1
California Asphalt IC Demonstration
I-80, Solano, CA (Sept 4-6, 2013)
On-Site Personnel
First name Last name Affiliation Telephone Email
FHWA IC Project Team George Chang Transtec Group 512-659-1231 [email protected] Qinwu Xu Transtec Group 512-709-4155 [email protected] Lee Gallivan FHWA 317-605-4704 [email protected]
Bob Horan Asphalt Institute 804-539-3036 [email protected]
Steve Healow FHWA - CA 916-498-5849 [email protected]
State DOT Chuck Suszko Caltrans 916-798-6029 [email protected] James Lee Caltrans 916-274-6095 [email protected] Ebi Fini Caltrans 916-227-5396 [email protected] Ken Darby Caltrans 916-227-5705 [email protected] Carl Butters Caltrans [email protected] Joe Holland Caltrans 916 227-5825 [email protected] Vendors Chris Connolly Bomag 301-529-8477 [email protected] Tim Kowalski Wirtgen/Hamm 615-594-4604 [email protected] Josh Weston Wirtgen/Hamm 615-693-9839 [email protected] Todd Mansell Caterpillar 763-447-5695 [email protected] Garry Aicken Kessler (LWD-a Test) 703-989-6612 [email protected] Steve Powers Sitech West 916-835-2939 [email protected] Gary Sanati GPR test (via [email protected]) Paving Contractors Chris Barkley Teichert Construction 530-308-1083 [email protected] Paving Association Russell Snyder CalAPA 925-548-5409 [email protected] Rita Leahy CalAPA 916-239-8315 [email protected]
Project webpage: (http://www.intelligentcompaction.com/index.php?q=node/397)
2
Main Contacts
FHWA IC project: Dr. George Chang, FHWA IC team.
Field Visits: Chris Barkley, Teichert Construction
Open House: Ebi Fini, Caltrans
Roller Shipment: Shipping address: 24207 County Road 100A, Davis, CA 95616; Contacts:
Chris Barkley, Teichert Construction, 530-308-1083; ETA: Friday, Aug. 30, 2013.
Responsibilities
FHWA IC Team
IC training,
Field data collection/analysis,
Presentation during Open House.
DOT
Personnel to be trained on IC,
Coordination of the Open House event,
Facility and AV for the Open House event,
Personnel and equipment for FWD/GPR testing,
Arrangement for personnel and equipment for coring,
Personnel and equipment for bulk density tests for cores.
Paving Contractor
Personnel to be trained on IC,
Two IC roller operators,
Mobilization of IC rollers onsite,
One density gauge and an operator,
Arrangement for personnel and equipment for coring,
Fuel for IC rollers.
Roller Vendors
IC Training (esp. IC operation, data collection and transfer),
Technical support during field demo,
Presentation during Open House.
3
GPS Vendor
GPS base station, rover and an operator,
GPS training,
Technical support during field demo,
Presentation during Open House.
LWD-a Vendor
Personnel and equipment for LWD tests.
Site Map
This project is a night-time paving job located at I-80 in Solano County, CA, from MP 30.6 to MP 38.7.
Pavement layers
o 3” intermediate asphalt mixture at paving 12 ft wide
4
Onsite Safety
Contact Chris Barkley, Teichert Construction, for any onsite visits.
DOT and Contractor require all onsite participants to observe safety rules:
o Ingress and egress to and from the work zone, vehicles shall be equipped with yellow flashing lights.
o Location to park vehicles.
o Location for people to safely observe operations.
o Adequate PPE provided for all personnel within the work zone. (hard hats, safety vests, working gloves, safety glasses, steel toed boots, etc.)
o Suggest carpool to the job site.
5
On-site Activities
Schedule Activities Night 1 Wednesday (Sept 4)
Conduct IC rollers/GPS setup and trial runs (equipment vendors and FHWA IC team only) at the staging area. (3PM-5PM)
Conduct project briefing at the staging area and IC training for roller operators (7PM-8PM).
Start paving with one IC roller at breakdown and another IC roller at intermediate position.
Select a 500-ft section as a test strip to establish the rolling pattern. Conduct NG/GPS/LWD-a testing immediately behind the paver and at selected locations after each breakdown and intermediate roller pass within the test strip.
Perform production compaction using the rolling pattern. Conduct NG/GPS/LWD-a at selected locations after the finishing
rolling Night 2 Thursday (Sept 5)
Set up the GPS base station and IC roller/GPS system (by 7PM). Start paving with one IC roller at breakdown and another IC roller at
intermediate position. Conduct NG/GPS/LWD-a testing immediately behind the paver and at
selected locations after each breakdown roller pass within the 1500-ft section.
Conduct NG/GPS/LWD-a testing at selected locations after each intermediate roller pass within the 1500-ft section.
After the finishing rolling, mark 60 locations within the 1500-ft paved section. Conduct NG/GPS tests at marked locations. Conduct GPR within the test section. Conduct FWD and LWD-a tests at designated locations. Conduct coring at the marked locations.
Days 3 Friday (Sept 6 PM)
Conduct the Open House event including presentation and equipment demonstration.
GPS: A base station and a rover will be provided by Sitech West. NG: Nuclear density gauge and an operator will be provided by Teichert Construction. LWD-a: Lightweight deflectometer for asphalt tests will be provided by Kessler. FWD: Falling weight deflectometer tests conducted by Caltrans. GPR: Ground penetrating radar conducted by Caltrans research contractor. Coring: 60 X 4” cores will be taken by Teichert via a contract change order. Core tests: Bulk density testing of cores will be performed by Caltrans District 4 lab.
