79
BUSINESS PLAN 2017 – 2020 1

BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Embed Size (px)

Citation preview

Page 1: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

BUSINESS PLAN 2017 – 2020

1

Page 2: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

CHAIRMAN’S STATEMENT It is my pleasure to present TPL’s Business Plan for the 2017-2020 period. The objective of this Business Plan is to achieve the Government’s core purpose to “reduce Tonga’s vulnerability to oil price shocks by increasingly accessing to state-of-the art energy technologies in an affordable and environmentally sustainable manner”. In order to achieve this objective, Tonga Power must reduce its reliance on Diesel Generation and introduce a higher proportion of Renewable Energy (RE) generation. Over the past three years, TPL has achieved approx. 8% of all electricity generation from RE leaving 82% of electricity generation from diesel generation. Our objective is to further reduce electricity generation from our diesel engines to 50% by 2020, which is the target set by the Government. In order to achieve this objective, TPL will require 15.3MW (8.7MW of Solar and 6.6MW of Wind) in new RE generation and at least 20MWh of storage capacity installed and commissioned by 2020. It has been estimated that up to 20 seniti/kWh electricity tariff reduction could be achieved from reaching a 50% RE penetration target. In addition, there will be reductions in carbon emissions from displaced diesel generation. Achieving this target however, is not an easy task. TPL will need to raise about $166 million to fund these projects. Funds will need to be raised either from Development Partners, Institutional lenders or by some other means. TPL will require strong Government cooperation and support to meet the objectives outlined in this Business Plan and I look forward to working in partnership with our Shareholder, the Minister of Public Enterprises together with the Minister of Energy and the Minister of Finance. In addition to the above RE projects which will be externally funded, TPL will contribute a further $32 million from its own balance sheet to fund various Network Upgrades, IT, Power Generation, and ERP projects during the 2017-2020 period. The objectives and strategies laid out in this Business Plan have taken the Board of Directors and TPL management considerable time, effort and thought in their preparation in order to develop a workable and achievable plan that I and my fellow Directors fully support through to its implementation. Over the coming few years, the business operations of TPL will become even more lean and efficient, especially through the implementation of our new ERP software which will be fully operational by the end of this year. TPL will adopt a proactive service oriented approach and focus on reducing waste and duplication and delivering our shareholder’s vision of a lower electricity tariff derived from efficiency gains through the introduction of more cleaner, greener Renewable Energy generation.

2

Page 3: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

TPL is also committed to the Utility Reform Project now under way. From creating the atmosphere conducive to growth, TPL is able to facilitate common meter reading, it already had in place the infrastructure for common billing, putting in place “One Stop Shop” for customer payment and feedback more convenience for customers. The 2015/2016 will see us built a common utility office building at Tufumahina. This highlight the wiliness of TPL to share its services from IT to HR and Fleet Repairs.

Last but not the least, I am quite glad with how Tonga Gas/Home Gas have operated through the years. The company for the first time presented a $200,000 dividend to Tonga Power last year and is looking at expanding its core businesses and expansion to other businesses. This will see an improvement in profitability by about $0.5 million next year and continue throughout the years.

I would like to take this opportunity to thank our CEO, Mr. Robert Matthews who has made a big impact and contribution in shaping the future direction across all aspects of the business operations. These major developments are designed to ensure TPL achieves a similar corporate governance framework and best practice operations similar to any utility company across New Zealand, Australia and the Pacific.

Furthermore, I specifically thank TPL management team for their significant effort in preparing this Business Plan. There are exciting but challenging times ahead for all TPL staff, but together we are committed to achieving the objectives and strategies of this Business Plan.

3

Page 4: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

CEO’S STATEMENT

Once again, it is a great privilege and honor to present Tonga Power Limited Business Plan for the period 2017-2020. This is the second Business Plan prepared and presented to TPL stakeholders under my Management.

The main objective of this plan is to deliver the Government’s 50% Renewable Energy target by 2020. Tonga Power intend to invest more than $166 million on various Renewable Energy (RE) plants over the next four years. However, due to the intermittent nature of these projects, the integration of renewables into our conventional diesel engines requires careful planning to ensure the balance between electricity production and demand is properly managed and maintained. The integration of further intermittent RE into our existing generation mix will need to be carefully engineered. This is particularly the case when expanding our current Micro-grid control system and Li-Ion capacitor capabilities and planed Energy Storage projects in the future.

Further, our distribution grid has been designed and built to operate with centralized generation. With limited capacity for alternative power flows and without control and communication at the point of use, our distribution grid cannot realise the full potential of increasing penetration of renewable generation. TPL intend to use a variety of technologies to solve the issues arising from intermittent renewable generation. For example, approximately $25 million will be allocated to “Enabling Power Systems” (EPS) projects consisting bulk energy storage, SCADA upgrades and demand side management to assist in accommodating RE generation in order to achieve the balance between electricity supply and demand. A further $2 million EPS project consisting a meshed-ring-communication philosophy, a fourth feeder and a new Vaini submarine cable will assist in accommodating RE generation into the existing Grid successfully. We also intend to move to “Smart-Grid” technology in the very near future to provide communication between generation plants and our network equipment. TPL has already commenced the first phase of the smart-grid program; with a $4 million project to rollout smart meters at our customer premises in order to achieve fast and automated response in load management, energy loss reduction, system stability, and enhanced power quality and reliability.

In addition, Tonga Power will continue to successfully manage its major ongoing projects such as TVNUP (Tonga Village Network Upgrade Project), Smart Metering, OIREP (Outer Island Renewable Energy Project) and ERP (Enterprise Resource Planning) projects during the planning period.

The Business Plan clearly describes how Tonga Power Limited will achieve the 50% renewable energy by 2020 with the following portfolio of projects costing about $252 million:

Priority projects essential to achieve 50% RE penetration target in the future ($166 millionto be funded by Development Partners).

Projects that are already in progress ($67 million funded by both TPL and DevelopmentPartners).

Projects that have been committed to and will be completed in the near future ($20 million).

4

Page 5: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

I am confident that Tonga Power Limited can successfully complete all the projects highlighted in the Business Plan by 2020 in order to provide safe, reliable, sustainable and affordable electricity to the people of Tonga.

5

Page 6: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Table of Contents

CHAIRMAN’S STATEMENT ................................................................................................................. 2

CEO’S STATEMENT ................................................................................................................................ 4

1. EXECUTIVE SUMMARY ............................................................................................................... 8

2. INTRODUCTION........................................................................................................................... 12

3. OVERVIEW OF THE BUSINESS .............................................................................................. 14

4. POLICIES AND GUIDELINES GOVERNING THE DEVELOPMENT OF THE BUSINESS PLAN .......................................................................................................................................................... 22

4.1 Ownership Guidelines ........................................................................................................ 22

4.2 Obligations under the NSDF ............................................................................................ 23

4.3 Boards expectations ........................................................................................................... 23

4.4 Energy Policy, Law and Legislation .............................................................................. 24

4.5 Purpose of the Public Enterprise ................................................................................... 27

5. PLANNING INPUTS ..................................................................................................................... 28

5.1 External Elements ............................................................................................................... 28

5.2 Internal Elements ................................................................................................................ 36

5.3 Summary and SWOT analysis ......................................................................................... 43

6. PLANNING PERIOD STRATEGIC OBJECTIVES & CHALLANGES ............................... 45

6.1 Strategic Objective 1 ........................................................................................................... 46

6.2 Strategic Objective 2 ........................................................................................................... 47

6.3 Strategic Objective 3 ........................................................................................................... 50

6.4 Strategic Objective 4 ........................................................................................................... 50

6.5 Strategic Objective 5 ........................................................................................................... 51

6.6 Strategic Objective 6 ........................................................................................................... 52

7. STRATEGIES/ACTIONS TO SATISFY OBJECTIVES ......................................................... 53

7.1 Priority Projects ........................................................................................................................ 53

7.2 Projects In-Progress ................................................................................................................ 58

7.3 Future Project Committed by TPL ..................................................................................... 61

8. PERFORMANCE MEASURES & TARGETS .......................................................................... 65

9. STATEMENT OF COMPLIANCE(S) ........................................................................................ 66

10. FINANCIAL FORECAST .......................................................................................................... 69

6

Page 7: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

1. EXECUTIVE SUMMARY

TPL’s vision is to provide safe, reliable, sustainable and affordable service to the people of Tonga. The vision is developed from the Government’s core purpose for energy which is to:

“Reduce Tonga’s vulnerability to oil price shocks, and achieve an increase in quality access to modern energy services in an environmentally sustainable manner”.

Thus TPL’s mission is to deliver the nation’s core purpose through this Business Plan and to remain financially sustainable. TPL’s mission is also in line with the Ministry of Public Enterprise’s objective “to be profitable and efficient”. The Business Plan 2017-2020 was developed systematically and constructively to achieve TPL’s vision and the government’s core purpose through achieving the following six key strategic objectives.

i. Achieving 50% electricity generation from RE generation by 2020 in order to achieve the government TERM objective and significant tariff reductions.

ii. Adopting technologies to manage the complexities arising from the increasing levels of RE penetration.

iii. Improving the network and replacing ageing assets to improve safety and reliability of TPL's services.

iv. Cultivating a hazard free safety culture to minimize any electrical hazards to both the public and staff.

v. Investing in leading business processes and systems to improve operational efficiency and quality of TPL's services to customers.

vi. Managing all external funding and internal financing sources successfully in order to maximise the shareholder value.

7

Page 8: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

The following table shows the key challenges that TPL will face in achieving the six key strategic objectives and their link to the vision:

The above six strategic objectives are translated into a set of strategic measures. These measures track the performance of each strategic objectives throughout the four year planning period. A summary of the performance measures are shown in the table below:

ID Strategic Objective Benefits Link to Vision Key Challenges

1

Achieving 50% electricity generation from

RE sources by 2020 in order to achieve the

government and TERM objective as well as

significant tariff reductions.

Tariff reduction, Increase

economic efficiency and growth

Affordability,

Sustainability

Seeking funding for selected projects, building

relationships with donors, slow progress rate,

managing power purchase agreement with IPP

owners.

2

Adopting technologies to manage the

complexities arising from increasing RE

penetration.

Enhance grid stability, security,

safety and reliability of supply

Safety, Reliability,

Sustainability

Very expensive to implement smart-grid

technology, may difficult to seek funding for asset

improvement/replacement, immature energy

storage technologies, develop/update asset

management plans.

3

Improving the network and replacing

ageing assets to improve safety and

reliability of TPL's services.

Improve power quality, line

losses, and reliability of supply

(or N-1 security)

Safety, Reliability,

Sustainability,

Affordability

Seeking funding for selected projects; update

asset management plans, compliance with ECC

standards, human resource availability.

4

Cultivating a hazard free safety culture to

minimize any electrical hazards to both

public and staff.

Reduce number of hazards,

incidents, accidents and near

misses

SafetyRegulation promulgation takes considerable

amount of time, HSE structure requires clarity.

5

Investing in excellent business processes

and systems in order to improve

operational efficiency and quality of TPL's

services to customers.

Reduce non-value added,

increase quality of service,

reduction in customer

complaints, increase

employee/customer satisfaction

Sustainability

Key staff constraints leading to outsourcing,

minimising very high consultation costs,

compliance with overburden policies and

procedures.

6

Managing all external funding and internal

financing sources successfully in order to

maximise the shareholder wealth for the

best interest of the company and the

people of Tonga.

Cost reduction, increase profit,

tariff reduction through

investing on right projects

Affordability,

Sustainability

Seeking free or low cost funding, lack of clear

policies on hedging, self/group interest on

implementing wrong projects, possible

government tariff freeze, unfavourable economic

activities.

Strategic Objectives & Challenges for the Planning Period 2017 -2020

Current

2016 2017 2018 2019 2020

Accumulated Fuel Displacement (%) Generation 12% 20% 30% 40% 50%

Tariff Reduction (%) due to RE Generation 4% 5% 8% 10% 12%

RE Penetration (%) Generation 15% 25% 40% 50% 60%

2

Adopting technologies to manage the

complexities arising from increasing RE

penetration.

Voltage Fluctuations Distribution +/-10% +/-10% +/-10% +/-10% +/-10%

System Loss (%) Distribution 11.0% 10.5% 10.0% 9.0% 9.0%

Fuel Efficiency (kWh/L) Generation 4.0 4.0 4.0 4.0 4.0

Reliability (SAIDI) (Minutes)Distribution &

Generation1000 950 925 900 850

N-1 Security Policy Compliance Generation 100% 100% 100% 100% 100%

4

Cultivating a hazard free safety culture to

minimize any electrical hazards to both public

and staff.

Loss Time Injuries Corporate 0 0 0 0 0

Staff Retention (%) Corporate > 90% > 90% > 90% > 90% > 90%

Customer Complaints Corporate 50 40 30 30 20

NPAT Retail $4.0M $4.0M $4.0M $4.5M $4.5M

ROE Retail 10% 10% 10% 10% 10%

Strategic Performance Targets for the Planning Period 2017 -2020

ID Strategic Objective Strategic Measures Business UnitTargets

5

Investing in excellent business processes and

systems in order to improve operational

efficiency and quality of TPL's services to

customers.

6

Managing all external funding and internal

financing sources successfully in order to

maximise the shareholder value.

1

Achieving 50% electricity generation from RE

generation by 2020 in order to achieve the

government TERM objective and significant

tariff reductions.

3

Improving the network and replacing ageing

assets to improve safety and reliability of TPL's

services.

8

Page 9: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Actual performance will be monitored against these targets on a regular basis. The results of the performance review will be used to review the current strategy and develop new strategic objectives and revise the performance measures for the next financial year. The current state of performance are the values shown in 2016 (where we are now) and the targets will be the future states of performance for each year from 2017-2020 (where we want to be). The projects mentioned below and strategies will have to be implemented to achieve the future states of performance (how do we get there). In order to achieve the future target performance, TPL plans to invest $252 million on capital projects (i.e. Capex) as shown below. Priority projects essential to achieve 50% RE penetration target in the future ($166 million). Projects that are already in progress ($67 million). Projects that are committed by TPL to complete in the future ($20 million). These strategic projects are highlighted in the following tables.

ID Project  50%

Target

Est. Cost

(T$)

Tariff Impact

(s/kWh)Notes

1

Demand Side

Management and

Energy Efficiency

EE 4.0m 3

Efficient lighting, MEPS, replace old appliances, water

heater controls, energy audits, tax changes, peak load

awareness, TOU or demand based tariffs .

2

Nuku’alofa Network

Upgrade Project

(NNUP)

EE 50m 2

Upgrade of Nuku’alofa network to reduce line losses and

improve reliability of the network further enabling RE. Full

roll out of smart metering should be undertaken at this

stage.

3Enabling Power System

(EPS) Project A EPS 2.0m TBD

Allows 20% RE penetration, essential for Wind Generation

in the East, partially funded by the World Bank (T$ 1.0m).

Submarine cable replacement is outstanding including

meshed ring philosophy and fourth feeder

41.3 MW Solar PV

(Central TBU)0.17 6.0m 2

Tariff impact assumes donor funded investment and 5%

into a sinking fund to replace assets. IPP being sought for

project.

52.2 MW Wind Farm

(Niutoua)0.26 20m 5.5

Tariff impact assumes donor funded investment and 5%

into a sinking fund to replace assets. NZ MFAT studying

project. A new tariff should be initiated at this stage. 

6 EPS Project B EPS 5.0m TBD

Allows 35% RE penetration, includes approx. 2 MWh of

energy storage (potentially to existing RE generation

schemes), SCADA upgrades, existing generation fine

tuning, capacitor banks. CBs and comms.

72.2 MW Wind Farm

Extension (Niutoua) 0.35 20 m 3

Tariff impact assumes donor funded investment and 5%

into a sinking fund to replace assets. Japan studying

project.

8 EPS Project C EPS 2.0m TBDAllows 50% RE penetration, EXCLUDES energy storage,

includes capacitor banks. CBs and comms

93 x 1.3 MW Solar PV

(Central-West) 0.41 18m 3 Tariff impact assumes donor funded investment

102.2 MW Wind Farm

Extension (Niutoua)0.52 20m 2.5 Tariff impact assumes donor funded investment

11Energy Storage (8 to 16

MWh)0.61 19m TBD

Required to prevent renewable energy spill from

exceeding 20%.

Total= 61% 166m 21 s/kWh

2016-2020

High Priority Projects Achieivng 50% RE Target

9

Page 10: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

The implementation of the strategies outlined in this plan will be instigated at a ‘fast pace’. The Business Plan will be updated annually, outlining how each area will be developed to produce decisive results both in the immediate to short term and over the full four years of this Business Plan.

ID Project  50%

Target

Est. Cost

(T$)

Funding

SourceNotes

1Smart & Prepay Metering

Stage 1EPS 4.0m TPL & MFAT Installation of 3000 smart/prepay meters in Tongatapu.

2Tonga Village Upgrade

Projects Phase 2/3EE 42.0m MFAT & TPL

Upgrade of Nuku’alofa network to reduce line losses and

improve reliability of the network further enabling RE. Full

roll out of smart metering should be undertaken at this

stage.

3 Tonga Police Solar Project 10% 2.5m DFAT Installation of 250KW PV plus 100kWh storage system.

4

Outer Islands Renewable

Energy & Energy Efficiency

Project

14% 16.0m ADB

Project cosists of both establising RE plants (550KW in

Ha'apai and 200KW in Eua) and upgrading of distribution

networks.

5IT Virtual Environment &

Disaster Recovery ProjectEPS 0.5m TPL

Virtual server development to provide high availability,

disaster recovery and data protection.

6Enterprise Resource

Planning ProjectEPS 2.0m TPL

The system will provide improved governance, the ability

to cope with growth and diversification and facilitate cost

reductions.

Total= 14% 67m

Projects In Progress

2016-2020

ID Project  50%

Target

Est. Cost

(T$)

Funding

SourceNotes

1Generator Replacement

Program (All Islands)EPS 9.0m TPL

Replacing or overhauling all CAT and Cummins generators

in Tongatapu and Outer Islands

2

Outer Islands Network

Upgrade Program (Vavau

& Eua)

EPS 3.0m TPL Network upgrade work left over from OIREP project.

3Tongatapu Village

Network Upgrade - Stage 4EPS 3.0m TPL

Network upgrade work (about 5 more villages) left over

from TVNUP and Nuku'alofa Ntwork Upgrade Projects .

