P a g e | 1
Capital Expenditure Report (CER) for Renovation of Redwood Hall Housing
complexTeam: JD-DOC
Deanna (Project Manager)Chuks – Scheduler/Control Engineer
Joy - PlanningChintan – R&D
Dhavalkumar – R&DBeverly - Financials
P a g e | 2
CONTENTS
PURPOSE STATEMENT........................................................................................................................................................................5
EXECUTIVE SUMMARY......................................................................................................................................................................5
Introduction:.........................................................................................................................................................................................5
Proposed Solution:............................................................................................................................................................................... 6
Market Analysis:......................................................................................................................................................................................6
Alternatives:.........................................................................................................................................................................................9
DETAILED AREA DESCRIPTION........................................................................................................................................................9
Current Layout Plan:............................................................................................................................................................................9
Proposed Layout Plan:......................................................................................................................................................................... 9
WORK BREAKDOWN STRUCTURE & GANTT CHART................................................................................................................11
PROJECT BUDGET ESTIMATION.....................................................................................................................................................13
The individual cost breakdown for each type of cost is given below:.................................................................................................14
COST BREAKDOWN...........................................................................................................................................................................19
SOURCES OF FUNDS..........................................................................................................................................................................20
CAPITAL BUDGETING.......................................................................................................................................................................21
RETURN ON INVESTMENT...............................................................................................................................................................22
Sources of Revenue............................................................................................................................................................................22
Project Considerations:...................................................................................................................................................................... 22
Housing Fees:.....................................................................................................................................................................................22
Amenities Fees:..................................................................................................................................................................................22
Equipment and maintenance fees.......................................................................................................................................................22
Total Revenue Generated from Housing Complex Over a Period of 10 years........................................................................................23
RISK & MITIGATION PLANS............................................................................................................................................................25
APPENDIX A........................................................................................................................................................................................26
Survey Questions............................................................................................................................................................................... 26
APPENDIX B........................................................................................................................................................................................ 27
Complete Work Breakdown Structure with task and sub task............................................................................................................27
APPENDIX C........................................................................................................................................................................................ 31
Projected revenue from Ameneties for 10 years.................................................................................................................................31
P a g e | 3
NJIT – HOUSING DEPARTMENT CAPITAL EXPENDITURE REQUEST
Date: 10/04/2016
Project Name: Redwood Hall Dormitory Renovation
Project Proposer: Team JD-DOC
Project Sponsor: NJIT
Physical Location of Asset: On-Campus
Executive Summary:
This documents contains the details for Capital Expenditure Request for the Renovation of NJIT Redwood Hall Dormitory Floors. The total estimated cost of the project is $36,493,197.00.
Note: Document is deemed confidential and is intended for official purposes only.
Nature of Expenditure include put is not limited to:
Equipment Replacement.
Increased Capacity.
Strategic Investment.
New Services.
Enhancement of Existing Service.
Health & Safety.
Project Financials Estimate:
NPV: $9M
Payback Period: 25 Years
Useful Project Life: Approx. 45 Years
Total Project Capital Spending Estimate:
Disposal Spending Estimate:
Equipment Spending Estimate:
Approvals and Signatures
Project Team/Owner: TEAM JD-DOC
Director (up to $25k):
Controller/Treasurer
CEO (>$25K)
Approval Date: 04/10/2016
P a g e | 4
PURPOSE STATEMENT
The purpose of this Capital Expenditure Request (CER) is to request funding approval in the amount of $35,500,000 for the Renovation of Redwood Hall Dormitory and the details of the project are described within this document.
EXECUTIVE SUMMARY
INTRODUCTION:
Redwood Hall Dormitory Center is one of the oldest housing constructions at the New Jersey institute of technology on-campus structures. The hall was first constructed in 1978 followed by Cypress, Oak and Laurel halls.
Redwood hall is currently home to 200 NJIT students this five floor building houses a mail room on the ground floor, a TV lounge, a study lounge, fully functioning staff office and a TV lounge. This main floor amenity currently serves as the only social floor of the whole building.
The other 4 floors are approximately constructed in a similar manner all have a publicly shared male bathroom to the right middle corner of each floors and publicly shared female bathroom to the left middle corner of each floor.
There currently exists a very basic standard rooming set up of a Length 19'-0" Width 12'-0"Ceiling Height 8'-0" rooms. Including two standalone beds a unidirectional window and an individual desk and chair setup.
Other facilities that are currently available in the redwood hall housing center includes A/C &heating systems on al floors an Ethernet cable connected to each room, a telephone jack, Cable TV HBO-included and a Laundry facility.
However, being one of the oldest yet standing structures at NJIT, housing 200 of it campus student, hosting a fully loaded staff environment bolstering safety and standard quality, there yet seems to be lacking a lot of modern structure and disciple in the redwood hall layout.
There’s currently no improvements being made to improve the housing situation at the redwood hall dorms and as of the completion of the expenditure report and a satisfaction survey taken in the process the redwood hall dorms remain the least satisfactory location for on-campus housing at the New Jersey institute of technology campus.
Existing Situation: Even though this Dorm looks slightly attractive in the process of building our satisfactory survey we have discovered main flaws and areas of improvements:
The building size is currently being underused as most housing constructions of equal size and space can house an increasing amount of people in the 300 – 500 range.
Currently students are forced to take showers in a less private manner than should be the case as bathrooms are designed to be public raising major sanitary issues.
The whole five floor housing complex consist of only one elevator traveling up and down through floors amassing foot traffic and unnecessary delays when maintenance is required.
Individual room spacing makes for awkward interactions and cramping of individual student amenities such as cloths, provisions etc.
The size of room makes it hard to host a guest. The room size and unilateral window placement encourages extreme weather conditions at any given time. Air
circulation is limited. There are no gym’s or recreational rooms in the redwood hall buildings. Finally, the Building is 38 years old and needs major structure and technological improvements.
P a g e | 5
PROPOSED SOLUTION:
We are proposing the renovation of the Redwood Hall building, which would solve all the above mentioned problems. This renovation would also be in accordance to the master plan that NJIT has for the coming 5 years. Some of the other reasons for proposing the reconstruction are:
The structure currently lacks in student satisfaction given the survey taken. Improving the room size and allocation would help increase the overall housing population at redwood from 200 to
over 300 students. A full size gym structure in the main floor with low monthly membership and a trainer would improve the social
location. Addition of a games and recreational room will also bolster housing interaction and social space. As per popular demand an addition of a laundry room on each floor. Also doubling the number of elevator from one to two to improve foot traffic and annul and delays in mobility when
the need for repairs arise. Addition of individual bathrooms and toilets to each room is also proposed to improve privacy and sanitary issues. The increase in the size of each individual rooms would foster spacing for students clothing and amenities with
cramping. The inclusion of multi-directional windows would also improve air circulation. Overhead heating and cooling systems would also help solve the problem of extreme heating and cooling conditions
in rooms.
MARKET ANALYSIS:
The main audience that we are trying to reach through this project is the NJIT students. So in order to understand the actual needs of the NJIT students and what they thought about our proposal, we created a survey and sent the survey link to as many as students as we could reach out. The question that were asked in the survey are attached in Appendix A.
We got 50 responses for our survey in 7 days and the results of the survey are as follows:
Male
Female
0 5 10 15 20 25
SURVEY NUMBERS
P a g e | 6
Graduate
Undergrad
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
CURRENT STATUS
Gym
Game room
Laundary on each floor
New Elevators Unsatisfied
Individual Bathrooms
Larger rooms
Improved Vents
Kitchen in rooms
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Additonal Facil ities
Very Satisfied
Moderately Satisfied
Unsatisfied
Extremely Unsatisfied
0% 10% 20% 30% 40% 50% 60% 70%
Satisfactory Survey
P a g e | 7
Neutral
No
Yes
0% 10% 20% 30% 40% 50% 60% 70%
Need for Individual Bathrooms
Neutral
No
Yes
0% 5% 10% 15% 20% 25% 30% 35% 40% 45% 50%
Need for Additional Elevator
Neutral
No
Yes
0% 10% 20% 30% 40% 50% 60% 70% 80%
Increased on-campus involvement with better housing
P a g e | 8
ALTERNATIVES:
Some of the alternatives pertaining to this project include:
Ignore student un-satisfaction and the opportunity to expand to realistic capacity the number of students hence revenue and continue to use Redwood hall as it is.
Reconstruct redwood hall by completely breaking down and rebuilding a new structure with a proposed budget of $143,325,500.
DETAILED AREA DESCRIPTION
CURRENT LAYOUT PLAN:
Currently Redwood hall has five floors. There is one elevator and two staircases located at either side of the building.
Ground Floor: Consist mainly of study lounge, a kitchen, lobby, front desk and staff office
Housing Floors (2-5): All consist of the same set-up walking in from the elevator you see a corridor that stretches all the way through to the end of the hall. On either side of the corridor to the left and to the right are rooms walking down the corridor approximately to the middle of the room are the female and male public bathrooms.
