Upload
lamcong
View
215
Download
0
Embed Size (px)
Citation preview
Scheme Data Sheet Scheme Name: A483 Machynys West, Llanelli Form of Contract: ECC Option B Value: £2.3 Million Programme: 2008 to 2010 (12 Months) __________________________________________________________________________________
jbhl.co.uk
Page 1
Principal Contractor: Jones Brothers (Henllan) Ltd Design Responsibility: Client Client: Welsh Government / Carmarthenshire CC Description / Key Delivery Features: JBHL were engaged by the
Welsh Government and CCC for the construction of a new roundabout and adjoining access roads on the A483 coastal link road, Llanelli. The contract also included utility service diversions, major surface water drainage, sewage rising main diversion and pumping station construction.
Relevance: The contract highlights our capability to effectively apply a robust
traffic and pedestrian management plan to facilitate the undertaking of construction related activities alongside a fully operational highway and coastal footpath.
Other significant elements of the contract included: • Installation of surface water drainage involving deep
excavations (up to 4.5m) and tidal working. • Sewage pumping main diversions (150mm dia). However,
a section across several high voltage cables was directionally drilled.
• Construction of a 7m deep foul sewage pumping station including M&E and Pump Installations.
• Continuous dewatering owing to ground conditions and location adjacent to the sea.
Challenges Met / Solutions Provided: Risk was minimised during the project by:
• Early site investigation to define works in detail. • Detailed planning and programming of project. • Undertaking a full site investigation of statutory undertaker
infrastructure. • Coordination of our programme to include all support
activities and associated diversionary works. The following challenges were encountered during the project: • Maintaining traffic flows and minimising disruption to road
Scheme Data Sheet Scheme Name: A483 Machynys West, Llanelli Form of Contract: ECC Option B Value: £2.3 Million Programme: 2008 to 2010 (12 Months) __________________________________________________________________________________
jbhl.co.uk
Page 2
users and inconvenience to pedestrian and cycle traffic. • Working safely in deep excavations and in tidal conditions. • Surface drainage obstructions caused by 132KV cable. • Contaminated land issues as a former steel works was
located on part of the site. • The site was located near a gypsy encampment and needed
24/7 security.
Surplus earthworks were recycled and used as fill over landscaped areas. This sustainable approach was in compliance with our Site Waste Management Plan and was fully endorsed by the EA.
Extensive use was made of temporary traffic barriers to protect the workforce and pedestrians. Outputs were also improved within well defined and properly protected safe working areas. The efficiencies and improvements implemented included: • Effective planning and systematic programming of the work
including collaborative meetings with stakeholders. • The importance of allocating adequate and appropriate
resources in order to effectively mobilise the contract. • Early appreciation of the HS&E implications of the site area
and the impact on work activities. • The importance of creating a culture of working together in
order to achieve the project objectives. Principal Supply Chain Partners: JBHL delivered substantive elements of the contract using our
directly employed workforce which helped ensure there was no duplication of supervision or ‘fee on fee’. However, the following specialist subcontractors were employed:
• Directional drilling • Traffic management • Street lighting • Surfacing works. • Mechanical and electrical installation works.
All subcontractors are included on JBHL Approved Supply Chain List.
References: Mr John Payne, Director of Waterman Consulting Engineers: ‘We were pleased with the way you managed the construction phase of this project and applied your knowledge and experience to many of the unforeseen and challenging activities encountered. Well done to everyone involved.’