PROGRAM OVERVIEW
2016
ECORESTORE ORIGINS
• April 2015 – Governor Announces EcoRestore along with California Water Fix
• EcoRestore implements parts of the California Water Action Plan
• Short term – 3 years to jumpstart restoration projects • California Department of Fish and Wildlife working on
a longer term program
6/20/2016
CALIFORNIA ECORESTORE
• RESTORATION PROJECTS: Program will accelerate the implementation of a comprehensive suite of habitat restoration actions in the Sacramento – San Joaquin Delta and Suisun Marsh MONITORING AND ADAPTIVE MANAGEMENT: Development of a landscape Adaptive Management process to maximize effectiveness of restoration projects. PLANNING: Delta Conservancy will develop restoration plans for sub-regions of the Delta
•
•
6/20/2016
RESTORATION PROJECTS
6/20/2016
ADDITIONAL PROJECTS
• Fish passage in the Yolo Bypass – Block off Colusa Basin Drain – Agricultural Crossings – Fremont Weir Fish Ladder
• Shaded Riparian Habitat – Measured in lineal feet of habitat
6/20/2016
6/20/2016
RESTORATION PROJECTS BREAKING GROUND IN 2016
6/20/2016
• Anticipated Construction Starts in 2016: • Wallace Weir • Hill Slough • McCormick Williamson Tract • Dutch Slough • Tule Red
HABITAT RESTORATION TARGETS & PLANNED PROGRESS THROUGH 2017
Planned In Permitting In Construction Completed EcoRestore Goals (total acres)
0Shaded Aquatic (linear
feet)
5,000
10,000
15,000
20,000
25,000
30,000
35,000
40,000
0
1
2
3
4
5
6
Fish Passage (# ofprojects)
3,500
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
20000
Floodplain Restoration (acres) Tidal & Sub-Tidal (acres) Emergent Wetland (acres) Aquatic, Riparian and Upland(acres)
17,500
1,000
9,000
RESTORATION CHALLENGES
• Complexity of regulatory permitting • Habitat/species trade-offs • State contracting and procurement • Funding of non-Biological Opinion projects • Incorporation of science
6/20/2016
ADAPTIVE MANAGEMENT
• Delta Independent Science Board recommends an Adaptive Management program for the Delta
• How well do habitat projects improve the environment? • Adaptive Management Cycle: Monitoring – Synthesis –
Decisions – Monitoring – etc. • Many well established monitoring programs exist • EcoRestore Adaptive Management is only for Ecosystem
Restoration projects in the Delta and Suisun Marsh
6/20/2016
6/20/2016
ADAPTIVE MANAGEMENT
• Need to Develop Institutional and Financial Structure for Ecosystem Adaptive Management
• Formation of Steering Committee and Technical Committee (IAMIT)
• Recommendation on Adaptive Management Program in 9 months from IAMIT
• Steering Committee to recommend structure and financing
6/20/2016
RESTORATION PROJECT PLANNING
• Delta Conservancy assigned to develop restoration plans for regions of the Delta
• Suisun Marsh Habitat, Management, Preservation and Restoration Plan already exists
• North East Delta Pilot Project • Cache Slough Complex • Other regions later • Medium and long term planning – current projects to be
implemented
6/20/2016
STAY INVOLVED
6/20/2016
http://resources.ca.gov/ecorestore/
@CAEcoRestore