21
06/06/2016 Page 1 NOT PROTECTIVELY MARKED NOT PROTECTIVELY MARKED @HorizonNuclear BWRVIP Mitigation Committee Meeting Plant Experience Report San Antonio 15-16 June 2016 Kathryn James Lead Chemist

BWRVIP Mitigation Committee Meeting Plant Experience Report · Production of the detailed safety case for all water chemical aspects of the plant. Defined risks as ALARP (As Low As

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: BWRVIP Mitigation Committee Meeting Plant Experience Report · Production of the detailed safety case for all water chemical aspects of the plant. Defined risks as ALARP (As Low As

06/06/2016 Page 1

NOT PROTECTIVELY MARKED

NOT PROTECTIVELY MARKED@HorizonNuclear

BWRVIP Mitigation Committee Meeting

Plant Experience Report

San Antonio

15-16 June 2016

Kathryn James

Lead Chemist

Page 2: BWRVIP Mitigation Committee Meeting Plant Experience Report · Production of the detailed safety case for all water chemical aspects of the plant. Defined risks as ALARP (As Low As

@HorizonNuclear

Horizon overview

Established 2009

Acquired by Hitachi November 2012

Provide at least 5.4GW of new capacity

across two sites - c.10 million homes

Deploy Hitachi-GE UK ABWRs

Expect first unit at Wylfa to be operating

in the first half of the 2020s

c.£20billion investment in the UK

Up to 60% of project value could be

spent in UK

Over 350 staff at new Gloucester HQ,

office on Anglesey growing

Wylfa Newydd

Gloucester HQ

Oldbury

Page 3: BWRVIP Mitigation Committee Meeting Plant Experience Report · Production of the detailed safety case for all water chemical aspects of the plant. Defined risks as ALARP (As Low As

@HorizonNuclear

Nuclear in the future UK energy mix

• Energy infrastructure in UK in need of renewal

• c.£110bn of new investment required over next decade

• 50-60GW of new generating capacity by 2025UK’s energy challenge

• Security of supply

• Low-carbon and sustainable

• Affordable – for UK government and consumersStrategic & policy drivers

• Expect around 16GW from new nuclear by 2030

• Deployed alongside other low carbon and baseload sources of electricity UK’s energy future

Page 4: BWRVIP Mitigation Committee Meeting Plant Experience Report · Production of the detailed safety case for all water chemical aspects of the plant. Defined risks as ALARP (As Low As

@HorizonNuclear

Wylfa Newydd – operations

Two Hitachi-GE UK ABWR units, each

1350MW

Commercial operation in first half of the

2020s (first unit)

Supply enough electricity to power five million

homes

Operational life of at least 60 years

Entire station employee complement will be

up to 850

Up to an additional 1000 staff during outage

periods*

Developing operational capabilities and

capacity – WANO, INPO – with potential to

bring in an operational partner alongside us

*Frequency and length to be defined

Page 5: BWRVIP Mitigation Committee Meeting Plant Experience Report · Production of the detailed safety case for all water chemical aspects of the plant. Defined risks as ALARP (As Low As

@HorizonNuclear

ABWR – a proven technology

Safe, reliable and cost competitive

Constructed to time and to budget

Licensed in Japan, Taiwan, USA

Operational - Kashiwazaki-Kariwa-6/7, Hamaoka-5, Shika-2

Under construction - Lungmen (Taiwan), Shimane 3, Ohma

Page 6: BWRVIP Mitigation Committee Meeting Plant Experience Report · Production of the detailed safety case for all water chemical aspects of the plant. Defined risks as ALARP (As Low As

@HorizonNuclear

ABWR assessment and justificationGeneric Design Assessment (GDA)

Step 1 - Assessment agreements signed

March 2013

Step 2 – overview of basic acceptability of the

proposed reactor design construction in the UK

Step 3 – launched August 2014, increasingly

detailed analysis covering Overall Design,

Safety Case and Security Arguments

Step 4 – launched October 2015

Target completion of final design acceptance

(Step 4), end 2017

To make a comment or pose a question on the

process please visit:

http://www.hitachi-hgne-uk-abwr.co.uk/

Steps mentioned here are for the ONR. EA and NRW have slightly different steps including public consultation.

Page 7: BWRVIP Mitigation Committee Meeting Plant Experience Report · Production of the detailed safety case for all water chemical aspects of the plant. Defined risks as ALARP (As Low As

@HorizonNuclear

Delivering Wylfa Newydd

Page 8: BWRVIP Mitigation Committee Meeting Plant Experience Report · Production of the detailed safety case for all water chemical aspects of the plant. Defined risks as ALARP (As Low As

@HorizonNuclear

Complexity of nuclear new build

Grid

Site

Boundary

Access Supply

chain

and skills

WasteOffsite

works

Defences

EcologyJetty

CW System

Page 9: BWRVIP Mitigation Committee Meeting Plant Experience Report · Production of the detailed safety case for all water chemical aspects of the plant. Defined risks as ALARP (As Low As

@HorizonNuclear

Forward priorities

All consents and permits by mid 2018:

End of tech assessment (GDA)……………2017

Development Consent………………………2018

Nuclear Site Licence…………………….….2018

Final Investment Decision early 2019

Page 10: BWRVIP Mitigation Committee Meeting Plant Experience Report · Production of the detailed safety case for all water chemical aspects of the plant. Defined risks as ALARP (As Low As

@HorizonNuclear

Baseline Schedule

Generic Design Assessment

ConstructionDevelopment

PAC 2

Site Licence Application

Development Consent Order All

agre

em

ents

/perm

issio

ns in

pla

ce

(F

ID)

Operation

Unit 1 Commercial Operation, first half of the 2020s

Page 11: BWRVIP Mitigation Committee Meeting Plant Experience Report · Production of the detailed safety case for all water chemical aspects of the plant. Defined risks as ALARP (As Low As

@HorizonNuclear

Corporate structure

Menter Newydd

Page 12: BWRVIP Mitigation Committee Meeting Plant Experience Report · Production of the detailed safety case for all water chemical aspects of the plant. Defined risks as ALARP (As Low As

@HorizonNuclear

Building the company

DeveloperIntelligent Customer

Site Licence Company

Operator/Utility

Page 13: BWRVIP Mitigation Committee Meeting Plant Experience Report · Production of the detailed safety case for all water chemical aspects of the plant. Defined risks as ALARP (As Low As

@HorizonNuclear

Creating an investible project

Investors

To be Site License Company and operator

Contract for Difference

DECC

Counterparty body

Power suppliers

Investor

Power sales

Infrastructure Guarantee

HM Treasury

Export credit agencies

Lenders

Operations partner

Wider supply chain

Page 14: BWRVIP Mitigation Committee Meeting Plant Experience Report · Production of the detailed safety case for all water chemical aspects of the plant. Defined risks as ALARP (As Low As

06/06/2016 Page 14

NOT PROTECTIVELY MARKED

NOT PROTECTIVELY MARKED

Main Workstreams

Delivering Wylfa Newydd

• Technology approval

• Planning & environmental permissions

• Nuclear Site Licence

• Site Development

Growing the Organisation

• Developer

• Intelligent Customer

• Site Licence Company

• Operator/Utility

Creating an Investible Project

• Contract for Difference

• Treasury Guarantee

• Future power sales

• Additional investors

Page 15: BWRVIP Mitigation Committee Meeting Plant Experience Report · Production of the detailed safety case for all water chemical aspects of the plant. Defined risks as ALARP (As Low As

@HorizonNuclear

Chemistry aims to:

