Upload
vutuong
View
217
Download
2
Embed Size (px)
Citation preview
133
Ing.Teodor Burilescu, Ing. Ioan Lungu, Ing. Petre Uţă
S.C. Road Consulting & Design S.r.l, S.C. IPTANA S.A., S.C. Geosond S.A.
STABILIZATION AND CONSOLIDATION OF SLOPES IN SUB-ALPINE
AREAS THROUGH CLASSIC AND SELF-DRILLING ANCHORS
Abstract: This article deals with presentation of executing one of jobs in sub-alpine areas of
stabilization slope using two common technologies. Aim of the article is to show advantages and
disadvantages of both technologies.
Profile selfdrilling bars are starting to be used more often in the geotechnical field, mainly
because of the superior advantages towards the classic techniques in certain field conditions, out
of which the most important (in the road building field) are:
• smaller dimensions of the necessary workbenches
• faster execution time
• high flexibility given by the possibility to adjust the lengths of the rods depending on
local events that may appear during execution
• easy access in difficult reachable areas.
Due to these advantages it was possible to solve the high risk instability phenomena for which we
will present you a project done on national road DN 1 km 114+400 – km 114+800. In this area
the road is built on a slope with a high inclination, aproximative 70°, being framed at digging and
filling with 100 year old supporting walls from solid rock stones. The slope consists of sandy
marl slates also known in the specialty paper works as “Sinaia layers”. The layering is almost
done at horizontal level, with a slight downwards inclination due to the bending of the layer
heads and later to the breaking and sliding of the layers downwards. Although this phenomena is
a few centuries old, the activity was slow without any significant changes.
Starting with construction of the road, when the first support stone walls were done (see Figure
1), the phenomena began to intensify and to produce unwanted effects which led to the rebuilding
and consolidation of the existing constructions at least 2 times in the past 80 years.
134
The continuous increase of traffic on this road which represents the main arterial road in the
national roads network in Romania had a major influence in the evolution of the instability
phenomena.
In the year 2005, after heavy rains, the phenomena began to intensify even more accelerated, the
movement reaching the speed of 1,5 cm/day. This cause the visible degradation of the
construction and the fast breaking of the road was foreshadowed. (see Figures 2, 3 and 4).
Fig. 1) Old supporting stone wall
Fig. 2) 2005 road situation
135
Fig. 3) 2005 road situation
Fig. 4) 2005 Supporting wall situation
The local conditions didn’t allow execution of a temporary solution, and the detours available
were over 200 km long which meant an additional expense for the transport.
At that moment a decision was made to urgently start consolidation of the supporting wall, and
the solution accepted consisted of using of micropiles and selfdrilling (see Figure 5).
136
Fig. 5) Micropiles and self-drilling anchors
Taking advantage of the opportunity risen, it was proposed also to make an adjustment to the
route because it was with a lot of curbs and narrow platform 7.00m (see Figure1).
The choosen solution took into consideration both the digging and the filling, and was built from
(see Figures 2 and 3):
1. At digging : Partial rebuilding of the supporting wall, coating with reinforced concrete of
the remaining segment and anchoring the structure with one or two rows of bars type
40/16 depending on the position in the design. The lengths were between 9.00m and
18.00m (see Figure 6).
2. At filling, because road was widened and the sliding plane was under the foundation of
the existing constructions at a depth of 3.00m ÷ 3.50m, it was done a coating with
reinforcement concrete with variable thickness from 0.50m to 0.80m and a cantilever also
variable between 1.50m and 2.00m (see Figure 7).
137
Fig. 6) Changes made at digging
Fig. 7) Coating with reinforcement concrete
For the new structure for the filling there were used vertical micropiles to support the vertical
loads and partially the horizontal ones as follows:
• one row of micropiles at the base of the existing wall which was used as a base for the
coating, with the length of 12.00m (see Figure 8).
• one row of micropiles through the old structure of the supporting wall, which contributed
at the reinforcement of the old structure to which the coating concrete bonded.
138
Fig. 8) First raw of micropiles from the base of existing wall
All micropiles were done with bars type 52/26 and their length was of 18.00m.
• in the areas with cantilevers, there were used bars 18.00m lengths in dimensions of 40/16
or 52/26 depending on position from the design.
The project used 6.400 lm of different selfdrilling anchors and a volume of aproximative 900m3
of reinforced concrete.
The job was done without stopping traffic, and the execution time was of 4 months. Apart from
the presented project, there were also done 12 columns of ø 1500mm (see Figure 10) anchored, to
replace an arch made from piers that was heavily damaged.
139
Fig. 9) Current situation
Fig. 10) Anchored columns
140
R=1
50 m
C=7
4mV
= 30k
m/ h
R= -
150
mC
=109
mV
=30k
m/h
R=3
50 m
C=9
9 m
V=5
0km
/ h
R=2
50 m
C=6
0mV
=30k
m/h
i=2.
5%
INCEPUT PROIECT
Km 114+694
Pod
L=48m
Km 115+150
SFARSIT PROIECT Km 115+127
Fig.
1 PL
AN
(TO
P VI
EW)
141
Km
=114
+832
.450
2.5%
2.5%
2.5%
2.5%
142
Km
=114
+871
.071
2.5%
2.5%
2.5 %
2.5 %
2 .5%