4Smart Metering Project -

Stage 2EPS 3.0m TPL

Installation of balance $14,000 smart meters in

Tongatapu.

5 Generation (Other) EPS 2.0m

Other inciliary generation projects including SCADA

upgrade, fire hydrants, G8 day tank, MAK/G8 load sharing

module, waste oil disposal system etc.

Total= Nil 20m

Future Projects Committed by TPL

2016-2020

10

Page 11: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

2. INTRODUCTION The Business Plan 2017-2020 complies with the requirements of the new template provided by the Ministry of Public Enterprises and details TPL’s planned journey for the next four years to achieve its vision and deliver on the Government’s core purpose. The key purpose of this Business Plan is to provide TPL staff with a clear direction and to keep the public and other stakeholders well informed about our objectives and to allow our shareholding ministry the opportunity to provide input into our strategic objectives. The plan is a systematic, structured and comprehensive document. It is a key part of our strategic development and highlights the challenges and opportunities the business faces and describes how we intend to monitor our performance against this plan. The major focus in this year’s Business Plan is fulfilling TPL’s commitment to Government’s 50% RE target in order to achieve the following benefits:

Reduced electricity tariff due to reduction of fuel use in the conventional generation. Improved efficiency and reduced system losses when generation is connected near the

load. Reduced need for bulk diesel generation from a centralized location. Sustainable and environmentally friendly energy sources resulting in low carbon

emissions. Improved power quality and reliability in the long run due to establishment of central

and distributed control systems that will allow an effective interaction of supply and demand.

Voltage and reactive power control capabilities from inverters. New Renewable Energy generation projects funded through Independent Power

Producers.

Multiple Renewable Energy (RE) sources at dispersed locations in Tonga requires a significant change in the protection and control methodologies compared to the single generation plant in Popua. The standard radial protection and relay approach will no longer be appropriate. Future generating sources must communicate with each other in a manner that ensures adequate system stability, proper frequency and voltage control, and optimal system performance in terms of efficiency and cost of energy production. In the future, energy generation and distribution in Tonga will be much more automated and ready to interact with distributed RE resources. Distribution automation and smart grids will apply to all the following elements of the distribution system:

Customers (meters and loads) Intelligent load-control devices on the distribution system Distributed RE generation and storage systems, including local energy control systems Intelligent switches, breakers and re-closers Communication and data management devices

11

Page 12: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

The transition to active distributed RE systems and a distribution system that is ready for integration of these systems cannot be achieved abruptly. As explained in this Business Plan, considerable time, skill, knowledge and resource is required to fully integrate the proposed distributed RE (predominantly solar and wind) systems with diesel generation to enhance power quality and reliability through automation and control. This Business Plan is a combination of TPLs strategic and operational plans. Strategically, it sets out TPL’s current and future unique strategies for all business units including Generation, Distribution, Retail and Corporate Compliance in line with the long term goal of achieving TPL’s vision. Operationally, project planning and implementation issues are discussed in order to provide the reader with an in-depth understanding of TPL’s business activities and issues for the planning period.

12

Page 13: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

3. OVERVIEW OF THE BUSINESS Tonga’s electricity sector was re-structured in 2008 when the Government established the Electricity Commission (EC) through the Electricity Act 2007, and purchased the electricity assets from a privately owned entity. The functions of the EC include the regulation of tariffs, establishing consumer service standards, managing electrical safety, as well as the licensing of electricians, and creation of regulations for major electrical works. TPL operates under a strict regulatory framework through the Electricity Concession Contract (ECC) in which tariffs, tariff adjustment formulas, operational efficiency benchmarks, consumer service standards and penalties are specified between the EC, the Government and Tonga Power Limited. TPL has its own Company Constitution and also operates under the Public Enterprises Act 2010 which provides greater commercialization incentives for state owned corporate entities.

TPL has been established with an independent Board of Directors drawn from the commercial sector of Tonga. TPL’s major objectives are to: Provide a safe, reliable, affordable and sustainable electricity supply throughout Tonga. Maximize shareholder value while maintaining prudent levels of exposure to operational

and financial risks. The electricity sector in Tonga is characterized by the existence of a single vertically integrated electricity utility. Tonga Power’s core business is generating, distributing and retailing electric power across our four-grid system within Tonga consisting of more than 21,000 customers. A complementary business is the provision of infrastructure services such as electrical lines services within Tonga. Tonga Power recently diversified into LPG supply and distribution businesses with the acquisition of Tonga Gas and Homegas.

TPL activities are outlined below:

Generation Capacities: As of March, 2016, TPL had installed firm (diesel) generating capacity of 17.2MW in all four islands as shown in the table below. Tongatapu capacity and its peak demand is about 13.8MW and 8.4MW respectively. Tongatapu is well served from the Popua Power Station where there is sufficient capacity to meet current peak demand even with one of the diesel units out of service (N-1 reliability). Vava’u also meets the N-1 security with a total of five generators. In Vava’u, two new 600 kW Cummins units are supported by smaller units (2x186 kW + 320kW units). Ha’apai has 320kW + 2x186kW unit also provides N-1 security. Two 186 kW Cummins units + 420kW hired unit installed in ‘Eua. The peak demand at ‘Eua is such that for a relatively small number of hours, both Cummins generators need to be operational to meet the peak demand. A new 11kV switchboard was installed at the Popua Power Station early this year to provide flexibility and reliability of supply.

13

Page 14: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Quick Facts as at March, 2016

Generation

Distribution

Customers

Tongatapu Equipment Two 2.67 MW Leroy Somer alternators coupled with 2.88 MW Cat 6CM32C engines. Six 1.4 MW Caterpillar 3516B diesel engines driving 11 kV Kato/Cat alternators. Governing done by Woodward DSLC. 2 .4 MW solar plants at Vaini and Popua. New switchgear installed in 2016. Capacity

13.74 MW (Firm) 2.4 MW (Intermittent) Staffing Semi-automated with SCADA monitoring.

Distribution standard 11 kV HV network. The LV network operates at a three/single phase standard of 415/240V. Lines 187km of HV overhead line, 12km of underground cables, and 1km of submarine cable. 452km of LV lines (single and three phase).

Domestic - 12,277 ¹Commercial - 3,037

Electricity tariff - s/kWh3

Fuel 25.64 Non-fuel 44.35

Total 69.99

Vava’u Equipment Two 600kW QSK23 Cummins generators, One 320 kW K19 Cummins generator and Two 186 kW LTA10 diesel generators. Stamford alternators are utilized with the engines. One centralized 420kW solar plant. Capacity

1.892 MW (Firm) 420 kW (Intermittent) Staffing Semi-automated. Monitored and controlled locally with SCADA monitoring.

Distribution standard 6.6 kV, three/single phase standard of 415/240V Lines 68km of HV overhead line, 2km of underground cables, and 97km of LV (single and three phase).

Domestic 2,344 ¹Commercial 863

Electricity tariff - s/kWh Fuel 25.64 Non-fuel 44.35 Total 69.99

Ha’apai Equipment Two containerised 186 LTA10 kW & 320 kW K19 diesel generation sets. Containerised switchgear. Capacity 0.692 MW (Firm) Staffing Semi-automated. Monitored and controlled locally.

Distribution standard 6.6 kV, three/single phase standard of 415/240V Lines 15km of HV overhead line, 2km of Under-ground cables, and 32km of LV lines (single and three phase).

Domestic 757 ¹Commercial 211

Electricity tariff - s/kWh Fuel 25.64

Non-fuel 44.35 Total 69.99

14

Page 15: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

‘Eua Equipment Two containerised 186 kW LTA10 & 420kW K19 (hired) diesel gen sets. Containerised switchgear. Capacity 0.792MW Staffing Semi-automated. Monitored and controlled locally.

Distribution standard 6.6 kV, three/single phase standard of 415/240V Lines 14km of HV overhead line and 42km of LV (single and three phase).

Domestic 937 ¹Commercial 90

Electricity tariff - s/kWh Fuel 25.64 Non-fuel 44.35

Total 69.99

Distribution Network: Tonga Power operates in four distinctly separate island grids:

Tongatapu – 11kV distribution network, 190 km of overhead line, 12km of underground cables, and 1km of submarine cable, in addition to 467 km of low voltage lines (single and three phase).

Vava’u – 6.6kV distribution network, 70km of overhead line, 2km of underground cables, and 97km of low voltage lines (single and three phase).

Ha’apai – 6.6kV distribution network, 15.5 km of overhead line, 2km of underground cables, and 38 km of low voltage lines (single and three phase).

‘Eua - 6.6kV distribution network, 14km of overhead line and 42km of low voltage lines (single and three phase).

Across the four grids, low voltage reticulation is at 400/240 volts. The four grids are exposed to extreme (cyclone, salt spray) weather conditions, primarily from strong winds that often cause indirect damage due to vegetation. A significant amount of vegetation management is on-going however the networks are vulnerable to falling coconut palms. The grids do not feature any sub-transmission circuits or trunk feeders as one would see in larger and more densely populated areas internationally. This makes all of Tonga Power’s grids largely radial in nature with little ability to interconnect or mesh the networks to provide multiple transmission routes to key customers or core areas of service. The only area where there is scope for interconnection and sectionalising of feeders is in and around Nuku’alofa. Under the Nuku’alofa Upgrade Project, work is being planned for this financial year to overhaul and repair network switches to help manage interconnection issues. Under the Asset Management Plan, TPL has progressively introduced asset condition monitoring using the following methods in order to enhance reliability of supply and safety. Identifying locations of old assets (insulators, transformers, recloses, street light control

boxes, poles and undersized conductors etc.) through the GIS and replacing/maintaining them as per the maintenance plan.

Utilising innovative technologies such as Acoustic Inspections on overhead distribution assets to identify defects such as corrosion, pitting, tree contact, overheating, contamination, cracks, loose connections, and electrical discharges etc. All of which contribute to network losses and when rectified will reduce network faults in the field.

15

Page 16: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

In general, TPL meets the demand for electricity with reasonable and fair quality of power from its generating stations, but the poor quality networks in some remote villages can create local supply failure from time to time. The grids are being upgraded for reliability and resilience (with increased ability to isolate faulted sections) under the following projects:

New Zealand Government funded (MFAT $42 million and TPL $12 million) Tongatapu Village Network Upgrade Project (TVNUP) to upgrade 50 villages in Tongatapu.

ADB funded (ADB $5 million and TPL $1 million) Ha’apai Cyclone Ian Recovery Project. ADB funded (ADB 9.2 million and TPL $900 k) Outer Islands Renewable Energy Project –

Grid Rehabilitation. These initiatives have brought distribution power losses down to about 11.25% as at March, 2016. Tariff: As 92% of the electricity on the TPL grid is supplied from diesel generation, the price of diesel fuel is the major component of the electricity tariff. The tariff structure changed in May 2009 through regulation and became known as the “one tariff for all” regulation which makes the tariff consistent across all the four island groups. The historical tariff movement is shown in the graph below.

Tonga electricity tariff (currently at 69.99 seniti/kWh) consists of two components: Fuel Component (25.64 seniti/kWh) and Non-fuel Component (44.35 seniti/kWh). The tariff structure (i.e. splits) is shown in the figure below. Fuel cost accounts for around 37% of the current electricity tariff and TPL operating costs account for 63% of the electricity tariff.

16

Page 17: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

The Concession Contract requires changes to the fuel component of the tariff based on the cost of diesel as determined by Government through The Competent Authority. At intervals of three months (unless a shorter period is agreed), an independently developed pricing model sets the change of price for this component. The changes are recommended to the Electricity Commission for approvals in line with the Concession Contract. The non-fuel tariff will be reviewed and updated on a five yearly basis (also called regulatory period) as per the Concession Contract. Demand: Tongatapu’s peak load demand is about 8.4MW on average, and the electricity demand profiles (see the figure below) clearly reflect contributions from the commercial and residential sectors. In general, there are two (2) electricity peak demands on weekdays, i.e. late morning to early afternoon peak and then an evening peak. Analysis of the load profile shows that the major contributors to daytime load are commercial customers (primarily air-conditioning and lighting). The decrease in commercial sector activities in the afternoon (around 4pm) is replaced by the increase in the residential sector activities (primarily lighting and cooking) resulting in an evening peak around 8pm. Unfortunately, solar generation is not able to address this timing of peak load without adding a substantial storage facility. In general, mid-day peak demands during weekdays are higher than weekends and the differences are estimated around 15% to 20%. On Sundays, instantaneous solar penetration levels can reach 20% as requirement for diesel generation declines due to low demand.

17

Page 18: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Tongatapu Load Profiles

Customers: A recent Population Census in Tonga shows that around 93% of the total households have access to electricity. Growth in the number of electricity consumers has been less than 0.7% annually since 2005 until 2012 as all consumers within the reach of the grid have been connected. However, TPL has seen a 2% growth in the last couple of years due to increase in power use by residential and commercial customers. As at March, 2016, the total number of customers in all 4 island groups was approx. 22,000. Approximate Electricity consumptions by end-user sectors are shown in the figure below.

18

Page 19: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Energy Generation, Consumption and Losses: Total generation (diesel plus renewables) on all four island groups for the year ending June 2015 was about 55.4 GWh. This quantity of generation was slightly more than the quantity generated in the year ending June 2014 of 54.6 GWh reflecting a growth in the demand for electricity. Out of the total power generated, 49.1 GWh was billed to customers with parasitic and line losses contributing 1.4 GWh and 4.9 GWh respectively. The overall system losses reduced to 11.26% at end of June 2015.

Renewable Energy: In 2009, the Government of Tonga approved a goal of 50% of electricity to be generated from renewable energy sources by 2020. Under TERM and with TPL direct operational input, three major solar plants were constructed: Maama Mai (1.4MW) and Mata ‘o e La’a (1MW) in Tongatapu and La’a Lahi (420KW) in Vava’u. The Mata ‘o e La’a in Vaini and Maama Mai in Popua plants are supplied with short-term (60 seconds) energy storage to reduce the effects of power fluctuations. Vaini and Popua Solar facility incorporates a micro-grid controller, which automatically optimises the output from a mix of renewable energy and diesel generation whilst stabilizing the frequency. Although the 1.4 MW Maama Mai solar farm and the 1 MW Mata ‘o e La’a solar plant add to the existing generation capacity, the intermittency of the energy source means it cannot be relied on to provide firm capacity. Hence the solar facilities do not fully alleviate the requirement for replacement diesel generation capacity in the medium term. The La’a Lahi 500 kW solar facility is controlled to curtail output when the diesel generator output falls to 30% of capacity. This limits the solar plant to 440 kW peak output. In addition, TPL own 65KW roof-top micro solar capacity with 111KW of third-party micro solar capacity owned by private customers. Total fuel savings from renewable projects from their inception dates was approximately 2.8 million liters, which is equivalent to $4.4 million in cost savings passed directly to consumers.

Generation & Consumption 2010 2011 2012 2013 2014 2015

Generation (kWh) 51,845,271 53,159,568 52,391,468 53,312,873 54,560,742 55,404,581

Billed (kWh) 42,625,211 44,566,226 44,730,599 46,388,331 47,817,820 49,165,194

Total losses (kWh) 9,220,060 8,593,343 7,660,869 6,924,542 6,742,922 6,239,387

System losses (%) 17.78% 16.17% 14.62% 12.99% 12.36% 11.26%

System losses (Target %) 13.00% 13.00% 13.00% 13.00% 13.00% 13.00%

No. of Customers 20,773 20,758 20,498 20,580 20,633 20,932

19

Page 20: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Financial Strength: TPL’s revenue is generated from our 22,000 customers from all four island groups with over 85% from Tongatapu.

20

Page 21: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

During the past five years there has been a significant increase in generation from 51GWh to 55GWh per annum despite an economic decline along with rising costs. In the year 2015, the company generated approximately $46 million in revenue with $3.0 million net profit after tax (NPAT) followed by a $2 million dividend which TPL has paid to the shareholder Government.

4. POLICIES AND GUIDELINES GOVERNING THE DEVELOPMENT OF THE BUSINESS PLAN

4.1 Ownership Guidelines The Letter of Expectation, dated 8 April, 2015, states several guidelines from the Minister for Public Enterprises as to how the Tonga Power Limited should operate to which TPL strictly adheres to. The major ownership guidelines include: The company should operate as a successful business and, to this end, to be as profitable and

efficient as comparable businesses that are not state owned. In other words by practicing continuous improvement, profitability of the company is expected to progressively increase annually as efficiency and productivity increases.

A great emphasis should be placed on quality of service delivery to the electricity consumers. From the customer services at the counters to households around the country, electricity supply services must be people-oriented and customer-friendly.

All public fees and charges should be clearly justified and explained to all customers through public media which may include in weekly newspapers.

Customer complaints and criticisms should be viewed as opportunities to improve performance and transparency rather than a barrier to development.

There is an absolute requirement that Tonga Power advises the Ministry of anything of significance that arises or likely to arise and that has not been previously disclosed in the

30-Jun-15 2010 2011 2012 2013 2014 2015

Revenue $36,321,524 $40,124,291 $44,038,707 $41,782,742 $48,505,746 $46,100,465

Expenses $31,915,137 $35,172,632 $40,782,045 $38,844,083 $44,991,917 $43,554,963

Profit Before Tax $4,406,387 $4,951,659 $3,256,662 $2,938,659 $3,513,829 $2,545,502

Tax Expense $1,524,510 $1,237,915 $780,314 $713,692 $878,457 $636,376

Net Profit After Tax $2,881,877 $3,713,744 $2,476,348 $2,224,967 $2,635,372 $1,909,126

21

Page 22: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Business Plan or otherwise, particularly if the matter is likely to (i) be commented upon in the media; (ii) have political significance; or (iii) have a material impact on the performance of the company or (iv) have a material impact on the customers or other stakeholders.

The company should prepare and submit to the Ministry a sound Asset Management Plan (AMP) and a Business Continuity Plan (BCP). These plans should be consistently reviewed and updated as the situations change.

The company should develop and maintain a suitable Risk Management Framework. All the potential risks that the company is exposed to should be identified, assessed, evaluated and included in a Company Risk Register.

4.2 Obligations under the NSDF The Government of Tonga has initiated a National Strategic Development Framework (NSDF) for creating a Tonga where enterprises can flourish, opportunity exists for all, there is confidence to face the challenges of global society, development builds on Tonga’s strong cultural traditions and evolution takes place to address a rapidly changing world. The NSDF aims to improve electricity generation and distribution systems and its safe operation in order to improve the living standards of all Tongans. The framework highlights a desire to improve services, accountability, and revenue collection, as well as the coordination of development partners.

