbers with the USF FPC Space Coordinator. The USF FPC Project Manager will serve as the point of contact. All room numbers are to be approved before use in the project.

TYPE OF SPACE TEXT NUMBERING STANDARD

Restrooms MEN or WOMEN number in sequence with all rooms

Custodial room JAN number in sequence with all rooms Electrical room ELEC number in sequence with all rooms Telephone Equip. TELE number in sequence with all rooms

Elevators ELEV number with alpha prefix “E”, ex: E0100, E0101 for 1st fl; E0200, E0201 for 2nd fl

Corridors -none- number with alpha prefix “C”, ex: C0100, C0101 for 1st fl; C0200, C0201 for 2nd fl

Stairs STAIR number with alpha prefix “S”, ex: S0100, S0101 for 1st fl; S0200, S0201 for 2nd fl

Mechanical Rooms MECH number with alpha prefix “M”, ex: M0100, M0101 for 1st fl;

M0200, M0201 for 2nd fl Mechanical Chases -none- number with alpha prefix “M”, ex: M0100, M0101 for 1st fl;

M0200, M0201 for 2nd fl External Circulation -none- number with alpha prefix “X”, ex: X0100, X0101 for 1st fl;

X0200 for 2nd fl. Bleachers / exterior seating -none- number with alpha prefix “B”, ex: B0100, B0101 for 1st fl;

B0200, B0201 for 2nd fl Partition wall (Cubicles) -none- number with alpha prefix “P”, ex: P0100, P0101 for 1st fl;

P0200, P0201 for 2nd fl

Page 97: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

AutoCAD Standards 01 78 39 - 23

Room Numbering Examples

All Rooms must be designated with numbers in the hundreds or thousands and must contain four (4) digits, using 01## or 1### for first floor, 02## or 2### for the second floor, etc. If there are many rooms or many suites on a floor, number rooms in the thousands, using 1000s, 1100s, 1200s, etc. for different areas or suites on the floor. Room numbers in the hundreds should always contain a zero in the thousands place, 0100 for example.

Label any room inside of a room whose main entry is off of the main corridor with an alpha suffix of the room it is within. For example, if room number 0100 is accessible from the corridor, the room inside of it (accessible only by going into room 0100) should be designated 0100A.

Page 98: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

AutoCAD Standards 01 78 39 - 24

Rooms need to be numbered consecutively from one end of the hall to the other. DO NOT start numbering at one room and circle around the corridor.

Floor areas designed for elevators, stairwells, internal and covered external circulation, restrooms, electrical, mechanical, custodial, and telephone equipment rooms also need designations. Please refer to the room type chart on page 19.

Total Gross Square Feet1 and Total Net Square Feet2 must be calculated and printed on the lowest floor level of the plan. The lowest level of the plan must be labeled “level 1”, not “ground floor” or “first floor”, whether it is below grade or not. The next levels above level 1 should be labeled concurrently level 2, level 3, etc.

(1) Gross Square feet = the area of the building defined from the exterior face of the building wall. The Gross also includes all covered external areas. (2) Net Square feet = All interior usable spaces excluding walls and mechanical chases. Do not include any exterior spaces in the net s.f.

Page 99: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

AutoCAD Standards 01 78 39 - 25

SECTION 11: SYMBOLOGY AND COMPOSITION

11.1 Line Types

Use standard line types whenever possible. Contour lines, dashed lines and other fonted lines shall be made of one continuous line segment, not a series of separate line segments. If the consultant is using pre-approved basic CAD software other than AutoCAD, insure that line types translate correctly in the .DWG file.

Polylines with increased width may be used only to depict non-building drawing elements such as cut-lines. Use of toned or pochéd line weights for use with inkjet or electrostatic plotters to differentiate new or existing work is acceptable.

Use only those linetypes provided with AutoCAD. Do not use third party linetypes. Only one (1) linetype per layer and only one (1) color per layer are permitted. Set linetype and

color bylayer. (See layer descriptions and the prototype drawing for additional information). 11.2 Line Type Scale

Line type scale should be set to 1.000 for all objects so that each line type is recognizable, easily identified, and distinguishable to individuals who are working in the model files and in final plotted output. Manipulation of linetype scale should then be achieved by software variable to adjust graphic representation of objects linetype globally.

11.3 Line Weight and Color

Consultants may use additional line weights or assign colors to layers as needed for effective communication of the project data.

The plot style type that is typically used by USF Facilities Planning & Construction is a Color based Plot-Style (.ctb). Line weight and color affect the usability of CAD data in different ways. Line weight typically is most useful when working with plotted CAD drawings. Plots, or reproductions of plots, are usually monochrome and the thickness of lines is an important means of communicating information about the facility and the design. Color is most useful when working with CAD data on a computer screen. Colors allow users to readily identify systems and types of information. On a computer screen, line weight often gets in the way of effective communication.

11.4 Text and Fonts

If fonts are used other than those provided with AutoCAD the font files must accompany the drawing file when submitted. Restrict the use of third party fonts when possible. Text size must be legible and appropriate for the graphic information presented and the intended plotted scale of the drawing. Text must be in all upper case letters throughout a drawing, except for electrical switch legs and symbols, which require lower case letters.

Text placement guidelines

Text usually should not touch other graphic objects, and must be placed with enough space around it to be legible when the drawing is plotted and reproduced.

Text may be placed at an angle. It must be readable from the bottom or right edges of the plotted sheet. Generally text should be placed at an angle of 0° or 90°. Text may be placed along (above or below) another element at an angle other than 0° or 90°.

English (Architectural in AutoCAD) units shall be the standard system of measurement. The base unit shall be inches.

Page 100: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

AutoCAD Standards 01 78 39 - 26

11.5 Annotation

Annotation can be placed in either model files or sheet files. Annotations related to model data, such as dimensions, notes, and callouts must be included in the model file where they are easier to coordinate and revise.

Other annotations, such as drawing titles, legends, and sheet-specific notes, are more convenient to work with when placed in the sheet file.

11.6 Dimensions

Associative dimensions should be used. Consultants should insure that all dimensions are in a named dimension style for all dimensions in CAD files, so the dimension parameters can be readily modified as needed. Dimension overrides are only acceptable if text is needed to be added to a dimension line. Overrides are not allowed to be used to change the measurement of the dimension.

11.7 Xref (External Reference) Files

Xrefs may be used to subdivide a large CAD drawing into several smaller, more efficient drawings. The use of this procedure will reduce drawing size, increase performance, improve operator efficiency and make coordination of disciplines easier. Xrefs may also be used to split a drawing by disciplines. Avoid nested xrefs. There shall be no specific drive or directory references associated with the xrefs. All xrefs must reside in the same directory as the drawing files.

Files submitted with external references must not contain other nested blocks or external references.

If submitting project files that have been combined (that once used xrefs) do not use the bind option for external references, use the insert option instead.

An E-transmit can be used to create a folder or .zip file that includes the main file with all attached xrefs still linked and is the preferred method for drawing deliverables.

11.8 Blocks

Any graphic entity that occurs repeatedly in drawings should be made into a block. Insertion points for blocks shall be consistent with its placement in the drawing. Use a logical insertion point (center of circle, bottom left corner of object, etc.). Keep names simple and descriptive. AutoCAD block names must be unique within each project.

Nested blocks contain more than one block definition. Nested blocks need to be un-nested before the files are submitted to the University.

11.9 Hatching

Use only those hatch patterns provided with AutoCAD. Do not use third party hatch patterns.

Page 101: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

AutoCAD Standards 01 78 39 - 27

EXHIBIT A

Master Campus Drawing General

The drawing known to USF as the “Master Campus Drawing” is an important part of the overall management of the physical facilities of the campus. This drawing is used for, but not limited to, the following:

1. Mapping of all utilities 2. Mapping of Drainage and Wet Lands 3. The planning of new Buildings, Roads, Parking, etc.

Facilities Planning and Construction at USF is responsible for updating and modifying this “Living Document.”

Consultants and Vendors will not be allowed to edit the original drawing file; however, they will be required to provide drawings which USF will insert into the original drawing. Therefore, it is extremely important that the consultant understand the requirements and concepts of manipulating this drawing.

This drawing was created by converting an aerial photograph to a vector image, therefore, inaccuracies exist. The use of this drawing does not relive the consultant from the responsibility of utilizing other information including as-built drawings, surveys, legal descriptions, field investigation, etc., to develop an accurate site plan.

Page 102: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

AutoCAD Standards 01 78 39 - 28

Master Campus Drawing (MCD) File Descriptions

The following is a list of the drawing file names and a general description of their contents which can be combined to create the “Master Campus Drawing” image:

DRAWING NAME

DESCRIPTION (files contain this content)

TAP_USF

This is the base drawing file which is used to build the desired image or combination of other drawing files. This file contains the "edge of paper" rectangle and the standard USF border with title block. Load this drawing into the AutoCAD editor first.

