Upload
others
View
4
Download
1
Embed Size (px)
Citation preview
BWROG Executive Oversight Committee & NRC Management
Meeting
July 26, 2018Rockville, MD
Copyright 2018, BWR Owners’ Group, All Rights Reserved
BWROG Introduction
Copyright 2018, BWR Owners’ Group, All Rights Reserved
1July 26, 2018
Tim Hanley (Exelon) – BWROG Executive Chairman
BWROG EOC & NRC Meeting
July 26, 2018
Rockville, MD
Topics
BWROG Background
BWROG Committees
Copyright 2018, BWR Owners’ Group, All Rights Reserved2July 26, 2018
BWROG Background - Structure
Copyright 2018, BWR Owners’ Group, All Rights Reserved3July 26, 2018
EXECUTIVE COMMITTEE
(Executive Oversight Committee)
TECHNICAL COMMITTEES
(Generic / Non-Generic)
Chairman
(Vice Chairman)
Prime Reps
(Advisory Committee)
GEH PMO - Supports all
BWROG Utility Members
BWROG Industry Management
Responsibilities
Executive Committee:
• Responsible for overall direction
/ progress of OG activities
• Approve work scope, funding,
schedule, and final products for
Generic activities
Chairman:
• Responsible for overall
management of OG activities
and GEH Program Manager
• Sign BWROG Correspondence
to NRC, EPRI, NEI, IPO, etc.
• Address emerging BWR issues
• Oversight of GEH PMO
Prime Reps:
• Review / Approve BWROG
Correspondence to NRC
• Approve work scope, funding,
schedule, and final products for
Non-Generic Activities
BWROG Background – Leadership
Copyright 2018, BWR Owners’ Group, All Rights Reserved4July 26, 2018
Tim Hanley Executive Chair
Paul Davison Executive Vice Chair
John Grubb General Chair
Greg Krueger General Vice Chair
Greg Holmes Program Manager
BWROG Background – Leadership
Copyright 2018, BWR Owners’ Group, All Rights Reserved5July 26, 2018
Executive Oversight Committee
• Tim Hanley (Exelon) – Chairman
• Paul Davison (PSEG) – Vice Chairman
• Steve Douglas (TVA)
• Oscar Limpias (Entergy)
• Joe Donahue (Duke Energy)
• Glen Watford (GEH)
BWROG Background - Membership
Copyright 2018, BWR Owners’ Group, All Rights Reserved6July 26, 2018
Utility (Members) Utility (Members)
DTE Energy - Fermi Exelon – Nine Mile Point
Duke Energy - Brunswick FirstEnergy -Perry
Energy Northwest - Columbia NPPD - Cooper
Entergy - Pilgrim NextEra Energy - DAEC
Entergy - River Bend / Grand Gulf PSEG - Hope Creek
Exelon - Clinton Southern Nuclear - Hatch
Exelon - Dresden / Quad Cities / LaSalle Talen Energy - Susquehanna
Exelon - FitzPatrick TVA - Browns Ferry
Exelon – Limerick / Peach Bottom Xcel Energy - Monticello
International (Members) International (Members)
CFE JAPC
Chubu KKL
Chugoku Taiwan Power Company
Hokuriku Tohoku
Iberdrola Tokyo Electric Power Holdings Inc.
Conditional (Members) Conditional (Members)
Horizon Nuclear Power J-Power
2018 Generic Technical Committees
Copyright 2018, BWR Owners’ Group, All Rights Reserved7July 26, 2018
• 50.69 Working Group
• BWR Water Chemistry
• Emergency Procedures
• Fukushima Response
• IRIR
• Licensing
• RCIC Extended Ops
• Reactivity Controls Review
• Reload Analysis & Core Mgmt.