Tonga Power’s major obligations under the NSDF are:

Maintaining and where possible expand the provision of reliable and cost efficient power

supplies using traditional and renewable options to all communities. Strengthening regulatory compliance and safety oversight of the utility sector to ensure

compliance with international safety standards. Implementing the proposed priority projects outlined in the NIIP (National Infrastructure

Investment Plan). Investing in a healthy, well-educated, skilled and gender equal workforce. Enhancing staff development and training to increase the value added to our business. Fostering innovation and technological development. Maintaining good relations with development partners for mutual partnership, aid

effectiveness and donor harmonization. Improving profitability, accountability, and return on equity of our public enterprise.

4.3 Boards expectations The Board of Directors has a role to control and monitor management and take the reasonable steps to ensure best practice governance and compliance. The Board also has a strategic and advisory role, which includes taking steps to ensure proper corporate performance and value creation. The key is avoiding being dysfunctional between the Board and executive management and to elevate poor and possibly fatal business decisions, but more importantly to set the stage for mutual benefit, respect and value creation.

22

Page 23: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

The Board expectations from TPL are: Maximise shareholder value: The Board wants management to invest in value added projects

that maximise shareholder wealth and enhances profitability. No surprises or spin: There should not be any surprises for a Board. The CEO and senior

management need to be proactive and advise the Board of the true state of affairs and without any spin.

Bad news must reach the board ASAP: The Board needs to be the first to know of problems when they arise. Management needs to further develop the systems, processes and incentives within the organization that promote full transparency and reporting, right up to the Board and its committees.

Deep expertise in the business: The Board requires expertise across the full management bench with no gaps.

Visibility of management thinking: The Board should see proposed strategic options from management. Management’s thinking and assumptions need to be fully transparent to the Board, in writing and open to critique.

Full access to information: Information has five dimensions: quality, quantity, source, format and timeliness. There should be no information funneling or blockage to any dimension. In order to do its job, the Board will have reasonable access to TPL information as directed by the Chairman and ensuring the CEO is notified.

4.4 Energy Policy, Law and Legislation In recent years there have been several policy and legislative initiatives in Tonga aimed at improving the legal framework of the electricity sector and the implementation of fossil fuel (diesel) reduction programs and development of renewable energy projects.

23

Page 24: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

The Department of Energy of MEIDECC (Ministry of Energy, Information, Disaster Management, Environment and Climate Change) is mandated to govern the energy strategy in Tonga under the NSDF (National Strategic Development Framework) policy framework.

In 2008, the Electricity Commission (EC) was established as the regulatory agency for grid-based diesel generated electricity supply, replacing the former TEPB as the regulator. The EC is specifically involved in regulating the generation and sale of electrical power. The establishment of the EC was legally defined by the Electricity Act 2007. The Electricity Act 2007 provides the governance framework for the electricity sector. It defines the role of the EC in regulating the generation and sale of electricity and establishes the role of the Concession Contract in producing and delivering electricity. In addition, the Act provides the Ministry of Finance with the authority to be a signatory in the Concession Contract between the EC and the Concessionaire (TPL) and to establish regulations to ensure effective management of the electricity utility. TPL is required to operate as a successful business and to be as profitable and efficient under the Ministry of Public Enterprises Act 2010. The Act also requires TPL to report its performance on a periodical basis.

24

Page 25: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

The Renewable Energy Act 2010 also creates a Renewable Energy Authority within the Department of Energy of MEECCDMMIC to deal with matters concerning RE including both on-grid and off-grid uses under the Tonga Energy Road Map (TERM) 2010-2020.

TERM 2010-2020 was launched in June 2010. TERM consolidates the priorities highlighted in the National Infrastructure Investment Plan (NIIP) and National Strategic Planning Framework (NSDF) and sets out an aggressive set of targets for the electricity sector.

The NIIP outlines the Government of Tonga’s priorities and plans for the major initiatives in the economic infrastructure sector (energy, telecom, water, waste and transport) over the next 5 to 10 years.

25

Page 26: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

4.5 Purpose of the Public Enterprise

TPL’s core purpose is to deliver the Government of Tonga’s vision for the energy sector and to deliver on the nation’s target for energy via its strategies identified in this Business Plan. GoT also calls for TPL to be financially sustainable. The values and key imperatives are the foundation to successfully achieve our Core Purpose. All these elements together achieving the broader energy outcomes at national level.

Values Mission Vision Imperatives

Govt. Core Purpose Reduce Tonga’s vulnerability to oil price shocks, and achieve an

increase in quality access to modern energy services in an

affordable and environmentally sustainable manner

TPL Values Value customers, people

and the environment Run the business as if it’s

your own Think differently, and

capture the value Success as a team,

success as an individual TPL Key Imperatives

Reputation & transparency Best Practice & embracing

technology Low Cost & low price Meeting and Managing

shareholder expectations Recognised quality

customer service

TPL Mission To deliver the

nation’s core purpose via our strategies and Business Plan

To be financially sustainable

TPL Vision Safe, Reliable, Sustainable and Affordable service to the people of Tonga

Key Energy Outcomes: National security of

supply of energy Economic

development- competitive energy pricing, quality services

Standard of Living- making electricity available at every home

Low carbon energy

26

Page 27: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

5. PLANNING INPUTS

5.1 External Elements Legal, Policy & Environmental Issues: The major legal and environmental issues can be summarised into the following five categories and they are discussed in detail below.

Aggressive TERM objectives

Third Party Generation (off-grid) Third Party Generation (on-grid) Lack of safety regulations Tonga’s Climate

Aggressive TERM objectives: In order to reduce the vulnerability of the country to future oil price shocks, in April 2009, Government together with its development partners embarked on a process to develop the Tonga Energy Road Map 2010-2020 (TERM). One of the objectives of the TERM is to achieve 50% of national energy generation through renewable resources by 2012 - 2020. This target is considered aggressive and achievable by Tonga Power but may be hampered for the following reasons: There is a high level of dependence on donor funding for energy projects that result in long

lead times due to the availability of insufficient donated funds to develop selected renewable projects. To date, although commendable, only 8% of the national energy generation has been replaced by renewable energy.

Government’s public debt can make it difficult to obtain Government guarantees. As at January 2015, government’s public debt estimated at $392 million or 48% of GDP of which external debt (debt to China and development partners) accounts for $361 million and domestic debt (government bonds) is $30 million.

The relative cost of renewable energy tends to be high, particularly initial investment, although costs are reducing gradually.

The difficulty in obtaining funds from donors and the considerable time taken to implement donor funded projects forces TPL to look for funds elsewhere. Alternative opportunities available for TPL is to take on debts at concessional rates or outsourcing power generation to IPPs. Third Party Generation (off-grid): The Electricity Act 2007 allows third party or self-energy generation. In addition, The Renewable Energy Act 2010 allows anyone to generate, store or distribute renewable energy under a concession agreement with the Renewable Energy Authority. This imposes a significant revenue risk to TPL.

27

Page 28: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Tonga has a single tariff rate system which is pro-poor in that contributions to fixed costs varying with volume. Since approximately 80% of the revenue is generated from about 20% of large customer base (i.e. 80% of the customers are using less than 150kWh in Tonga) large customers in principle carry a large proportion of TPL’s fixed costs compared to small customers. Since the Electricity Act 2007 allows self-generation, it is financially viable for large customers (such as Tonga Police, Digicel, LDS Church, & TCC etc.) to generate their own electricity with off-grid power facilities (e.g. roof-top solar with a small diesel generator to supply power when sun is not available). This would eventually lead to significant revenue reduction for TPL from large customers. In the same manner, as allowed by The Renewable Act 2010, if any person generates, stores and distributes renewable energy to some selected customer segment using a mini off-grid system (outside TPL’s four island grid systems), TPL would lose its existing revenue from this customer base. If a significant number of parties continue to generate renewable energy using private owned or mini off-grid systems in this manner, TPL may have to increase its existing tariff base to cover its fixed costs. Third Party Generation (on-grid): On-grid or grid-connected systems are also called Distributed Generation (small or large) where third parties generate their own electricity and connect to TPL’s main network to inject surplus electricity or draw more electricity if there is deficit in the energy requirement. Distributed Generators connect to TPL’s network mainly because they do not have energy storage facilities for night use. TPL offers to manage Large Distributed Generation (LDG) through Power Purchase Agreements (PPA’s) negotiated on a case-by-case basis. Similar to the off-grid third-party generation, the on-grid distributed generation also brings significant revenue losses to TPL. However, this risk could be mitigated by constructing a suitable agreement including various mechanisms such as charging a grid availability charge or setting up a multi tariff system. However, there are other risks inherent in the distributed generation. They are: Loss of grid stability & security of supply: The private investment in renewable electricity

generation of capacity less than 10kW (i.e. SDG or small distributed generation) has impact on grid stability and security of supply in the medium and long run. The greater the degree of renewable penetration, the greater the impact on the centralised generation and distribution assets. This in turn imposes significant financial risks to TPL as it has to invest large amount of money on technologies such as smart technology which includes smart meters, storage facilities and micro-grid controllers to avoid grid instability.

Deterioration of generation assets: Due to the intermittent nature of third-party renewable generation, TPL should still maintain a large spinning reserve, keeping existing firm (diesel) generation operating at inefficient levels. This would see TPL incur extra diesel or other fuel costs and likely an accelerated rate of deterioration of existing diesel and other firm generators.

Renewable energy spillage: As more distributed generation are introduced to the network means that at some stage, TPL’s own renewable generation would become redundant due

28

Page 29: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

to surplus energy in the system. This surplus energy will have to be curtailed somehow and perhaps battery storage will provide a solution moving forward.

Economic by-pass: As mentioned above, the single tariff system in Tonga is pro-poor. The larger electricity users do cross-subsidise the smaller customers by carrying larger proportion of fixed costs. If large customers generate their own power without paying their contribution to fixed costs, the ability to cross-subsidise the smaller (largely “energy poor”) customers will be difficult to maintain.

Many people argue that third party on-grid distributed renewable generation is a good thing as it can achieve the TERM objective faster towards achieving the 50-100% renewable generation target. However, third party renewable generation may be unsustainable if not properly managed through a suitable PPA to recover non-fuel revenue loss and other TPL associated costs. TPL is in the process of implementing a Gross Metering Policy which can recover the non-fuel revenue that would otherwise have been lost. Limited safety regulations: Building wiring is not the responsibility of Tonga Power as TPL’s responsibility is up to the power entry point at the electricity meter only. House wiring is the responsibility of the Electricity Commission and qualified, licensed Electrical contractors. It is the responsibility of EC licensed electrical contractors to inspect the house wiring initially during construction of the building and conduct periodical inspections thereafter. There have been several deaths in Tonga over recent years due to poor electrical wiring. This reflects badly on TPL’s reputation and the Electricity Commission not to mention the sector in general. EC asserts that the old Wiring By-Laws developed and promulgated in 1985 are materially deficient in regard to electrical safety. The EC has argued that under the current regulations they have no authority to disconnect customers when an electrical hazard is found or reported by a third party. EC have drafted new safety regulations to replace the existing regulations in accordance with the New Zealand and Australian standards and submitted to the Government for promulgation which is still under consideration by the GoT. However, the paramount consideration of both EC and TPL is electrical safety and they shall take all reasonable measures to prevent electrical hazards which may include disconnection from TPL network. It is also worth noted that all electrical contractors in Tonga adopts the international AS/NZS 3000/2007 Wiring Code to ensure electrical wiring safety while the Regulation is still developed. Tonga Climate: The climate in Tonga is attractive for certain forms of renewable power generation including solar, wind and bio-mass etc. However, the hot weather gives rise to formation of tropical cyclones in Tongan seas on an annual basis. Cyclones often destroy TPL’s network and generation assets extensively. Even though insurance and surplus of donor funds are available to reconstruct the damaged network, this takes a considerable amount of time to bring the network back to a normal state of operation. This also imposes various economic and safety risks to the people of Tonga when the nation experiences prolonged outages.

29

Page 30: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Market Issues: The major market issues can be summarised into the following four categories and they are discussed in detail below.

Fuel price volatility Steady electricity demand growth Flat overseas remittances Shifting business landscape

Fuel Price Volatility: Petroleum dependency makes Tonga highly vulnerable to oil price shocks, affecting the affordability of food, goods, electricity and transportation. The reliance on fossil fuels has been exposing the Tongan economy to high electricity tariffs linked to volatile oil prices over the last decade. More than 90% of Tonga’s overall grid connected electricity demand was supplied by generators fueled by imported diesel. Linked to these fluctuations and the electricity tariff reached its peak in September 2008 at 102 seniti per kWh, and again in July 2011 at 98 seniti per kWh and then slowly dropping to 70 seniti per kWh in March, 2016 due to reduction in global fuel prices.

Shifting Business Landscape: The TERM along with the Renewable Energy Act, promote the use of renewable energy technologies to achieve 50% RE generation target. This represents a clear intention to reduce vulnerability to future oil price shocks and promote renewable energy to enhance energy security. The Act shifted the energy business landscape from a simple model to a more complex one as shown in the picture below.

30

Page 31: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

TPL is a vertically integrated business providing electricity to the four major island groups. TPL was established in 2008 to act as the concessionaire in Tonga’s regulated electricity regime. In outer island communities electricity is provided either by discrete diesel gen sets or Solar Home System serviced by community-owned cooperatives that act as ‘off-grid’ utilities and charge a fee to users.

The Government’s TERM aspirations mean that the business model will need to change to take into account a more complex market space, meeting new opportunities and risks faced by ‘donor funded’ and third party renewable energy projects. To this end, internal separation of the business will allocate costs to the various business units, enabling a better understanding of our efficiency drivers and allowing future time of day based tariffs (e.g. to incentivise energy storage). Steady Electricity Demand Growth: There are two sources of electricity demand growth, the addition of new customers and increased use by existing customers. Both are economically driven factors that may be expected to respond to economic change.

31

Page 32: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

In the 2015 year, TPL experienced a slight electricity demand growth of about 2%. For the coming years, electricity demand use by existing customers is likely to increase by about 3% to 5% due to economic growth factors such as airport runway upgrade, cyclone reconstruction, expected ramping up of preparations for the 2019 South Pacific Games, increase of small businesses such as retail and fast-food outlets, increase in street lights, and increasing agricultural production and tourism activities. Asian Development Bank (2016) has predicted about 3% increase in GDP growth for the years 2016 and 2017 mainly due to the increasing economic activities as a result of decreasing fuel prices. GDP growth for the year 2015 was recorded at 3.4%. Other domestic factors that drive demand for electricity supply are increases in household appliance numbers due to better quality of life aspirations, the return of wealthy Tongans from overseas and arrival of expatriates. The factors that drive down the electricity demand are the installation of energy saving light bulbs, the use of energy efficient appliances and off-grid renewable energy sources (e.g. Solar). The genuine growth opportunities mentioned above are subject to considerable uncertainty but may be slightly on an increasing trend for the next few years and depend largely on the effectiveness of energy efficiency campaigns over the coming years. Flat Overseas Remittances: Like many other Pacific island nations, Tonga has become economically dependent on migrant remittances and foreign aid as its major sources of revenue. At the national level, remittances are the major source of foreign exchange and accounted in 2007 for about 50 percent of GDP. At the village and household levels, remittances are an integral part of income and consumption. In addition to receiving shipping containers filled with appliances, clothing, toys, and building materials, villagers are regularly sent cash remittances by their relatives overseas.

32

Page 33: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Seventy-five percent of all Tongan households report receiving remittances from overseas (mainly New Zealand, Australia and United States), making remittances the single most widespread source of income in Tonga. As a result of the global financial crises, however, a steep decline of private cash remittances being sent to Tonga was reported in 2008/09. Since then the remittances shrunk by about 60% by the end of 2014 and accounted about for about 12% of GDP. However, remittances saw a significant increase in the last year (to USD92 million) mainly due to the following reasons:

Private transfers for the celebrations of King’s Coronation and church conferences Weakening of Tongan dollar against US dollar Improvement of overseas economies such as USA and Australia.

If the flat or declining remittances continues into the future, some less fortunate villagers in Tonga may not be able to pay their electricity bills on time and the result would be to face disconnection of power supply.

33

Page 34: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

External Business Risks: The following risk analysis shows the risks inherent from the above legal, political, environmental, market and social issues. The suggested mitigation controls and the current level of control effectiveness are also shown in the table:

Risk Description Mitigation Control Control Effectiveness

Significant business continuity risk to TPL due to significant tariff

increases hence economic inefficiency for poor customers if large

customers move to off-grid renewable generation plus storage.

This is a rare risk. It is expected that tariff will

decrease significantly by 2020 with the 50% RE

penetration target preventing large customers

going off-grid.

Partially Effective

Significant business continuity risk to TPL due to reduction in

non-fuel revenue, poor fuel efficiency and increase in diesel

generation maintenance costs (hence tariff increase) resulting

from likely increase of on-grid distributed renewable generation.

TPL has put in place Gross Metering policy to

protect its non-fuel revenue. Storage, smart-

grid & smart-meter solutions will be used to

address the technical risks.

Partially Effective

Significant financial and reputation losses to TPL due to public

lawsuit taken against the company as a result of members of

public getting electrocuted from poor house wiring.

TPL take all possible actions to increase safety

awareness to public from electrical hazards.

However, new safety regulations must be

promulgated with the recommendation of

Electricity Commission to hold parties

accountable.

Ineffective

Significant business continuity risks to TPL due to hot weather in

Tonga that forms tropical cyclones and destroy large portion of

TPL distribution/generation assets. The recovering from a

cyclone takes a considerable amount of time leaving people of

Tonga without power.

Insurance and donor funds are available to

reconstruct the network and power station

assets. But TPL's Business Continuity Plan

provides the speedy recovery.

Effective

Significant financial and reputation losses to TPL due to any

public discontent resulting from unaffordable electricity tariffs

through rising oil price.

Tonga's current electricity price has reduced to

69.9s/kWh due to reduction in global fuel

price. The 50% RE penetration and engaging in

effective fuel hedging strategies will also help

reduce tariff.

Effective

Significant revenue loss to TPL as a result of slow electricity

demand growth in Tonga.

Government policy formation to encourage

population growth and economic efficiency

activities. Reduction of electricity tariff through

global oil price reduction and introduction of

RE sources.