TAP_STGR The "Florida State Plane Coordinate System" grid. TAP_CPGR The "Campus Grid". TAP_PROP The campus property lines, lease lines, etc. TAP_ROAD All surfaces designed for vehicles. TAP_WALK All paved surfaces designed for pedestrians. TAP_ELEV All survey spot elevations. TAP_CONT All contour lines based upon survey information. TAP_FNCE All fence lines on the property. TAP_SIGN All signage on the campus. TAP_LAND All landscape and landscape features i.e.; tree, hedge, etc. TAP_LITE All lighting system components i.e.; poles, conduits, manholes, etc. TAP_ELEC All electrical system components i.e.; poles, conduits, manholes, etc. TAP_COMM All communication system components i.e.; antennas, conduits, manholes, etc. TAP_GAS All natural gas piping on the property. TAP_SEWR All sanitary sewer components. TAP_POTW All potable water system components. TAP_MECH All mechanical system components. TAP_IRRG All irrigation system components. TAP_LEASE-EASE The campus property lines, campus lease lines, and utility easements. TAP_HOLE The location, date, and approximate size of all sinkholes on the campus. TAP_FIRE-HYD The location and most recent pressure testing data for all campus fire hydrants. Assign all of the physical elements of the campus which are to be graphically shown in the Master Campus Drawing to one of the above described files. The elements in each drawing file have been located as accurately as possible; therefore if the operator views the TAP_POTW and TAP_MECH drawings at the same time some elements will be on top of each other and will “muddy” the image. The text associated with each file will be contained in that file and has not been coordinated with other files. This text conflict may also produce an unreadable image.

The Master Campus Drawing system has been prepared and is intended to be used at a plotted scale of 1” = 200’. The text has been given special heights, however, so that it is readable at 1” = 200’ yet is not to large at 1” = 100’. Therefore the drawing can be plotted at 1” = 100’, however, larger scales are not recommended. The inaccuracies of the drawing elements will become very apparent and the text height will be out of proportion.

Page 103: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

AutoCAD Standards 01 78 39 - 29

Master Campus Drawing (MCD) Layer Chart

The following is a list of all “LAYERS” associated with each drawing file in the Master Campus Drawing System. Adhere to the general rule of one (1) linetype and one (1) color per layer in this system of drawings. All drawings will contain layer “0” which will be empty of any drawing entities, set to color 7 (white), and linetype continuous, therefore it will not be shown below with each drawing. The drawing file chart below includes layer names, descriptions, color and line type for each layer.

MCD LAYER CHART

LAYER NAME DESCRIPTION COLOR LINE-TYPE TAP_USF.DWG

USF_EDGE This layer contains the rectangle which represents the edge of the paper at a plot scale of 1”=200’ and a paper size of 30” x 42”.

White cont.

USF_TITLE This layer contains the standard border and title block White cont.

USF_TEXT This layer contains all of the title block text which can be edited by the operator and is not part of the standard title block. White cont.

TAP_STGR.DWG

STGR_GRID This layer contains the grid lines and the text which labels the coordinates for the “Florida State Plane System”. Yellow cont.

TAP_CPGR.DWG

CPGR_GRID This layer contains the grid lines and text which labels the coordinates for the “Campus Grid Yellow cont.

TAP_PROP.DWG PROP This layer contains the USF property lines. Cyan cont. TAP_BLDG.DWG

BLDG_STRU This layer contains all of the physical building structures on the campus 160 cont.

BLDG_MISC This layer contains all miscellaneous building structures such as retaining walls, flag poles, etc. White cont.

BLDG_TEXT This layer contains the building identification text. White cont. TAP_ROAD.DWG ROAD_TXT1 This layer contains the text which belongs with the roadways White cont.

WALK_PAVD This layer contains all of the paved surfaces designed for pedestrians. 252 cont.

TAP_ELEV.DWG SPOTELEV This layer contains the spot elevations. 8 cont. TAP_CONT.DWG CONT This layer contains the contour lines at 1’-0” intervals 253 cont. CONT_FIVE This layer contains the contour lines at 5’-0” intervals. 253 cont. TAP_FNCE.DWG FNCE_LINE This layer contains the fence lines. 252 cont. TAP_SIGN.DWG SIGN_SYMB This layer contains the sign locations on the Campus Green cont. TAP_LAND.DWG

LAND This layer contains the location of all trees, shrubs, landscaping material, etc. 253 cont.

TAP_RETN.DWG RETN_LINE This layer contains the edge of all water Retention areas. 253 cont. TAP_STRM.DWG STRM_LINE This layer contains the storm water pipe lines. 188 cont. STRM_STRU This layer contains all storm water structures 188 Cont

Page 104: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

AutoCAD Standards 01 78 39 - 30

LAYER NAME DESCRIPTION COLOR LINE-TYPE STRM_TEXT This layer contains all storm water text. 188 Cont TAP_LITE.DWG LITE_LINE This layer contains the lighting conduit lines. 10 cont. LITE_STRU This layer contains all lighting structures. 10 cont. LITE_TEXT This layer contains all lighting text. 10 cont. TAP_ELEC.DWG ELEC_LINE This layer contains all electrical conduit lines. Red cont. ELEC_STRU This layer contains all electrical structures. Red cont. ELEC_TEXT This layer contains all electrical text. Red cont. TAP_COMM.DWG COMM_LINE This layer contains the communication conduit lines. 40 cont. COMM_STRU This layer contains the communication structures 40 cont. COMM_TEXT This layer contains all communications text. 40 cont. TAP_GAS.DWG GAS_LINE This layer contains the gas lines. Yellow cont. GAS_STRU This layer contains all gas structures. Yellow cont. GAS_TEXT This layer contains all gas text. Yellow cont. TAP_SEWR.DWG SEWR_LINE This layer contains the sanitary sewer pipe lines. Green cont. SEWR_STRU This layer contains all sanitary sewer structures. Green cont. SEWR_TEXT This layer contains all sanitary sewer text. Green cont. TAP_POTW.DWG POTW_LINE This layer contains the potable water pipe lines. Blue cont. POTW_STRU This layer contains all potable water structures. Blue cont. POTW_TEXT This layer contains all potable water text. Blue cont. TAP_MECH.DWG

MECH_LINE This layer contains the mechanical chilled water supply and hot water return lines. Magenta cont.

MECH_STRU This layer contains all mechanical structures. Magenta cont. MECH_TEXT This layer contains all mechanical text. Magenta cont. TAP_IRRG.DWG IRRG_LINE This layer contains the irrigation pipe lines. 130 cont. IRRG_STRU This layer contains all irrigation structures. 130 cont. IRRG_TEXT This layer contains all irrigation text. 130 cont. TAP_LEASE-EASE.DWG CITY_TAMPA_EASEMENT This layer contains City of Tampa easement information. Cyan Hidden EASEMENT This layer contains general easement delineations. 24 Cont. NEW EASEMENT LINES This layer contains new easement lines that need final approval. Green Cont. OLD EASEMENT LINES KEEP This layer acts as a record of old or outdated easements. Cyan Cont.

PROPOSED EASEMENT LINES

This layer contains information regarding proposed easements not in effect. 24 Cont.

SUBLEASE_LINE This layer contains information regarding sublease boundaries within the campus. Cyan Cont.

TECO_EASEMENT This layer contains information regarding Tampa Electric Company utility easements. 24 Cont.

TAP_HOLE.DWG

SINKHOLE This is the only layer in this drawing. It contains all symbols and textual/numeric information. Red Cont.

TAP_FIRE-HYD.DWG

Page 105: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

AutoCAD Standards 01 78 39 - 31

LAYER NAME DESCRIPTION COLOR LINE-TYPE

FH_TEXT This layer contains textual / numeric parametric information for each hydrant. White Cont.

FH_SYMBOL This layer contains the hydrant symbols. Red Cont.

Page 106: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

AutoCAD Standards 01 78 39 - 32

EXHIBIT B

Electronic File Submission Checklist *Sign and attach to deliverables

All externally referenced drawings, images, and files are included in a .zip file created with e-transmit

Layers are consistent with USF CAD standards and unused layers have been purged

If needed, files have been translated into a version of AutoCAD compatible with the version currently being used by USF Facilities Planning

File names clearly indicate the drawing sheet number

Referenced font and shape files have been included with submission

All nested blocks & external references (xref) have been un-nested

Model Space drawings are scaled at life size and all paper space drawings are scaled 1:1

Drawing sets have been checked for missing and illegible sheets/drawings

All consultants / discipline drawings are included

Room numbers adhere to USF room numbering standards and have been approved by USF

CDs/DVDs have been clearly labeled with official project information

Full size hardcopy set is provided with the electronic files for use by the FPC Archive Department

Project Name Date Name of Company or Department Submitting Deliverables

Signature of Person Submitting Printed Name

For: Archive Department use only (below this line)

Accepted Returned Name of Archive Department Reviewer Date

Page 107: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

MISC. CAST-IN-PLACE CONCRETE & CONCRETE REPAIR 03 30 53 - 1

SECTION 03 30 00 – MISC. CAST-IN-PLACE CONCRETE & CONCRETE REPAIR

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes cast-in-place concrete, including reinforcement, concrete materials, mixture design, placement procedures, and finishes. This section also includes provisions for temporary excavation support and protection systems.

1.2 PERFORMANCE REQUIREMENTS

A. Furnish and install concrete and concrete accessories, formwork and other materials to provide a complete and finished product.

B. Dewatering Performance: Design, furnish, install, test, operate, monitor, and maintain dewatering system of sufficient scope, size, and capacity to control hydrostatic pressures and to lower, control, remove, and dispose of ground water and permit excavation and construction to proceed on dry, stable subgrades.

C. Design, furnish, install, monitor, and maintain excavation support and protection system capable of supporting excavation sidewalls and of resisting soil and hydrostatic pressure and superimposed and construction loads. Provide temporary dewatering systems as required to maintain safe access to necessary materials and work areas.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of product indicated.

B. Other Action Submittals:

1. Design Mixtures: For each concrete mixture.

2. Shop Drawings: For excavation support and protection systems.

1.4 QUALITY ASSURANCE

A. Regulatory Requirements: Comply with governing AHJ notification regulations before beginning dewatering. Comply with hauling and disposal regulations of authorities having jurisdiction.