PROPOSED LAYOUT PLAN:
We are convinced that the overall layout and the space of the building can be better utilized. Since we are proposing an increase in number of students that can occupy the building, an additional elevator is added as compared to current layout to avoid overload. Each floor has well equipped rest rooms for men and women and bunk beds would come in each room. The detail descriptions of the floor plans are as follows:
Ground Floor: This floor is strictly the main lobby of the housing complex which would include the housing staff rooms and fully functional gym and recreational center and a TV room/game room. This floor would not contain any housing rooms, laundry or a kitchen.
P a g e | 9
Housing Floors: These floors would include a combination of eight four-bedroom living compartments each room housing a bunk bed to give the floor a total of sixty-four students per floor and a total of 256 students occupied in the Redwood hall building. With elevators on either side of the halls and an extension of a mini laundry room containing a washer and drier of each four floors.
WORK BREAKDOWN STRUCTURE & GANTT CHART
P a g e | 10
The renovation of the Redwood hall housing center would take 365 days to complete. We would like to start the project on April 25th, 2016 and therefore the project would be completed as of September 15nd 2017. We have taken into consideration a six-day work week with Sunday being off. We have also to add a couple contingency days in our schedule due to the unpredictable weather changes, changes or out sourcing complications.
We would like to have the Grand opening of the new Redwood Hall housing in the first week of 2017 FALL semester session.
Below is a complete WBS (Work Breakdown Structure) as well as Gantt Chart for the purposed project timeline and completion:
A more detailed work breakdown structure with all the tasks and sub tasks can be found in APPENDIX B.
Task Mode Task Name Duration Start Finish PredecessorsAuto Scheduled
Redwood Hall Construction 365 days Mon 4/25/16 Fri 9/15/17
Auto Scheduled Planning 16 days Mon 4/25/16 Mon 5/16/16
Auto Scheduled Bids and Contractors 25 days Tue 5/17/16 Mon 6/20/16 2
Auto Scheduled
Approval of reconstruction permit 20 days Tue 6/21/16 Mon 7/18/16 9
Auto Scheduled
Permit Approval process 19 days Tue 7/19/16 Fri 8/12/16 14
Auto Scheduled Pre-Site Preparation 55 days Mon 8/15/16 Fri 10/28/16 14,9,2
Auto Scheduled Construction 57 days Mon 10/31/16 Tue 1/17/17 22,14,19,9
Auto Scheduled
Overall Building Recalibration 22 days Wed 1/18/17 Thu 2/16/17 29,22,19
Auto Scheduled Structural Analysis 24 days Fri 2/17/17 Wed 3/22/17 38,29,22,19
Auto Scheduled
Power and Cable Installation 19 days Thu 3/23/17 Tue 4/18/17 29,22,19
Auto Scheduled
Sewage and Water pipe Installation 17 days Wed 4/19/17 Thu 5/11/17 29,22,19
Auto Scheduled Heating Installation 22 days Fri 5/12/17 Mon 6/12/17 50,29,22,19
Auto Scheduled Interior Design Layout 38 days Tue 6/13/17 Thu 8/3/17 59,54,50,44,38,29,22,19
Auto Scheduled Project Finalization 31 days Fri 8/4/17 Fri 9/15/17 64,59,54,50,44,38,29,22,19,14,9
Manually Scheduled Finish
PROJECT BUDGET ESTIMATION
P a g e | 11
Capital Estimate
Type of Cost Total Cost ($)
Demolishing Cost $1,642,000.00
Disposal Cost $ 1,324,000.00
Construction Cost $25,350,000.00
Equipment Cost $1,153,467.00
Total $29,469,467.00
Total Budget
Type of Cost Total Cost ($)
Capital $29,469,467
Expense for 45 yrs. $7,023,730
Total $36,493,197.00
Expenses over a 45 year period
Type % of the
Capital costsTotal Expense for 30
years Annual Expense
Building Repairs 25% $2,426,180 $124,206
Mechanical (HVAC, Plumbing, FireProtection) 12% $558,800 $145,960
Electrical (Service and Distribution, Lighting, Power, etc) 5% $507,580 $50,586
Interior Decoration 15% $125,750 $15,325
Depreciation* $3,552,017 $201,734
Insurance $250,000 $55,000
Total $7,023,730 $656,082
*Straight Line Depreciation is being considered and the salvage value of the Equipment at the end of 30 yrs. is 0.
THE INDIVIDUAL COST BREAKDOWN FOR EACH TYPE OF COST IS GIVEN BELOW:
P a g e | 12
Demolishing Cost
Level Cost per Cu.