2018 Non- Generic Technical Committees
Copyright 2018, BWR Owners’ Group, All Rights Reserved8July 26, 2018
System Improvement (SI) Committees | Specific Issue Committees | Plant Performance Committees
• BWR6 Rod Control & Information System
• BWR Parts Obsolescence
• Control Rod Drive (CRD)
• ECCS
• Feedwater
• BWR I&C Maintenance
• Offgas
• Operations Significant Event Review (OSER)
• Outage Management
• Radiation Protection/ALARA
• Refueling Performance
• Reactor Recirculation
• RWCU
• Target-Rock 2-Stage SRV Performance Improvement
• Turbine Generator & Aux
• Valve Technical Resolution Group
9
BWROG Introduction
Copyright 2018, BWR Owners’ Group, All Rights Reserved
QUESTIONS
9July 26, 2018
Licensing Committee Update
Copyright 2018, BWR Owners’ Group, All Rights Reserved
1July 26, 2018
John Grubb (Xcel Energy) – BWROG Chairman
BWROG EOC & NRC Meeting
July 26, 2018
Rockville, MD
Topics
Joint Activities with the PWROG Licensing Committee
Industry Implementation of TSTF-542
Travelers of Interest Under NRC Review
Copyright 2018, BWR Owners’ Group, All Rights Reserved2July 26, 2018
Joint Activities with the PWROG Licensing Committee
The BWROG Licensing Committee is holding overlapping meetings with the PWROG Licensing Committee three times a year
• A joint meeting day held between the PWROG and BWROG separate meetings
• Expanding on the long-standing cooperation on TSTF travelers, such as:
– Impact of 50.69 adoption on Surveillance Requirements that reference the Inservice Testing Program
– ATF lead test assembly regulatory requirements
– Coordinated license amendment request submittal process
– Regulatory requirements on training and qualification of personnel
• The next joint meeting is August 15
Copyright 2018, BWR Owners’ Group, All Rights Reserved3July 26, 2018
Industry Implementation of TSTF-542, "Reactor
Pressure Vessel Water Inventory Control" (RPV
WIC)
• The Licensing Committee continues to support fleet
adoption of TSTF-542
• Amendments have been submitted by all applicable
plants except Browns Ferry
– All but Pilgrim and Oyster Creek are adopting
• Amendments approved for 8 plants
• NRC "tiger team" review approach has halved the review
time for later amendments
• BWROG implementation guidance revised to reflect plant
experience
– Guidance supports consistent industry implementation
July 26, 2018 4Copyright 2018, BWR Owners’ Group, All Rights Reserved
Active Traveler Status
Currently Nine TSTF Travelers Under NRC Review
• Eight travelers are applicable to BWRs
• Six scheduled for approval this year
July 26, 2018 5Copyright 2018, BWR Owners’ Group, All Rights Reserved
TSTF-505, Provide Risk-Informed Extended
Completion Times
The BWROG, PWROG, and NEI have been working to
resolve the NRC concerns with TSTF-505.
• TSTF-505, Rev. 2, submitted on July 2, with comments
on the NRC’s draft Safety Evaluation
• Expect final SE (approving Rev. 2), clearing the way for
plant-specific amendments, in fourth quarter 2018
July 26, 2018 6Copyright 2018, BWR Owners’ Group, All Rights Reserved
TSTF-563, Revise Instrument Testing Definitions
to Incorporate the Surveillance Frequency
Control Program
Revises TS definition of Channel Calibration and Channel
Functional Test such that testing frequencies for components
or devices in each step can be determined in accordance
with surveillance frequency control program
• Submitted May 10, 2017
• Draft SE scheduled for August 2018, with approval this
year
July 26, 2018 7Copyright 2018, BWR Owners’ Group, All Rights Reserved
TSTF-564, Safety Limit MCPR
Replaces the cycle-specific SL MCPR with a fuel design-
based SL MCPR. Will avoid rush amendment requests
Submitted August 28, 2017
Supported by GNF and Westinghouse
Draft SE scheduled for August 2018, with approval this year
July 26, 2018 8Copyright 2018, BWR Owners’ Group, All Rights Reserved
TSTF-565, Revise the LCO 3.0.2 and LCO
3.0.3 Bases
Clarifies the application of the TS by eliminating the
phrase "operational convenience" and other subjective
Bases qualifying statements from the LCO 3.0.2 and
LCO 3.0.3 Bases
• Expect NRC acceptance in 2018
• Licensees can adopt the changes using the TS
Bases Control Program
July 26, 2018 9Copyright 2018, BWR Owners’ Group, All Rights Reserved
TSTF-566, Revise Actions for Inoperable
RHR Shutdown Cooling Systems
Revises the actions for an inoperable RHR-SDC
