13
Business Contingency Planning at DTCC Business Contingency Planning at DTCC Mark Vercruysse

Business Contingency Planning at DTCC

  • Upload
    cassia

  • View
    62

  • Download
    3

Embed Size (px)

DESCRIPTION

Business Contingency Planning at DTCC. Mark Vercruysse. Business Contingency Planning Mission. To guide the organization in the creation of a tested plan which, when executed, will permit an efficient and timely resumption of critical business functions. - PowerPoint PPT Presentation

Citation preview

Page 1: Business Contingency Planning at DTCC

Business Contingency Planning at DTCCBusiness Contingency Planning at DTCC

Mark Vercruysse

Page 2: Business Contingency Planning at DTCC

2

Business Contingency Planning Mission

Business Contingency Planning Mission

•To guide the organization in the creation of a tested plan which, when executed, will permit an efficient and timely resumption of critical business functions.

• To minimize the potential disruption of services to customers.

Page 3: Business Contingency Planning at DTCC

3

Agenda Agenda

• BCP & Safety Structure

• Data Center

• Business Center

• Client Readiness

• Continuing Business Continuity Initiatives

• BCP & Safety Structure

• Data Center

• Business Center

• Client Readiness

• Continuing Business Continuity Initiatives

Page 4: Business Contingency Planning at DTCC

4

BCP & Safety Structure BCP & Safety Structure • Disaster Recovery Coordinators

• Interface with business department & their coordinators

• Coordinate recovery space and tests at the recovery site

• BCP Task Force

• Managing Directors from various corporate areas

• Tasked with identifying and recommending BCP initiatives

• Corporate Infrastructure Contingency Planning

• Focus business resiliency

• BCP reports to C E O

• Disaster Recovery Coordinators

• Interface with business department & their coordinators

• Coordinate recovery space and tests at the recovery site

• BCP Task Force

• Managing Directors from various corporate areas

• Tasked with identifying and recommending BCP initiatives

• Corporate Infrastructure Contingency Planning

• Focus business resiliency

• BCP reports to C E O

Page 5: Business Contingency Planning at DTCC

5

BCP & Safety Structure cont’dBCP & Safety Structure cont’d• Employee Safety and Security

• Coordinates safety in the workplace

• Coordinates fire drills, evacuations, points of assembly etc

• Corporate Command team

• First responder teams

• Safety awareness sessions

• Employee safety kits

• Employee Safety and Security

• Coordinates safety in the workplace

• Coordinates fire drills, evacuations, points of assembly etc

• Corporate Command team

• First responder teams

• Safety awareness sessions

• Employee safety kits

Page 6: Business Contingency Planning at DTCC

6

Data Centers Data Centers • Primary data center outside Manhattan

• Data centers in the NY Region and outside the region

• Route client traffic thru all sites daily

• Local IT staff on site

• Staff performs functions daily in each location

• Remote control of all data centers from any data center

• Command center calls distributed among sites daily

• An out of region center used during the August 2003 blackout

• Test permutations have increased

• Primary data center outside Manhattan

• Data centers in the NY Region and outside the region

• Route client traffic thru all sites daily

• Local IT staff on site

• Staff performs functions daily in each location

• Remote control of all data centers from any data center

• Command center calls distributed among sites daily

• An out of region center used during the August 2003 blackout

• Test permutations have increased

Page 7: Business Contingency Planning at DTCC

7

Data Replication Data Replication NSCC & DTC

• DTCC as of May 28 has implemented EMC’s SRDF-A/STAR

• Required to reduce replication lag time

• Lag time has been reduced to < 2 minutes from 30 minutes

• Potential data loss

• Implemented 4 months ahead of schedule

NSCC & DTC

• DTCC as of May 28 has implemented EMC’s SRDF-A/STAR

• Required to reduce replication lag time

• Lag time has been reduced to < 2 minutes from 30 minutes

• Potential data loss

• Implemented 4 months ahead of schedule

Page 8: Business Contingency Planning at DTCC

8

Planned Data Replication Planned Data Replication FICC

• DTCC will implement EMC’s SRDF-A/STAR for FICC applications

• Testing started in 2006 with implementation

• Will be phased in by application

• First application in Q4 2006

• Completion in 2007

• Simplifies recovery and is consistent with DTC & NSCC entities

FICC

• DTCC will implement EMC’s SRDF-A/STAR for FICC applications

• Testing started in 2006 with implementation

• Will be phased in by application

• First application in Q4 2006

• Completion in 2007

• Simplifies recovery and is consistent with DTC & NSCC entities

Page 9: Business Contingency Planning at DTCC

9

Business Centers Business Centers

• Staff decentralized

• Locations in NY and Tampa

• Sites operate in an active / active model

• Staff started to operate in Tampa - Dec. 6, 2004

• Operations staff on site as of Feb. 21, 2005

• Reduces the impact a regional event has on the business

• Reduces the effect a regional attack has on the staff

• Out of region business and data centers are not in same city

• Video Conferencing

• Staff decentralized

• Locations in NY and Tampa

• Sites operate in an active / active model

• Staff started to operate in Tampa - Dec. 6, 2004

• Operations staff on site as of Feb. 21, 2005

• Reduces the impact a regional event has on the business

• Reduces the effect a regional attack has on the staff

• Out of region business and data centers are not in same city

• Video Conferencing

Page 10: Business Contingency Planning at DTCC

10

Client ReadinessClient Readiness•Developed communication requirements for

clients

• Require dedicated backup connection

• Disaster recovery testing once a year now required

• Testing is now required from client’s primary and backup sites to DTCC processing sites

•Utilize Government telecom program

• Telecommunication Service Priority (TSP)

• Government Emergency Telecommunications Service (GETS)

•Developed communication requirements for clients

• Require dedicated backup connection

• Disaster recovery testing once a year now required

• Testing is now required from client’s primary and backup sites to DTCC processing sites

•Utilize Government telecom program

• Telecommunication Service Priority (TSP)

• Government Emergency Telecommunications Service (GETS)

Page 11: Business Contingency Planning at DTCC

11

Pandemic Preparations Pandemic Preparations

• Social Distancing

• Sanitization program

• Essential staff

• Critical functions

• Remote access

• Social Distancing

• Sanitization program

• Essential staff

• Critical functions

• Remote access

Page 12: Business Contingency Planning at DTCC

12

Continuous BCP InitiativesContinuous BCP Initiatives• Building evacuation

• Client testing

• Command team

• Corporate BCP risk assessments

• First responder team

• Officer rotation program

• Pandemic preparations

• Safety training

• Tabletop exercises

• Building evacuation

• Client testing

• Command team

• Corporate BCP risk assessments

• First responder team

• Officer rotation program

• Pandemic preparations

• Safety training

• Tabletop exercises

Page 13: Business Contingency Planning at DTCC

13

Questions Questions

George Perretti 212 855 – 8176

Email [email protected]

Ken Wright 212 855 – 1368

Email [email protected]

George Perretti 212 855 – 8176

Email [email protected]

Ken Wright 212 855 – 1368

Email [email protected]