Ft Total Cu. Ft per Floor Cost
First Floor $2.00 173,000 $346,000.00
Second Floor $2.00 162,000 $324,000.00
Third Floor $2.00 162,000 $324,000.00
Fourth Floor $2.00 162,000 $324,000.00
Fifth Floor $2.00 162,000 $324,000.00
Total $1,642,000.00
Disposal Cost (20% of Cu. Ft to develop Cu. Yard)
Level
Cost per Cu. Yard
20%Cu. Ft per
Floor Cost
First Floor $5.00 30,800 $154,000.00
Second Floor $5.00 25,400 $127,000.00
Third Floor $5.00 25,400 $127,000.00
Fourth Floor $5.00 25,400 $127,000.00
Fifth Floor $5.00 25,400 $127,000.00
Total $662,000.00
Construction Cost Break Down
Description % of Total Cost per SF Total
P a g e | 13
Construction Cost
Construction Cost $190 $25,550,000
Structural Cost 30% $7,665,000
Contractor Fees (GC, Overhead, Profit) 5% $1,277,500
Engineering Cost 10% $2,555,000
Mechanical (HVAC, Plumbing, FireProtection) 15% $3,832,500
Electrical (Service and Distribution, Lighting, Power, etc) 15% $3,832,500
Architectural Fees 9% $2,299,500
Interior Construction 5% $1,277,500
Permits 1% $255,500
Contingency 10% $2,555,000
Total 100% $25,550,000.00
Equipment Cost Estimate
Description No. of Units Unit Cost Total Cost
Sports Equipment
Ping Pong Paddle 6 $150 $900
Ping Pong Balls 6 $40 $240
Ping Pong Tables 4 $650 $2,600
Snooker Pool Tables 4 $1,000 $4,000
Snooker Balls ( 2 SETS) 3 $200 $600
Que Sticks (2 PCs 1 SET) 4 $55 $220
Total $8,560.00
Arcade Games
P a g e | 14
Standard Arcade Games 2 $2,500 $5,000
Car race simulators games 2 $3,250 $6,500
Simulator games 4 $5,000 $20,000
FPS games 4 $5,000 $20,000
WII Nintendo with 6 games 2 $1,250 $2,500
XBOX One with Kinect & games 2 $1,250 $2,500
Total $56,500.00
Gym Equipment
Leg Press 2 $2,350 $4,700
Adductor/Abductor 2 $2,319 $4,638
Leg Extension 2 $2,099 $4,198
Prone Leg Curl 2 $2,925 $5,850
Leg Pull down 2 $2,199 $4,398
Seated Row 2 $2,395 $4,790
Seated Lug Row 2 $1,799 $3,598
Lateral Raise 2 $1,995 $3,990
Triceps Extension 2 $3,021 $6,042
Bicep Curl 2 $1,540 $3,080
Abdominal 2 $3,495 $6,990
Lower Back 2 $3,130 $6,260
Freedom Trainer 1 $5,077 $5,077
Incline Press 2 $3,035 $6,070
Vertical Chest 2 $2,095 $4,190
Super Pullover 1 $2,199 $2,199
Overhead Press 2 $5,399 $10,798
P a g e | 15
Graviton 1 $1,195 $1,195
Xpload Incline Leg Press 2 $1,299 $2,598
Power Squat 2 $1,095 $2,190
Olympic Spine Bench 1 $1,895 $1,895
Adjustable 0 to 90 Bench 2 $1,495 $2,990
Modular Low Row 1 $1,899 $1,899
Modular Cable Crossover 1 $1,595 $1,595
Olympic Incline Press 2 $999 $1,998
Treadmills 6 $5,995 $35,970
Elliptical 6 $3,279 $19,674
Bikes 4 $1,659 $6,636
Stairmaster 4 $4,889 $19,556
Steps 3 $2,995 $8,985
Delivery & Installation Charges $6,500
Total $200,549.00
Electronics
Complete Group Fitness Sound System1 $2,999 $2,999
Television 7 $2,500 $17,500
PC 15 $1,500 $22,500
Access Control, Security, and Surveillance Systems 1 $20,000 $20,000
Projectors 5 $2,200 $11,000
Total $79,828.00
Closets/Dressers
Standard Dresser 256 $250 $64,000
P a g e | 16
Standard Closet 256 $250 $64,000
Total $128,000.00
Washroom / Restrooms
Sinks 96 $280 $26,880.00
Toilets 80 $425 $34,000.00
Urinals 80 $425 $34,000.00
Faucets 80 $480 $38,800.00
Showers 80 $450 $36,000.00
Total $169,280.00
Heating & Cooling System
Air Conditioner & Heater 80 $2,500 $200,000.00
Fans 5 $150 $750
Total $200,750.00
Elevator
Commercial Elevator(Including Installation)
2 $155,000 $310,000.00
Total $310,000.00
Total Cost of Equipment $1,153,467.00
COST BREAKDOWN
P a g e | 17
Construction Cost
Disposal CostEquipment Cost Demolition Cost
Cost breakdown
Structural Cost
Contractor Fees
Engineering Cost
Mechanical Cost
Electrical Cost
Architectural Fees
Interior ConstructionPermits ContingencyConstruction cost breakdown
SOURCES OF FUNDS
P a g e | 18
52%
19%
24%
5%
Initial Project Funding
NJIT allocated Budget Recycling Re-sale of old housing euipment Reallocation of housing cost
The initial project funds needed are divided mainly into 4 categories:
1. NJIT allocated Budget. 2. Recycling.3. Re-sale of old housing equipment.4. Reallocation of Old housing cost for previous semester
The budget NJIT allocated for the renovation project would contribute to 55% of the total capital. The re-sale of the old building equipment via auction services will contribute to 25% of the total capital. The recycling of wood and metal parts mitigates another 20% of the total capital and reallocation of Old housing cost for previous semester contributed the final 5% of the total project capital.