subsystem and clarifies that an inoperable but available
subsystem can be used as an alternate
• Submitted January 2018
• Draft SE scheduled for October 2018
• Expect approval in early 2019
July 26, 2018 10Copyright 2018, BWR Owners’ Group, All Rights Reserved
11Copyright 2018, BWR Owners’ Group, All Rights Reserved
QUESTIONS
11July 26, 2018
50.69 Working Group Committee Update
Copyright 2018, BWR Owners’ Group, All Rights Reserved
1July 26, 2018
Tim Hanley (Exelon) – BWROG EOC Executive Chairman
BWROG EOC & NRC Meeting
July 26, 2018
Rockville, MD
Topics
Background/Timeline
BWROG 50.69 Working Group Committee
Industry Alignment
OM Part 29
Copyright 2018, BWR Owners’ Group, All Rights Reserved2July 26, 2018
Background/Timeline
Copyright 2018, BWR Owners’ Group, All Rights Reserved3July 26, 2018
• South Texas Project – exemption request – approved 2001
• 10CFR50.69 Rule – issued 2004
• PWROG Pilot – Letter Report WOG-04-237 - issued 2004
– Passive categorization and other implementation issues identified
• NEI 00-04 Categorization Guideline - issued 2005
• NRC RG 1.201 - issued 2006
• Vogtle Pilot – approved 2014
– Passive categorization and other implementation issues resolved
• NEI 16-09 Risk-Informed Engineering Programs (10 CFR 50.69)
Implementation Guidance – issued 2017
• NEI 17-05 Risk Informed Engineering Programs (10 CFR 50.69): RISC-
3 Alternative Treatments – issued 2018
Background/Timeline (Cont.)
The rule allows licensees to use an NRC approved risk-informed process to categorize plant components as either High Safety Significant (HSS) or Low Safety Significant (LSS). Components that are categorized as LSS – even if they are Safety-Related – are removed from a number of NRC "special treatment" requirements:
Instead, these components must meet the "alternative treatment" requirements described in 10 CFR 50.69(d). The alternative treatment requirements enable increased flexibility and licensee control over design, procurement, inspection and testing, and maintenance activities. This flexibility allows resources to be focused on areas of safety significance and reduces burden on areas that are not. Copyright 2018, BWR Owners’ Group, All Rights Reserved
4July 26, 2018
50.69 Working Group Committee (WGC)
In 2017, utility members requested that BWROG and PWROG lead a joint industry Owners’ Group (OG) effort with a goal of ensuring consistent implementation of 10 CFR 50.69
June 28-29, 2017: Ad Hoc meeting with BWROG, PWROG, NEI, EPRI, and supporting vendors
October 11-12, 2017: 1st Official 50.69 WGC Meeting
February 21-23, 2018: 50.69 WGC Meeting
July 9-11, 2018: 50.69 WGC Meeting
November 27-29, 2018: Next Planned 50.69 WGC Meeting
2019: 3 Meetings Planned
Copyright 2018, BWR Owners’ Group, All Rights Reserved5July 26, 2018
50.69 Working Group Committee (WGC) (Cont.)
Charter - Purpose
• Provide oversight and infrastructure for the industry’s
coordinated 50.69 efforts
• Identify industry needs with regard to 50.69
• Determine the appropriate lead and scope of the work
to be performed by sub-groups (OG led)
• Ensure progress is made in a suitable timeframe with
no unnecessary overlap with other organizations
Copyright 2018, BWR Owners’ Group, All Rights Reserved6July 26, 2018
50.69 Working Group Committee (WGC) (Cont.)
Focus Groups for Major Areas of Interest:
• Training and Change Management
• Categorization
• Alternative Treatments
• Procurement and Design Engineering
Copyright 2018, BWR Owners’ Group, All Rights Reserved7July 26, 2018
Industry Alignment – Swim Lanes
Copyright 2018, BWR Owners’ Group, All Rights Reserved8July 26, 2018
OM Part 29
• OM Part 29 adds a layer of unwarranted additional requirements beyond 50.69 (the rule itself) that limit/negate a licensee's opportunity to increase overall levels of safety through more safety-benefit-focused alternate treatments of RISC-3 SSCs
• Since OM Part 29 was approved in 2008, significant industry guidance has been established in the form of NEI 00-04,16-09, 17-05, EPRI Tech Reports, and PWROG/BWROG guidelines that communicate a consistent and aligned industry position on establishing alternate treatment requirements for RISC-3 SSCs during 50.69 implementation
• Imposing additional requirements on AT through the ASME standards is a backdoor approach to adding additional regulation
Copyright 2018, BWR Owners’ Group, All Rights Reserved9July 26, 2018
OM Part 29 (Cont.)
• The NRC already has a 50.69 Inspection Procedure (IP 37060) which is where inspection guidance is covered; this does not belong in a Code Case
• One of the objectives of the IP is, “To verify that the licensee properly implements alternate treatment requirements for those SSCs evaluated using the 10 CFR 50.69 categorization process and subjected to alternative treatments”
• 50.69 WGC supports removal of OM Part 29 and rejection of any proposed ASME prescribed guidance on 50.69 Alternative Treatment
Copyright 2018, BWR Owners’ Group, All Rights Reserved10July 26, 2018
11
50.69 Working Group Committee Update
Copyright 2018, BWR Owners’ Group, All Rights Reserved
QUESTIONS
11July 26, 2018
FLEX Equipment Data Collection for Use in Risk Informed Decision Making
Copyright 2018, BWR Owners’ Group, All Rights Reserved
BWROG EOC & NRC Meeting
July 26, 2018
Rockville, MD
Bob Rishel (Duke Energy) – BWROG IRIR Chairman
2
Topics
Maintenance Rule Impact for FLEX
FLEX in Risk Informed Decision Making (FRIDM)
Plant FLEX Equipment
Industry Strategy
Data Collection
EPRI and FLEX Maintenance WG
Owners’ Group Effort
SAFER Centers Equipment
Current State of FLEX Implementation
Potential Numerical Impact of FLEX
July 26, 2018
Copyright 2018, BWR Owners’ Group, All Rights Reserved
2
Maintenance Rule Impact for FLEX
Draft RG 1.160 Rev 4, (DG1336) endorsing NUMARC 93-01
Rev 4f states:
Nonsafety related SSCs that are used in Emergency Operating
Procedures
The following two items apply when EOP steps are added that direct operators to
FSGs for additional defense-in-depth measures. If these are met, then the non-
safety-related equipment in the FSGs is not considered “used” in the EOPs:
• Differentiate the non-safety-related equipment in the FSGs from the equipment
providing EOP mitigation function in the Maintenance Rule scoping evaluation
or EOP change process documentation.
• Equipment already scoped into the Maintenance Rule under the “used in plant
EOPs” criteria should not be removed from the Maintenance Rule scope based
solely on the addition of non-safety-related equipment in the FSGs as a
defense-in-depth measure.
July 26, 2018 3Copyright 2018, BWR Owners’ Group, All Rights Reserved
Maintenance Rule Impact for FLEX
(Cont.)
Draft RG 1.160 Rev 4, (DG1336) endorsing NUMARC 93-01
Rev 4f states:
Nonsafety related SSCs that are used in Emergency Operating
Procedures
“FLEX Support Guidelines (FSGs) are not considered to be EOPs. Equipment
described only in FSGs would not be in scope of the Maintenance Rule unless
otherwise required by paragraph 50.65(b).”
Additional clarifications are made:
“that equipment described in FSGs are not “used” in EOPs for purposes of
scoping into the Maintenance Rule under 50.65(b)(2)(i) (stating that the scope of
the monitoring program includes nonsafety related SSCs that “are used in plant
emergency operating procedures (EOPs)”) as long as the other criteria are
assessed.”
July 26, 2018 4Copyright 2018, BWR Owners’ Group, All Rights Reserved
FLEX in Risk Informed Decision Making (FRIDM)
FLEX in Risk-Informed Decision Making (FRIDM) Task Force established by NEI in September 2015
The Task Force objective was to develop a number of streamlined approaches for crediting FLEX in risk-informed decision making activities, including PRA models
FRIDM Task Force developed an effective framework for considering the benefits of FLEX equipment and mitigating strategies in risk-informed regulations, applications, and plant PRA models without imposing undue regulatory burden
Copyright 2018, BWR Owners’ Group, All Rights Reserved
July 26, 2018 5
FLEX in Risk Informed Decision Making (FRIDM) (Cont.)
July 26, 2018
Copyright 2018, BWR Owners’ Group, All Rights Reserved
NEI 12-06 NEI 16-06 NEI 16-08
6
Plant FLEX Equipment
July 26, 2018
Copyright 2018, BWR Owners’ Group, All Rights Reserved7
Plant FLEX Equipment (Cont.)
July 26, 2018
Copyright 2018, BWR Owners’ Group, All Rights Reserved8
Industry Strategy
Maximize Areas of Credit
Maximize FLEXibility
FLEX and Beyond
Expand operational and regulatory credit given to mitigating strategies
Expand where portable equipment is used in plant operations
Be inclusive of all portable equipment beyond just FLEX
(e.g. B.5.b portable equipment)
The goal is to maximize the benefit of the large
investment in portable equipment at sites
July 26, 2018
Copyright 2018, BWR Owners’ Group, All Rights Reserved9
Industry Strategy (Cont.)
Copyright 2018, BWR Owners’ Group, All Rights Reserved
July 26, 2018
Graphic provided with permission of NEI
Potential Applications of NEI 16-06
10
Data Collection
To be able to credit FLEX in the applications need to
meet data requirements of RG 1.200
• Data sources that are verifiable
• Generic data
• Plant specific information
NRC staff has doubts about some of the licensee
assumptions of FLEX/Portable equipment reliability
and availability
• Need to resolve question on meeting
requirements of RG 1.200 data
July 26, 2018 11Copyright 2018, BWR Owners’ Group, All Rights Reserved
Data Collection (Cont.)
Equipment starts
Run hours
Failures by type (FTR, FTS)
Failure cause (what was wrong)
Type of equipment
• Diesel driven pumps (may need to separate by
capacity)
• Engine driven generators (may need to separate out
by size/design of generator
• Fans
• Air Compressors
July 26, 2018 12Copyright 2018, BWR Owners’ Group, All Rights Reserved
EPRI and FLEX Maintenance WG
Maintain existing Flex Maintenance Database
• We don’t want to interfere with primary role of
database
• Leverage information in Database to improve
efficiency of Utility data gathering
• Not a referenceable source of data for OG
Reports
FLEX Maintenance Working Group
• Continue to collect data for PM purposes
• Communicate data collection lessons learnedJuly 26, 2018 13
Copyright 2018, BWR Owners’ Group, All Rights Reserved
Owners’ Group Effort
Download utility specific data from Flex
Maintenance Database (optional)
Collect supplemental data
Validate Data
Provide data to OGs
Retain plant specific equipment data to met RG
1.200 Capability Category II
July 26, 2018 14Copyright 2018, BWR Owners’ Group, All Rights Reserved
Owners’ Group Effort (Cont.)
Develop Instructions for data collection/validation
• Participate in Flex Maintenance WG calls
• Evaluate/Calculate Data
Provide NRC opportunity for review (targeted fall
2018)
Publish Reports (targeted 1st quarter 2019)
July 26, 2018 15Copyright 2018, BWR Owners’ Group, All Rights Reserved
Owners’ Group Effort (Cont.)
Public Report• Process description
• Calculations
• Evaluations
• Failure rates and uncertainty distributions
• Number of Failures
• Demands
• Run Hours
Lessons Learned Report• Update Frequency
• Recommendations to improve efficiency of data
collection
July 26, 2018 16Copyright 2018, BWR Owners’ Group, All Rights Reserved
SAFER Centers Equipment
Large inventory of equipment
• Most of the current EPRI data is from SAFER
Centers
• SAFER Center Equipment generally not
credited in PRA
• SAFER Center data will only be credited
where it is similar to on-site equipment
– Additional cost to SAFER Center for data
collection
July 26, 2018 17Copyright 2018, BWR Owners’ Group, All Rights Reserved
Current State of FLEX Implementation
FLEX capabilities are being included in PRAs numerically
• Both simplified approach and detailed approach
– Limited number of PRA completed with FLEX
implemented
• Most Utilities have plans to incorporate FLEX into the base
PRA models
– Includes External Events PRA models
o Fire PRA
o High Winds PRA
o Seismic PRA
Flex equipment being used to support refueling outage risk
reduction
Flex equipment being credit to reduce risk of maintenance
July 26, 2018 18Copyright 2018, BWR Owners’ Group, All Rights Reserved
Current State of FLEX Implementation
(Cont.)Examples for use of FLEX Equipment in FRIDM
• NRC allowances to delay shut-down to allow time
for repairs– Extended Diesel Repair to 62 days and another for 30 days
– Extended Service Water Pump rebuild to 14 days
• Significance Determination Process (SDP) for
NRC violation for external hazards– External flooding
– Extended loss of off-site power
• Refueling Outage risk reduction– Spent Fuel Pool make-up
– Rx vessel water inventory control
– Water transfer to installed tanks
July 26, 2018 19Copyright 2018, BWR Owners’ Group, All Rights Reserved
Potential Numerical Impact of FLEX
CDF/LERF
BWR CDF (IE) reduction ranges: 1% to 40%
➢ Primary influence: HCVS and FLEX portable generators
BWR CDF (Fire) reduction: 40% at one pilot site
➢ Primary influence: Diverse injection free from fire damage
BWR CDF (Seismic) reduction:17% at one pilot site
➢ Primary influence: Additional diverse injection
• The calculated risks vary based on site specific plant design and existing mitigation capabilities
• Model updates are pending final considerations of HRA methods and dependent operator actions
July 26, 2018
Copyright 2018, BWR Owners’ Group, All Rights Reserved20
21
FLEX Equipment Data Collection for use in Risk Informed Decision Making
July 26, 2018
Copyright 2018, BWR Owners’ Group, All Rights Reserved
QUESTIONS
21
BWROG EPG/SAG Rev 4 and TSG Rev 1 Update
Copyright 2018, BWR Owners’ Group, All Rights Reserved
1July 26, 2018
Steve Douglas (TVA) – BWROG Executive
BWROG EOC & NRC Meeting
July 26, 2018
Rockville, MD
Topics
BWROG – Emergency Procedures Committee Guidance
Updates (Rev 4)
Proposed U.S. BWR Fleet Wide Implementation Schedules
Product Lines Addressed
All Operating Modes Addressed
Extended Loss of AC Power (ELAP)
Severe Accident Water Addition / Severe Accident Water
Management (SAWA/SAWM)
Improved Anticipated Transients Without SCRAM (ATWS)
Guidance
Copyright 2018, BWR Owners’ Group, All Rights Reserved2July 26, 2018
3
BWROG – Emergency Procedures Committee Updated Guidance (Rev 4)
July 26, 2018
Copyright 2018, BWR Owners’ Group, All Rights Reserved
• Emergency Procedures and Severe Accident Guidelines (EPG/SAG) Rev 4 & Technical Support Guidelines (TSG) Rev 1: Formally published on June 1, 2018:
– On time delivery per agreed schedule / publication date
– U.S. fleet wide completion date: 2 refueling outages or 3 years which ever is greater from publication date (NEI 14-01)
• The Rev 4 Guidelines consist of:
– EPG/SAGs (multiple volumes for operating modes)
– EPG/SAG Appendices A to C
– TSGs
– TSG Appendix A
– TSG Calculational Aids
– Event Case Studies (Training aids)
– Optional products; Emergency Management Guideline (EMG) & the Station Blackout (SBO) flowcharts
U.S. BWR Fleet Implementation
Schedule
EPG/SAG Rev. 4 TSG Rev 1
Proposed Implementation Schedule
• Legend: # of units (# of sites)
• Note: Two sites have different submittal dates for its units
First – Q2 2020
Last – Q2 2022
One Site Under Evaluation
Dates are approximate (Survey - July 2018)
July 26, 2018 4Copyright 2018, BWR Owners’ Group, All Rights Reserved
2020 2021 2022