B. Ready-Mix-Concrete Manufacturer Qualifications: A firm experienced in manufacturing ready-mixed concrete products and that complies with ASTM C 94/C 94M requirements for production facilities and equipment.

C. Comply with ACI 301.

Page 108: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

MISC. CAST-IN-PLACE CONCRETE & CONCRETE REPAIR 03 30 53 - 2

PART 2 - PRODUCTS

2.1 FORMWORK

A. Furnish formwork and formwork accessories according to ACI 301.

2.2 STEEL REINFORCEMENT

A. Recycled Content of Steel Products: Postconsumer recycled content plus one-half of preconsumer recycled content not less than 60 percent.

B. Reinforcing Bars: ASTM A 615/A 615M, Grade 60, deformed.

C. Plain-Steel Welded Wire Reinforcement: ASTM A 185/A 185M, fabricated from as-drawn steel wire into flat sheets.

2.3 CONCRETE MATERIALS

A. Cementitious Material: Use the following cementitious materials, of the same type, brand, and source throughout Project:

1. Portland Cement: ASTM C 150, Type I or Type II. Supplement with the following:

a. Fly Ash: ASTM C 618, Class C or F.

B. Normal-Weight Aggregate: ASTM C 33, graded, 1-1/2-inch nominal maximum aggregate size.

C. Water: ASTM C 94/C 94M.

2.4 RELATED MATERIALS

A. Vapor Retarder: Polyethylene sheet, ASTM D 4397, not less than 10 mils thick; or plastic sheet, ASTM E 1745, Class C.

B. Joint-Filler Strips: ASTM D 1751, asphalt-saturated cellulosic fiber, or ASTM D 1752, cork or self-expanding cork.

C. Epoxy Adhesives: 2-Part epoxy adhesives to allow installation of dowels or anchors.

2.5 CURING MATERIALS

A. Moisture-Retaining Cover: ASTM C 171, polyethylene film or white burlap-polyethylene sheet.

Page 109: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

MISC. CAST-IN-PLACE CONCRETE & CONCRETE REPAIR 03 30 53 - 3

2.6 CONCRETE MIXTURES

A. Normal-Weight Concrete: Prepare design mixes, proportioned according to ACI 301, as follows:

1. Minimum Compressive Strength: 3000 psi at 28 days. 2. Maximum Water-Cementitious Materials Ratio: 0.50. 3. Cementitious Materials: Use fly ash, and silica fume as needed to reduce the total

amount of portland cement, which would otherwise be used, by not less than 40 percent. 4. Air Content: Maintain within range permitted by ACI 301. Do not allow air content of

trowel-finished floor slabs to exceed 3 percent.

2.7 CONCRETE MIXING

A. Ready-Mixed Concrete: Measure, batch, mix, and deliver concrete according to ASTM C 94/C 94M[ and ASTM C 1116/C 1116], and furnish batch ticket information.

1. When air temperature is above 90 deg F, reduce mixing and delivery time to 60 minutes.

PART 3 - EXECUTION

3.1 CUTTING AND REMOVAL OF EXISTING MATERIALS

A. Clearly mark on existing materials where proposed limits of removal are to extend. Strike lines or mark with clear indications prior to removal.

B. Cut existing materials in a clean, straight line to allow clean removal of materials.

C. Remove existing materials as required to perform Work safely and adequately and to allow a neat and workmanlike re-installation of materials.

D. Dispose of removed materials by recycling whenever possible.

3.2 DEWATERING SYSTEMS

A. Install dewatering system utilizing wells, well points, or similar methods complete with pump equipment, standby power and pumps, filter material gradation, valves, appurtenances, water disposal, and surface-water controls.

1. Space well points or wells at intervals required to provide sufficient dewatering. 2. Use filters or other means to prevent pumping of fine sands or silts from the subsurface.

B. Provide an adequate system to lower and control ground water to permit excavation, construction of structures, and placement of fill materials on dry subgrades. Install sufficient dewatering equipment to drain water-bearing strata above and below bottom of foundations, drains, sewers, and other excavations. 1. Monitor dewatering systems continuously.

Page 110: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

MISC. CAST-IN-PLACE CONCRETE & CONCRETE REPAIR 03 30 53 - 4

2. Provide standby equipment on site, installed and available for immediate operation, to maintain dewatering on continuous basis if any part of system becomes inadequate or fails. If dewatering requirements are not satisfied due to inadequacy or failure of dewatering system, restore damaged structures and foundation soils at no additional expense to Owner.

3. Remove dewatering system from Project site on completion of dewatering. Plug or fill well holes with sand or cut off and cap wells a minimum of 36 inches below overlying construction.

3.3 EXCAVATION SUPPORT AND PROTECTION

A. Piling: Install piles or piling and bracing as required to support adjacent construction or soils to allow safe access and construction of necessary Work.

1. Do not place temporary materials where it will be cast into or included in permanent concrete work unless otherwise approved by Architect.

2. Install internal bracing, if required, to prevent spreading or distortion of braced frames.

B. Maintain bracing until structural elements are supported by other bracing or until permanent construction is able to withstand lateral earth and hydrostatic pressures

C. Remove excavation support and protection systems when construction has progressed sufficiently to support excavation and bear soil and hydrostatic pressures. Remove in stages to avoid disturbing underlying soils or damaging structures, pavements, facilities, and utilities.

3.4 FORMWORK

A. Design, construct, erect, brace, and maintain formwork according to ACI 301.

3.5 EMBEDDED ITEMS

A. Place and secure anchorage devices and other embedded items required for adjoining work attached to or supported by cast-in-place concrete. Use setting drawings, templates, diagrams, instructions, and directions furnished with items to be embedded.

B. When installing new concrete slabs or materials where existing concrete materials had been removed, drill and epoxy dowels of #4 deformed steel reinforcing bars @ 18” on center into existing slabs or beams to avoid movement.

3.6 VAPOR RETARDERS

A. Install, protect, and repair vapor retarders according to ASTM E 1643; place sheets in position with longest dimension parallel with direction of pour.

1. Lap joints 6 inches and seal with manufacturer's recommended adhesive or joint tape.

Page 111: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

MISC. CAST-IN-PLACE CONCRETE & CONCRETE REPAIR 03 30 53 - 5

3.7 STEEL REINFORCEMENT

A. Comply with CRSI's "Manual of Standard Practice" for fabricating, placing, and supporting reinforcement.

1. Do not cut or puncture vapor retarder. Repair damage and reseal vapor retarder before placing concrete.

3.8 JOINTS

A. General: Construct joints true to line with faces perpendicular to surface plane of concrete.

B. Contraction Joints in Slabs-on-Grade: Form weakened-plane sawed contraction joints, sectioning concrete into areas no larger than 100 SF. Cut contraction joints for a depth equal to at least one-fourth depth of concrete thickness. Cut contraction joints as soon as able, once the material has hardened so as not to damage the surface texture or finish.

C. Isolation Joints: Install joint-filler strips at junctions with slabs-on-grade and vertical surfaces, such as column pedestals, foundation walls, grade beams, and other locations, as indicated.

1. Extend joint fillers full width and depth of joint, terminating flush with finished concrete surface, unless otherwise indicated.

3.9 CONCRETE PLACEMENT

A. Ensure substrate or soil below slabs is fully compacted to minimum of 96% modified proctor density and properly prepared for re-installation of concrete and necessary reinforcing and vapor barriers are in place and have been inspected and approved by Agencies Having Jurisdiction prior to placement.

B. Comply with ACI 301 for placing concrete.

C. Do not add water to concrete during delivery, at Project site, or during placement.

D. Consolidate concrete with mechanical vibrating equipment.

3.10 FINISHING FORMED SURFACES

A. Rough-Formed Finish: For areas not in the public view or where maintenance staff will not come into contact with the material on a regular basis. As-cast concrete texture imparted by form-facing material with tie holes and defective areas repaired and patched. Remove fins and other projections exceeding 1/4 inch

B. Rubbed Finish: Apply the following rubbed finish, defined in ACI 301, to smooth-formed finished as-cast concrete where indicated:

1. Smooth-rubbed finish.

Page 112: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

MISC. CAST-IN-PLACE CONCRETE & CONCRETE REPAIR 03 30 53 - 6

3.11 FINISHING UNFORMED SURFACES

A. General: Comply with ACI 302.1R for screeding, restraightening, and finishing operations for concrete surfaces. Do not wet concrete surfaces.

B. Screed surfaces with a straightedge and strike off. Begin initial floating using bull floats or darbies to form a uniform and open-textured surface plane before excess moisture or bleedwater appears on surface.

C. Scratch Finish: Apply scratch finish to surfaces to receive concrete floor topping or mortar setting beds for ceramic or quarry tile, and other bonded cementitious floor finishes, unless otherwise indicated.

D. Float Finish: Apply float finish to surfaces to receive trowel finish, and to floor and slab surfaces to be covered with fluid-applied or sheet waterproofing, fluid-applied or direct-to-deck-applied membrane.

E. Trowel and Fine-Broom Finish: Apply a partial trowel finish, stopping after second troweling, to surfaces where ceramic or quarry tile is to be installed by either thickset or thin-set methods. Immediately after second troweling, and when concrete is still plastic, slightly scarify surface with a fine broom.