Building Revenue
NJIT Allocated Budget
Corporate Sponsorship
Donations
Future operational funding
The cost in order to operate and maintain the Redwood hall housing would come from the revenue that the building generates, the annual allotted budget for the maintenance of NJIT’s facilities by NJIT students living on campus, the corporate sponsorships and a part of it from the generous donations that NJIT receives on a yearly basis.
P a g e | 19
Every student pays a per semester housing fees, equipment service and maintenance fees, a non-compulsory gym membership fee. Also a low equipment usage fee will be charged for access to the snooker tables, ping pong tables. This percentage allotted to maintenance is close to 20% of the operating costs. Once the redwood housing hall is open there is a decrease in the funds through Corporate Sponsorships to 10%. The new housing hall also gets a part of the donations that NJIT receives annually and this number will be close to about 5% of the operating cost.
CAPITAL BUDGETING
Capital budgeting is a decision making process to select a viable investment project. In simple terms it is a benefit to cost analysis for a project selection. Project Managers are often involved in this process. Some of the capital budgeting techniques used for evaluating this project are as follows:
1. Net Present Value (NPV): This technique suggests calculating the difference between the sum of the present value of the project’s future cash flows and the initial investment. The Net present value rule for the project is to accept a project with a positive NPV.
For our calculations we have only included cash inflows (i.e. revenues) since the cash outflows (i.e. expenses) are very small when compared to the cash inflows. We have considered 10% as our cost of capital. In order to simplify our calculations, we approximated our values of revenues and taking only the revenues up to 7 years.
The cash flow diagram for our project is as follows:
Using the above formula, we have:
NPV = initial investment + Present value of (Future cash flows).
On calculating the present value of future cash flows, we get the value as: $44.00M.
Therefore, NPV = -$35M +$44.00M = $9.00M
NPV for our project is $9.00M >0. So, ACCEPT the project based on the NPV rule.
2. Pay Back Period: This technique tells you the exact length of time required for a corporation or a firm to recover its initial investment. According to our calculation the payback period for our project is: 25 years.
RETURN ON INVESTMENT
SOURCES OF REVENUE
12 M$ 9.6 M$ 9.4 M$ 7.8 M$ 7.4 M$
2 3 4
6 M$
0
1 5 6 7
M6.5$
35 M$
P a g e | 20
Our sources of revenue are Gym membership, Housing Fees, Social center revenue, Amenities Fees, Maintain ace Fees and Laundry Service Fees from the students.
PROJECT CONSIDERATIONS:
1. Project figures of the student enrollment are all based on an increase of attendance in future years.
2. We have analyzed the last 5 years’ data to come up with an average value that will be used for the projections of future figures.
3. We chose to consider just the SPRING and the FALL semesters to represent one academic year as they are the periods in which most students are housed.
4. In attempt to also bolster revenue a portion of equipment maintenance cost are also applied to non-housing students.
HOUSING FEES:
One of our main sources of revenue is the student housing fees that all the students have to pay in other to be housed at the on-campus living facilities (Redwood Hall). For the Academic year 2015-2016, the housing Fees were $3,950 per semester for full time students. As for our suggestions due to the upgraded system and additional amenities the per semester cost should be increased to $5000 for the first 12 years to mitigate cost of renovation.
Average increase in fulltime students (Undergrad and Graduate) at NJIT is projected at 5% each year currently NJIT houses 1400 students at all four housing locations.
This increases the percentage of our complete on campus housing students to at least 95% every semester meaning revenues constantly increase with no fear of loss over time.