Partially Effective

External Business Risks

34

Page 35: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

5.2 Internal Elements People Issues: Tonga Power has a skilled and experienced senior management team consisting both local and expatriate staff. The company structure below shows the CEO, senior managers and their subordinates in each business unit.

The number of established staff at Tonga Power Limited has increased to 180. Around 25 of our staff are dedicated to implementation of the projects, including development of new generation, customer and network initiatives as well as the trainee linesmen and women working on the village project. Distribution field staff are subjected to line mechanic training with financial support from the New Zealand Government. Training brings all field staff to a level where they will have qualifications (New Zealand Qualification Accreditation or NZQA) that will be recognised internationally, and will be certified by the Electricity Supply Industry Training Organisation (ESITO). Line staff will become increasingly sought after by New Zealand and potentially Australian line companies and contractors. Arrangements have been put in place for ongoing recruitment and transfer of trained line staff into a New Zealand contracting company, a unique opportunity for these employees to further develop their skills and improve their lifestyles overseas. Tonga Power wants to facilitate these opportunities, but it means strengthening its staff recruitment and training processes and managing the loss of key personnel.

35

Page 36: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Ongoing refresher training in first aid and fire safety / control keeps staff aware of managing a safe working environment. Our zero accident target has helped change working habits. The safety officer acts as the watchdog. Staff are encouraged to report near misses, which are seen as a means to drive continuous improvement. This is a difficult transition, as the natural response to a near miss or accident is not to report it. Increased focus on safety as the number one priority, coupled with monthly Health and Safety meetings will help deliver and operations around a culture of continuous improvement. Diesel generators will continue to provide the bulk of Tonga’s power generation into the foreseeable future. Staff with a background in diesel engines/operations will be pivotal to the continuing smooth operation of our power stations. As more distributed generation is planned for the future, generation staff will have the advantage of understanding both generating units and network response. Developing staff to monitor and control the network from a central control perspective will not be a huge stretch. However, trainings and development programs are planned in order to keep operations safe as well as maintaining reliability. Specific HSE initiatives are managed by the individual business unit managers. In addition, Risk & Compliance division administers the compliance reporting and monthly HSE committee meetings. Tonga Power is a vertically integrated utility providing services to the people of Tonga, but we also develop both new capacities within the core business and undertake new business opportunities for which we will require to introduce new skills and resources. Examples include increasing our involvement in the gas and fuel sectors, financial reporting, communications and marketing skills, engineering design expertise, and project and commercial management. The table below summarises areas of existing capability and areas in need of development.

36

Page 37: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Physical Assets/Equipment Issues: Both Generation and Distribution Asset Management Plans address issues regarding network or power station assets. Some of the major issues are highlighted below. Deteriorated network assets: When Tonga Power acquired the electricity generation and distribution business from the previous owner in 2008, it inherited a deteriorated and inefficient network. The condition of the network assets was very poor in all four island grids. Most of the poles were ‘stick poles’, distribution lines were low hanging so low that the public were able to touch, pole top equipment were run down, the connectors at the transformer were loose and too many loads were connected to one transformer. The poor quality network presented several risks: high level of losses, estimated to be up to 20%, voltage fluctuations causing damages to household appliances and safety hazard to the public. Upon acquisition by TPL, this poor network status was improved in safety and reliability. The New Zealand Government through the New Zealand Aid Program has generously donated a total of NZD$32 million to finance the Tonga Village Network Upgrade Project (TVNUP) with $7.5 million as TPL’s contribution, which runs in three stages. The TVNUP targets about 50 villages with the worst stick pole networks, the poorest electricity transmission, and are the greatest distance from the capital, Nuku‘alofa. The first phase of the project started in June 2011 and the final stage of the project is expected to be completed in May, 2018. The TVNUP project helps improve the Tongatapu village network largely. However, Nuku’alofa CBD and outer island network status still require further improvement. The poor state of equipment on these networks include de-rated cables, broken insulators, weak poles, broken air-break switches, incorrect HV/LV fuses, over utilized transformers and connectors and much more. The company is still seeking donated funds to improve these networks. SCADA (Supervisory Control and Data Acquisition) System: The SCADA systems installed at Tongatapu (Popua) and Vava’u has been a useful tool for generation (for ongoing monitoring of the engines and generators) and distribution network planning. In the Power Station, each generator can be monitored on a shift by shift basis for fuel use and efficiency. The data is helpful in monitoring any fuel losses including theft as well as engine condition monitoring. However, there are limitations to TPL’s current SCADA capabilities. Ha’apai and ‘Eua do not have SCADA systems; these power stations use utility metering with logging capabilities to capture electrical parameters, with the engine parameters monitored locally. In addition, SCADA parameters cannot be monitored from the Tongatapu main Power Station due to lack of remote communication capabilities. TPL is waiting to use either Satellite or Fiber communication links to monitor outer island power station equipment performance.

37

Page 38: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Security of supply (N-1): TPL’s Security of Supply Policy ensures enough FIRM (diesel) generation capacity is available at short notice to cover faults or to meet sudden changes in consumer demand. In other words, if the largest capacity generator is out of action due to a breakdown, other generators in the fleet must be able to continue to supply power to meet the consumer demand at any time of the day. The solution for the N-1 redundancy policy is to duplicate the largest generator in each of TPL’s four power stations. The policy assumed intermittent generation (solar and wind) cannot be relied on at any time and are excluded. Currently Tongatapu and all three outer islands meet the N-1 security policy; however, there is slight ambiguity of maintaining the reliability of supply due to potential load growth during the upcoming Pacific Games in 2019. Tongatapu Submarine Cables: The two submarine cables (armoured three core PILCSWA 70mm2 Cu) across the lagoon, from Popua to the pole line at Folaha, connecting the station supply to existing Feeder Three (Vaini), are about 30 years old and are due for replacement. The two (2) cables are not rated submarine cables, one cable has failed already and the other cable is at the end of its useful life and may fail anytime. This presents a higher probability of failure than TPL can allow when considering the risks and consequences of an unplanned failure. In addition, TPL has established that there is no equipment available at short notice on Tongatapu that could assist in locating an underwater cable fault. This leads to the possibility that it would eventually require (in the event of identifying the location of the fault) lifting the cable and completing a repair. TPL considers the cost and time delay would lead to an unsatisfactory outage time for Feeder Three. The replacement of this cable will also ensure a capacity that anticipates future load growth considerations. It is expected that if the submarine cable (i.e. feeder 3) fails, customers on feeder 3 can be supplied by back-feeding from the feeder 1, however, this could lead to overload of feeder 1 causing supply to feeder 1 customers to also fail. Bulk Diesel Storage Tank: TPL currently has only one bulk storage tank installed at the Popua Power Station. The present storage tank has a capacity of 250,000 liters and supplies fuel to diesel generators for 10 days (25,000 liters supply per day). However, in case of catastrophic damage to the present tank due to a disaster (e.g. earthquake, fire etc.), the power station does not have any redundancy plan for storage of fuel for generation of electricity. TPL will build a second storage tank with the same capacity in the very near future. Generator Replacement: Tongatapu (Popua) power station has six CAT generators (3516B) and two MAK generator (6CM32). All six 1400KW CAT generators have come to their end of their economic lives, hence, requires replacement. TPL have put in place plans to retire existing CAT generators and replace them with new generators or refurbish them at low costs. The risk is not that significant as long as the old generators are replaced or refurbish at regular intervals in the future in accordance with the manufactures’ recommendations. Outer island generators, however, have been overhauled in a timely manner, thus have no such risks. However, it should be noted that TPL is moving towards the 50% renewable energy (including energy storage solutions) penetration by 2020. In this case, these generators will not be made operational on a continuous basis but will be used as future backup firm generation. It is

38

Page 39: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

important to note that the majority of the engineering and planning for the incorporation of renewable energy into the electricity grid has been based on the current diesel generation portfolio. Therefore refurbishment of the existing generators would be beneficial with continuity of the future development plans. Product/Service and Supply Issues: Services standards: TPL’s service standards to consumers are regulated through the Electricity Concession Contract. Any violations of these standards contribute to rule breaches and payment of penalties by TPL to affected customers. A summary of these services standards are described below:

Maximum time for new connection (<30 meters – 4&10 days, >30 meters – 10&20 days) Minimum notification time prior to disconnection (5 days) Reconnection after payment of arrears & reconnection fee (1 day –rural, 2 days – urban) Maximum time for first bill to be delivered (50 days) Maximum time between bills (45 days) Respond to customer queries (5 days) Maximum time for power supply connection – maintenance works (5 days advertise in

the wider media) Temporary disconnection of supply for maintenance (2 days) Response time to emergency or faults calls (2 days) Voltage stability standards (240V +/- 10% & 415 +/- 5%) Response to voltage test requirements (5 days) Fuel efficiency target (4.0kWh/L) System loss target (12%)

TPL is in compliance with all the above requirements except the voltage stability standard. Occasionally, breach of this standard occurs due to poor quality networks. Customer complaints: TPL manages all customer complaints through its Customer Complaints Management Policy. All complaints are reported to the Board on a monthly basis. There are on average about 40 customer complaints from all four island groups per month, and mainly relation to: incorrect meter reading, not receiving a power bill, incorrect bill received, over/under voltage, meter error, over charge, high consumption, and power not connected after disconnection for non-payment etc. Unsafe working practices: TPL staff are well trained in ESITO L2, L3 and L4 requirements for working in electrical network equipment installation activities. However, occasionally, they unintentionally carry out unsafe working practices that in the past has included incorrect cable and equipment installation due to ambiguity and/or a lack of training. This has caused damages to customers’ household appliances resulting in compensations to be paid by the company however the major risk is the lives of the public and those staff involved. Power quality: Occasionally TPL is in breach of power quality (voltage and frequency) standards due to the poor state of the network equipment. In these occasions TPL pays

39

Page 40: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

compensations to the affected customers upon completion of an investigation conducted by TPL engineers and if necessary by independent sources. Reliability of supply: Reliability measures indicate the average interruption time (in minutes) that a customer experiences power outage due to a network failure for a certain period, which can be for up to a month or more. The key reliability measure TPL uses is SAIDI (System Average Interruption Duration Index), which measures the average total duration of interruption per connected customer. During the last 2014/15 financial year, on average a connected customer has experienced about 1058 minutes (about 1.4 hours per month) power outage. This value is quite high when compared with countries such as New Zealand or Australia but quite acceptable for pacific island countries like Tonga. However, it is important to note that about 50% these outages have been caused by planned events mainly for the network upgrade projects. Business Systems and other Resources: TPL uses various software systems for different purposes by different business units. A summary of software systems used by TPL are shown in the table below.

There are issues associated with the use of the above softwares as described below:

File Maker Asset Management Software (FMAM) – the reports generated from FMAM software are sometimes incorrect (e.g. SAIDI data). This leads company to making incorrect decisions. The main reason behind this is that users input incorrect raw data which in turn produces incorrect output reports.

GIS Software – requires upgrade and update. Sincal Software – requires upgrade and update.

TPL has started an Enterprise Resource Planning (ERP) project which will unify some of the above software systems into one single software platform.

Software Name Purpose

Orion Billing System Billing and customer relations management

QuickBooks Accounting Software Accounting and reporting

File Maker Asset Management Software Asset management, maintenance and network auditing

Quantate Risk Management Software Risk analysis and reporting

GIS Software Geographical interface system

Sincal Software Load flow analysis

Xsol Software Business process redesign and mapping

TPL Business Systems

40

Page 41: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Internal Business Risks: The following risk analysis shows the risks inherent from the above internal issues. The suggested mitigation controls and the current level of control effectiveness are also shown in the table.

Risk Description Mitigation Control Control Effectiveness

Significant financial and reputation losses to TPL due to payment

of high penalties to customers when customers' household

appliances are damaged or when they receive serious electrical

shocks from voltage surge resulting from loose neutral connections

at the transformers.

Expedite transformer inspection program to

identify loose neutral connections at the

transformers. TVNUP project also help

mitigating this risk.

Partially Effective

Significant revenue loss to TPL due to poor state of the Nuku'alofa

and outer island distribution networks that contribute to high line

losses and voltage fluctuations.

Nuku'alofa and outer island Network Upgrade

projects have been planned. TPL is waiting to

receive funds from potential development

partners.

Ineffective

Significant revenue and reputation loss to TPL due to non-

achievement of N-1 security policy as a result of ageing generators

which could go out of actions any time of the day due to sudden

breakdowns.

Generators must be maintained and replaced as

per the manufactures'' recommendations. A

generator replacement plan is in place for all

four island power stations.

Partially Effective

Significant health impact on the power station staff due to

excessive noise levels emanated from the large diesel engines.

Current noise level is 110-120dBA in the power station which is

greater than permissible level of 50dBA.

Ear muffs are available at the moment. Noise

pollution could be further improved by

installing sound proof doors and windows (e.g.

double glaze vacuum windows and doors).

Effective

Significant financial and reputation risks to TPL due to public

fatality or serious injury to a member of the public by touching low

hanging live LV conductors.

Survey non TVNUP villages and outer island

networks to identify and fix low hanging LV

conductors or conductors close to buildings.

Partially Effective

Significant financial, reputation and HSE risks to TPL due to injury,

death, or public legal action against TPL as a result of staff carrying

out unsafe working practices and installation of incorrect

equipment.

Safety and network construction training

provided to all staff ESITO and NZQA standards,

L2, L3 and some L4 (not enough certified

equipment for all L4 certification). Develop a

design and construction manual to be used by

staff during installations.

Effective

Significant financial and reputational risk to TPL due to incorrect

reports generated from the File Maker software. This makes

company making incorrect decisions.

New ERP system will replace the existing File

Maker software. Until then, systems users must

be trained to manage the system accurately.

Partially Effective

Internal Business Risks

41

Page 42: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

5.3 Summary and SWOT analysis

Strengths Weaknesses TPL’s reputation as a best performing vertically

integrated Electricity Generation and Distribution Company in the Pacific.

Electricity Concession Contract (ECC) provides the foundation for TPL stay to in business. ECC encourages donors and development partners to release debt and donor funds.

Established four island network and power station facilities and assets worth of $110M.

Strong liquidity ratio of 1.4 meaning that company has sufficient cash to service short-term debt obligations.

Strong capital structure or low gearing: 25% debt: 75% equity.

Experienced and skilled senior management team consisting both local and expat staff.

World class systems and tools have been established to perform company operations smoothly.

Lower electricity tariff at 69.9 s/kWh.

Accomplished system losses and fuel efficiency rates.

Much improved distribution network to provide reliability of supply.

TPL complies with all the service standards and efficiency targets stipulated in the Electricity Concession Contract.

Ability to earn non-tariff revenue outside the energy selling business (e.g. service lines, street lights etc.). This is about $2M per annum.

Skilful and intelligent board who make well informed strategic decisions.

Customer growth is expected to increase by about 3 to 5% per annum over the next four years.

Government’s support for raising donor funds for future RE projects to achieve 50% RE penetration.

Reduction in customer complaints.

Nuku’alofa CBD and some of the outer island grids are still at poor quality state contributing significant amount of outages, energy losses and safety issues.

A greater focus is placed on Tongatapu development activities (both distribution and generation) leaving less attention on outer islands.

Deteriorated network and ageing generation assets in some areas.

Loose or broken neutral connections at the transformers cause some customers to experience line voltages (i.e. 415V) instead of phase (230V) voltage causing damages to household appliances. TPL paying significant amount of compensation for these damaged appliances.

Crews conduct unsafe working practices on the network. They should be given adequate refreshment training.

Reliability of supply measured in minutes of supply interruption time (SAIDI) getting worst shown through the rising SAIDI min’s trend.

Reports generated from File Maker software are sometimes inaccurate due to incorrect input data.

GIS to be upgraded and updated.

Obsolete network design & construction manual.

Wasting considerable amount of time on researching technologically unproven project initiatives (e.g. bio-diesel, wave technology, water to power etc.)

Increasing workload on existing senior management due to company growth.

42

Page 43: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Threats Opportunities Electrical and the Renewable Energy Acts allow

third parties to self-generate (off-grid or on-grid) renewable energy causing revenue reduction to TPL and as a result tariff could increase further.

Increasing RE penetration to achieve the TERM objectives leads to loss of grid stability, safety, reliability of supply and increase generation asset maintenance cost.

Increasing off-grid RE penetration by large customers leads to economic inefficiency and leaving poor people more vulnerable to further tariff increases.

Increasing RE penetration causes fuel efficiency to decrease due to reduction of load factors from their intermittent operations.

Lack of safety regulation in Tonga makes it impossible to hold parties accountable when there is an electrical accident.

Tonga’s vulnerability to tropical cyclones means that it takes a considerable amount of time to restore the electricity network once destroyed by a cyclone.

Highly volatile fuel prices expose to high electricity tariff in Tonga.

Slow electricity demand growth in some years reduces cash inflows to TPL and making it unable to invest on efficiency improvement projects.

Possible reduction in migrant remittance causes people to use less electricity and exposes people to disconnection when they are unable to pay their bills on time.

Donors reluctant to fund money on projects due to various reasons.

Access to donor funds for RE generation and grid improvement projects.

Policy makers should be influenced to discourage off-grid RE generation.

Design and develop suitable power transfer agreement with DG owners to recover all TPL’s costs.

Increasing RE penetration provides TPL an opportunity to embrace smart-grid technologies to provide grid-stability and reliability. DG generation sources can be disconnected using smart-grid technology when they have a negative impact on the generators load factors.

Opportunity to look for multi-tariff structures with increased RE penetration (e.g. life-line tariff, demand based tariff at the peak time, RE use tariff etc.)

TPL should manage most of the RE generation projects placing a maximum limit for customer owned distributed generation.

Encourage EC to promulgate safety regulations through the government.

Seek help from development partners for speedy recovery of the network destroyed by the cyclone.

Achieving government/TERM objective of 50% RE generation leads to significant tariff reduction if the projects are donor funded.

Encouraging government policy makers to boost the economy so that more people use electricity.

High RE penetration could reduce the diesel generators base load requirement. This enables opportunity to draw donor funds to replace them with small generators.

Seek cheaper IPPs who sell electricity to TPL at lower rates than cost of supply.

43

Page 44: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

6. PLANNING PERIOD STRATEGIC OBJECTIVES & CHALLANGES The following table shows six key strategic objectives formed by TPL during a recent strategy update workshop for the next four years. The benefits from each strategic objective, key challenges that TPL faces when pursuing these objectives, and how they relate to our overall vision are also shown in the table.

