Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
CASE-LAW UPDATE
Victoria Hutton
20 November 2018
Topics
• Fracking and Protest Injunctions
• Nuisance and Japanese Knotweed
• Habitats and the ECJ
• Human Rights and Salmon
Fracking and Injunctions
Fracking and Injunctions
• Over the course of 2018:
– R(oao Dennett) v Lancashire CC [2018] 10 WLUK
224
– Cuadrilla Bowland Ltd v Persons Unknown [2018] 7
WLUK 223
– Ineos Upstream Ltd v Lord Advocate [2018] CSOH 66
– Cuadrilla Bowland Ltd v Persons Unknown [2018] 5
WLUK 628
– Preston New Road Action Group v SSCLG [2018]
EWCA Civ 9
Challenges to Fracking
• Preston New Road Action Group v SSCLG
– PP granted for exploratory works to assess feasibility
of extracting shale gas by fracking at two sites. Six
year process followed by restoration of the sites.
– SoS concluded that proposals were compliant with
relevant policies. He also concluded that it could be
assumed that the regulatory regime would operate
effectively to control emissions and that there would
be no public health impacts
Preston New Road (cont.)
• Grounds of challenge:
– SoS misapplied policy CS5 in concluding that
temporary harm was not a breach of the policy.
– SoS misapplied policy DM2 by failing to consider
whether the proposal would make a positive
contribution.
– SoS misapplied valued landscapes policy in the
NPPF
– Procedural unfairness
– Failure to heed health effects
Preston New Road (cont.)
• Appeal Dismissed:
– CS policies lawfully interpreted and applied
– Para.109 in NPPF was not framed in terms of
preventing any harm at all it was for the
decision maker to conclude whether
temporary harm would breach the policy
– No procedural unfairness
– SoS had reached rational conclusion on
health effects.
R(oao Dennett) v Lancashire CC [2018] 10 WLUK 224
• Application for interim injunction to prevent
commencement of fracking and also for judicial
review of LPA’s decision with regards to their
assessment of safety risks.
• The IP had been granted petroleum exploration
and development license and environmental
permit for site in Preston and PP for horizontal
shale gas well by SoS.
• Drilling had been completed for two sell sites
and fracking due to commence.
R(oao Dennett) (Cont.)
• C submitted that the LPA had failed to take a
precautionary approach to the environmental
impact and risks.
• Application refused, Supperstone J held that the
risks had been properly considered and not for
the court to substitute its own risk assessment
for that of the experts.
• Risk assessment had proceeded on
precautionary basis by applying worst-case
scenario.
Ineos Upstream v Lord Advocate [2018] CSOH 66
• JR which alleged that the Scottish
Government had unlawfully prohibited
fracking.
• Court held, no legally enforceable
prohibition. Instead, emerging and un-
finalised planning policy which did not
express support for fracking.
Protest Injunctions
• Two interim injunction applications by
Cuadrilla
– Cuadrilla Bowland Ltd v Persons Unknown
[2018] 7 WLUK 223 (continuation)
– Cuadrilla Bowland Ltd v Persons Unknown
[2018] 5 WLUK 628 (original)
Protest Injunctions
• Originally against persons unknown
• 4 named defendants came forward on day
of hearing
• Causes of action included trespass,
unlawful interference with access and
obstructing the highway
Protest Injunctions
• Injunction granted and later continued.
• American Cyanamid test applied
• Rights under arts 10 and 11 ECHR
engaged
• Court applied test in s12(3) HRA 1998
• Held more likely than not that the
claimants would succeed at trial
Nuisance and Japanese Knotweed
Nuisance and Japanese Knotweed
• Network Rail Infrastructure Ltd v Williams [2018]
EWCA Civ 1514
– NR appealed against county court decision allowing
actions in private nuisance for the effects of Japanese
Knotweed on their properties
– No physical damage, but Recorder had found NR had
failed to carry out obligation as a reasonable
landowner to prevent interference with quiet
enjoyment of the properties, causing continuing
nuisance and damage.
Network Rail (cont.)
• CoA’s conclusions on nuisance:
– Private nuisance is a violation of property rights
involving either an interference with legal rights of a
landowner or interference with amenity of the land.
– Categories of encroachment, interference and
physical injury are examples not exhaustive list.
– Damage not always an essential requirement for the
cause of action. Concept of damage is elastic.
– Nuisance could be caused by inaction.
– Broad unifying principle is reasonableness between
neighbours.
Network Rail (cont.)
• CoA further held:
– Recorder was wrong to conclude that the presence of
knotweed was actionable because it diminished
market value of the properties.
– The knotweed carried risk of future physical damage,
this with the failure of NR reasonably to prevent
interference was sufficient to form the cause of action.
– Encroachment by the rhizomes diminished the utility
and amenity of the properties and therefore nuisance
was committed.
– Final mandatory injunctions may be possible.
HABITATS
HABITATS
• People Over Wind and Sweetman v Coillte
Teoranta
• Edel Grace and Sweetman v An Bord
Pleanala
– ECJ disagrees with long line of E&W caselaw
and confirms that mitigation measures may
not be taken into account in deciding whether
to carry out an AA.
Salmon and Human Rights
R(Mott) v Environment Agency [2018] UKSC 10
• EA imposed annual ‘catch limit’ on Mr
Mott’s commercial fisherman’s license to
operate a salmon fishery in the Severn
Estuary.
• Limit imposed by Salmon and Freshwater
Fisheries Act 1975, Sch.2 para.14A
• Limit reduced catch by 95%
R(Mott) v Environment Agency [2018] UKSC 10
• Purpose of limit was to protect salmon
stocks in the River Wye (SAC)
• No compensation paid.
• Mott claimed this breached his rights
under Art 1, Protocol 1 ECHR
R(Mott) v Environment Agency [2018] UKSC 10
• EA argued that there was a distinction
between the control and expropriation of
an individual’s rights (R(oao Trailer and
Marina (Leven) Ltd v SSEFRA [2004] EWCA
Civ 1580)
R(Mott) v Environment Agency [2018] UKSC 10
• Appeal dismissed.
• Distinction between expropriation and control
not clear-cut in Strasbourg case law and not
crucial to instant case.
• The effect on Mott was excessive and
disproportionate.
• Need to attach special importance to protection
of the environment did not detract from need to
strike fair balance between public and private
interests.
R(Mott) v Environment Agency [2018] UKSC 10
• Although not necessary to define as either expropriation
or control the elimination of 95% of the benefit of the
rights made it closer to deprivation.
• EA had not considered impact on Mott’s livelihood.
• Court stressed exceptional nature of Mr Mott’s case and
wide margin of discretion in imposing necessary
environmental controls.
• No general expectation of compensation under art.1
protocol.1 for adverse effects.
Case-law Update
39 Essex Chambers LLP is a governance and holding entity and a limited liability partnership registered in England and Wales (registered number 0C360005) with its registered
office at 81 Chancery Lane, London WC2A 1DD. 39 Essex Chambers‘ members provide legal and advocacy services as independent, self-employed barristers and no entity
connected with 39 Essex Chambers provides any legal services. 39 Essex Chambers (Services) Limited manages the administrative, operational and support functions of Chambers
and is a company incorporated in England and Wales (company number 7385894) with its registered office at 81 Chancery Lane, London WC2A 1DD.
Victoria Hutton
20 November 2018