F. Nonslip Broom Finish: Apply a nonslip broom finish to surfaces indicated and to exterior concrete platforms, steps, and ramps. Immediately after float finishing, slightly roughen trafficked surface by brooming with fiber-bristle broom perpendicular to main traffic route.

3.12 CONCRETE PROTECTING AND CURING

A. General: Protect freshly placed concrete from premature drying and excessive cold or hot temperatures. Comply with ACI 306.1 for cold-weather protection and with ACI 301 for hot-weather protection during curing.

B. Evaporation Retarder: Apply evaporation retarder to concrete surfaces if hot, dry, or windy conditions cause moisture loss approaching 0.2 lb/sq. ft. x h before and during finishing operations. Apply according to manufacturer's written instructions after placing, screeding, and bull floating or darbying concrete, but before float finishing.

C. Begin curing after finishing concrete but not before free water has disappeared from concrete surface.

D. Curing Methods: Cure formed and unformed concrete for at least seven days by one or a combination of the following methods:

1. Moisture Curing: Keep surfaces continuously moist for not less than seven days with the following materials:

a. Water. b. Continuous water-fog spray.

Page 113: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

MISC. CAST-IN-PLACE CONCRETE & CONCRETE REPAIR 03 30 53 - 7

2. Moisture-Retaining-Cover Curing: Cover concrete surfaces with moisture-retaining cover for curing concrete, placed in widest practicable width, with sides and ends lapped at least 12 inches, and sealed by waterproof tape or adhesive. Cure for not less than seven days. Immediately repair any holes or tears during curing period using cover material and waterproof tape.

3.13 FIELD QUALITY CONTROL

A. Testing Agency: Contractor shall engage a qualified testing agency to perform tests and inspections.

B. Tests: Perform according to ACI 301.

1. Testing Frequency: One composite sample shall be obtained for each day's pour of each concrete mix exceeding 5 cu. yd. but less than 25 cu. yd, plus one set for each additional 50 cu. yd. or fraction thereof.

2. Testing Frequency: One composite sample shall be obtained for each 100 cu. yd. or fraction thereof of each concrete mix placed each day.

3.14 REPAIRS

A. Remove and replace concrete that does not comply with requirements in this Section.

- END OF SECTION 03 30 00 -

Page 114: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

JOINT SEALANTS 07 92 00 - 1

SECTION 07 92 00 - JOINT SEALANTS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Silicone joint sealants. 2. Urethane joint sealants.

1.2 PRECONSTRUCTION TESTING

A. Preconstruction Field-Adhesion Testing: Before installing sealants, field test their adhesion to Project joint substrates. Test joint sealants according to Method A, Field-Applied Sealant Joint Hand Pull Tab, in Appendix X1 in ASTM C 1193 or Method A, Tail Procedure, in ASTM C 1521.

1.3 ACTION SUBMITTALS

A. Product Data: For each joint-sealant product indicated.

B. Samples: For each kind and color of joint sealant required.

1.4 INFORMATIONAL SUBMITTALS

A. Product test reports.

B. Preconstruction field-adhesion test reports.

C. Field-adhesion test reports.

D. Warranties.

1.5 WARRANTY

A. Warranty: Manufacturer's standard form in which Installer agrees to repair or replace joint sealants that do not comply with performance and other requirements specified in this Section within specified warranty period.

1. Warranty Period: One year from date of Substantial Completion.

B. Special Manufacturer's Warranty: Manufacturer's standard form in which joint-sealant manufacturer agrees to furnish joint sealants to repair or replace those that do not comply with performance and other requirements specified in this Section within specified warranty period.

Page 115: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

JOINT SEALANTS 07 92 00 - 2

1. Warranty Period: Twenty-Five years from date of Substantial Completion.

PART 2 - PRODUCTS

2.1 MATERIALS, GENERAL

A. Low-Emitting Interior Sealants: Sealants and sealant primers used inside the weatherproofing system shall comply with the testing and product requirements of the California Department of Health Services' "Standard Practice for the Testing of Volatile Organic Emissions from Various Sources Using Small-Scale Environmental Chambers."

B. Liquid-Applied Joint Sealants: Comply with ASTM C 920 and other requirements indicated for each liquid-applied joint sealant specified, including those referencing ASTM C 920 classifications for type, grade, class, and uses related to exposure and joint substrates.

1. Suitability for Immersion in Liquids. Where sealants are indicated for Use I for joints that will be continuously immersed in liquids, provide products that have undergone testing according to ASTM C 1247.

C. Stain-Test-Response Characteristics: Where sealants are specified to be nonstaining to porous substrates, provide products that have undergone testing according to ASTM C 1248 and have not stained porous joint substrates indicated for Project.

2.2 SILICONE JOINT SEALANTS

A. Mildew-Resistant Silicone Joint Sealant: ASTM C 920.

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. BASF Building Systems. b. Dow Corning Corporation. c. GE Advanced Materials - Silicones. d. Pecora Corporation. e. Polymeric Systems, Inc. f. Sika Corporation; Construction Products Division. g. Tremco Incorporated.

2. Type: Single component (S). 3. Uses Related to Exposure: Nontraffic (NT), based upon the specific location of use.

a. Use sealants specifically listed for use in swimming pools for underwater applications.

2.3 URETHANE JOINT SEALANTS

A. Urethane Joint Sealant: ASTM C 920.

Page 116: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

JOINT SEALANTS 07 92 00 - 3

1. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

a. BASF Building Systems. b. Bostik, Inc. c. Pecora Corporation. d. Polymeric Systems, Inc. e. Sika Corporation; Construction Products Division. f. Tremco Incorporated. g.

2. Type: multicomponent (M). 3. Grade: nonsag (NS). 4. Uses Related to Exposure: Traffic (T).

2.4 JOINT SEALANT BACKING

A. Cylindrical Sealant Backings: ASTM C 1330, Type C (closed-cell material with a surface skin)with a size and density to control sealant depth and otherwise contribute to producing optimum sealant performance.

B. Bond-Breaker Tape: Polyethylene tape or other plastic tape recommended by sealant manufacturer.

2.5 MISCELLANEOUS MATERIALS

A. Primer: Material recommended by joint-sealant manufacturer where required for adhesion of sealant to joint substrates indicated, as determined from preconstruction joint-sealant-substrate tests and field tests.

B. Cleaners for Nonporous Surfaces: Chemical cleaners acceptable to manufacturers of sealants and sealant backing materials.

C. Masking Tape: Nonstaining, nonabsorbent material compatible with joint sealants and surfaces adjacent to joints.

PART 3 - EXECUTION

3.1 PREPARATION

A. Surface Cleaning of Joints: Clean out joints immediately before installing joint sealants to comply with joint-sealant manufacturer's written instructions.

1. Remove laitance and form-release agents from concrete. 2. Clean nonporous joint substrate surfaces with chemical cleaners or other means that do

not stain, harm substrates, or leave residues capable of interfering with adhesion of joint sealants.

Page 117: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

JOINT SEALANTS 07 92 00 - 4

B. Joint Priming: Prime joint substrates where recommended by joint-sealant manufacturer or as indicated by preconstruction joint-sealant-substrate tests or prior experience. Apply primer to comply with joint-sealant manufacturer's written instructions. Confine primers to areas of joint-sealant bond; do not allow spillage or migration onto adjoining surfaces.

C. Masking Tape: Use masking tape where required to prevent contact of sealant or primer with adjoining surfaces that otherwise would be permanently stained or damaged by such contact or by cleaning methods required to remove sealant smears. Remove tape immediately after tooling without disturbing joint seal.

3.2 INSTALLATION

A. Sealant Installation Standard: Comply with recommendations in ASTM C 1193 for use of joint sealants as applicable to materials, applications, and conditions indicated.

B. Install sealant backings of kind indicated to support sealants during application and at position required to produce cross-sectional shapes and depths of installed sealants relative to joint widths that allow optimum sealant movement capability.

1. Do not leave gaps between ends of sealant backings. 2. Do not stretch, twist, puncture, or tear sealant backings. 3. Remove absorbent sealant backings that have become wet before sealant application and

replace them with dry materials.

C. Install bond-breaker tape behind sealants where sealant backings are not used between sealants and backs of joints.

D. Install sealants using proven techniques that comply with the following and at the same time backings are installed:

1. Place sealants so they directly contact and fully wet joint substrates. 2. Completely fill recesses in each joint configuration. 3. Produce uniform, cross-sectional shapes and depths relative to joint widths that allow

optimum sealant movement capability.

E. Tooling of Nonsag Sealants: Immediately after sealant application and before skinning or curing begins, tool sealants according to requirements specified in subparagraphs below to form smooth, uniform beads of configuration indicated; to eliminate air pockets; and to ensure contact and adhesion of sealant with sides of joint.

1. Remove excess sealant from surfaces adjacent to joints. 2. Use tooling agents that are approved in writing by sealant manufacturer and that do not

discolor sealants or adjacent surfaces. 3. Provide concave joint profile per Figure 8A in ASTM C 1193, unless otherwise

indicated. 4. Ensure depth of sealant is no greater than 60% of the width of the joint being sealed.

F. Clean off excess sealant or sealant smears adjacent to joints as the Work progresses by methods and with cleaning materials approved in writing by manufacturers of joint sealants and of products in which joints occur.

Page 118: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

JOINT SEALANTS 07 92 00 - 5

3.3 FIELD QUALITY CONTROL

A. Field-Adhesion Testing: Field test joint-sealant adhesion to joint substrates as follows:

1. Extent of Testing: Test completed and cured sealant joints as follows:

a. Perform 2 tests for the first 100 feet of joint length for each kind of sealant and joint substrate.

b. Perform 1 test for each 250 feet of joint length thereafter or 1 test per each floor per elevation.