ID Strategic Objective Benefits Link to Vision Key Challenges

1

Achieving 50% electricity generation from

RE sources by 2020 in order to achieve the

government and TERM objective as well as

significant tariff reductions.

Tariff reduction, Increase

economic efficiency and growth

Affordability,

Sustainability

Seeking funding for selected projects, building

relationships with donors, slow progress rate,

managing power purchase agreement with IPP

owners.

2

Adopting technologies to manage the

complexities arising from increasing RE

penetration.

Enhance grid stability, security,

safety and reliability of supply

Safety, Reliability,

Sustainability

Very expensive to implement smart-grid

technology, may difficult to seek funding for asset

improvement/replacement, immature energy

storage technologies, develop/update asset

management plans.

3

Improving the network and replacing

ageing assets to improve safety and

reliability of TPL's services.

Improve power quality, line

losses, and reliability of supply

(or N-1 security)

Safety, Reliability,

Sustainability,

Affordability

Seeking funding for selected projects; update

asset management plans, compliance with ECC

standards, human resource availability.

4

Cultivating a hazard free safety culture to

minimize any electrical hazards to both

public and staff.

Reduce number of hazards,

incidents, accidents and near

misses

SafetyRegulation promulgation takes considerable

amount of time, HSE structure requires clarity.

5

Investing in excellent business processes

and systems in order to improve

operational efficiency and quality of TPL's

services to customers.

Reduce non-value added,

increase quality of service,

reduction in customer

complaints, increase

employee/customer satisfaction

Sustainability

Key staff constraints leading to outsourcing,

minimising very high consultation costs,

compliance with overburden policies and

procedures.

6

Managing all external funding and internal

financing sources successfully in order to

maximise the shareholder wealth for the

best interest of the company and the

people of Tonga.

Cost reduction, increase profit,

tariff reduction through

investing on right projects

Affordability,

Sustainability

Seeking free or low cost funding, lack of clear

policies on hedging, self/group interest on

implementing wrong projects, possible

government tariff freeze, unfavourable economic

activities.

Strategic Objectives & Challenges for the Planning Period 2017 -2020

44

Page 45: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

These strategic objectives are discussed in detail below:

6.1 Strategic Objective 1 In-order to deliver the Government’s renewable energy target of 50% electricity generation from renewables by 2020 as well as applying sustained downward pressure on the electricity tariff for all customers, TPL plans to complete the following projects during the 2017-2020 planning period. Some of these projects (up to case 4) have already been completed, and others will be completed before 2020 with either donor funding, TPL funding, debt funding or under a PPA by IPP as shown in the table below. It is assumed the majority of TPL’s investment in these projects will likely increase the non-fuel component of tariff but overall a net reduction in tariff (up to 20 seniti/kWh) will result due to a greater off-set resulting from the substitution of fuel through the fuel component of the tariff.

Solar: Solar power is the conversion of sunlight into electricity directly using photovoltaics (PV) technology. Photovoltaics were initially solely used as a source of electricity for small and medium-sized applications, from the calculator powered by a single solar cell to remote homes powered by an off-grid rooftop PV system. However, solar PV is rapidly becoming inexpensive, hence grid-connected solar PV systems and medium size utility-scale solar power stations can be built in Tonga to harness renewable energy from the Sun.

Case Plant InvolvedIncremental

Peak kW Year Built

Accumulated Peak

Output (kW)

Annual Energy

Output (MWh)

Accumulated

Energy (MWh)

Net Penetration

(%)

1 Maama Mai (PV) 1,332 2012 1,332 2,100 2,100 4%

2 La'a Lahi (Vavau Solar) (PV) 420 2013 1,752 662 2,763 5%

3 Case 2 + Vaini PV 1,000 2015 2,752 1,577 4,339 8%

4 Case 3 + 320KW SDG PV 320 2012 3,072 505 4,844 9%

5Case 4 + 300KW

(Police/Digicel) PV 300 2015 3,372 473 5,317 10%

6Case 5 + 750KW OIREP PV

(550KW Ha'apai + 200KW Eua) 750 2016 4,122 2,168 7,485 14%

7 Case 6 + 1.3MW IPP Solar PV 1,300 2016 5,422 2,050 9,535 17%

8 Case 7 +2.2MW Wind 2,200 2017 7,622 6,360 15,895 29%

9 Case 8 + 2.2MW Wind 2,200 2017 9,822 6,360 22,254 35%

10 Case 9 + 3x1.3MW Solar PV 3,900 2019 13,722 6,150 28,404 41%

11 Case 10 + 2.2MW Wind 2,200 2019 15,922 6,360 34,764 52%

12Case 11 + 3MW (18MWh) IPP

Storage 3,000 2019 18,922 5,585 40,348 61%

Road to 50% RE Penetration

45

Page 46: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Wind: Wind powered generation is one of the most mature and cost-effective renewable technologies available today. Although wind resource measurements in Tonga have had varying results, simulations show wind generation could be cost effective on Tongatapu due to the high cost of diesel. A wind farm of 6.6MW could produce 20% of Tonga’s electricity. Small wind is also an option for outer islands and/or remote locations. Storage: Electrical energy from renewable energy sources could be stored in storage devices (e.g. Lithium-ion or Redox flow batteries) when their production exceeds the load demand and returned to the grid when production falls below the load demand. Storage would help to shave Tonga’s peak demand at night time, ramp-control/frequency regulation and provide reserve capacity in the supply system. Storage systems, however, are expensive to adopt at the moment but storage prices are expected to come down in the future. Key challenges faced by the objective are: Achieving 50% electricity generation from renewables by 2020 although quite ambitious is

very achievable. Fast tracking of project development and pre-emptive implementation does not come without risk and will need to be properly managed by TPL.

Developing appropriate Power Purchase (PPA) Agreements with IPP owners and managing outcomes will present a challenge to TPL. Outsourcing energy from IPP owners’ enables cost saving (both fuel and non-fuel). At the same time TPL has to incur additional expenses including the cost of automation to monitor IPP’s RE generation facility to ensure safety and stability with fuel savings being passed through to customers.

Seeking funding for selected projects and building relationships with development partners remains a priority but is also a challenge to TPL. There remains a high level of dependence on donor funding for projects which tends to result in longer lead times.

Most donor-funded projects have a very strict policy on the origin of equipment that may not be optimal for Tonga’s climate.

The cost of electricity generation from renewable energy sources relative to generation from tradition energy sources still tends to be higher although costs continue to decline.

6.2 Strategic Objective 2 TPL’s distribution system traditionally comprised of radial circuits fed from a centralised power station and designed to supply load based on customer demand while maintaining an adequate level of power quality and reliability in compliance with the Electricity Concession Contract. Protection is based on relays and fuses that use nested time delays to clear faults by opening the closest protective device to a fault and minimise interruptions. It is designed to safely clear faults and get customers back in service as quickly as possible. Sectionalising switches are manually controlled to restore load in un-faulted sections downstream from the failure. TPL’s current distribution systems are generally considered to be ready to support small DG sources without change, however, with increasing RE penetration, TPL’s current power distribution system may experience complications in connecting to RE sources.

46

Page 47: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Therefore, as aggregations of RE continue to grow, changes in design and control practices will eventually be required at all levels of the power system. The limitations of TPL’s current system are: Current voltage control is achieved with devices that have localised controls. These

schemes work well for today’s radial circuits (where flow is outward from the power station to loads) but do not handle circuit reconfigurations and voltage impacts of locally distributed intermittent RE systems well.

Similarly, for radial distribution systems, fault current protection is predicted on the

principle that current flows from the power station to the loads. The presence of distributed RE sources introduces new sources of fault currents that can change direction of flow, introducing new fault current paths, increase fault current magnitudes, and redirect ground fault currents in ways that can be problematic for certain types of overcurrent protection schemes.

Minimal communication and metering infrastructure is in place to aid in restoration

following faults on the system. Limited communication infrastructure exists to facilitate control and management

of distributed RE and storage resources. Without communication and control, the high penetration of RE generation on most circuits will be limited.

There is no communication to customer facilities to allow customers and customer

loads to react to electricity price changes during on/off peak times. Some automation schemes are being implemented to reconfigure circuits to improve

reliability, but these schemes do not achieve the coordinated control needed to improve energy efficiency, manage demand and reduce system losses.

High penetration of RE can cause a reversal of power flow direction on the primary

feeders leading to lack of coordination or sensing in protection devices.

Increasing RE sources can significantly stress network equipment such as transformers due to its cyclic output variations.

To directly address the issues related to connecting large amounts of RE sources in the distribution system, smart-grid technological requirements in three key areas are required:

47

Page 48: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Key challenges faced by the objective are: High cost associated with the implementation of smart-grid technology means TPL has to

turn to donors for funding. Difficult to gain Board approval on high-tech projects because the high cost of

implementation can often outweigh the economic benefits from the project. Additionally the economic benefits are not always as direct as compared to say introduction of renewable energy and therefore take time to adequately appraise and provide to the Board for decision.

Category Smart Grid Technological Requirements

All Diesel and RE generators should communicate with each other in a manner that ensures adequate

load sharing, system stability, proper frequency and voltage control, and optimal system performance in

terms of efficiency and energy production cost.

Energy storage devices should be used to correct temporary load/generation mismatches, regulate

frequency, mitigate flicker, as a result of fluctuating RE sources and assist advanced islanding functions

and service restoration.

RE sources should be made to participate actively in the scheme by adjusting reactive or real power

levels as needed. Transformers, voltage regulators, local inverter regulators and switched capacitors

should be interactive with each other by means of communication links with a control point to ensure

voltage stability and required reactive power flow.

Inverters should be used to prevent unacceptable voltage conditions in the local RE unit.

Advanced inverters/controllers and energy management systems (EMS) should be sophisticated enough

to interface with smart-grid technology to maximise efficiency, quality and reliability.

The distribution systems should include more extensive use of directional relaying, communication

based transfer trips, pilot signal relaying, and impedance-based fault protection schemes to work

effectively with multiple distributed RE sources on the distribution system.

Sectionalising schemes for interactive service restoration should enable distributed RE systems to pick

help pick load during the restoration process.

Distributed RE and distribution devices should address grounding incompatibilities among power system

sensing, protection and harmonic flows.

Over current protection should involves coordinated operation of many devices including circuit

breakers, relays (differential or directional), reclosers, sectionalising switches, and various types fuses.

Increasing RE sources can significantly stress network devices such as transformers. Through advanced

status monitoring of network assets a replacement can be scheduled before the device fails or causes an

outage.

Monitoring voltage profiles (and power factors) at various points of the distribution lines and loads to

assess impacts on the customers and take corrective actions to avoid any voltage regulation breaches.

Automatic fault location and restoration by reconfiguring feeders to identify fault locations and route

around fault locations.

Smart meters should be installed at the customer supply point in order to manage customer loads

remotely.

Smart metering technology helps to provide consumers with information that allows them to use

electricity only when it is available from renewable at cheaper price.

Smart meters can also be used to collect data on power quality, power outages, power factor, reactive

power usage, and grid voltage and frequency to be used in the control of RE generation sources.

Power Generation

Distribution

Customer Supply

48

Page 49: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

6.3 Strategic Objective 3 Strategic objective 3 focuses on successful asset management activities such as procuring, maintaining and renewing/replacing network and generator assets in order to improve the asset condition to enhance power quality, safety and reliability. TPL inherited a substantial amount of ageing and/or defective assets from the previous owner. These include ‘stick’ poles, inefficient transformers, broken or damaged insulators, fretted cables, and ageing generators. The deficient assets exposed TPL for non-compliance with frequency, fuel efficiency and line loss targets set in the Concession Contract. Most of the inefficient network assets are being replaced by donor and TPL funded projects. Some generators have been replaced at TPL’s cost (e.g. 2.4MW MAK generator at Popua Power Station). TPL strives to achieve a future asset management strategy that enhances the efficiency of our network and generation assets and this is explained in the next section in detail. Key challenges faced by the objective are: There are a number of projects in the pipeline of which TPL has a limited amount of ability

to fund. Seeking funding for selected projects may also be a challenge especially as many donors prefer to invest in RE projects to reduce tariff rather than asset improvement projects that enhances safety and reliability.

Continuous review and updating of asset management plans continues to be a challenge to TPL due to limited skilled staff in house.

With all the improvement plans currently set in motion, TPL is still facing challenges of meeting standards stipulated in the Electricity Concession Contract. One of the major challenges TPL faces is meeting voltage standards. Poor quality transformer connections and service lines results in supply voltage fluctuations outside the regulatory limits. TPL usually pays a significant amount of compensation and penalties to affected customers when their household appliances are damaged from high/low voltages.

6.4 Strategic Objective 4 Cultivating a hazard free safety culture to minimize any electrical hazards to both the public and staff is one of the top strategic objectives for Tonga Power Limited. The key deficiency in Tonga is the need for increased safety regulations which must be approved by Cabinet. The current safety regulations are largely outdated and materially deficient. It is EC’s responsibility to develop safety regulations and forward them to Parliament for promulgation. The company however, uses ESITO safety standards in electrical network construction and largely leads the pacific when it comes to safe work practices. Key challenges faced by the objective are: EC’s capacity to develop and promoting safety regulations. Safety regulations are to be approved by the Cabinet before they become legally effective.

This process normally takes a long period of time. Adoption of safety regulations by all staff and employees of TPL as well as industry members

such as electrical contractors.

49

Page 50: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

6.5 Strategic Objective 5 As shown in the diagram below, Tonga Power uses a ‘Systems Approach’ to achieving continuous improvement and therein maximising profits to our shareholder. During our annual strategic planning meeting, the long-term vision is translated into tangible strategic objectives. The strategies are then developed in order to achieve these objectives. The strategies are delivered through our comprehensive five year business plan. TPL’s Performance Management Plan identifies if the objectives have not been achieved for the year due to any disturbances (or risks). The objectives are then reviewed and readjusted for the following year.

Investing in leading business processes and systems in order to improve the operational efficiency and quality of TPL's services to customers is vital to TPL’s long term success. The company has already engaged in a number of systems such as risk management, GIS, asset management, business continuity management, HSE management, process redesigning, and billing and payroll activities. The relationship between TPL and the community is critical if TPL is to achieve its core purpose of providing reliable, safe, sustainable and affordable electricity to the people of Tonga, while satisfying its shareholders requirement for the public good. TPL’s customer strategy aims to build solid customer relations and satisfaction through the implementation of activities such as enhanced communication with customers, pre-payment metering, electronic bill payment services, energy efficiency education and the eventual introduction of ‘multilevel’ tariffs to manage the costs for the most vulnerable in the community.

50

Page 51: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Key challenges faced by the objective are: Systems and processes can sometimes overburden the existing staff when adequate staffing

levels are not available. When the staffing levels are reduced, the existing staff can find it difficult to comply with processes and systems which in turn can lead to inaccuracies and/or poor quality outputs.

The lack of key staff availability to perform some major business functions leads the company to outsource expertise at a generally higher cost.

Design and development of multi-tariff systems to satisfy all classes of customers. Design best regulatory framework for the current (second) Reset Period including sensible

and proactive adjustments to the Concession Contract.

6.6 Strategic Objective 6 Managing external funding and internal financing sources successfully in order to maximise the shareholder value is a key TPL focus. The external capital funds can be provided from various sources: free capital from donors at no cost, debt finance from banks and debt finance from development partners at low cost. Internal funds are expended from the company’s revenue earned through selling electricity to customers or from company’s retained earnings. TPL conducts comprehensive economic analysis in order to ensure funds are invested on selected value added projects that maximise shareholders’ value. TPL has established a number of financial policies and procedures when it comes to capital or operational expenditure. Controls are in place for verification and approval by another party as necessary.

Key challenges faced by the objective are: Scarcity of capital funding for investment on all the available projects is a key issue for TPL.

The challenge for TPL is to choose a portfolio of projects that fits the best available funds for implementation as a number of potentially good projects may be forced outside the five year planning period.

In order to manage the diesel price volatility risk successfully, the Concession Contract allows TPL to undertake ‘fuel hedging’ to ensure price stability. However, the challenge for TPL is to use the right hedging instrument at the right time, which neutralises profit prospective that requires external advice and expertise.

Unfavorable economic activities also challenge TPL’s profit prospective. This in turn reduces investment funds for TPL funded projects resulting in TPL having to rely heavily on donors to fund future projects. The economic activities such as poor economic growth, high oil prices, low overseas remittances and higher than desirable inflation also has an impact on TPL’s ability to deliver a lower electricity tariff to the people of Tonga.

51

Page 52: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

7. STRATEGIES/ACTIONS TO SATISFY OBJECTIVES The proposed strategies and strategic actions for the planning period have been divided in to the following three categories: Priority projects essential to achieve 50% RE penetration target in the future ($166 million). Projects that are already in progress ($67 million). Projects that are committed by TPL to complete in the future ($20 million).

7.1 Priority Projects The eleven projects shown in the table below have been specially designed to achieve 50% RE target. The priority project portfolio includes 4x1.3MW solar and 3x2.2MW wind farms designed to achieve the 50% RE penetration. The total capital cost have been estimated to be about $166 million and expected to be funded by either development partners, lending agencies, private equity investors and to a lesser extent, Tonga Power Limited for expenses such as land, fencing and civil works.

ID Project  50%

Target

Est. Cost

(T$)

Tariff Impact

(s/kWh)Notes

1

Demand Side

Management and

Energy Efficiency

EE 4.0m 3

Efficient lighting, MEPS, replace old appliances, water

heater controls, energy audits, tax changes, peak load

awareness, TOU or demand based tariffs .

2

Nuku’alofa Network

Upgrade Project

(NNUP)

EE 50m 2

Upgrade of Nuku’alofa network to reduce line losses and

improve reliability of the network further enabling RE. Full

roll out of smart metering should be undertaken at this

stage.

3Enabling Power System

(EPS) Project A EPS 2.0m TBD

Allows 20% RE penetration, essential for Wind Generation

in the East, partially funded by the World Bank (T$ 1.0m).

Submarine cable replacement is outstanding including

meshed ring philosophy and fourth feeder

41.3 MW Solar PV

(Central TBU)0.17 6.0m 2

Tariff impact assumes donor funded investment and 5%

into a sinking fund to replace assets. IPP being sought for

project.

