Building Committee Presentation: JUNE 12, 2012PRELIMINARY DESIGN PROGRAM Hanson, MA | Whitman-Hanson Regional School District
Module 3 Preliminary Design Program
CONTENTS
1. INTRODUCTION
2. EDUCATIONAL PROGRAM
3. INITIAL SPACE SUMMARY
4. EVALUATION OF EXISTING CONDITIONS
5. SITE DEVELOPMENT REQUIREMENTS
6. PRELIMINARY EVALUATION OF ALTERNATIVES
7. LOCAL ACTIONS AND APPROVALS
APPENDIX
Module 3 Preliminary Design Program
1. INTRODUCTION
1. Overview• Educational Facilities
2. Project Initiation and Statement• Statement of Interest• Project Team• Enrollment Agreement
3. Narrative Summary of Capital Budget Statement
4. Process and Schedule• Site visits• Public Outreach• Education Program • Initial Space Summary
5. Summary of Findings, Existing Conditions• Site• Maquan School• Indian Head School
Module 3 Preliminary Design Program
2. EDUCATIONAL PROGRAM
1. Overview• Current and Proposed Educational Program• Fit of Program to Physical Space
2. Educational Program
3. Functional Diagrams
Module 3 Preliminary Design Program
3. INITIAL SPACE SUMMARY
1. Overview
2. Process and Observations• Overview• Analysis of Existing Educational Facilities• Visionary Session and Summary Findings• Initial Assessment of Existing to Proposed (Matrix)
3. Initial Space Summary• Summary of Differences from MSBA Template• Space Summary Spreadsheets (PK-2 and PK-5)
Module 3 Preliminary Design Program
3. INITIAL SPACE SUMMARY
3. Initial Space Summary
• Summary of Differences from MSBA Template
• Pre-Kindergarten• Multi Purpose Room (STEM/STEAM)• Special Needs• Enlarged Gym• Teacher Planning / Collaboration Centers
• Space Summary Spreadsheets (PK-2 and PK-5)
PK-2 Proposed Existing90,834 GSF 74,600 GSF
PK-5 Proposed Existing131,599 GSF 144,490 GSF
Module 3 Preliminary Design Program
4. EXISTING CONDITIONS
1. Introduction: Summary of Property Restrictions• Title and Deed • Appropriateness for Development• Development Restrictions• Historic Restrictions (Memorial Hall)
2. Maquan Existing Conditions
3. Indian Head Existing Conditions
Module 3 Preliminary Design Program
5. Site Development Requirements
1. Introduction: Summary of Concerns
2. Site Development Requirements
3. Existing Site Plan
Module 3 Preliminary Design Program
6. Evaluation of Alternatives
1. School District Assignment Practices
2. Tuition Agreements with Adjacent School Districts
3. Rental or Acquisition of Existing Buildings
4. Construction Options Overview
5. Construction Option Narrative Descriptions
6. Construction Option Drawings
7. Option Cost Comparison
8. Options Comparison Chart
9. Base Repair Option Costs for Indian Head
Maquan PK-2: A comprehensive renovation including code required upgrades, full accessibility, and a fire suppression system.
Indian Head 3-5: Targeted improvements to correct known deficiencies.
Approx. Costs:$32,038,947 Total$18,291,297 Hanson share
Maquan Elementary SchoolFeasibility Study
Hanson, MA Whitman-Hanson Regional School District
Option 1| Base Repair – Site Plan
6. Construction Option Drawings
Option 2| Renovation and Addition to Maquan with No, or Limited Demolition – Site Plan
Maquan PK-2:No / Limited Demolition
• Minor interior modifications
Comprehensive renovation including code required upgrades, full accessibility, and a fire suppression system.
New addition to meet the program requirements for Pre-K to grade 2.
Approx. Costs:$34,750,899 Total$18,160,486 Hanson share
Maquan Elementary SchoolFeasibility Study
Hanson, MA Whitman-Hanson Regional School District
6. Construction Option Drawings
Exact configuration of additions
to be determined
New Septic Field
Option 3| PK-2, Renovation and Addition to Maquan with Partial Demolition – Site Plan
Maquan PK-2:Enrollment: 395
Demolition of the 1-story core
Addition of a new 2-story core,
Renovation of the existing 2-story classroom wing, for Pre-K to grade 2.
Approx Costs:$35,993,551 Total$18,782,420 Hanson share
Maquan Elementary SchoolFeasibility Study
Hanson, MA Whitman-Hanson Regional School District
6. Construction Option Drawings
New Septic Field
Option 3| PK-2, Renovation and Addition to Maquan with Partial Demolition – Building Plans
LOWER LEVEL UPPER LEVEL
Maquan Elementary SchoolFeasibility Study
Hanson, MA
6. Construction Option Drawings
Option 4A| PK-2, New 2-Story School on Maquan Site – Site Plan
Maquan PK-2:Enrollment: 395
A new 2-story school building on the Maquan site for Pre-K to grade 2.