2. Test Method: Test joint sealants according to Method A, Field-Applied Sealant Joint Hand Pull Tab, in Appendix X1 in ASTM C 1193 or Method A, Tail Procedure, in ASTM C 1521.

B. Evaluation of Field-Adhesion Test Results: Sealants not evidencing adhesive failure from testing or noncompliance with other indicated requirements will be considered satisfactory. Remove sealants that fail to adhere to joint substrates during testing or to comply with other requirements. Retest failed applications until test results prove sealants comply with indicated requirements.

3.4 JOINT-SEALANT SCHEDULE

A. Joint-Sealant Application: Joints in horizontal traffic surfaces.

1. Joint Locations:

a. Control and expansion joints in brick pavers. b. Isolation and contraction joints in cast-in-place concrete slabs. c. Joints between plant-precast architectural concrete paving units. d. Joints in paving units, including steps. e. Tile control and expansion joints. f. Joints between different materials listed above.

2. Joint Sealant: Urethane. 3. Joint Sealant: Pourable 4. Joint-Sealant Color: As selected by Architect from manufacturer's full range of colors.

B. Joint-Sealant Application: Joints in vertical surfaces and horizontal nontraffic surfaces.

1. Joint Locations:

a. Construction joints in cast-in-place concrete. b. Joints between plant-precast architectural concrete units. c. Control and expansion joints in unit masonry. d. Control and expansion joints in ceilings and other overhead surfaces. e. Joints between different materials listed above.

2. Joint Sealant: Urethane. 3. Joint Sealant: Non-Sag. 4. Joint-Sealant Color: As selected by Architect from manufacturer's full range of colors.

Page 119: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

JOINT SEALANTS 07 92 00 - 6

C. Joint-Sealant Application: Joints in vertical surfaces and horizontal nontraffic surfaces.

1. Joint Locations:

a. Construction joints in cast-in-place concrete. b. Joints between plant-precast architectural concrete units. c. Control and expansion joints in unit masonry. d. Joints between metal panels. e. Perimeter joints between materials listed above and frames of doors, windows,

louvers, or cover plates. f. Control and expansion joints in ceilings and other overhead surfaces. g. Joints between different materials listed above. h. Other joints as indicated.

2. Joint Sealant: Silicone. 3. Joint Sealant: Non-Sag. 4. Joint-Sealant Color: White, Paintable.

D. Joint-Sealant Application: Mildew-resistant interior joints in vertical surfaces and horizontal nontraffic surfaces.

1. Joint Sealant Location:

a. Joints between plumbing fixtures and adjoining walls, floors, and counters. b. Tile control and expansion joints where indicated. c. Other joints as indicated.

2. Joint Sealant: Silicone. 3. Joint Sealant: Non-Sag 4. Joint-Sealant Color: As selected by Architect from manufacturer's full range of colors.

- END OF SECTION 07 92 00 -

Page 120: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovation

SIGNAGE 101400 - 1

SECTION 101400 - SIGNAGE

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following: 1. Panel signs.

a. Provide rules and regulations signage as required by code.

1.2 DEFINITIONS

A. ADA-ABA Accessibility Guidelines: U.S. Architectural & Transportation Barriers Compliance Board's "Americans with Disabilities Act (ADA) Accessibility Guidelines for Buildings and Facilities; Architectural Barriers Act (ABA) Accessibility Guidelines."

1.3 ACTION SUBMITTALS

A. Product Data: For each type of product indicated.

B. Shop Drawings: Show fabrication and installation details for signs.

1. Show sign mounting heights, and accessories. 2. Provide message list, typestyles, graphic elements, and layout for each sign.

1.4 QUALITY ASSURANCE

A. Regulatory Requirements: Comply with applicable provisions in Florida Administrative Code 64E.

PART 2 - PRODUCTS

2.1 MATERIALS

A. Acrylic Sheet: ASTM D 4802, Category A-1 (cell-cast sheet), Type UVA (UV absorbing).

B. Applied Vinyl: Die-cut characters from vinyl film of nominal thickness of 3 mils with pressure-sensitive adhesive backing, suitable for exterior applications.

Page 121: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovation

SIGNAGE 101400 - 2

2.2 PANEL SIGNS

A. Available Manufacturers: Subject to compliance with requirements, manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:

B. Manufacturers: Subject to compliance with requirements, provide products by one of the following:

1. ACE Sign Systems, Inc. 2. Advance Corporation; Braille-Tac Division. 3. Allen Industries Architectural Signage 4. Allenite Signs; Allen Marking Products, Inc. 5. APCO Graphics, Inc. 6. ASI-Modulex, Inc. 7. Best Sign Systems Inc. 8. Bunting Graphics, Inc. 9. Fossil Industries, Inc. 10. Gemini Incorporated. 11. Grimco, Inc. 12. Innerface Sign Systems, Inc. 13. InPro Corporation 14. Matthews International Corporation; Bronze Division. 15. Mills Manufacturing Company. 16. Mohawk Sign Systems. 17. Nelson-Harkins Industries. 18. Seton Identification Products. 19. Signature Signs, Incorporated. 20. Supersine Company (The)

C. Interior Panel Signs: Provide smooth sign panel surfaces constructed to remain flat under installed conditions within a tolerance of plus or minus 1/16 inch (1.5 mm) measured diagonally from corner to corner, complying with the following requirements: 1. Acrylic Sheet: 0.080 inch (2.03 mm) thick. 2. Edge Condition: Beveled. 3. Corner Condition: Rounded. 4. Mounting: Unframed.

a. Wall mounted with stainless steel anchors. b. Manufacturer's standard anchors for substrates encountered.

5. Color: As selected by Owner from manufacturer's full range...

D. Applied Vinyl: Die-cut characters from vinyl film of nominal thickness of 3 mils (0.076 mm) with pressure-sensitive adhesive backing. Apply copy to exposed face of panel sign or glass

1. Panel Material: Opaque acrylic sheet.

E. Colored Coatings for Acrylic Sheet: For copy [and] [background] [and frame] colors, provide colored coatings, including inks, dyes, and paints, that are recommended by acrylic manufacturers for optimum adherence to acrylic surface and are UV and water resistant for [five] years for application intended.

Page 122: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovation

SIGNAGE 101400 - 3

1. Color: As selected by Owner from manufacturer's full range.

2.3 ACCESSORIES

A. Anchors and Inserts: Provide nonferrous-metal or hot-dip galvanized anchors and inserts for exterior installations and elsewhere as required for corrosion resistance. Use toothed steel or lead expansion-bolt devices for drilled-in-place anchors. Furnish inserts, as required, to be set into concrete or masonry work.

2.4 FABRICATION

A. General: Provide manufacturer's standard signs of configurations indicated. 1. Conceal fasteners if possible; otherwise, locate fasteners where they will be

inconspicuous.

2.5 ACRYLIC SHEET FINISHES

A. Colored Coatings for Acrylic Sheet: For copy and background colors, provide colored coatings, including inks, dyes, and paints, that are recommended by acrylic manufacturers for optimum adherence to acrylic surface and that are UV and water resistant for five years for application intended.

PART 3 - EXECUTION

3.1 INSTALLATION

A. Locate signs and accessories where indicated, using mounting methods of types described and complying with manufacturer's written instructions.

1. Install signs level, plumb, and at heights indicated, with sign surfaces free of distortion and other defects in appearance.

2. Interior Wall Signs: Install signs on walls adjacent to latch side of door where applicable. Where not indicated or possible, such as double doors, install signs on nearest adjacent walls. Locate to allow approach within 3 inches (75 mm) of sign without encountering protruding objects or standing within swing of door.

B. Wall-Mounted Signs: Comply with sign manufacturer's written instructions except where more stringent requirements apply. 1. Shim Plate Mounting: Provide 1/8-inch- (3-mm-) thick, concealed aluminum shim plates

with predrilled and countersunk holes, at locations indicated, and where other mounting methods are not practicable. Attach plate with fasteners and anchors suitable for secure attachment to substrate. Attach panel signs to plate using method specified above.

Page 123: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovation

SIGNAGE 101400 - 4

2. Mechanical Fasteners: Use non-removable mechanical fasteners placed through

predrilled holes. Attach signs with non-corrosive fasteners and anchors suitable for secure attachment to substrate as recommended in writing by sign manufacturer.

3. Signs Mounted on Glass: Provide matching opaque plate on opposite side of glass to conceal mounting materials.

- END OF SECTION 101400 -

Page 124: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

Swimming Pool and Pool Equipment

13 11 00-1

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

SECTION 13 11 00

SWIMMING POOLS PART 1 - GENERAL

1.01 SUMMARY OF WORK

A. Introduction

1. Furnish all labor, materials, equipment and services necessary to remodel the following: (1) recreation pool. This work shall include the demolition and installation of new pool finishes as well as all products listed in Part 2 of Section 13 11 00.

B. Work included in this section

1. It is the intent of this section to place the entire responsibility for the construction remodel of

the pool under one vested CONTRACTOR. Under this section the Swimming Pool Contractor will provide but is not necessarily limited to the following:

a. Provide, erect and maintain all necessary barricades, signs, lights and flares for pool

construction to protect workers and the public.

b. Provide all equipment and services required for erection and delivery onto the premises of any equipment or apparatus furnished. Remove equipment from premises when no longer required.

c. Layout, excavate, remove from the construction site, replace and grade materials as

required to complete the work described in this section.

d. Provide and maintain proper shoring and bracing for existing utilities, sewers and building foundations where required in order to complete the work.

e. Remove existing water from pool prior to renovations. Provide pre-treatment and

pumping systems to enable water to be disposed of on grade and flow to local storm water drainage systems.

f. Provide all electrical conduit, wiring, junction boxes etc. to all low voltage pool equipment

and underwater lighting per Code. (Low voltage is considered less than 110 V.)

g. Ground and bond all new pool structures, fittings and equipment in accordance with Article

680 of the N.E.C. Test and verify that the system electrical ground is true and solid. Provide certification to this effort.

Page 125: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

Swimming Pool and Pool Equipment

13 11 00-2

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

h. Obtain permits, inspections, and approvals of all wiring including grounding and bonding of all metal components associated with the pool in accordance with Local, State and National Electrical Codes.

i. Confirm all electrical conduits that penetrate the pool shell are watertight and installed per

N.E.C. Article 680.

j. Furnish and install all necessary piping and valving required for a proper and complete job, and to properly control the operations of the pool and ancillary systems and to enable logical and safe repairs in the future.

k. Furnish and install a new finish in the pool with a slip resistant surface. l. Furnish and install specialty tile for the perimeter water line tile, depth markings and warning

signs, lane lines and all other tile installation within the pool structure.

m. Replace all rusted and deteriorated deck and pool-mounted anchors, sockets, and inserts for the pool.

n. Furnish and install deck finish beyond perimeter tile band as indicated on the drawings.

o. Provide chlorine resistant caulking (sealant) and backer rod on pool decks.

p. Provide for the storage of all pool related equipment, materials and systems. All items

are the responsibility of the CONTRACTOR until accepted by Owner. q. Provide all safety and notification signage required by Agencies Having Jurisdiction over

the facility, as outlined in the Florida Administrative Code.

r. Obtain final acceptance by jurisdictional health department(s).

s. Start, test, calibrate and adjust all mechanical equipment, electrical equipment, recirculation, chemical, and other supplied systems including deck, loose, maintenance, and safety equipment. Instruct the Owner's representative in the systems operation and maintenance as described herein.

1.03 QUALITY ASSURANCE

A. The specifications describe Work for one (1) swimming pool system that shall be utilized for

recreational use. Certain technical aspects of the design are common only to pool systems planned for public use. Understanding these aspects, their functions and interaction through experience is vital to completing a successful operating system.

B. Contractor shall be a Swimming Pool Contractor, currently licensed by the State of Florida. 1. Contractor shall be certified/licensed by the Pool Finish Manufacturer to install the pool finish

and shall have been performing satisfactory installations for a minimum of (5) years. 1.04 REGULATORY AGENCY REQUIREMENTS AND ENGINEERING SERVICES

A. The entire system shall be designed and installed to meet all national and local codes and be in

compliance with applicable sections of the American National Standards Institute / National Spa

Page 126: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

Swimming Pool and Pool Equipment

13 11 00-3

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

and Pool Institute (ANSI /NSPI-1 2003).

B. The system shall comply with all necessary approvals obtained by the Contractor from local and state regulatory agencies governing the design and construction of public swimming pools.

C. The Contractor shall give all necessary notices, obtain all permits and pay all government fees, and

other costs in connection with his work; file all necessary drawings, prepare all documents and obtain all necessary approvals of governmental departments having jurisdiction; obtain all required certificates of inspection for his work and deliver same to the Owner before request for acceptance and final payment for the work.

D. The Contractor shall include in the work, without extra cost to the Owner, any labor,

materials, services, apparatus, professional engineering services or drawings in order to comply with all applicable laws, ordinances, rules and regulations.

E. All water discharged from pool for the execution of this Work shall be to the storm water

drainage system and shall meet the water quality guidelines as established for disposal herein. 1.05 CONTRACTOR’S ALTERNATE PROPOSALS

A. Contractor shall submit his bid to the owner based on materials, equipment and methods as

specified in this Section. No substitutions of material will be allowed.

B. It is the intent of the contract documents to encourage competition. The base proposal must be on furnishing the construction methods and equipment as specified. Any proposed system substitution must have prior written approval by the Owner.

C. All proposed substitutions of specified construction methods and equipment shall include a

complete submittal incorporating all proposed changes. The Contractor shall provide a list of at least ten (10) satisfactory installations comparable to this project that have been manufactured and installed under the manufacturer's current legal name. Submit a list of such projects with the name, address and current telephone number of the Owner on the bid date.

D. Any changes or modifications to the Contract Documents that are not authorized by the Owner

shall be the sole responsibility of the Contractor. 1.07 SUBMITTALS

A. Include complete product data indexed, tabbed, and referenced to specifications with 8

½” x 11” cover sheet covering: 1. Overflow System

2. Pumping Equipment

3. Filtration Equipment

4. Recirculation Fittings

5. Piping Systems

6. Chemical Treatment System

Page 127: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

Swimming Pool and Pool Equipment

13 11 00-4

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

7. Water Level Controller

8. Inserts and Anchor Sockets

9. Deck Equipment

10. Maintenance Equipment

11. Finishes

12. Underwater Lights

13. Pool Tile

14. Joint Sealants

B. Drawings: Provide complete Drawings prepared by a Professional Engineer licensed in the State Of

Florida to show replacement of filtration and treatment systems as required by Florida Administrative Code 64-E9.

1.08 PRODUCT DELIVERY, STORAGE, AND HANDLING

A. Deliver material in manufacturer's original, unopened containers and crates with all labels intact

and legible.

B. Deliver materials in sufficient time and quantity to allow continuity of work and compliance with approved construction schedule.

C. Handle materials in a manner to prevent damage.

D. Store all materials on clean raised platforms with weather protective coverings. Provide

continuous protection of materials against damage or deterioration.

E. Remove damaged materials from site. 1.09 WARRANTIES

A. The CONTRACTOR warrants to the Owner that materials and equipment furnished under

the contract will be of good quality and new unless otherwise required or permitted by the contract documents, that the work will be free from defects not inherent in the quality required or permitted, and that the work will conform with the requirements of the contract documents. Work not conforming to these requirements, including substitutions not properly approved and authorized may be considered defective. The CONTRACTOR'S warranty may exclude remedies for damage or defect caused by abuse, improper or insufficient maintenance, improper operations, modifications not executed by the CONTRACTOR or improper wear and tear under normal use. If required by the Owner, the CONTRACTOR shall furnish satisfactory evidence as to the kind and quality of materials and equipment. All warranties shall be for a period of one year from the date of substantial completion or the owner begins using the pool unless otherwise specified.

B. The CONTRACTOR shall agree to repair or replace any defective or non-complying work

Page 128: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

Swimming Pool and Pool Equipment

13 11 00-5

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

at no cost to the Owner upon written notification from the Owner within the warranty period. Pro-rated warranties are not acceptable.

C. Submit all warranties covering, but not limited to the following:

1. All pool deck equipment and accessories against defects in material, manufacturer and

installation for a period of one (1) year.

2. Defects in material, workmanship, and installation of the pool piping system for a period of three (3) years.

1.10 START-UP CHEMICALS AND WATER SUPPLY

A. The CONTRACTOR shall provide the necessary plant equipment so that the temperature of

fill water will be within plus or minus 10 degrees of the ambient air and/or the pool structure at the time of filling. Extreme caution is urged if the temperature variance is greater than 10 degree F.

B. The CONTRACTOR shall provide the necessary chemicals and to adjust and balance the water

chemistry in the pools to the following levels:

pH 7.4 - 7.6 Calcium Hardness 200 - 400 PPM

Total Alkalinity (Sodium Hypochlorite) 80 - 120 PPM Langelier saturation index -0.3 - +0.3

C. The CONTRACTOR shall maintain the chemical balance of the pool water (including the cost of

all chemicals required) until the pool and mechanical system(s) are fully operational and accepted by the Owner.

D. Chemicals to be provided to the Owner shall include those required by the chemical feed systems

installed. PART 2 - PRODUCTS

2.01 OVERFLOW SYSTEM

A. It is the intent of the specifications that the perimeter overflow system and surface cleaning

be maintained under all conditions of normal operation and that no water be discharged to waste except when cleaning the filters or emptying the pool.

B. The equalizer piping and fittings shall be sized to meet the capacity requirements of the filter and

pump and shall be in no case less than 2 inches in diameter. The equalizer float valve assembly shall remain tightly closed under normal operating conditions but will automatically open when the water level drops below the lowest weir operating level.

1. The equalizer fitting shall be a design to reduce the possibility of hair entrapment in the

fitting.

2. Pool skimmers shall be Sta-Rite Model U-3 #08650-1403 white,or equal. Hayward Model SP108 2-1 skimmer is acceptable. Equalizer suction fittings shall have a Federal Pool and Spa Safety Act (ASME / ANSI A112.19.8-2007) compliant cover

Page 129: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

Swimming Pool and Pool Equipment

13 11 00-6

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

manufactured by Aquastar, model #AV9101, Pentair model Starguard, or approved equal. 2.02 PUMPING EQUIPMENT

1. Recirculating Pumps (2) – Pentair EQ series variable speed, 10 HP, 208volt, 3 phase, or

equivalent. Mount on vibration isolators and Inertia Pads, with all necessary connections, new valves, check valves, and flanged fittings, etc.

2. Install new pumps with Variable Frequency Drive systems, interlocked and integrated with existing DCM5 control system.

a. Set pumps to run at peak efficiency.

3. Integrate pumps and motor drives with existing control system.

2.03 FILTRATION EQUIPMENT

A. The filter system shall be converted to utilize multiple high rate pressure sand filter

tanks, sized to meet existing pool size, and purification and regulatory requirements. 1. Remove existing DE grids from collector tank. 2. Acid-wash interior of existing collector tank. 3. Remove any loose materials or surfaces with hollowing backing. 4. Repair substrate of collector tank. 5. Apply new finish to collector tank to match finish being installed on pool walls. 6. Remove existing concrete tank supports from Equipment Storage Room and dispose of

debris. 7. Set new housekeeping pads/filter pads for mounting new filters. 8. Install new high-rate sand filtration systems; minimum (2) Stark S Series filters, sized for

pool demands. 9. Integrate automatic backwash with system controlled by pool system control system 10. Install manual backwash bypass system 11. Install 6” sight glass spool and influent, effluent gauges. 12. Install piping and supports as required for full and complete installation.

2.04 OZONE TREATMENT SYSTEM A. Install in-line ozone treatment system after filtration and treatment systems.

1. Size system for water flow and quantity. 2. Provide electrical hook-ups and connections. 3. Connect to and integrate with existing DCM5 control system.

2.05 SALT SALINE CHLORINE GENERATION SYSTEM (ALTERNATE BID #2) A. Install in-line salt saline chorine system after filtration and treatment systems.

1. Size system for water flow and quantity (approx 24 lbs of chlorine per day) a. Provide multiple chorine generators installed in series b. Provide (4) Hayward Saline C6.0 or equivalent

2. Provide electrical hook-ups and connections. 3. Connect to and integrate with existing DCM5 control system.

Page 130: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

Swimming Pool and Pool Equipment

13 11 00-7

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

a. Install new gold-tipped ORP probe and PPM probe and connect to controller as required.

2.06 RECIRCULATION FITTINGS

A. Install new VGB code-compliant main drain frames and grate covers at existing

concrete sumps.

B. Wall inlet fittings shall be cycolac directional inlet by Hayward, Sta-Rite, or Swimtime.

C. Static water line inlet fitting for the automatic water level controller shall be provided consisting of a cycolac body, grate and construction shield. The body shall have a 1-1/2 inch solvent weld connection and provided with an integral molded "knock-out" membrane to facilitate line pressure testing. The static water line inlet fitting shall be a Hayward SP-1026 mounted in a Hayward Model SP-1022S or equal.

2.07 PIPING SYSTEMS

A. General

1. Provide all recirculating piping between the pool and equipment room.

2. Provide all necessary pipe supports and support systems required to support all associated piping and valves.

3. Provide all other tubing, conduit, or piping associated with equipment specified herein.

Coordinate with other trades.

B. Pipes

1. Pipe routing as shown and detailed on the contract drawings is diagrammatic only and is not intended to show minor details or exact locations of piping systems. Installation is required to be adjusted to accommodate interference and adjustments anticipated and encountered. Pipe sizes on plans refer to nominal inside diameter of the pipe.

2. All PVC swimming pool piping shall be NSF approved and conform to the

requirements of ASTM D-1785.

3. All PVC pipes and fittings shall be the product of one manufacturer. Approved manufacturers of PVC piping are Eslon, Harvel, and Chemtrol or approved equal.

4. Swimming pool piping above the floor in the equipment room shall be Schedule 40

PVC.

5. Swimming pool piping below the deck shall be NSF approved, Schedule 80 PVC.

6. All below grade swimming pool piping can be backfilled with native granular material free of ice, clay, debris, organic matter, and rocks larger than 4" across their greatest dimension, and per recommendations indicated in the project geotechnical report.

7. All materials shall be installed by workmen thoroughly skilled in their trades and all work

Page 131: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

Swimming Pool and Pool Equipment

13 11 00-8

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

shall present a neat and mechanical appearance when complete. The CONTRACTOR, at no additional expense to the Owner, shall replace or correct any work not judged acceptable by the Owner’s or their consultants.

8. No installation shall be made that will provide a cross-connection or interconnection between

a distributing supply for drinking purposes and the swimming pool, or between the pool and a sanitary or storm water sewer system that will permit a backflow of water into the pool water system.

9. All piping shall be hydrostatically (water) pressure tested for leaks before and after

backfilling to guarantee water tightness. Pneumatic (air) pressure test not allowed.

10. All mechanical equipment to be connected into the recirculation piping system shall be done so using flanged or union connections.

11. Provisions shall be made to purge all pipes in the system.

2.08 CHEMICAL TREATMENT SYSTEM - EXISTING

A. EXISTING (Liquid Chlorine) feed system.

B. EXISTING pH Buffering System (Muriatic Acid) – hand supplied.

2.09 WATER LEVEL CONTROLLER A. In-Deck Water Level Controller. Provide a make-up water solenoid valve, normally closed,

stainless steel fitted, bronze body, 115 VAC slow closing type. Size to pipe. Such as Asco, OAE.

2.10 INSERTS AND ANCHOR SOCKETS

A. Sockets and anchors shall be provided as stainless steel or cast bronze for swimming pool

accessories and set prior to placing any concrete. The CONTRACTOR shall confirm compatibility of deck equipment and deck anchors with the deck equipment manufacturer. All anchors or sockets shall be furnished with flush closure caps and escutcheons with set screws where indicated. Escutcheons shall be of the keyhole or oblong shape, similar to the Kiefer CPB escutcheon, product #700303, or equal.

1. Anchor sockets for all railings and grab rails shall be of the wedge type, cast of grade

300 series stainless steel, 6 inches in depth and made to receive 1.50 inch OD tubing as manufactured by Spectrum Products, part number 24090 or equal. The wedge shall be cast brass (85-5-5-5), incorporate a stainless steel tightening bolt and flat washer, and be designed as the sacrificial element to the anchor system. All metallic components shall be passivated, in compliance with ASTM A967-99, incorporating organic acid passivation techniques for maximum corrosion resistance.

2.11 DECK EQUIPMENT

A. Grab rails and ladders shall be furnished and installed as required in existing locations and quantities

as required by Agencies Having Jurisdiction over the Pool. Grab rails shall be fabricated of one continuous length of polished and buffed tubing. The tubing shall be ASTM-A-554 grade 304L

Page 132: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

Swimming Pool and Pool Equipment

13 11 00-9

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

stainless steel, 1.50 inch OD x .120 inch wall thickness, polished and buffed to 320 grit finish and shall be passivated, in compliance with ASTM A967-99, incorporating organic acid passivation techniques for maximum corrosion resistance. All bends shall be smooth and free of wrinkles. Grab rails shall be pretzel bend as manufactured by Spectrum Products, SR Smith, Paragon Aquatics similar to Spectrum Cisco, part no. 23437, or approved equal.

2.12 POOL TILE

A. Pool Tile – Replace all existing tile with new tile. a. Install tile around existing gutter lip to provide a maximum ¼” variation around

perimeter of pool, as required by Code. b. Install factory-glazed Depth Marker tiles, as required by Code. c. Install factory-glazed “No Diving” tiles, using international signage graphics, as

required by Code. d. Install new Lap Lane tile and Target tile on walls to match existing lane

configurations. e. Install other tiles as required by Code and by Best Practices. f. Provide non-slip tiles on horizontal surfaces. g. Provide smooth-glazed tiles at water edge surfaces. h. All tile shall be commercial grade, porcelain body. i. Install tile using current TCA Installation Guidelines and systems (#P601TB for thin-

set applications and #PB601MB for Mud Bed applications) i. Follow ANSI A108.5 for tile installation specifications.

ii. Follow ANSI A108.6 for Cementitious Grout iii. Provide movement joints at 8’ – 12’ on center (TCA system EJ171F)

j. Install Flexible sealant between tile and adjacent, dis-similar surfaces. i. Utilize sealants meeting ASTM C920, suitable for pool applications.

2.13 POOL FINISHES

A. “Hydrazzo ®” marble-cement plaster by Aquavations shall be included as the Base Bid.

1. Description: “Hydrazzo ®” finish shall be a blend of selected quartz aggregates and fortified

white Portland cement. Color: white, utilizing manufacturer’s standard color mixes.

2. Surface Preparation: Pool surface must be free of dirt, oil, grease or other foreign materials. Prepare surface as required to properly accept new finish.

3. Mixing: Thoroughly mix finish to a homogeneous lump-free consistency, following

manufacturers instructions.

4. Application: Finish shall be applied to a uniform thickness of 3/8” to 1/2” over the entire surface. The walls shall be scratch-coated followed by a finish coat. Material applied to the floor after the walls have been applied shall be accelerated to assure uniform setting time throughout the pool surface.

a. Provide logical and clean stopping points where finish cannot be completed in one days work. Make adequate provisions to allow for continuation of Work without visible or noticeable seams or joints.

5. Manufacturers Assurance: All bidders shall be prepared to submit a performance bond for their work.

Page 133: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

Swimming Pool and Pool Equipment

13 11 00-10

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

6. Warranty: All applicators must provide a minimum of one (1) year warranty for application

and workmanship additional to the manufactures warranty for product.

a. All bidders must also submit material safety data sheets (MSDS) and product reference specifications prior to installation.

B. “Pebble-Fina®” quartz-cement plaster by Pebble Technology Inc. shall be included in Alternate Bid #1.

1. Description: Pebble-Fina® finish shall be a blend of selected quartz aggregates and fortified

white Portland cement. Color: white, from manufacturer’s standard colors.