AMENITIES FEES:
Some of the amenities that are going to be introduced in the proposed Redwood housing center come at a cost. The pricing has been done to take into account the needs for the students. Cost for some of the amenities is as follows:
Use of Laundry facilities: $0.50 or 50 cents per every wash load and another $0.50 for drying.
Use of Ping Pong & Snooker Pool: $1 for every 2 hrs.
Use of WII or XBOX or play station: $1 for every 1 hrs.
Gym amenities: $30 per semester.
To begin with we are assuming a minimum number of 15 students who would use all of the above mentioned amenities for at least 20 days in a month for 9 months in an academic year. We are also projecting an increase in the number of students at least by 20% every year. The prices of the above amenities will be increased by 10% after every two years.
Please refer APPENDIX C to see the projected revenue for the next 10 years from Amenities Fees.
EQUIPMENT AND MAINTENANCE FEES
P a g e | 21
The students would be charged per semester for equipment maintenance to take care of damage and replacement of on-campus equipment’s. A per-semester charge of roughly $150 per student an extra sur-charge can be issued per case after review for any damages or de-facing of college equipment’s found.
Inspections should be carried out bi-weekly by housing employees, for which students are required to fill out a checklist this would help housing staff keep track of equipment damages/conditions. Additionally, before student’s sign-out and leave at the end of the semester an on-cite inspection should be done to ensure no property damage exist on-sight.
TOTAL REVENUE GENERATED FROM HOUSING COMPLEX OVER A PERIOD OF 10 YEARS
Year Housing Fees Equipment/Maintenance Fees
Amenities Fees Total
Revenue
1st year $2,560,000 $76,800 $15,500 $2,652,300
2nd year $2,560,000 $76,800 $15,500 $2,652,300
3rd year $2,816,000 $84,480 $17,050 $2,917,530
4th year $2,816,000 $84,480 $17,050 $2,917,530
5th year $3,520,000 $105,600 $21,312 $3,646,912
6th year $3,520,000 $105,600 $21,312 $3,646,912
7th year $3,872,000 $126,720 $26,640 $4,025,360
8th year $4,259,200 $152,064 $33,300 $4,444,564
9th year $4,685,120 $182,477 $41,625 $4,909,222
10th year $5,153,632 $218,972 $52,031 $5,424,635
P a g e | 22
1st year 2nd year 3rd year 4th year 5th year 6th year 7th year 8th year 9th year 10th year$0
$1,000,000
$2,000,000
$3,000,000
$4,000,000
$5,000,000
$6,000,000
Sources of Revenue
Housing Fees Equipment/Maintenance Fees Amenities Fees
1st year 2nd year 3rd year 4th year 5th year 6th year 7th year 8th year 9th year 10th year$0
$1,000,000
$2,000,000
$3,000,000
$4,000,000
$5,000,000
$6,000,000
Total Revenue
P a g e | 23
RISK & MITIGATION PLANS
Type Risk Mitigation
Environmental Risk
Weather changes Add contingency days into the schedule
People Risk Union Strike Same as above
Legal Risk Student using equipment not meant for his/her use
Having a professionally certified trainer. Especially for strength or weigh training, making sure the student provides
the medical fitness certificate.
Financial Risk Increase in the estimated Cost due to increase in the prices of the building
materials
Making sure that there is an escalation clause in the contractor ‘s agreement
P a g e | 24
APPENDIX A
SURVEY QUESTIONS
1. What is your gender? □ Male □ Female
2. What is your current college status? □ Graduate □ Undergraduate
3. Do you think you need kitchens in your dorm room? □ Yes □ No