Demolition of existing Maquan School.
Approx. Costs:$36,454,887 Total$17,867,654 Hanson share
Maquan Elementary SchoolFeasibility Study
Hanson, MA Whitman-Hanson Regional School District
6. Construction Option Drawings
New Septic Field
Option 4A| PK-2, New 2-Story on Maquan Site – Building Plans
UPPER LEVEL
LOWER LEVEL
Maquan Elementary SchoolFeasibility Study
Hanson, MA
6. Construction Option Drawings
Option 4B| PK-2, New 2-Story School on Maquan Site – Site Plan
Maquan PK-2:Enrollment: 395
A new 2-story school building on the Maquan site for Pre-K to grade 2.
Demolition of existing Maquan School
Approx. Costs:$36,454,887 Total$17,867,654 Hanson Share
New Septic Field Maquan Elementary School
Feasibility Study
Hanson, MA Whitman-Hanson Regional School District
6. Construction Option Drawings
Option 4B| PK-2, New 2-Story School on Maquan Site – Building Plans
LOWER LEVEL
UPPER LEVEL
Maquan Elementary SchoolFeasibility Study
Hanson, MA
6. Construction Option Drawings
Option 5| PK-5, Renovation and Addition to Indian Head with Partial Demolition – Site Plan
Combined PK-5:Enrollment: 800
Demolition of the Indian Headone story wing.
New 2-story additions.
Targeted renovation of the existing 2-story 1951 wing.
Demolition or re-purposing of Maquan School
Approx. Costs:$52,751,926 Total$26,362,010 Hanson share
Maquan Elementary SchoolFeasibility Study
Hanson, MA Whitman-Hanson Regional School District
6. Construction Option Drawings
Option 5| PK-5, Renovation and Addition to Indian Head with Partial Demolition – Building Plan
Maquan Elementary SchoolFeasibility Study
Hanson, MA
LOWER LEVEL
6. Construction Option Drawings
Option 5| PK-5, Renovation and Addition to Indian Head with Partial Demolition – Building Plans
MAIN LEVEL
Maquan Elementary SchoolFeasibility Study
Hanson, MA
UPPER LEVEL
6. Construction Option Drawings
Option 6A| New 2-Story School on Indian Head Site – Site Plan
Combined PK-5:Enrollment: 800
A new 2-story building for Pre-K to grade 5 on the Indian Head site.
Demolition or re-purposing of Maquan and Indian Head Schools
Approx. Costs:$53,149,800 Total$26,529,668 Hanson share
Maquan Elementary SchoolFeasibility Study
Hanson, MA Whitman-Hanson Regional School District
6. Construction Option Drawings
Option 6A| New 2-Story School on Indian Head Site – Building Plans
UPPER LEVEL
Maquan Elementary SchoolFeasibility Study
Hanson, MA
LOWER LEVEL
6. Construction Option Drawings
Option 6B| New 2-Story School on Maquan Site- Site Plan
Combined PK-5:Enrollment: 800
A new 2-story building for Pre-K to grade 5 on the Maquan site.
Demolition of Maquan School and demolition of re-purposing of Indian Head School
Approx. Costs:$53,149,800 Total$26,529,668 Hanson share
Maquan Elementary SchoolFeasibility Study
Hanson, MA Whitman-Hanson Regional School District
6. Construction Option Drawings
New Septic Field
Option 6B| New 2-Story School on Maquan Site – Building Plans
UPPER LEVEL
Maquan Elementary SchoolFeasibility Study
Hanson, MA
LOWER LEVEL
6. Construction Option Drawings
Module 3 Preliminary Design Program
6. Evaluation of Alternatives
7. Option Cost Comparison
Option Total Cost Hanson Cost
6 New School at Indian Head $53,149,800 $26,529,668or Maquan, PK-5
2 Add. Reno. Maquan $34,750,899 $18,160,486(no demo) (Not Including Indian Head Repairs)
4 New school at Maquan $36,454,887$17,867,654PK-2 (Not Including Indian Head Repairs)
3 Add. Reno. Maquan $35,993,511 $18,782,420(partial demo) (Not Including Indian Head Repairs)
5 Add. Reno. Indian Head $52,751,926$26,362,010(partial demo) PK-5
1 Base Repair $32,028,947$18,291,297
2 (Not Including Indian Head Repairs)
Module 3 Preliminary Design Program
MOVING FORWARD
TO DO FOR MODULE 3.1:• Narrow Options to 3 and complete Executive Summary
• Local Action Certification
TO DO FOR MODULE 3.2:• Joint Meeting with Selectmen and Historic Commission regarding
Memorial Hall
• Community Outreach as Defined by Town/District
• Recreational Department Meeting(s)
• Identify Preferred Solution (July 17-24)
• Determine Funding Needed for Survey, Traffic, Hazmat and Soils
TO DO FOR MODULE 4:• Seek Town Funding Approval for Site Exploration at October Town
Meeting
Thank You