2. Surface Preparation: Pool surface must be free of dirt, oil, grease or other foreign materials. Prepare surface as required to properly accept new finish.

3. Mixing: Thoroughly mix finish to a homogeneous lump-free consistency, following

manufacturers instructions.

5. 4. Application: Finish shall be applied to a uniform thickness of 3/8” to 1/2” over the entire surface. The walls shall be scratch-coated followed by a finish coat. Material applied to the floor after the walls have been applied shall be accelerated to assure uniform setting time throughout the pool surface.

a. Provide logical and clean stopping points where finish cannot be completed in one days work. Make adequate provisions to allow for continuation of Work without visible or noticeable seams or joints.

5. Manufacturers Assurance: All bidders shall be prepared to submit a performance bond for their work.

6. Warranty: All applicators must provide a minimum of one (1) year warranty for application

and workmanship additional to the manufactures warranty for product.

C. All bidders must also submit material safety data sheets (MSDS) and product Pool Plaster, Reference specifications.

2.14 UNDERWATER LIGHTS

A. Underwater lights shall be equivalent to 500 watts of incandescent light and provided by the

CONTRACTOR. Pool lights shall be UL listed and in the quantities shown and as detailed in the construction drawings and as described in these specifications. Coordinate for proper installation. Refer to the drawings for quantities and locations.

B. The lights shall be 120VAC or 12VAC, 70 watts LED-type, and equivalent to 440 watts of

incandescent light. Fixture housing shall be stainless steel construction with minimum wall thickness of 0.020 inch per UL 676 underwater pool lighting standard. The niche shall be stainless steel with cast brass mounting ring or PVC plastic with stainless steel mounting ring. Brass construction pressure grounding lug on interior and exterior services. Lens shall be 8-3/8 diameter clear tempered heat resistant glass. Gasket to be single-piece "U" shaped santoprene or silicone. Fasteners shall be silicon-bronze or stainless steel. The light fixture shall be supplied with a #16-3 STW (120V) or 12-3 SJTW (12V) submersible cord with ground wire

Page 134: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

Swimming Pool and Pool Equipment

13 11 00-11

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

positively grounded inside the fixture. Cord entrance shall be a watertight seal and epoxy encapsulated. Light fixture to be IntelliBrite White LED series (5000 deg-K) by Pentair Commercial Pool and Aquatics or equal. Cord length as required.

C. Junction boxes shall be furnished in the quantities required and shall be located at least 8”

above the pool coping and 5' from the pool edge. Refer to the Electrical drawings. Cord length shall be sufficient to run from fixture to the junction box with sufficient cable in the niche to re-lamp the fixture on the deck. The conduit from the niche to the junction box shall be sealed and hydrostatically pressure tested for leaks before and after backfilling to guarantee water tightness.

2.15 POOL CONCRETE BEAM

A. Clean and repair the existing concrete perimeter beam.

a. Remove all existing tile on beam and replace where required to comply with current codes.

b. Patch cementitious plaster to match existing adjacent surfaces. c. Provide Alternate cost #3 to coat existing beam with new, integral color cementitious

coating over existing. 2.16 POOL HEAT EXCHANGER - EXISTING

A. The existing Heat Exchanger shall be re-used. Make connections thereto as required using existing piping. Install new valves and fittings as required to control water flow and to facilitate maintenance.

PART 3 - EXECUTION

3.01 EXISTING CONDITIONS, INSPECTION AND PREPARATION

A. Carefully examine all of the contract documents for requirements that affect the work of this section. Prior to starting any work, notify the Owner of defects requiring correction. Do not start work until conditions are satisfactory.

B. Protect all materials and work from damage while completing the work in this section. 3.02 REMOVAL OF EXISTING SYSTEMS AND MATERIALS

A. Remove existing equipment that is not to be re-used. Dispose of equipment off site; recycling or repurposing is desired wherever possible. Credits or Rebates for recycling of materials shall be credited back towards the Project.

B. Remove existing water from pool by pumping water to grade and allowing flow to local stormwater drainage systems.

a. Test and Pre-treat water as required to adjust water chemistry to within the parameters listed below in order to discharge into the environment:

i. pH: minimum 6.0 maximum 8.5 ii. Disolved Oxygen minimum 5.0 maximum n/a mg/L

iii. Chlorine (Total Residual): minimum 0.0 maximum 0.04 mg/L iv. Specific Conductance: minimum 0.0 maximum 1275 umhos/cm

Page 135: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

Swimming Pool and Pool Equipment

13 11 00-12

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

v. Total Alkalinity minimum 20 not listed mg/L b. Provide testing of water being discharged at a rate of 1 test per 50,000 gal. c. Route discharge so no adverse washouts or erosion occurs. Install silt fencing or filter

cloth where required to maintain existing grade conditions. C. Hydroblast or sandblast existing pool finishes as required to remove previous finish containing

fiberglass. a. Protect existing adjacent surfaces as required to ensure existing finishes or surfaces to

remain are not damaged.

3.03 PIPING INSTALLATION

A. General

1. Provide and erect, according to the best practices of the trade, all piping shown on the engineering drawings provided for permitting and required for the complete installation of these systems. The piping shown on the drawings shall be considered as diagrammatic in indicating the general run and connections, and may or may not in all parts be shown in its true position. The piping may have to be off set, lowered or raised as required or as directed at the site. This does not relieve the CONTRACTOR from responsibility for the proper erection of the systems or piping in every respect suitable for the work intended as described in the specifications and approved by the Owner. In the erection of all piping, it shall be properly supported and proper provisions shall be made for expansion, contraction and anchoring of piping. All piping shall be cut accurately for fabrication to measurements established at the construction site. Pipe shall be worked into place without springing and/or forcing, properly clearing all windows, doors, and other openings and equipment. Cutting or other weakening of the building structure to facilitate installation will not be permitted. All pipes shall have burrs and/or cutting slag removed by reaming or other cleaning methods in strict accordance with the manufacturer's instructions. All changes in direction shall be made with fittings. All open ends of pipes and equipment shall be properly capped or plugged to keep dirt and other foreign materials out of the systems. Plugs of rags, wool, cotton waste or similar materials may not be used in plugging. All piping shall be arranged so as not to interfere with removal and maintenance of equipment, filters or devices, and so as not to block access to manholes, access openings, etc. Flanges or unions as applicable for the type of piping specified shall be provided in the piping at connections to all items of equipment. All piping shall be installed to ensure noiseless circulation. All valves and specialties shall be so placed to permit easy operation and access.

B. Pipe Hangers and Supports

1. Pipes shall be adequately supported by pipe hangers and supports as required.

C. Piping Installation

1. Trench bottoms shall be smooth and free of rocks and debris. If the trench is dug in ledge rock, hardpan or where large boulders are not removed, place 3 inches of sand or compacted fine-grained soil below pipe. Pipe must be supported over its entire length with firm, stable material. Blocking may not be used to change pipe grade or provide intermittent support over low sections in the trench. Surround the pipe with backfill with a particle size of 1-1/2 inch or less and in accordance with the project geotechnical report. Compact in layers not to exceed 6 inches with vibratory method. Follow installation methods of ASTM D2774

Page 136: BUILDING CODE ADMINISTRATION PROGRAMusfweb2.usf.edu/Bids/bid web/2013-2014 Bids/14-15... · The Contractor shall furnish the Owner with a State of Florida 100% Labor and Materials

Swimming Pool and Pool Equipment

13 11 00-13

University of South Florida USF Campus Facilities Planning and Construction Swimming Pool and Pool Equipment Renovations

"Underground Installation of Thermoplastic Pressure Piping".

D. Flushing, Draining and Cleaning Pipe Systems

1. The CONTRACTOR shall flush out all water systems with water before placing them in operation. Other systems shall be cleaned by using compressed air or nitrogen. After systems are in operation and during the test period, all strainer screens shall be removed and thoroughly cleaned.

E. Expansion and Contraction

1. The CONTRACTOR shall make all necessary provisions for expansion and

contraction of piping with offsets, loops, flexible connections and anchors as required to prevent undue strain. The CONTRACTOR shall provide shop drawings for proposed method and arrangement for control of expansion and contraction of piping.

3.03 EQUIPMENT AND SYSTEMS INSTALLATION

A. The CONTRACTOR shall assemble and install all equipment, special parts and accessories as shown on pool drawings, specifications and shop drawings of the equipment suppliers.

B. The CONTRACTOR shall furnish all anchors and inserts to be imbedded in the deck

including all fittings, inserts and structure sleeves and required anchorage as shown on the plans and as indicated in this section of the specifications. Equipment shall be set true and plumb, using factory jigs where available. Removable equipment items shall be easily removable from anchors and shall fit without noticeable wobble.

C. The CONTRACTOR shall install all equipment and systems in accordance with

manufacturer's directions. Equipment shall all be assembled and in place for final observation.

D. All items necessary to complete this section are shown on the plans or described in the specifications including items that may be purchased by the Owner. Items are detailed and specified as a guide for dimensional purposes. The CONTRACTOR must make provisions accordingly and submit shop drawings and submittals based on that data.

3.04 CONCLUSION

A. It is the intention of these specifications to provide a complete installation. All accessory

construction and apparatus necessary in the operation or testing of the performance of the work shall be included. The omission of specific reference to any part of the work necessary for such complete installation shall not be interpreted as relieving the CONTRACTOR from furnishing and installing such parts. Any such omission or clarification shall be brought to the attention of the Owner prior to bidding as provided in this section.

END OF SECTION 13 11 00