52.2 MW Wind Farm

(Niutoua)0.26 20m 5.5

Tariff impact assumes donor funded investment and 5%

into a sinking fund to replace assets. NZ MFAT studying

project. A new tariff should be initiated at this stage. 

6 EPS Project B EPS 5.0m TBD

Allows 35% RE penetration, includes approx. 2 MWh of

energy storage (potentially to existing RE generation

schemes), SCADA upgrades, existing generation fine

tuning, capacitor banks. CBs and comms.

72.2 MW Wind Farm

Extension (Niutoua) 0.35 20 m 3

Tariff impact assumes donor funded investment and 5%

into a sinking fund to replace assets. Japan studying

project.

8 EPS Project C EPS 2.0m TBDAllows 50% RE penetration, EXCLUDES energy storage,

includes capacitor banks. CBs and comms

93 x 1.3 MW Solar PV

(Central-West) 0.41 18m 3 Tariff impact assumes donor funded investment

102.2 MW Wind Farm

Extension (Niutoua)0.52 20m 2.5 Tariff impact assumes donor funded investment

11Energy Storage (8 to 16

MWh)0.61 19m TBD

Required to prevent renewable energy spill from

exceeding 20%.

Total= 61% 166m 21 s/kWh

2016-2020

High Priority Projects Achieivng 50% RE Target

52

Page 53: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

The above mentioned priority projects are described in great detail in TPL’s Least Cost Development & Investment Plan (LC-DIP) prepared separately to this plan however, projects are described briefly below:

Demand Side Management & Energy Efficiency: This project is the least infrastructure intensive project, and is largely focused around foundation issues with regards to the electricity sector. It is chiefly concerned with institutional, policy, regulatory, legal, financial, planning, training and capacity building. This is a suitable starting point as it does address and form a strong platform for more intensive investment in renewables that will more directly achieve the goals and objectives as set forth through the TERM. Tongatapu’s load profile includes an evening peak lasting for 2-3 hours. In summer the evening peak is typically about 0.5 MW higher than the day time peak and in winter the evening peak is typically slightly over 1 MW higher than the day time peak. The overall summer load is higher than the winter load. The evening peak creates a need for short-term generation capacity over and above the capacity required for the daytime load. Since electricity tariffs are set partly in reference to TPL’s asset base, this requirement effectively increases electricity costs for all consumers.

The addition, solar photovoltaic (PV) capacity in the future will reduce the load served by the diesel generators during the day so that, in the absence of measures to reduce the evening peak, the difference between the load that is met by the diesel generators during day time and the evening peak will increase. The overall objectives of the project is to implement demand side management (DSM) and energy efficiency (EE) measures to:

53

Page 54: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Contribute to achieving the overall goal of 10% reduction in average monthly energy

consumption in the residential, commercial and public sectors. Establish the policy and implementation frameworks to move towards the goals of

reducing fossil fuel imports by 10%, achieving energy savings and reducing GHG emissions by the end of 2020.

The project focuses on such activities as: energy audit program & energy efficiency education program, residential lighting replacement, solar powered water and freezer systems, old fridge and freezer replacement, home water heating control, air-conditioning replacement, water pumping peak shaving, TOU or demand based tariffs, and load shifting program. Initial project investment costs have been estimated at $4 million and is expected to yield about 2MW evening peak shaving and 3 seniti/kWh tariff reduction. Nuku’alofa Network Upgrade Project: The Nuku’alofa Network Upgrade Project (NNUP) will follow the same model as the NZMFAT funded Tonga Village Network Upgrade Project (TVNUP)-Stage 1 completed in August 2013. The estimated cost of the NNUP is $50 million. The project deliverables include renewing 8,358 customer connections, upgrading 23 km of high voltage lines, upgrading 185 km of low voltage lines, and replacing 5,330 power poles, renew 8,358 customer connections, 1,000 new connections, and advanced prepayment meters to cater for new low usage connections. The NNUP is expected to provide the following benefits: Reduced network losses, both technical and non-technical (including reduced incidence of

power theft). Increased access to electricity. A safe and reliable electricity supply to approximately 7,960 households and businesses in

the greater Nuku’alofa area in Tongatapu. Reduced electricity tariffs as a result of reduced diesel fuel consumption (through reduced

system losses), reduced capex spend and improved operating and maintenance capability within TPL, with direct financial benefit to households and businesses.

Social benefits in terms of an affordable and reliable electricity supply. A safe electricity network, both for the public and for staff working on the network assets. The project is expected to reduce diesel consumption by 1.9Gwh (500,000 liters or $800,000) per annum.

54

Page 55: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Enabling Power System (EPS) – Projects A, B, & C: As discussed in Section 6.2, TPL’s current distribution systems are generally considered to be ready to support small DG sources without change, however, with increasing RE penetration, TPL’s current power distribution system may experience complications in connecting to RE sources. Therefore, as aggregations of RE continue to grow, changes in design and control practices will eventually be required at all levels of the power system. The EPS projects are expected to provide the following changes to the current generation and distribution systems in line with the ‘smart-grid’ technology: Phase A: Feeder 4, Ring Feeder Lines (moving from radial 11kV network to a ring or meshed

network), Ring Feeder Switching, Differential protection, Generator Circuit Breakers and Comms, Existing RE generator tuning, power quality metering.

Phase B: Western Ring Feeder Switching, Generator Circuit Breakers and Comms, Eastern Ring Re-conductor, SCADA upgrade/replacement, Tune Voltage support controls, Bulk energy storage (Vaini or Popua 1.3 MW, 2 MWh), capacitor banks.

Phase C: Generator Circuit breakers and Comms, capacitor banks.

Once a ring philosophy is adopted it will provide adequate power quality and reliability particularly through improved fault clearance times which most renewable generation plant can ride through if certain generation connections requirements are followed. The network’s reliability will also improve overall as feeder faults will no longer result in the loss of all load on that feeder. The real benefit is that the network will be able to absorb renewable energy and the main challenge will be upskilling and up sourcing human resources to manage the changed philosophy of asset operation and maintenance. In total the enabling power systems (EPS) projects will cost an estimated $9 million. These different phases of enabling projects require a significant amount of capacity building for TPL operations staff. High intermittent renewable penetration levels (50% +) on grids the size of Tongatapu’s is a very new concept, and for TPL to manage such a system will require TPL to have very qualified and well trained personnel. Solar PV Generation (4x1.3MW): Solar PV is the most proven form of renewable energy electricity generation in the Kingdom of Tonga today. The Tongatapu electricity grid and power system can manage the instantaneous loss of 1.3MW of generation due to a diesel generation trip. If PV generation is limited to 1.3MW plants and dispersed geographically then fluctuations caused by cloud impacts have less impact than a power plant trip and will therefore be manageable. Each large scale (approximately 1MW) solar plant should be located at least 4km from the nearest large scale solar plant and each solar plant should be smaller than 1.3 MW. Total project costs are estimated at $24 million and it is expected that a 6 seniti/kWh tariff reduction will be achieved.

55

Page 56: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

The potential locations for PV plants are shown in the map below.

Wind Farm Generation (3x2.2MW): Electricity generation using energy from wind is still relatively unproven in Tonga, only two small wind turbines (11kW) have been installed and are operational in the country. However comprehensive data collection and analysis has taken place with numerous pre-feasibility studies being completed and now a full feasibility close to completion. The latest studies show a relatively good wind resource averaging slightly more than 7m/s at 30m to 50m heights. It is highly recommended that an approximate balance between the total installed capacity of wind and solar be maintained as much as possible as this achieved the highest levels of renewable energy electricity productions shares. There are simple rules that guide the introduction of wind turbine generators to the Tongatapu electricity grid, they must be pitch regulated turbines with frequency governor and must NOT have a vertical cut out profile at high wind speeds. Total project costs are estimated at $60 million and it is expected that an 11 seniti/kWh tariff reduction will be achieved. The potential locations for Wind farms are shown in the map above.

56

Page 57: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Bulk Energy Storage: Currently, TPL uses 16kWh (2x8kWh) small storage systems (i.e.

2x500KW designed to last for 60 seconds) only for the purpose of frequency and engine ramp

controls required to stabilize the system from the fluctuating 2.4MW solar PV pants (1MW plant

at Vaini + 1.4MW plant at Popua). However, current solar storage capacity is very minimal. Bulk

storage capacity is required to use for such functions as: correcting temporary load/generation

mismatches, regulating frequency, mitigating flicker, as a result of fluctuating RE sources and

assisting advanced islanding functions and service restoration.

The project investment cost is estimated at $19 million and consists of the following milestones:

16 MWh of Energy Storage Capacity Battery Building Construction Battery System integration to SCADA and power management systems Due to the falling costs of solar and energy storage, the line between implementing additional solar, large battery storage or both is blurred. However what is clear is that all efforts should be made to optimise the electricity produced from renewable energy sources. This means that spilling or curtailing the output of renewable electricity generating plant is not an optimized solution. Additionally, a system with only renewable energy generating plants of a significant portion overall of the generation mix will cause network instability and power quality issues. Given the falling costs of energy storage in particular it makes sense to plan to introduce bulk energy storage as an enabler that will also optimize and translate the investment in renewable energy generating plant to greater electricity tariff reductions.

7.2 Projects In-Progress Currently, TPL is undertaking a $67 million worth projects as shown in the table below. Of the $67 million, $16 million is contributed by TPL and $51 million are contributed by development partners.

57

Page 58: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

The above projects are described briefly below:

Smart & Prepay Metering Project: The Smart Metering and Prepay Project deploys 3000 meters to the most disconnected customers and 500 three phase meters for industrial customers plus network monitoring. TPL will offer the 3000 customers with a selection of post-paid or the newly installed pre-paid service. The 500 meters will enable Tonga Power to adequately monitor large industrial customers as well as monitor the electrical network. The Smart Metering and Pre-pay infrastructure are provided by Agility CIS and Itron. It includes three high end back-office systems, Itron’s Openway Headend system, Meter Data Management (MDM) system, and the Pre-payment system. There is also a field area network (FAN) platform which is a private Access Point Name (PAPN) provided by Digicel Tonga, Connected Grid Routers (CGR) and Smart Meters manufactured by Itron. The total cost of the project as planned is $4.1 million of which $401,368.95 has been spent as at end of February 2016. As shown in the table below, there are nine project milestones spreading over a 13 months period covering deliverables by Agility CIS, Itron and Tonga Power. The project is expected to be completed by September 2016.

ID Project  50%

Target

Est. Cost

(T$)

Funding

SourceNotes

1Smart & Prepay Metering

Stage 1EPS 4.0m TPL & MFAT Installation of 3000 smart/prepay meters in Tongatapu.

2Tonga Village Upgrade

Projects Phase 2/3EE 42.0m MFAT & TPL

Upgrade of Nuku’alofa network to reduce line losses and

improve reliability of the network further enabling RE. Full

roll out of smart metering should be undertaken at this

stage.

3 Tonga Police Solar Project 10% 2.5m DFAT Installation of 250KW PV plus 100kWh storage system.

4

Outer Islands Renewable

Energy & Energy Efficiency

Project

14% 16.0m ADB

Project cosists of both establising RE plants (550KW in

Ha'apai and 200KW in Eua) and upgrading of distribution

networks.

5IT Virtual Environment &

Disaster Recovery ProjectEPS 0.5m TPL

Virtual server development to provide high availability,

disaster recovery and data protection.

6Enterprise Resource

Planning ProjectEPS 2.0m TPL

The system will provide improved governance, the ability

to cope with growth and diversification and facilitate cost

reductions.

Total= 14% 67m

Projects In Progress

2016-2020

58

Page 59: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

The Village Network Upgrade Project (TVNUP) Stage 2/3: Having completed the first 17 villages in Stage-1 for $11 million, an additional $32 million funding has been provided by NZ MFAT for a new project to complete another 33 villages on Tongatapu. TPL contribution towards the project is about $10 million. To date (March, 2016), 15 out of 33 villages have been completed. The project provides an upgraded low voltage reticulation network and the service line connections to each premise in the village. The project includes installation of over 5,370 LV poles, 1,330 HV poles, 215Km of LV cables, 118 transformers and 7,640 customer connections. TPL’s responsibility is to provide the high voltage network and transformers which in most cases are relocated to meet the location of the loads. New transformers are installed or upgraded where power quality demands such works.

Tonga Police Solar Project: In order to reduce their annual electricity costs, Tonga Police has initiated a third party solar (250KW) and storage facility (100kWh) in Tongatapu. The $2.5 million project is funded by the Australian Government. The project is in progress at the moment and constructed by REID Technology Ltd. TPL has signed an agreement with Tonga Police to purchase energy (about 324,674 kWh) from the PV plant at a certain rate complying with TPL’s Gross Metering Project.

Outer Island Renewable Energy & Energy Efficiency Project: ADB has generously approved a $16 million funding (with $600,000 TPL contribution) for installation of 550kW of solar with 660kWh storage on Ha’apai and 200kW of Solar on ‘Eua and fine tuning of existing TPL SCADA system on Vava’u. This is called the “Phase 1” or “on-grid” scope. Phase 1 (on-grid) started in February 2016 and will be completed in October 2016. The Project also comprise the rehabilitation of the existing grid network through the replacement of electricity cables; electricity poles; distribution transformers; switchgear and other associated grid network equipment in Vava'u and 'Eua. There is also a separate “Phase 2” or “off-grid” scope that contains 350kW PV with 670kWh of storage spread across 4 Ha’apai outer island mini grids and the associated 4 mini-grid network upgrades. In addition, a new mini-grid and centralised PV and diesel generation on Niuatoputapu combined with 25kW of solar home systems on Niuafo’ou will be installed. The Phase 2 (off-grid) will be started in January 2017 and completed in January 2018.

IT Virtual Environment & Disaster Recovery Project: The proposed new IT architecture includes a SAN (Storage Area Network) Server connecting to three other physical servers.

# Milestones Date

1 Contracts Agreement to Proceed Jul-15

2 Itron and Agility Design Approval Dec-15

3 Factory Acceptance Test approval Jan-16

4 System Delivery Mar-16

5 User Acceptance Testing May-16

6 Transitions and Handover Jun-16

7 Final Itron Deliverable Jul-16

8 2500 meter installations Aug-16

9 Project closure Aug-16

59

Page 60: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

These three physical servers hold ten virtual servers which represents TPL’s all application servers (e.g. Orion, email, SCADA, IMS/HR, ERP, SMS servers, etc.) This architecture enables high availability where if one physical server fails, the two other physical servers pick up the application servers instantly in the virtual environment. A similar system will be duplicated at the Distribution Centre or at the Popua Power Station as a disaster recovery solution. If both head office and DR sites were destroyed in case of a disaster, the applications will be made accessible from the cloud.

Enterprise Resource Planning Project: ERP system’s database integrates and unifies information from different business units enabling a single source of truth which is the foundation for business intelligence (BI) and analytics. In other words, The ERP system integrates and automates internal and external information across all the business units and functions embracing procurement, inventory management, finance & accounting, billing & revenue collection, payroll, human resources management, customer relationship management, and project management. The system will provide improved governance, the ability to cope with growth and diversification and facilitate cost reductions. The budget for this project is $1.915 million. The project was officially kick off at the end of March 2016, and work on site will begin in late April. All modules are expected to be live by the end of the calendar year.

7.3 Future Project Committed by TPL In addition to the projects that are currently work in-progress above, TPL is committed to undertake a further $19 million worth of projects during the planning period as shown in the table below.

ID Project  50%

Target

Est. Cost

(T$)

Funding

SourceNotes

1Generator Replacement

Program (All Islands)EPS 9.0m TPL

Replacing or overhauling all CAT and Cummins generators

in Tongatapu and Outer Islands

2

Outer Islands Network

Upgrade Program (Vavau

& Eua)

EPS 3.0m TPL Network upgrade work left over from OIREP project.

3Tongatapu Village

Network Upgrade - Stage 4EPS 3.0m TPL

Network upgrade work (about 5 more villages) left over

from TVNUP and Nuku'alofa Network Upgrade Projects .

4Smart Metering Project -

Stage 2EPS 3.0m TPL Installation of balance 14,000 smart meters in Tongatapu.

5 Generation (Other) EPS 2.0m

Other ancillary generation projects including SCADA

upgrade, fire hydrants, G8 day tank, MAK/G8 load sharing

module, waste oil disposal system etc.

Total= Nil 20m

Future Projects Committed by TPL

2016-2020

60

Page 61: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Generator Replacement Program: One of the major projects TPL plans to complete during the next five years is the retirement or full refurbishment of six 1.4MW CAT generators in Tongatapu as they have approached the end of their useful live. The major objective of the asset replacement program is to provide uninterrupted supply to consumers whilst maintaining N-1 security of supply. Phasing out old generators and installing new generators will be completed in several stages, being conscious of timing and implementation of renewable energy projects. On Tongatapu, the first CAT generator was retired in 2015 and replaced with a 2.8MW MAK generator which was commissioned in December, 2015. Two more CAT generators will be retired in 2016 (subject to demand growth and the effects of any renewable generation investment) and replaced with a one 2.2MW CAT generator. Another two CAT generators will be retired after 2016. In 2018 (or shortly after), one more CAT generator will be retired and replaced with another 2.2MW CAT generator. In 2020, the last CAT generator will be retired and replaced with another 2.2MW CAT generator. The timing and nature of replacements will depend largely on the availability of grant funded renewable projects. In the interim, TPL has assumed that diesel generators will be required to provide security for the network including spinning reserve for RE. In the future battery storage will have an increasing impact on the generation fleet.

Demand growth is not expected to be significant in the outer island grids, hence generator replacement at these locations will largely follow end of life patterns. The replacement generation will be optimised around any renewable generation as opportunities arise.

The total cost of the asset replacement and improvement program has been estimated at $9 million for the next five year period across all four island groups.

Outer Islands Network Upgrade Project – Stage 2: The Ha’apai network upgrade has been 100% completed under the Ha’apai Cyclone Ian Recovery Project. However, Vava’u and ‘Eua network upgrades are not fully completed yet. The ADB funded Outer Island Network Upgrade Project only upgrades 40% of Vava’u’s Network and 75% of ‘Eua’s Network. The balance of 60% of Vava’u’s distribution network and 25% of ‘Eua’s upgrade will be completed under this project. Project costs for the Vava’u upgrade is estimated at $2 million and ‘Eua upgrade at $1 million. Project scope for the Vava’u Upgrade include replacement of HV poles, HV/LV network equipment and service lines. The project ensures enhanced public safety, reduced system losses and reliability of supply.

Tongatapu Village Upgrade Project – Stage 4: The New Zealand Government funded TVNUP project discussed above completes 70% of the Tongatapu distribution network upgrade. In addition, Nuku’alofa Network Upgrade project completes about 25% of the Tongatapu network. However, there is still 5% of the total Tongatapu network is left out from being upgraded. These are five remote villages where a small number of customers reside. Under the Stage-4 project, TPL intends to upgrade both HV and LV networks of these five villages at TPL’s own cost of about $3 million. Smart Metering Project – Stage 2: The smart metering project discussed above only manages installation of 3,000 prepay meters and respective radio-mesh and head-end communication systems. However, there are about 17,000 customers residing in Tongatapu. The Stage-2 of the

61

Page 62: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

project manages installation of the balance or 14,000 smart meters. The project cost is expected to be about $3 million. Generation (Other) Projects: In addition to the generator replacement plan discussed above, the following auxiliary systems will be dealt with during the planning period. The allocated budget for the work is about $2 million.

Repairing MAK/CAT Load sharing communication module Replacing new flow meters to improve fuel reconciliation Installation of a separate Day Tank for G8 Installation of lagging CAT exhaust pipe Painting Power Station piping Attending to sea water cooling pump improvements Installation of additional over-speed protection device (air-flap) Laying DC underground cables in conduits Procuring a waste oil disposal system (boiler/steam engine) Procuring the Hired Generator Upgrading SCADA in all three outer island and enable communications between outer

islands and Tongatapu Replacement of station transformers Repairing MAK gantry crane in the oil power house

62

Page 63: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Utility Reform Project: As part of the Tongan government’s ongoing restructuring and reform programe to improve operational efficiency and profitability, Tonga Power Ltd, Waste Authority Ltd and Tonga Water Board combined Board have established the steps in the table below (Utilities Reform Status Update) which will be implemented in stages as key milestones towards achieving the shareholders expectation for the Combined Utility Companies reform programme. It is further anticipated that this reform will reduce up to 10% of annual costs and enhance service delivery (e.g. on-time delivery, safety & quality).

Utilities Reform Status Update

Jan-16 Feb-16 Mar-16 Apr-16 May-16 Jun-16 Jul-16 Aug-16 Sep-16 Oct-16 Nov-16 Dec-16 Jan-17 Feb-17 Mar-17 Status

•Common building facilities to house all three

utilities (by December 2016) 50% Complete

•Common billing (TPL & WAL Billing May 2016,

TPL/WAL/TWB by December 2016) 75% Complete

•Joint meter reading in villages (August 2016) 80% Complete

•Common IT service (December 2016) 40% Complete

•Shared recruitment, inter-company staff

movement, training & development (December

2016) 20% Complete

•Common vehicle management (maintenance,

fuel) – (December 2016) 50% Complete

•Combined procurement (March 2017) 40% Complete

•Common secretariat to the board (May 2016) 100% Complete

•Common tariff (fuel & non-fuel components)

(March 2017) 60% Complete

•Additional payment collection outlets in far east &

west to receive TPL/WAL payments 50% Complete

63

Page 64: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

8. PERFORMANCE MEASURES & TARGETS

The effectiveness of the strategic objectives will be measured on an annual basis and compare with the actual values against the annual targets shown in the table below. The variances between the actual and target values will be used to review and update the Business Plan in the next year.

Current

2015 2016 2017 2018 2019 2020

Accumulated Fuel Displacement (%) Generation 9% 12% 20% 30% 40% 50%

Tariff Reduction (%) due to RE Generation 3% 4% 5% 8% 10% 12%

RE Penetration (%) Generation 9% 15% 25% 40% 50% 60%

Voltage Fluctuations Distribution +/-10% +/-10% +/-10% +/-10% +/-10% +/-10%

Frequency Fluctuation Generation 0% 0% 0% 0% 0% 0%

System Loss (%) Distribution 12.0% 12% 11% 11% 10% 10%

Fuel Efficiency (kWh/L) Generation 4.0 4.0 4.0 4.0 4.0 4.0

Reliability (SAIDI) (Minutes)Distribution &

Generation1100 1000 950 925 900 850

Number of outages (SAIFI)Distribution &

Generation5 4 4 3 3 3

Reduction in Maintenance Cost (%) Generation 5% 5% 5% 5% 5% 5%

Reduction in Material Cost (%) Distribution 5% 5% 5% 5% 5% 5%

Load factor (%) Generation 62% 58% 59% 54% 54% 54%

N-1 Security Policy Compliance Generation 100% 100% 100% 100% 100% 100%

Rework Cost (TOP$)/Annum Distribution < 5,000 < 5,000 < 5,000 < 5,000 < 5,000 < 5,000

Capex Jobs Audited/Annum (%) Distribution >80% >80% >80% >80% >80% >80%

Firm Installed Capacity (KW) Generation 15236 15410 16270 16444 16416 17276

Installed Capacity (KW) (All Sources) Generation 18142 18316 21376 21550 21522 22382

Data Quality in File Maker (%) Distribution 100% 100% 100% 100% 100% 100%

Update Asset Management PlansDistribution &

GenerationYES YES YES YES YES YES

Incident Rate Corporate < 10 < 10 < 9 < 9 < 8 < 8

Loss Time Injuries Corporate 0 0 0 0 0 0

Number of Incident Reports Corporate 100 125 140 150 160 175

Safety Awareness Activities/Annum Corporate 3 3 3 3 3 3

Safety Committee Meeting

AttendanceCorporate 100% 100% 100% 100% 100% 100%

Number of Emergency Drills/Annum Corporate 2 2 2 2 2 2

Staff Retention (%) Corporate > 90% > 90% > 90% > 90% > 90% > 90%

Customer Complaints Corporate 60 50 40 30 30 20

Exercise BCM Plan/Annum Corporate 1 1 1 1 1 1

Number internal audits/Annum Corporate 3 3 3 3 3 3

Compliance with Company Policies Corporate 100% 100% 100% 100% 100% 100%

Compliance with ECC & Applicable

LegislationCorporate 100% 100% 100% 100% 100% 100%

Staff Training Register Corporate > 90% > 90% > 90% > 90% > 90% > 90%

Staff Absenteeism (%) Corporate < 5% < 5% < 5% < 5% < 5% < 5%

Revenue Retail $36.8M $37.9M $36.8M $37.1M $36.7M $37.6M

NPAT Retail $3.1M $3.3M $3.4M $3.4M $3.4M $3.5M

Debt Ratio Retail < 50% < 50% < 50% < 50% < 50% < 50%

ROE Retail 10% 10% 10% 10% 10% 10%

Debtor Days Retail 20 20 20 20 20 20

Liquidity Ratio Retail 1.5 1.5 1.5 1.5 1.5 1.5

Opex Reduction (%) Retail 3% 3% 3% 3% 3% 3%

6

Managing all external funding and internal

financing sources successfully in order to

maximise the shareholder value.

Investing in excellent business processes and

systems in order to improve operational

efficiency and quality of TPL's services to

customers.

3

Improving the network and replacing ageing

assets to improve safety and reliability of TPL's

services.

5

4

Cultivating a hazard free safety culture to

minimize any electrical hazards to both public

and staff.

Strategic Performance Targets for the Planning Period 2017 -2020

1

Achieving 50% electricity generation from RE

generation by 2020 in order to achieve the

government TERM objective and significant

tariff reductions.

2

Adopting technologies to manage the

complexities arising from increasing RE

penetration.

ID Strategic Objective Strategic Measures Business UnitTargets

64

Page 65: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

9. STATEMENT OF COMPLIANCE(S)

Statement of compliance with relevant Government Policies:

Electricity Act: All requirements including payment of regulatory fees and other levies, offences, Concession Contract etc. are met.

Electricity Concession Contract: TPL complies with all the reporting requirements, efficiency, technical and services standards sets forth in the Concession Contract II effective September 2015 except for voltage standards. There are occasional situations where the 230V (-/+10%) standard is not met due to the poor state of the network equipment (e.g. transformers) in some areas of the network.

Ministry of Public Enterprise Act: All the requirements including reporting requirements, directors’ requirements, Board meeting requirements, and auditing requirements are met.

Companies Act: All the requirements including constitution, share register, shareholder rights, directors’ duty of care, disclosure interest, keeping accounting records, appointment of auditors, annual report, and annual return requirements are met.

Pursuant to Section 18 (4) (j) of the Act, the following matters have been agreed with the Responsible Minister:

Corporate governance: The company is committed to the highest standards of corporategovernance, with core values of accountability, probity and transparency. The companyis adopting policies and procedures aimed at maintaining these standards.

Anti-corruption: The Board, through the Chief Executive will ensure compliance by thecompany with statutory and regulatory requirements including avoidance of any act thatwould or could be construed as an illegal, corrupt or unethical practice.

Share subscriptions or purchases: Subscriptions for shares in any company or acquisitionof interests in any other organisation that involve equity investment will be subject toprior consultation with the Responsible Minister.

Subsidiary companies: The establishment of subsidiary companies or sale of materialinterest in or assets of subsidiary companies will be subject to prior consultation withthe Responsible Minister.

Other legislation requirements to which TPL complies with are: Renewable energy Act, Business licenses Act, Public audit Act, Public health Act, National retirement benefit Scheme, Price and wage control Act, Anti-corruption commissioner Act, and Public finance management Act.

65

Page 66: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Statement of Community Services, claims for GPO

TPL has spearheaded the implementation of projects that align with the following GPO.

Under the TSDF: Outcome Objective 3 (11) – Maintaining and where possible expanding the provision of reliable and cost efficient power supplies, using traditional and renewable options, to all communities. The results to date, a 12% system losses down from 18% in 2010, Average total duration of power interruption per customer down to 88 minutes from 299 in 2011 and 8% of energy coming from renewable energy source in 2015.

Outcome Objective 5 – Appropriately skilled workforce to meet the available opportunities in Tonga and overseas. The TVNUP project up skills TPL lines staff to an internationally recognized standard of line mechanic. The results to date, 10 lines staff have been recruited by overseas company to help satisfy opportunities that are available there for skilled lines staff.

Enabling Theme C – Ensuring Public Enterprises are sustainable and accountable, and where appropriate moved into the private sector.

Under the NIIP: Priority projects E11 and E16 – Results to date, a 1.2MW of Solar PV have been added on Tongatapu with support of JICA, Outer Islands On-Grid RE funded committed with procurement of EPC contractor underway.

Under TERM: Minimizing the need for imported fuels by transitioning to a renewable energy based system. Seeking to achieve greater efficiencies in customer use and distribution through improving network efficiency and energy efficiency awareness campaigns.

Specific GPO: Lifeline Tariff – TPL is currently a lifeline tariff program for customer who uses less then 50kWhrs per month under GoT GPO.

Suggested GPO: Potentially a GPO should be considered for if TPL are to take – over maintenance of off-grid island generation schemes i.e. Diesel mini-grids and Solar Home Systems.

66

Page 67: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Statement of Support from Government and/or Development Partners

Currently, donor support is available for the projects shown in the above table. These projects are in progress at the moment. The donor funds for the future priority projects have not been confirmed yet.

Statements of Financial capacity in regard to dividends

TPL’s dividend policy is that 35% of Net Profit After Tax is paid as dividend to the government. However, TPL has paid a special dividend of $2 million in the year 2015. As shown in the following table, the estimated dividend stream for the next five years will be $1.5M (2016), $1.5M (2017), $1.5M (2018), $1.6(2019) and $1.7M (2020).

ID Project  50%

Target

Est. Cost

(T$)

Funding

SourceNotes

1Smart & Prepay Metering

Stage 1EPS 4.0m TPL & MFAT Installation of 3000 smart/prepay meters in Tongatapu.

2Tonga Village Upgrade

Projects Phase 2/3EE 42.0m MFAT & TPL

Upgrade of Nuku’alofa network to reduce line losses and

improve reliability of the network further enabling RE. Full

roll out of smart metering should be undertaken at this

stage.

3 Tonga Police Solar Project 10% 2.5m DFAT Installation of 250KW PV plus 100kWh storage system.

4

Outer Islands Renewable

Energy & Energy Efficiency

Project

14% 16.0m ADB

Project consists of both establishing RE plants (550KW in

Ha'apai and 200KW in Eua) and upgrading of distribution

networks.

Projects In Progress

2016-2020

Dividend Forecast 2015-2020 (millions)2016 2017 2018 2019 2020

EBITDA 11.4 13.3 14.7 15.5 16.7

Add change in working capital 7.7 -0.5 5.6 4.5 -1.6

Add Long-term Debt 6 6 0 1.11 3

25.1 18.8 20.3 21.11 18.1

Less interest -1 -1.1 -1.1 -1 -1

Less income tax -1.2 -1.4 -1.5 -1.5 -1.6

Less Capex -14.2 -9.4 -11.4 -8.4 -9.9

Less Long-term Debt -4.2 -4.8 -5 -5 -5

-20.6 -16.7 -19 -15.9 -17.5

Retained Earnings 4.5 2.1 1.3 5.21 0.6

Provision for Dividend -1.5 -1.5 -1.5 -1.6 -1.7

Net Cash Balance 3.0 0.6 -0.2 3.61 -1.1

Opening Cash 1.0 4.0 4.6 4.4 8.0

Cash at Year End 4.0 4.6 4.4 8.0 6.9

NPAT 3.5 4.3 4.4 4.5 4.9

Dividend (% of NPAT) 43% 35% 34% 36% 35%

67

Page 68: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

10. FINANCIAL FORECAST

10.1 Profitability

2017 2018 2019 2020 2021

1 Jul-30 Jun 1 Jul-30 Jun 1 Jul-30 Jun 1 Jul-30 Jun 1 Jul-30 Jun

Total Revenue 36,807,700 37,186,916 36,715,303 37,601,288 38,508,378

Total Expenses 24,051,917 24,007,977 23,210,258 23,691,183 24,048,992

EBITA 12,755,783 13,178,938 13,505,045 13,910,105 14,459,386

Depreciation 6,930,372 7,382,128 7,882,324 8,188,636 8,688,978

Interest 1,175,630 1,231,731 1,152,080 1,083,492 875,976

Income Tax 1,162,445 1,141,270 1,117,660 1,159,494 1,223,608

NPAT 3,487,336 3,423,809 3,352,980 3,478,482 3,670,824

Variance -1.8% -2.1% 3.7% 5.5%

TPL is expecting to achieve a net profit after tax of $3.5 million at the end of the 2017 financial year. Profitability level of the company is stabilised as it is projected that the company will continue to be profitable in the years to follow. NPAT is expected to decrease by 0.06 million/1.8% in 2017. Furthermore, TPL is expected yield 10% Return on Shareholder’s Fund at the end 2017 financial year

Total revenue is forecasted to be at $36.8 million at the end of 2017 and is expected to increase steadily by 1% from 2018 onward.

Total expenses is expected to remain generally stable at 24 million from 2017 to 2021.

Even though TPL is proposing a dividend of 35% of its Net Profit after Tax, the final amount will always be negotiated between the TPL Board and the Minister at end of each financial year. The estimated dividend for 2017 financial year will be $1,200,000. The previous year’s dividend was 105% of NPAT which was equated to $1,318 payout for each ordinary share issued.

68

Page 69: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

10.2 Liquidity

2017 2018 2019 2020 2021

1 Jul-30 Jun 1 Jul-30 Jun 1 Jul-30 Jun 1 Jul-30 Jun 1 Jul-30 Jun

Projection T$m T$m T$m T$m T$m

Net Cash From Operations 11,562,260 11,308,218 11,453,706 12,600,459 13,599,141

Current Ratio 1.2 1.4 1.5 1.3 1.5

Liquidity Ratio 1.1 1.3 1.4 1.2 1.4

Liquidity position of the company is at a satisfactory level at around $1.2 to cover $1 current liabilities. It is expected to improve slightly in subsequent years. Liquidity Ratio is above 1.1 sufficient to cover its short term debt as they falls due.

10.3 Stability

2017 2018 2019 2020 2021

Projection 1 Jul-30 Jun 1 Jul-30 Jun 1 Jul-30 Jun 1 Jul-30 Jun 1 Jul-30 Jun

T$m T$m T$m T$m T$m

Debt ratio (= Total Debt/Total Assets) 0.33 0.33 0.31 0.29 0.26

Gearing ratio (= Longterm Debt/Total Equity) 0.37 0.36 0.32 0.29 0.23

Debt to equity ratio (=Total Liability/ Total

Equity) 0.50 0.49 0.45 0.42 0.35

Interest Cover Ratio (= EBIT/ Interest Expense) 10.85 10.70 11.72 12.84 16.51

TPL is projecting debt to be 33 cents of every dollar of its assets in 2017 financial year, and will generally decrease over the years. Debt to equity ratio will remain generally decrease from 50% to 35% throughout the 5 years. Times interest earned ratio shows adequate cover for the entire period 2017 – 2021.

The main causing factor is that TPL is projecting to invest in Renewal Energy Projects in addition to its commitments from Generation, Distribution and Retailing operations.