4. Would you prefer a better ventilation system? □ Yes □ No
5. What do you think about Larger Rooms? □ Absolutely □ Prefer smaller Rooms
6. Would you like individual bathroom? □ Yes □ No
7. What do you think about a second elevator? □ Preferred □ Doesn’t Matter
8. Would you like a laundry linked to each floor? □ Yes □ No
9. Would you prefer a game room/recreational center? □ Yes □ No
10. What do you think of a basement Gym for your housing building? □ Yes □ No
P a g e | 25
APPENDIX B
COMPLETE WORK BREAKDOWN STRUCTURE WITH TASK AND SUB TASK
Task Mode Task Name Duration Start Finish Predecessors
Auto Scheduled
Redwood Hall Construction 365 days Mon 4/25/16 Fri 9/15/17
Auto Scheduled
Planning 16 days Mon 4/25/16 Mon 5/16/16
Auto Scheduled Document Review 3 days Mon 4/25/16 Wed 4/27/16
Auto Scheduled
Review and Finalize site prep 3 days Thu 4/28/16 Mon 5/2/16 3
Auto Scheduled
Overlook construction drawing 2 days Tue 5/3/16 Wed 5/4/16 4
Auto Scheduled
Editing and review if needed 2 days Thu 5/5/16 Fri 5/6/16 5
Auto Scheduled Approval of final plan 4 days Mon 5/9/16 Thu 5/12/16 6
Auto Scheduled Financial Analysis 2 days Fri 5/13/16 Mon 5/16/16 7
Auto Scheduled
Bids and Contractors 25 days Tue 5/17/16 Mon 6/20/16 2
Auto Scheduled Distribute cite specs 7 days Tue 5/17/16 Wed 5/25/16 8
Auto Scheduled
Review contractor Budget proposal 3 days Thu 5/26/16 Mon 5/30/16 10
Auto Scheduled
Redo Overall Budget analysis 10 days Tue 5/31/16 Mon 6/13/16 11
Auto Scheduled
Execute sub-contractor agreement 5 days Tue 6/14/16 Mon 6/20/16 12
Auto Scheduled
Approval of reconstruction permit 20 days Tue 6/21/16 Mon 7/18/16 9
Auto Scheduled File Permit Application 5 days Tue 6/21/16 Mon 6/27/16 13
Auto Scheduled Sewage system permit 5 days Tue 6/28/16 Mon 7/4/16 15
Auto Scheduled Electrical Permit 5 days Tue 7/5/16 Mon 7/11/16 16
Auto Scheduled HVAC Permit 5 days Tue 7/12/16 Mon 7/18/16 17
Auto Schedule
Permit Approval process 19 days Tue 7/19/16 Fri 8/12/16 14
P a g e | 26
dAuto Scheduled Pay Permit fees 5 days Tue 7/19/16 Mon 7/25/16 18
Auto Scheduled issuance of permit 14 days Tue 7/26/16 Fri 8/12/16 20
Auto Scheduled
Pre-Site Preparation 55 days Mon 8/15/16 Fri 10/28/16 14,9,2
Auto Scheduled Evac of furniture’s 14 days Mon 8/15/16 Thu 9/1/16 21
Auto Scheduled Wall breakdown 9 days Fri 9/2/16 Wed 9/14/16 23
Auto Scheduled
Protective sealant installation 6 days Thu 9/15/16 Thu 9/22/16 24
Auto Scheduled Side wall Breakdown 5 days Fri 9/23/16 Thu 9/29/16 25
Auto Scheduled
Install building expansion slabs 14 days Fri 9/30/16 Wed 10/19/16 26
Auto Scheduled Floor tile removal 7 days Thu 10/20/16 Fri 10/28/16 27
Auto Scheduled
Construction 57 days Mon 10/31/16 Tue 1/17/17 22,14,19,9
Auto Scheduled Site Preparation 10 days Mon 10/31/16 Fri 11/11/16 28
Auto Scheduled
Re-installing proposed walls 10 days Mon 11/14/16 Fri 11/25/16 30
Auto Scheduled Room Expansion 8 days Mon 11/28/16 Wed 12/7/16 31
Auto Scheduled
platering using recycled agents 6 days Thu 12/8/16 Thu 12/15/16 32
Auto Scheduled Wall assembly 5 days Fri 12/16/16 Thu 12/22/16 33
Auto Scheduled Side expansion 8 days Fri 12/23/16 Tue 1/3/17 34
Auto Scheduled Elevator Installation 7 days Wed 1/4/17 Thu 1/12/17 35
Auto Scheduled Inspection 3 days Fri 1/13/17 Tue 1/17/17 36
Auto Scheduled
Overall Building Recallibration 22 days Wed 1/18/17 Thu 2/16/17 29,22,19
Auto Scheduled Wall strength test 6 days Wed 1/18/17 Wed 1/25/17 37
Auto Scheduled Foundation Strength test 7 days Thu 1/26/17 Fri 2/3/17 39