6
Test Settings
Date TB MachineSetting Spot Tests Notes/Comments
Night 1
1A IC 1
Low amp at 3000 or 4000 vpm
NG, GPS, LWD-a
Breakdown compaction for asphalt base course. 1. Compact with normal roller passes. 2. NG/GPS/LWD-a tests after each roller pass at selected locations within the test section.
1B
IC 2
Low amp at 3000 or 4000 vpm
NG, GPS, LWD-a
Intermediate compaction for asphalt base course. 1. Compact with normal roller passes. 2. NG/GPS/LWD-a tests after each roller pass at selected locations within the test section.
1C IC 3
Static
NA Finishing rolling 1. Compact with normal roller passes. 2. NG/GPS/LWD-a tests after each roller pass at selected locations within the test section.
Night 2
2A IC 1
Low amp at 3000 or 4000 vpm
NG, GPS, LWD-a
Breakdown compaction for asphalt base course. 1. Compact with normal roller passes. 2. NG/GPS LWD-a tests after each roller pass at selected locations within the test section.
2B IC 2
Low amp at 3000/4000 vpm
NG, GPS, LWD-a
Intermediate compaction for asphalt base course. 1. Compact with normal roller passes. 2. NG/GPS LWD-a tests after each roller pass at selected locations within the test section.
2C IC 3
Static
NG, GPS, LWD-a, FWD, GPR Coring
Finishing rolling 1. Compact with normal roller passes. 2. NG/GPS/LWD-a tests after each roller pass at selected locations within the test section. 3. NG/GPS/LWD-a/FWD/GPR/Coring tests after the finishing rolling at the marked locations within the test section.
*. The rolling pattern will be designated by Teichert Construction.
7
Night 1 – Test Section
NG, LWD-a(after each pass) and GPS
paving width
500
ft
paving width
Roller 1IC Compaction(breakdown)
Roller 2IC Compaction(intermediate)
paving width
Roller 3Compaction(finishing)
8
Night 2 – Test Section
1500
ft
paving width
Roller 2IC Compaction(breakdown)
NG, LWD-a(after each pass) and GPS
paving width
Roller 1IC Compaction(intermediate)
paving width
50 ft spacing
NG, GPS, Coring
LWD-a, FWD
Roller 3Compaction(finishing)
9
Bomag Double Drum IC rollers
Manufacturer/ Vendor
Bomag
Model VarioControl Model Number BW 278AD-4 Drum Size 78’’ (front) and 48” (rear) dia. x 78” wide Machine Weight 23,900 lbs. (~ 10.84 tons) Amplitude Settings 0.019’’ (low) and 0.029’’(high) Frequency Setting/ Range
4,000 (high) 3,400 (low) vpm
Auto-Feedback Yes Measurement System Evib with temperatures and passes mapping Measurement Value Evib Measurement Unit MN/m2 GPS Capability Yes Documentation System BCM 05 Office and Mobile
10
HAMM Double-Drum IC Roller
Manufacturer/ Vendor
HAMM/Wirtgen
Model Name HCQ (Hamm Compaction Quality) Model Number HD+ 90 / HD+ 110, HD+ 120 / HD+ 140 Drum Width 78" w/offset to 84.7" Machine Weight Operating wt. 27,569 lbs. w/max of 32,187 lbs. Amplitude Settings High/Low - .028/.011 in. (0.71/0.27 mm) Frequency Settings Variable from 2700 - 4020 vpm Auto-Feedback NA Measurement System HAMM Compaction Quality (HCQ) Measurement Value HMV, density estimator, temperature, passes Measurement Unit [unitless, % compaction, °C, color coded] Documentation System
HCQ with ability to export to Veda
Contact Tim Kowalski (615) 594-4604 [email protected]
11
Caterpillar Double-Drum IC Roller
Manufacturer Caterpillar Model Name Tandem vibratory roller Model Number CD54B split drum Drum Width 67" (1700 mm) Machine Weight Operating wt. 22,311 lbs.
Static linear load 165 lb/in. Amplitude Settings 0.024 – 0.013” Frequency Settings 2,520 and 3,200 vpm Auto-Feedback NA Measurement System Compaction Meter Value (CMV) Measurement Value CMV Measurement Unit [unitless] Documentation System
VisionLink
Contact Bryan Downing, 763-493-7533 [email protected]
12
Global Positioning System (GPS)
Grid Reference
UTM-10N is the preferred coordinate reference for all devices.
Trimble GPS
A Trimble GPS receiver and a radio will be mounted on the Bomag IC machine.
A Trimble GPS receiver and a radio will be mounted on the Caterpillar IC machine.
A Trimble GPS base station will be setup to provide RTK correction signals.
A hand-held Trimble GPS rover will be used for in-situ point measurements.
OmniStar GPS
A GPS receiver with OmniStar subscription will be mounted on the HAMM IC machine.
13
Open House
Time: 1:00 PM to 5PM, Friday, Sept 6, 2013
Location: Translab Auditorium
5900 Folsom Boulevard, Sacramento, CA 95819
Contact: Ebi Fini, Caltrans, (916) 227-5396, [email protected]
Agenda
o Session 1 - 1:00PM to 4:30AM - Indoor Presentation
o Session 2 - 4:30PM to 5PM – Outdoor Equipment Demonstration (LWD-a, GPS)
Online Registration is required: