Page 1: California DR Integration Projects: San Diego and Marin County

California DR Integration Projects:

San Diego and Marin County

Frances ClevelandXanthus Consulting Internationalg

Xanthus Consulting International

Page 2: California DR Integration Projects: San Diego and Marin County

Topics

• Background on DOE and CEC Distributed Energy Resources and Renewable Programsg

• San Diego Gas & Electric (SDG&E) Microgrid Project

• Marin County Sustainable Community Project with Infotility y y j yGridAgents

Xanthus Consulting International December 10, 20082

Page 3: California DR Integration Projects: San Diego and Marin County

(US) Department of Energy (DOE): Renewable and Distributed Systems Integration (RDSI) Programy g ( ) g

• DOE’s Office of Electricity Delivery and Energy Reliability

R bl d Di t ib t d S t I t ti (RDSI)• Renewable and Distributed Systems Integration (RDSI)RDSI focuses on integrating renewable energy, distributed generation, energy storage, thermally activated technologies and demand response into the electrictechnologies, and demand response into the electric distribution and transmission system.

• This integration is aimed toward managing peak loads, g g g p ,offering new value-added services such as differentiated power quality to meet individual user needs, and enhancing asset use.

• The program goal is to demonstrate a 20% reduction in peak load demand by 2015, through increased use of both utility and customer owned assets

Xanthus Consulting International December 10, 20083

utility- and customer-owned assets.

Page 4: California DR Integration Projects: San Diego and Marin County

California Energy Commission (CEC) and its Public Interest Energy Research (PIER) gy ( )• California Energy Commission (CEC) was formed in 1974 with the

mission to assess, advocate and act through public/private t hi t i t th t t tpartnerships to improve energy systems that promote a strong

economy and a healthy environment. • The California State Legislature created the Public Interest

Energy Research (PIER) Program in 1996 during California'sEnergy Research (PIER) Program in 1996 during California s utility restructuring legislation.

• This law requires that $62.5 million be collected annually from the three investor-owned electric utilities for energy-related researchthree investor owned electric utilities for energy related research, development and demonstration (RD&D) efforts not adequately provided by competitive and regulated markets.

• In doing so, administration of public interest RD&D was shifted g , pfrom California's investor-owned utilities to state government, a major change intended to ensure an appropriate role for public interest energy research in a newly competitive energy marketplace

Xanthus Consulting International December 10, 20084

marketplace.

Page 5: California DR Integration Projects: San Diego and Marin County

CEC Public Interest Goals for a Sustainable Communityy

• Integrate utility and customer-based energy resources, including carbon and non-carbon-based energy sources g gy

• Enhance the management of intermittent renewable resources, including the impact of resources from sustainable communitiessustainable communities

• Identify and evaluate the key technical and operational issues with designing, implementing, and managing an g g, p g, g gintegrated energy portfolio of utility and non-utility interconnected resources

• Improve power reliability and quality via utility asset• Improve power reliability and quality via utility asset optimization

Xanthus Consulting International December 10, 20085

Page 6: California DR Integration Projects: San Diego and Marin County

California and Renewable Energy

• On November 17, 2008, Governor Arnold Schwarzenegger signed Executive Order # S-14-08 that raises California's renewable energy goals to 33 percent by 2020 and clears red tape for licensing renewable projects.

• The Executive Order will advance California's transition into a clean energy economy and directs state agencies to create comprehensive plans to prioritize regional renewable projects based on an area's renewable resource potential and the level of

t ti f l t d i l h bit tprotection for plant and animal habitat.

• In 2007, 11.8 percent of all electricity came from renewable resources such as wind, solar, geothermal, biomass and small hydroelectric facilities. Large hydro plants generated another 11.7 percent of our electricity.

Xanthus Consulting International December 10, 20086

Page 7: California DR Integration Projects: San Diego and Marin County

Xanthus Consulting International December 10, 20087

Page 8: California DR Integration Projects: San Diego and Marin County

Xanthus Consulting International December 10, 20088

Page 9: California DR Integration Projects: San Diego and Marin County

SDG&E Beach Cities Microgrid Project

Jointly funded by the Department ofXanthus

Consulting International

Jointly funded by the Department of Energy (DOE) and the California

Energy Commission (CEC)

Page 10: California DR Integration Projects: San Diego and Marin County

SDG&E Beach Cities Microgrid Project Objectives• Achieve > 15% reduction in feeder peak loadAchieve 15% reduction in feeder peak load• Demonstrate capability of Volt-Amps-Reactive (VAr) management • Develop a strategy and demonstration of information integration focused on

both security and overall system architecture:both security and overall system architecture:– Integrate Advanced Metering Infrastructure (AMI) into Microgrid

operations;– Develop self healing networks through the integration of Feeder

Automation System Technologies (FAST)Automation System Technologies (FAST) – Integrate an Outage Management System (OMS) and a Distribution

Management System (DMS) into Microgrid operations• Develop Information requirements and appropriate tools to assess theDevelop Information requirements and appropriate tools to assess the

impact of multiple DER technologies– control algorithms for autonomous DER operations/automation that

address multiple DER interactions and stability issuescoordination and interoperability of multiple DER technologies with– coordination and interoperability of multiple DER technologies with multiple applications/customers.

• Use automated distribution control to intentionally island customers in response to system problems

Xanthus Consulting International December 10, 200810

p y p• Demonstrate Programmable and Controllable Thermostats (PCT) to

achieve Demand Response goals within the smart grid.

Page 11: California DR Integration Projects: San Diego and Marin County

Benefits

• Allow more power to be delivered through existing infrastructure and reduce the need to build more in the future

• Increase in the reliability and security of the grid by adding elements that make the grid more stable andelements that make the grid more stable and reconfigurable.

• Allow Utility to utilize and control customer-owned resourcesy

• Optimize the design of circuit operations for microgrid capabilities given consumer DG, demand response, automated response and other advanced toolsautomated response, and other advanced tools

Xanthus Consulting International December 10, 200811

Page 12: California DR Integration Projects: San Diego and Marin County

Project Strategies

• Design and demonstrate a smart electrical grid that incorporates sophisticated sensors, communications, and controls in the following ways:– Intelligently incorporate solar power generators on homes and

businesses into the electrical delivery system.– Enable coordinated Demand Response (DR) programs

whereby heavy electrical use during peak demand periods can be moderated to prevent electrical supply emergencies.

– Integrate and control multiple distributed generation and electrical energy storage devices to operate the grid in a more cost-effective and reliable manner, benefiting customers and electrical rateselectrical rates.

• This project will proactively identify and apply leading-edge technologies to improve the security and reliability of electricity

l d t l t t

Xanthus Consulting International December 10, 200812

supply and to lower costs to consumers.

Page 13: California DR Integration Projects: San Diego and Marin County

SDG&E Smart Meter Technology Selection

• SDG&E has selected Itron’s OpenWay technology for its AMI technology solution

OpenWay Implementation Scope:• Electric Meters• Gas Modules• Network Devices (Cell Relays)• Head-End Collection Engine

* Itron Enterprise Edition (IEE)MDMS also being implemented

Xanthus Consulting International December 10, 200813

Page 14: California DR Integration Projects: San Diego and Marin County

Tasks for Beach Cities Microgrid Project

Just started in late 2008

• FAST: Feeder Automation System Technologygy

• OMS: Outage Management System

• PDLM: Price-DrivenPDLM: Price Driven Load Management

• DSI: Distributed Systems Integration Testing

Xanthus Consulting International December 10, 200814

g

Page 15: California DR Integration Projects: San Diego and Marin County

Participants in Project

• SDG&E (PM, facilities, customers, AMI, implementation)

H i E G ( j t di ti d i t ti )• Horizon Energy Group (project coordination, design, testing)

• Pacific Northwest National Labs (DER design)

U i it f S Di ( l t d i )• University of San Diego (regulatory design)

• Advanced Control Systems (software, modeling)

M t l ( i ti it )• Motorola (communications, security)

• Lockheed Martin (system architecture, facilities)

IBM (DER automation security)• IBM (DER automation, security)

• Xanthus (protocol standards, security, integration)

Xanthus Consulting International December 10, 200815

Page 16: California DR Integration Projects: San Diego and Marin County

Marin County Sustainable CommunityMarin County Sustainable Community Project

Xanthus Consulting International

Page 17: California DR Integration Projects: San Diego and Marin County

Marin County Sustainable Community• US Department of Energy

funding: – Three year –three phase Marin County

project schedule and scope with $1.6 Million budget for 2008-2010.Collaboration and cost share– Collaboration and cost share with ECN –Netherlands for EU field testing and technology transfer.

• California Energy Commission (CEC) funding – incremental work focusing on integration and communications standards using IEC 61850.

• Contractors: Infotility, Inc. and

Xanthus Consulting International December 10, 200817

Xanthus Consulting International

Page 18: California DR Integration Projects: San Diego and Marin County

Marin County Sustainable Community – Using Infotility Grid Agents to Monitor Photovoltaic Systems, Control Load and Bid into the Electricity MarketLoad, and Bid into the Electricity Market

• Infotility is providing “Grid Agents” which collect information from municipal PV and other distributed pgeneration

• Grid Agents then use that information to develop market strategies

• Collaborating with the Marin County Sustainability Office on using the Civic Center Campus, and near-by municipal facilities for early stage u c pa ac es o ea y s agedemonstrations.– PV already installed– Access to EMS systems with

biliti t b d G id A tcapabilities to embed Grid Agent intelligence.

– Potential load control of lights and HVAC

Xanthus Consulting International December 10, 200818

– PG&E also receiving monitored data

Page 19: California DR Integration Projects: San Diego and Marin County

Marin County Solar Potential Map

Xanthus Consulting International December 10, 200819

Page 20: California DR Integration Projects: San Diego and Marin County

Marin County – Public Electric Solar Sites• Existing 6.4 MW g

Solar Energy

• Potential for significantly more

Xanthus Consulting International December 10, 200820

Page 21: California DR Integration Projects: San Diego and Marin County

Infotility’s Grid Agents in Marin County

Xanthus Consulting International December 10, 200821

Page 22: California DR Integration Projects: San Diego and Marin County

Overview of IEC 61850-7-420: Logical Devices and Logical Nodes for Distributed Energy Resource (DER) Systems

Recip Engine

DCRP, DOPA, DOPR, DOPM,DPST, DCCT, DSCC, CSWI,

XCBR, MMXUDCIP

DER Plant ElectricalConnection Point (ECP)

DRCT, FSEQ, MMXU

DER Unit Controller

ECP

ECPFuel Cell

PhotovoltaicsCombined Heat Power

DER

CSWIXCBR

MMM

MMM

DGEN,DRAT,DRAZ,DCST CSWI

XCBRMITV

DREX,DEXC

,

MITVYRCT,YINV,MMDC

ConverterDC ConverterRSYNGenerator

EnergyConverter

DFCL, DSTK, DFPMDPVM, DPVA, DPVC, DTRCDCHC, DCHI, DCHX, DCHS

ECP

CircuitBreaker

DER Protective

Utility GridUtilityCircuit

Breaker

Electric PowerSystem

UtilityCircuit

Breaker

MMM

GenerationGeneration

PCDLPBROPBTCPTUFMMXU

SyncGenerator

UnitStorageDevice

ExciterDFUL, DFLV

FuelSystem

DBAT, DBTCBatteryS t DER Protective

Relaying

Load CircuitBreaker(s) Local Loads

GenerationProtectionGenerationProtection

PTUFPTOF…

CSWI

Power SystemMeasurements

System

Physical Measurements

Temperature

MTMP

Pressure

MPRS

Heat

MHET

StationServiceStationService

MMM

MITV

XCBR

New Logical NodesE i ti L i l N d

Flow

MFLW

Vibration

MVBR

Emission

MENV

Meteorological

MMET

Xanthus Consulting International December 10, 200822Energy Converter = Microturbines,Fuel Cell, Photovoltaic System, Windturbines, Diesel Generators,Combustion Turbines

Storage Device = Battery, PumpedHydro, Superconducting MagneticEnergy Storage, Flywheels, Micro -flywheels

Converter = DC to AC,frequency conversion, voltagelevel conversion

Auxiliaries = Battery, Fuel Cell

Logical DeviceLogical Device

Existing Logical Nodes

Page 23: California DR Integration Projects: San Diego and Marin County

Marin Community ConfigurationGridAgent

HostIEC 61850-7-420 Between Systems

PG&E CAISOHostBetween Systems

Xanthus Consulting International December 10, 200823

Eventually: IEC 61850-7-420 Inside PV Inverter

Page 24: California DR Integration Projects: San Diego and Marin County

Q ti ?Questions?

Xanthus Consulting International