Auto Scheduled Wind pressure test 3 days Mon 2/6/17 Wed 2/8/17 40
Auto Scheduled
Floor to floor vibration test 3 days Thu 2/9/17 Mon 2/13/17 41
P a g e | 27
Auto Scheduled Sound test 3 days Tue 2/14/17 Thu 2/16/17 42
Auto Scheduled
Structural Analysis 24 days Fri 2/17/17 Wed 3/22/17 38,29,22,19
Auto Scheduled Parts assembly 7 days Fri 2/17/17 Mon 2/27/17 43
Auto Scheduled Floor by floor anaysis 5 days Tue 2/28/17 Mon 3/6/17 45
Auto Scheduled Data Acquisition 3 days Tue 3/7/17 Thu 3/9/17 46
Auto Scheduled Inspection 2 days Fri 3/10/17 Mon 3/13/17 47
Auto Scheduled Parts removal 7 days Tue 3/14/17 Wed 3/22/17 48
Auto Scheduled
Power and Cable Installation 19 days Thu 3/23/17 Tue 4/18/17 29,22,19
Auto Scheduled Electrical wiring 5 days Thu 3/23/17 Wed 3/29/17 49
Auto Scheduled
Cable TV & Internet wiring 9 days Thu 3/30/17 Tue 4/11/17 51
Auto Scheduled Inspection 5 days Wed 4/12/17 Tue 4/18/17 52
Auto Scheduled
Sewage and Water pipe Installation 17 days Wed 4/19/17 Thu 5/11/17 29,22,19
Auto Scheduled Bathroom Assembly 3 days Wed 4/19/17 Fri 4/21/17 53
Auto Scheduled Toilet Assembly 7 days Mon 4/24/17 Tue 5/2/17 55
Auto Scheduled
Zinc and Despenser Assembly 5 days Wed 5/3/17 Tue 5/9/17 56
Auto Scheduled Inspection 2 days Wed 5/10/17 Thu 5/11/17 57
Auto Scheduled
Heating Installation 22 days Fri 5/12/17 Mon 6/12/17 50,29,22,19
Auto Scheduled Air-conditioning system 5 days Fri 5/12/17 Thu 5/18/17 58
Auto Scheduled Heating system 7 days Fri 5/19/17 Mon 5/29/17 60
Auto Scheduled
Fan and thermo systems installation 5 days Tue 5/30/17 Mon 6/5/17 61
Auto Scheduled Inspection 5 days Tue 6/6/17 Mon 6/12/17 62
Auto Scheduled
Interior Design Layout 38 days Tue 6/13/17 Thu 8/3/17 59,54,50,44,38,29,22,19
Auto Electronics 5 days Tue 6/13/17 Mon 6/19/17 63
P a g e | 28
ScheduledAuto Scheduled Painting 4 days Tue 6/20/17 Fri 6/23/17 65
Auto Scheduled
Laundry Equipment installation 7 days Mon 6/26/17 Tue 7/4/17 66
Auto Scheduled
Game room/ TV installation 8 days Wed 7/5/17 Fri 7/14/17 67
Auto Scheduled
Gym Equipment Installation 14 days Mon 7/17/17 Thu 8/3/17 68
Auto Scheduled
Project Finalization 31 days Fri 8/4/17 Fri 9/15/17 64,59,54,50,44,38,29,22,19,14,9
Auto Scheduled Re-analysing Blueprint 7 days Fri 8/4/17 Mon 8/14/17 69
Auto Scheduled
Re-check structural Integrity 5 days Tue 8/15/17 Mon 8/21/17 71
Auto Scheduled
Equipment check and callibration 7 days Tue 8/22/17 Wed 8/30/17 72
Auto Scheduled Sewage system check 2 days Thu 8/31/17 Fri 9/1/17 73
Auto Scheduled
Electrical and Power check 2 days Mon 9/4/17 Tue 9/5/17 74
Auto Scheduled
Administrative final check/approval 2 days Wed 9/6/17 Thu 9/7/17 75
Auto Scheduled Final Inspection 5 days Fri 9/8/17 Thu 9/14/17 76
Auto Scheduled Grand Opening 1 day Fri 9/15/17 Fri 9/15/17 77
Manually Scheduled Finish
P a g e | 29
APPENDIX C
PROJECTED REVENUE FROM AMENETIES FOR 10 YEARS
Year No. of
students
Ping Pong & Snooker
(for 2 hrs.)
WII &
XBOX (for 2 hrs.)
Gym Membership
Laundry Cost. (Wash and Dry)
Per year (20 days per month for 9 months) Total
Revenue per year 1st year 35 $1 $1 $30 $1 $10,395 $11,3952nd year
42 $2 $1 $30 $1.10 $12,909 $13,909
3rd year
53 $2 $2 $31 $1.21 $16,707 $17,707
4th year
62 $2 $2 $31 $1.33 $20,093 $21,093
5th year
72 $2 $2 $31 $1.46 $24,054 $25,054
6th year
85 $2 $3 $32 $1.61 $29,367 $30,367
7th year
92 $2 $4 $32 $1.77 $32,994 $33,994
8th year
110 $3 $5 $32 $1.95 $41,123 $42,123
9th year
123 $3 $6 $32 $2.14 $48,169 $49,169
10th year
150 $3 $7 $33 $2.36 $61,877 $62,877