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2
3 (2) - 5 (3) 3 (2) 18 (12) - - 2 (2)
Product Lines Addressed
• BWR Product Lines
– BWR/2-6
– ABWR
• BWR Containments
– Mark I, II, III
– ABWR
Copyright 2018, BWR Owners’ Group, All Rights Reserved5July 26, 2018
All Operating Modes Addressed
• EPGs for Events from Modes 1 to 4
• EPGs for Events from Mode 5 (refueling)
• SAGs for Events from Modes 1 to 5
Includes new guidance for shutdown and refueling
Previous EPG/SAGs (Rev 0 to 3) & the TSGs only
addressed events beginning from Modes 1-3
Copyright 2018, BWR Owners’ Group, All Rights Reserved6July 26, 2018
Extended Loss of AC Power
Copyright 2018, BWR Owners’ Group, All Rights Reserved7July 26, 2018
Extended Loss of AC Power Addressed in Rev. 4
• Improved guidance is provided for conditions where core cooling is maintained by steam driven systems or by low capacity low pressure systems (FLEX)
• Guidance is provided to transfer core cooling from installed equipment to FLEX type systems
SAWA/SAWM
Severe Accident Water Addition / Severe Accident Water Management (SAWA/SAWM) in Rev 4
• Guidance Preserves the Hardened Severe Accident Containment Vent
• New additions to TSG Rev. 1 (determination that ex-vessel core debris is stabilized)
Copyright 2018, BWR Owners’ Group, All Rights Reserved8July 26, 2018
Improved Anticipated Transients Without SCRAM (ATWS) Guidance
New ATWS Guidance:
• A significant update for operating crews
• Improves Crew Performance and the plant’s response to ATWS events
• A pressure control parameter is provided that improves ATWS response:
– Also includes 20 years of O/E, crew insights and analysis which indicates that high pressure injection provides similar results whether injection occurs inside or outside the shroud.
Copyright 2018, BWR Owners’ Group, All Rights Reserved9July 26, 2018
10
EPG/SAG Rev 4 and TSG Rev 1
Copyright 2018, BWR Owners’ Group, All Rights Reserved
QUESTIONS
10July 26, 2018
Tim Hanley (Exelon) – BWROG EOC Executive Chairman
Anchor Darling Double Disk Gate Valve (ADDDGV) Part 21 Update
Copyright 2018, BWR Owners’ Group, All Rights Reserved
BWROG EOC & NRC Meeting
July 26, 2018
Rockville, MD
July 26, 2018 1
Topics
2
Timeline
Industry Survey
July 26, 2018
Copyright 2018, BWR Owners’ Group, All Rights Reserved
Timeline
3
February 25, 2013: Flowserve issues 10CFR Part 21
Notification concerning wedge pin failure of an Anchor
Darling Double Disc Gate Valve.
April 2013: BWROG VTRG issues TP-13-006 to provide
a recommended industry response to the Flowserve
10CFR Part 21 Notification.
July 26, 2018
Copyright 2018, BWR Owners’ Group, All Rights Reserved
4
Timeline (Cont.)
December 2016, TP-13-006 revised (TP16-1-112).
• Included results of 26 stem/disc connection inspections.
• 24 of 26 connections were found with loose connections but
no pin damage was observed.
• Report revised to recommend only two long-term solutions:
• Analyze the stem/wedge connection from a torque
perspective and show all anticipated loads are
acceptable (assuming no factory pre-load per the results
of the 26 inspections).
• Disassemble the valve and torque the stem/wedge
connection to a value that exceeds all anticipated
operational loads.
• The above recommended actions were to be completed
within three refueling outages (maximum of six years).July 26, 2018
Copyright 2018, BWR Owners’ Group, All Rights Reserved
5
Timeline (Cont.)
February 11, 2017: LaSalle HPCS MOV A/D DDGV
Stem/Disc Separation Event
• 12”-900# valve manufactured in 1972 and installed in
1984 had operated without incident since plant startup.
• Identified as one of 22 susceptible MOVs using the
original BWROG guidance TP-13-006 R0).
• Wedge pin analysis could not provide evidence that the
wedge pin alone could handle the operational torque
load.
• Stem rotation checks and diagnostic thrust signature
analysis performed as interim actions.
July 26, 2018
Copyright 2018, BWR Owners’ Group, All Rights Reserved
6
Timeline (Cont.)
May 2017: BWROG TP-16-1-112, R2, Issued• Revision to incorporate lessons learned and recommendations
resulting from the stem/disc separation event that occurred at
LaSalle station in February 2017.
• Maximum stem rotation changed to 5 degrees combined with need for better
accuracy to support trending.
• More aggressive corrective action (either wedge pin analysis or valve internal
work) recommended.