- Reduce risk of corrosion and SSC failure to ALARP

- Reduce radiological (Dose) and environmental impact (waste and

discharge) to ALARP

- Determine the UKABWR source term for normal operations and expected

events

RCS Water Chemistry Regime demonstrated to be ALARP:

• Hydrogen Water Chemistry

• Noble Metal Chemical Addition

• Depleted Zinc Oxide Injection

• Optimum iron control

Ref: UKABWR GDA Generic PCSR Chapter 23

– Reactor Chemistry (GA91-9101-0101-23000)

UK ABWR – Chemistry Lead Chemist – Kathryn James([email protected])

Page 16: BWRVIP Mitigation Committee Meeting Plant Experience Report · Production of the detailed safety case for all water chemical aspects of the plant. Defined risks as ALARP (As Low As

@HorizonNuclear

Production of the detailed safety case for all water chemical aspects of the plant.

Defined risks as ALARP (As Low As Reasonably Practicable) for reactor coolant chemistry during commissioning, 1st start up, at power, shutdown and outages.

Source term reduction through material selection, operating practices and regimes

Consideration in the safety case for conventional safety hazards e.g. radiolytic gases in conjunction with UK Health and Safety Legislation

16

Chemistry Status in GDA

Page 17: BWRVIP Mitigation Committee Meeting Plant Experience Report · Production of the detailed safety case for all water chemical aspects of the plant. Defined risks as ALARP (As Low As

06/06/2016 Page 17

NOT PROTECTIVELY MARKED

NOT PROTECTIVELY MARKED

UK Safety Case and ALARP

UK Safety Case approach differs from Safety Evaluations:

• Non prescriptive regulators; Goal setting

• Minimum Levels must be met (Basic Safety Limit)

• As Low As Reasonably Practicable; requirement in law to

demonstrate that risks as ALARP:

- Use of relevant good practice

- Demonstration of gross disproportion of ‘cost’ vs

benefit

• Safety Case presents the ALARP argument:

- Claims – Arguments – Evidence

- ‘Safety Case’ documents provide the road map,

engineering documents provide the evidence

Page 18: BWRVIP Mitigation Committee Meeting Plant Experience Report · Production of the detailed safety case for all water chemical aspects of the plant. Defined risks as ALARP (As Low As

@HorizonNuclear

Production of the detailed safety case for all chemical aspects of the plant including those out of scope of GDA:

Make up water treatment plant (demineralised water plant)

Oil chemistry (turbine, transformers etc.)

Stator water and gas chemistry

Laboratory analytical procedures and instruments

Online chemical instrumentation

Storage and use of chemicals including emergency arrangements

Compliance with UK Health and Safety legislation e.g. legionella

Defined risks as ALARP (As Low As Reasonably Practicable) for reactor coolant chemistry in light of current OPEX.

18

Chemistry Status in Site Specific

Page 19: BWRVIP Mitigation Committee Meeting Plant Experience Report · Production of the detailed safety case for all water chemical aspects of the plant. Defined risks as ALARP (As Low As

@HorizonNuclear

Currently reviewing all available OPEX (BWROG, EPRI as well as

Japanese OPEX) to demonstrate to Regulators all risks are

ALARP for all aspects of chemistry safety case.

www.horizonnuclearpower.com

http://www.hitachi-hgne-uk-abwr.co.uk/

Best Practices

Page 20: BWRVIP Mitigation Committee Meeting Plant Experience Report · Production of the detailed safety case for all water chemical aspects of the plant. Defined risks as ALARP (As Low As

@HorizonNuclear

For more information

Horizon Nuclear Power channel

@HorizonNuclear

LinkedIn

www.horizonnuclearpower.com

Page 21: BWRVIP Mitigation Committee Meeting Plant Experience Report · Production of the detailed safety case for all water chemical aspects of the plant. Defined risks as ALARP (As Low As

06/06/2016 Page 21

NOT PROTECTIVELY MARKED

NOT PROTECTIVELY MARKED@HorizonNuclear

Thank you