69

Page 70: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Pro Forma Financial Statements for Tonga Power Limited

Table 1 Year ending 30 June 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026Millions of pa'anga 1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun

T$m T$m T$m T$m T$m T$m T$m T$m T$m T$mStatement of Financial PerformanceRevenueFuel 12.9 13.2 13.6 13.9 14.2 14.5 14.9 15.2 15.6 16.0Savings from Renewables -1.9 -1.9 -3.2 -3.2 -3.2 -3.2 -3.2 -3.2 -3.2 -3.2Net Fuel Revenue 11.1 11.4 10.3 10.7 11.0 11.3 11.7 12.0 12.4 12.8Non-fuel 22.1 22.1 22.7 23.2 23.7 24.3 24.9 25.5 26.1 26.7Other revenue 3.7 3.7 3.7 3.7 3.8 3.8 3.8 3.9 3.9 3.9Total Revenue 36.8 37.2 36.7 37.6 38.5 39.4 40.4 41.4 42.4 43.4

ExpensesFuel 11.1 11.4 10.3 10.7 11.0 11.3 11.7 12.0 12.4 12.8Renewables costs 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1Non-fuel

Repairs & maintenance 2.2 1.9 2.0 1.9 1.8 2.1 1.7 1.8 1.8 1.8Salary & wages 4.5 4.6 4.6 4.7 4.9 5.0 5.0 5.1 5.1 5.2Materials 0.4 0.4 0.4 0.4 0.4 0.5 0.5 0.5 0.5 0.5Operating overhead 1.9 2.0 2.1 2.1 2.1 2.1 2.1 2.1 2.2 2.2Administration 3.7 3.6 3.6 3.7 3.6 3.6 3.7 3.7 3.8 3.7Bad debt 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1Total non-fuel expense 12.9 12.5 12.7 12.9 12.9 13.4 13.1 13.2 13.5 13.5

Total expense 24.1 24.0 23.2 23.7 24.0 24.8 24.9 25.4 26.0 26.4EBITDA 12.8 13.2 13.5 13.9 14.5 14.6 15.5 16.0 16.4 17.0Depreciation 6.9 7.4 7.9 8.2 8.7 9.1 9.4 9.8 10.3 10.8 Interest 1.2 1.2 1.2 1.1 0.9 0.7 0.6 0.4 0.2 0.2

Net profit before tax 4.6 4.6 4.5 4.6 4.9 4.9 5.6 5.7 5.8 6.0Income tax 1.2 1.1 1.1 1.2 1.2 1.2 1.4 1.4 1.5 1.5Net profit after tax 3.5 3.4 3.4 3.5 3.7 3.6 4.2 4.3 4.4 4.5Provision for dividend 1.2 1.2 1.2 1.2 1.3 1.3 1.5 1.5 1.5 1.6Transfer to retained earnings 2.3 2.2 2.2 2.3 2.4 2.4 2.7 2.8 2.8 2.9

70

Page 71: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Year ending 30 June 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026Millions of pa'anga 1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun

T$m T$m T$m T$m T$m T$m T$m T$m T$m T$mTable 2 Statement of Financial Position

Current assetsAccounts receivable & Other Receivables 7.0 7.1 7.2 7.4 7.6 7.8 8.0 8.1 8.3 8.5Inventory 0.9 0.9 0.9 0.9 0.9 1.0 1.0 1.0 1.0 1.1Cash 1.3 1.7 1.3 1.2 0.8 1.8 2.6 1.0 2.5 2.7Short Term Investments 4.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0Total current assets 13.2 12.7 12.4 12.5 12.3 13.6 14.6 13.1 14.9 15.3

Current liabilitiesAccounts payable & Other Payables 4.7 4.8 4.9 5.0 5.1 5.2 5.3 5.5 5.6 5.7Current portion of term debt 5.7 5.9 6.0 6.0 5.4 4.5 4.5 4.5 4.0 1.8Total current liabilities 10.5 10.7 10.8 11.0 10.5 9.7 9.8 10.0 9.6 7.5

Net working capital employed 2.7 2.0 1.6 1.6 1.8 3.8 4.7 3.2 5.3 7.8Term assetsOpening fixed assets 99.2 106.0 109.4 109.2 109.7 107.6 104.2 104.0 103.9 101.7Capital expenditure 13.8 10.8 7.6 8.8 6.5 5.7 9.1 9.8 8.1 13.0Depreciation 6.9 7.4 7.9 8.2 8.7 9.1 9.4 9.8 10.3 10.8Fixed assets 106.0 109.4 109.2 109.7 107.6 104.2 104.0 103.9 101.7 103.8

Total term assets 106.0 109.4 109.2 109.7 107.6 104.2 104.0 103.9 101.7 103.8Non current liabilitiesDebt 22.0 22.3 19.6 17.7 13.2 9.4 7.1 2.5 -0.7 0.8Deferred Tax Liability 7.2 7.3 7.2 7.4 7.5 7.7 7.9 8.1 8.3 8.5

Total Non Current liabilities 29.2 29.6 26.8 25.1 20.7 17.1 15.1 10.6 7.6 9.3Net assets 79.5 81.8 84.0 86.2 88.6 91.0 93.7 96.5 99.3 102.2

71

Page 72: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Year ending 30 June 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026Millions of pa'anga 1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun

T$m T$m T$m T$m T$m T$m T$m T$m T$m T$mTable 3 Statement of Movements in Equity

Net Assets 79.5 81.8 84.0 86.2 88.6 91.0 93.7 96.5 99.3 102.2Represented by:Opening share capital 33.8 33.8 33.8 33.8 33.8 33.8 33.8 33.8 33.8 33.8Change in working capital 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0Share capital at year end 33.8 33.8 33.8 33.8 33.8 33.8 33.8 33.8 33.8 33.8

Opening retained earnings 15.0 17.3 19.5 21.7 23.9 26.3 28.7 31.4 34.2 37.0Transfers to retained earnings 2.3 2.2 2.2 2.3 2.4 2.4 2.7 2.8 2.8 2.9Retained earnings at year end 17.3 19.5 21.7 23.9 26.3 28.7 31.4 34.2 37.0 40.0

Assets revaluation reserve 28.5 28.5 28.5 28.5 28.5 28.5 28.5 28.5 28.5 28.5Shareholders' equity 79.5 81.8 84.0 86.2 88.6 91.0 93.7 96.5 99.3 102.2

72

Page 73: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Year ending 30 June 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026Millions of pa'anga 1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun

T$m T$m T$m T$m T$m T$m T$m T$m T$m T$mTable 4 Statement of Cash Flows

Cash from operating activities 2.3 2.2 2.2 2.3 2.4 2.4 2.7 2.8 2.8 2.9Adjusted by: Depreciation 6.9 7.4 7.9 8.2 8.7 9.1 9.4 9.8 10.3 10.8Change in working capital 4.6 2.5 0.1 1.2 0.5 -0.1 -0.6 0.0 0.4 -1.8Increase in Term Investments 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

Net Cash from operations 13.8 12.1 10.1 11.7 11.6 11.3 11.5 12.6 13.6 11.9Long term assetsCash from (used by) long term assets -13.8 -10.8 -7.6 -8.8 -6.5 -5.7 -9.1 -9.8 -8.1 -13.0

Long term liabilitiesIncr in long term debt 5.0 5.0 3.0 3.0 0.0 0.0 3.0 0.0 0.0 3.0Decr in long term debt -5.7 -5.9 -6.0 -6.0 -5.4 -4.5 -4.5 -4.5 -4.0 -1.8Incr (decr) in capital 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0Cash from (used by) liabilities and capital -0.7 -0.9 -3.0 -3.0 -5.4 -4.5 -1.5 -4.5 -4.0 1.2

Net incr (decr) in cash -0.7 0.4 -0.4 -0.1 -0.4 1.1 0.8 -1.7 1.5 0.2Opening cash 2.0 1.3 1.7 1.3 1.2 0.8 1.8 2.6 1.0 2.5Cash at year end 1.3 1.7 1.3 1.2 0.8 1.8 2.6 1.0 2.5 2.7

Draft Budget 25/4/2016

73

Page 74: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

KEY PERFORMANCE INDICATORS

Year ending 30 June 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026Returns to shareholders (%) Return on Assets (EBITDA/Total Assets) 11% 11% 11% 11% 12% 12% 13% 14% 14% 14%

Return on Assets (NPAT/Total Assets) 3% 3% 3% 3% 3% 3% 4% 4% 4% 4%Return on Equity (NPAT/Equity) 3% 3% 3% 3% 3% 3% 3% 3% 3% 3%Return on Shareholder's Funds ( Net Profit/Share Capital)

10% 10% 10% 10% 11% 11% 12% 13% 13% 13%

Profitability (%)Rate of Return (NPAT/Sales) 6% 6% 6% 6% 6% 6% 7% 7% 7% 7%

Capital structure (%)Loan Finance Only [Loan/Total Liabilities] 70% 70% 68% 66% 60% 52% 47% 34% 19% 16%Loan Finance as a % of Sources of Funds [Loan/ (Liabilities + Equity)]

23% 23% 21% 19% 16% 12% 10% 6% 3% 2%

Debt Ratio [Debt/ (Debt+Equity)] 33% 33% 31% 29% 26% 23% 21% 18% 15% 14%

Year ending 30 June (TOP $m) 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026Forecast dividend (T$m) 1.2 1.2 1.2 1.2 1.3 1.3 5.6 10.1 14.6 19.6

Dividend as % of NPAT (%) 35% 35% 35% 35% 35% 35% 135% 235% 335% 435%Six weeks of normal operating & debt service expense (T$m)0.8 0.8 0.8 0.8 0.7 1.2 1.1 0.9 0.7 0.4

Year ending 30 June (TOP $m) 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026Capital structure (%)

Debt Ratio [Debt/ (Debt+Equity)] 33% 33% 31% 29% 26% 23% 21% 18% 15% 14%Interest cover (X)

EBIT/interest 5.0 4.7 4.9 5.3 6.6 8.3 10.9 15.4 26.2 32.5

Year ending 30 June (TOP $m) 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026Installation and Maintenance of Street Lighting 0.6 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3

Capital Expenditure 0.8 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3Operating Expenditure 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1

74

Page 75: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Year ending 30 June 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026Customer service levels

Meets 2015 Concession Contract requirements TO MEET TO MEET TO MEET TO MEET TO MEET TO MEET TO MEET TO MEET TO MEET TO MEETAvailable capacity- INSTALLED CAPACITY (FIRM CAPACITY ONLY) 17116 17116 16970 17670 17670 17670 17670 17670 17670 17670- INSTALLED CAPACITY (INCL AS AVAILABLE SOURCES) 20716 22716 24950 27980 27980 27980 27980 27980 27980 27980Generating capacity utilisation

Load factor (%) 56% - 61% 35% - 62% 36% - 60% 37% - 61% 38% - 62% 40% - 64% 40% - 64% 40% - 64% 40% - 64% 40% - 64%Distribution efficiency1,2

Line loss (%) 11% 11% 10% 10% 9% 9% 9% 9% 9% 9%Efficiency of generation1,3

KwH Generated per Litre of Fuel (L) 4.15 4.13 3.95 3.95 3.95 3.95 3.95 3.95 3.95 3.95

75

Page 76: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Pro Forma Consolidated Financial Statements for Tonga Power Limited and Subsidiaries

Table 1 Year ending 30 June 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026Millions of pa'anga 1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun

T$m T$m T$m T$m T$m T$m T$m T$m T$m T$mStatement of Financial PerformanceRevenueFuel 12.9 13.2 13.6 13.9 14.2 14.5 14.9 15.2 15.6 16.0Savings from Renewables -1.9 -1.9 -3.2 -3.2 -3.2 -3.2 -3.2 -3.2 -3.2 -3.2Net Fuel Revenue 11.1 11.4 10.3 10.7 11.0 11.3 11.7 12.0 12.4 12.8Non-fuel 22.1 22.1 22.7 23.2 23.7 24.3 24.9 25.5 26.1 26.7Other revenue 3.7 3.7 3.7 3.7 3.8 3.8 3.8 3.9 3.9 3.9Gas Revenue 7.2 7.3 7.3 7.4 7.5 7.6 7.6 7.7 7.8 7.9Total Revenue 44.0 44.5 44.1 45.0 46.0 47.0 48.0 49.1 50.2 51.3

ExpensesFuel 11.1 11.4 10.3 10.7 11.0 11.3 11.7 12.0 12.4 12.8Renewables costs 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1Non-fuel

Repairs & maintenance 2.2 1.9 2.0 1.9 1.8 2.1 1.7 1.8 1.8 1.8Salary & wages 4.5 4.6 4.6 4.7 4.9 5.0 5.0 5.1 5.1 5.2Materials 0.4 0.4 0.4 0.4 0.4 0.5 0.5 0.5 0.5 0.5Operating overhead 1.9 2.0 2.1 2.1 2.1 2.1 2.1 2.1 2.2 2.2Administration 3.7 3.6 3.6 3.7 3.6 3.6 3.7 3.7 3.8 3.7Bad debt 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1Total non-fuel expense 12.9 12.5 12.7 12.9 12.9 13.4 13.1 13.2 13.5 13.5Gas Expenses 6.5 6.6 6.6 6.7 6.8 6.8 6.9 7.0 7.0 7.1

Total expense 30.6 30.6 29.8 30.4 30.8 31.7 31.8 32.3 33.0 33.5EBITDA 13.5 13.9 14.2 14.6 15.2 15.3 16.2 16.7 17.1 17.8Depreciation 7.2 7.7 8.2 8.5 9.0 9.4 9.7 10.1 10.6 11.1 Interest 1.3 1.3 1.3 1.2 1.0 0.8 0.7 0.5 0.3 0.3

Net profit before tax 4.9 4.9 4.8 5.0 5.2 5.2 5.9 6.1 6.2 6.4Income tax 1.2 1.2 1.2 1.2 1.3 1.3 1.5 1.5 1.5 1.6Net profit after tax 3.7 3.7 3.6 3.7 3.9 3.9 4.4 4.6 4.6 4.8Provision for dividend 1.3 1.3 1.3 1.3 1.4 1.4 1.6 1.6 1.6 1.7Transfer to retained earnings 2.4 2.4 2.3 2.4 2.5 2.5 2.9 3.0 3.0 3.1

76

Page 77: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Year ending 30 June 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026Millions of pa'anga 1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun

T$m T$m T$m T$m T$m T$m T$m T$m T$m T$mTable 2 Statement of Financial Position

Current assetsAccounts receivable & Other Receivables 7.0 7.1 7.2 7.4 7.6 7.8 8.0 8.1 8.3 8.5Inventory 0.9 0.9 0.9 0.9 0.9 1.0 1.0 1.0 1.0 1.1Cash 3.0 5.9 5.9 6.3 6.4 7.9 9.2 8.0 10.0 10.6Short Term Investments 4.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0Gas current assets 2.9 2.9 3.0 3.0 3.0 3.0 3.1 3.1 3.1 3.2Total current assets 17.8 19.8 20.0 20.6 20.9 22.7 24.2 23.3 25.5 26.4

Current liabilitiesAccounts payable & Other Payables 4.7 4.8 4.9 5.0 5.1 5.2 5.3 5.5 5.6 5.7Current portion of term debt 5.7 5.9 6.0 6.0 5.4 4.5 4.5 4.5 4.0 1.8Gas current liabilities 2.1 2.1 2.1 2.2 2.2 2.2 2.2 2.3 2.3 2.3Total current liabilities 12.6 12.8 13.0 13.1 12.7 11.9 12.1 12.2 11.9 9.8

Net working capital employed 5.3 7.0 7.0 7.5 8.2 10.8 12.1 11.0 13.6 16.6Term assetsOpening fixed assets 99.2 105.7 108.8 108.3 108.5 106.1 102.4 101.9 101.5 99.0Capital expenditure 13.8 10.8 7.6 8.8 6.5 5.7 9.1 9.8 8.1 13.0Depreciation 7.2 7.7 8.2 8.5 9.0 9.4 9.7 10.1 10.6 11.1Fixed assets 105.7 108.8 108.3 108.5 106.1 102.4 101.9 101.5 99.0 100.8Gas capital expenditure 2.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3 0.3

Total term assets 108.0 109.1 108.6 108.8 106.4 102.7 102.2 101.8 99.3 101.1Non current liabilitiesDebt 22.0 22.3 19.6 17.7 13.2 9.4 7.1 2.5 -0.7 0.8Deferred Tax Liability 8.6 8.7 8.6 8.8 9.0 9.2 9.4 9.6 9.8 10.0Total Non Current liabilities 30.6 31.0 28.2 26.5 22.2 18.6 16.6 12.1 9.1 10.9

Net assets 82.7 85.1 87.4 89.8 92.4 94.9 97.8 100.7 103.8 106.9

77

Page 78: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Year ending 30 June 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026Millions of pa'anga 1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun

T$m T$m T$m T$m T$m T$m T$m T$m T$m T$mTable 3 Statement of Movements in Equity

Net Assets 82.7 85.1 87.4 89.8 92.4 94.9 97.8 100.7 103.8 106.9Represented by:Opening share capital 35.7 35.7 35.7 35.7 35.7 35.7 35.7 35.7 35.7 35.7Change in working capital 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0Share capital at year end 35.7 35.7 35.7 35.7 35.7 35.7 35.7 35.7 35.7 35.7

Opening retained earnings 16.1 18.5 20.9 23.2 25.6 28.2 30.7 33.6 36.6 39.6Transfers to retained earnings 2.4 2.4 2.3 2.4 2.5 2.5 2.9 3.0 3.0 3.1Retained earnings at year end 18.5 20.9 23.2 25.6 28.2 30.7 33.6 36.6 39.6 42.7

Assets revaluation reserve 28.5 28.5 28.5 28.5 28.5 28.5 28.5 28.5 28.5 28.5Shareholders' equity 82.7 85.1 87.4 89.8 92.4 94.9 97.8 100.7 103.8 106.9

78

Page 79: BUSINESS PLAN 2017 2020 - Tonga Power BusinesPlan 2017.pdf · It is my pleasure to present TPLs Business Plan for the ... Reform Project now ... my Management. The main objective

Year ending 30 June 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026Millions of pa'anga 1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun1 Jul-30 Jun

T$m T$m T$m T$m T$m T$m T$m T$m T$m T$mTable 4 Statement of Cash Flows

Cash from operating activities 2.4 2.4 2.3 2.4 2.5 2.5 2.9 3.0 3.0 3.1Adjusted by: Depreciation 7.2 7.7 8.2 8.5 9.0 9.4 9.7 10.1 10.6 11.1Change in working capital 5.2 4.8 0.4 1.5 0.8 0.2 -0.3 0.3 0.7 -1.5Increase in Term Investments 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0

Net Cash from operations 14.8 14.9 10.9 12.4 12.3 12.1 12.2 13.4 14.4 12.7Long term assetsCash from (used by) long term assets -16.1 -11.1 -7.9 -9.1 -6.8 -6.0 -9.4 -10.1 -8.4 -13.3

Long term liabilitiesIncr in long term debt 7.0 5.0 3.0 3.0 0.0 0.0 3.0 0.0 0.0 3.0Decr in long term debt -5.7 -5.9 -6.0 -6.0 -5.4 -4.5 -4.5 -4.5 -4.0 -1.8Incr (decr) in capital 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0Cash from (used by) liabilities and capital 1.3 -0.9 -3.0 -3.0 -5.4 -4.5 -1.5 -4.5 -4.0 1.2

Net incr (decr) in cash 0.0 2.9 0.0 0.4 0.1 1.5 1.3 -1.2 2.0 0.7Opening cash 3.0 3.0 5.9 5.9 6.3 6.4 7.9 9.2 8.0 10.0Cash at year end 3.0 5.9 5.9 6.3 6.4 7.9 9.2 8.0 10.0 10.6

79