• Present diagnostic test data anomalies preceding LaSalle MOV Failure.
June 2017: BWROG TP-16-1-112, R3, Issued
• Revision to incorporate comments from Flowserve and others to
facilitate formal Flowserve Corporation endorsement of the updated
Topical Report.
• Flowserve evaluation of the LaSalle Stem/Disc separation event.July 26, 2018
Copyright 2018, BWR Owners’ Group, All Rights Reserved
7
Timeline (Cont.)
August 2017: BWROG TP-16-1-112, R4
• Revision incorporated results of detailed failure analysis
of the LaSalle HPCS MOV stem/disc separation event.
• Provides discussion on potential scope impacts of the
failure as well as recommended actions to permanently
resolve the issue.
• Includes guidance on proper conduct of MOV stem
rotation checks as well as a new recommendation to
periodically perform rotation checks for applicable
valves.
July 26, 2018
Copyright 2018, BWR Owners’ Group, All Rights Reserved
8
Timeline (Cont.)
NRC Draft Temporary Instruction (TI)
• NRC issued draft TI in April 2018.
• Industry had significant comments / feedback regarding
the content of TI.
– Draft TI appeared to establish expectations that
exceeded the legacy Generic Letter 89-10/96-05
programs (e.g., designing against stall torque).
• Feedback provided to NRC at public meeting held in
May 2018.
• NRC received feedback and planned to incorporate
comments, as necessary, and hold a second public
meeting to review resolution (has not occurred).
July 26, 2018
Copyright 2018, BWR Owners’ Group, All Rights Reserved
9
Industry Survey
• During 1Q2018 VTRG meeting, committee
members agreed to provide inspection results for all
DDGV disassemblies
• Following May 2018 NRC public meeting, industry
survey was expanded to include PWRs as well
• Results were submitted July 16, 2018 to the NRC
July 26, 2018Copyright 2018, BWR Owners’ Group, All Rights Reserved
10
ADDDGV Part 21 Update
July 26, 2018
Copyright 2018, BWR Owners’ Group, All Rights Reserved
QUESTIONS
10
Copyright 2018, BWR Owners’ Group, All Rights Reserved
BWROG Target Rock SRV Performance Improvement Committee
Steve Douglas (TVA) – BWROG Executive
BWROG EOC & NRC Meeting
July 26, 2018
Rockville, MD
2
Topics
History/Scope
What is Being Done by the BWROG
Copyright 2018, BWR Owners’ Group, All Rights Reserved
3
History/Scope
Non-Generic Committee formed in 2016
Membership: DTE/Fermi, Duke/Brunswick,
Exelon/FitzPatrick, NPPD/Cooper, PSEG/Hope Creek,
TVA/Browns Ferry
Committee Scope: address the common causes of
repetitive Target Rock 2-stage SRV as-found set-point test
failures in the fleet
• Technical Exchange Meetings: share site set point drift
performance, best practices, roadmap planning
• 2-stage valve focus
• Scope focused on setpoint drift
Copyright 2018, BWR Owners’ Group, All Rights Reserved
4
What is Being Done by the BWROG
2017-18 Activities
• Industry-shared IBAD procedure (application of Platinum to disc surface).
• Autoclave Screening Test - used to develop sputtering application process of Platinum on test coupons and comparison to IBAD.
• Sputter Coating of (Quantity 3) pilot discs and perform valve testing. Sputtering application process of Platinum application on SRV pilot discs.
• Static Autoclave Material Screening - baseline conditions of corrosion bonding with control group and screening other materials.
Copyright 2018, BWR Owners’ Group, All Rights Reserved
5
What is Being Done by the BWROG (Cont.)
2019 Planned Activities
Test different thickness of (sputtered) Platinum coated on pilot discs in valve lift tests.
• Sputtering opens process space for different thicknesses of Platinum Coating.
• Potential for fleet usage
– Know that current thickness of Platinum coating provided step-improvement in set point drift performance.
– Does increase in thickness provide more protection from corrosion bonding?
June 26-27, 2018Copyright 2018, BWR Owners’ Group, All Rights Reserved
6
BWROG Target Rock SRV Update
July 26, 2018
Copyright 2018, BWR Owners’ Group, All Rights Reserved
QUESTIONS
6