Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
1
Case Studies on 2 Weekend Closures for Bridge Replacements
Bala Sivakumar
FIU Virtual Symposium on ABCs of ABC
December 4, 2020
Agenda
ABC Case Studies
❖ PennDOT SR 30 Bridge over Bessemer Avenue: Superstructure Replacement in One Weekend Using PBES
❖Weekend Slide-in Replacement of Two I-84 Bridges in New York State
❖ Q & A
2
Time Metrics for ABC – Mobility Impact Time
TRAFFIC IMPACTS WITHIN:
Tier 1 24 hours
Tier 2 3 days (weekend)
Tier 3 2 weeks
Tier 4 3 months
Tier 5 > 3 months but overall project schedulesignificantly reduced
Quick Facts
Quick Facts –PennDOT District 11-0
Designer – HNTB (2015)
Contractor – Brayman Construction
Contract Value -- $2.4 M
SR 30 ADT is 21,798 (2015) with 4% trucks
3 mile detour
5
Existing Bridge
6
• Existing bridge in poor condition with falling debris.
• Substandard under-clearance• Overhead wires
Built 1930
Carries State Route 30 over Bessemer Ave. in East Pittsburgh, PA; high traffic volume
Concrete T-Beam Superstructure
Span = 52’ - 2” on curved alignment
Under-clearance 13’-9”
Existing Bridge
7
Project Goals
Replace the superstructure over a weekend using PBES
Utilize as many precast/pre-fab elements as possible, new precast abutment cap, UHPC connections with a latex overlay to provide long service life
Minimize impact to the adjacent property owner
Increase under-clearance
Apply lessons learned from past ABC projects
8
Accuracy of As-Built Information to ensure fit
Choice of ABC method that fits site constraints and 57-hour closure period
Urban area; limited ROW; overhead wires
Skew, curvature, super-elevation considerations for ABC design
Removal and replacement of deteriorated portions of abutment walls
Approach slab replacement
ABC connections
ABC Design
Decisions
9
ABC Construction Sequence
Pre-Weekend Closure
Precut and brace abutment walls along frontface
Sawcut roadway pavement at ends
Repair abutment spalls and cracks
12
ABC Construction Sequence
Weekend Closure (57 Hours) continued
Demolish superstructure, remove approach slabs and excavate backfill
Sawcut abutment along backface and remove sections
Connect abutments caps with dowels
Erect the six superstructure modules with cranes
Erect precast sleeper slabs and approach slabs
Place accelerated cure UHPC closure pours
Reopen to traffic — Monday 6 AM
13
ABC Construction Sequence
Post-Weekend Closure
Backfill abutments with flowable fill (approach slabs are designed to support traffic loads)
Place and cure rapid set Latex Modified Concrete (LMC) overlay to 1 ¼” depth and sawcut grooves
Apply epoxy resin protective coating to abutment surfaces
14
Engineer’s ABC Schedule
15
Activity Duration (hrs)
Superstructure & approach roadway removals, backfill excavation
8
Substructure saw-cutting and removal 6
Install precast abutment caps 8
Install superstructure modules 8
Install approach slabs 4
Place UHPC closure pours 5
Cure time for UHPC 12
Total Duration (ABC) 51 Hrs
ABC Replacement Using Prefabricated Bridge Elements
54’-0” Single Span
Composite Steel Modular Superstructure (shop painted)
Straight Steel Beams with Variable Overhangs to Accommodate Curvature
Accelerated Cure UHPC Closure Pours
New Precast Abutment Caps to Address Deterioration and Super-elevation
New Precast Approach Slabs
16
Crane sizes limited by overhead high voltage electrical lines (De-energized during ABC weekend).
Lightweight Concrete (117 pcf) to minimize lifting weights
Concrete Stresses During Erection:
Not to Exceed Modulus of Rupture fr = 7.5*Sqrt(f'ci), Divided by a Safety factor of 1.5.
Dead Loads Multiplied by a Factor of 1.25.
Did not control design
Lifting locations shown for each element
Design Checks
for Erection
18
AutoCad Revit Software
3D model of existing bridge using Lidar
New elements modeled in 3D and superimposed on existing
Virtual assembly of bridge during design
Check fitup at each stage of assembly
Several dimensional adjustments were made to precast elements to ensure fit
3D renderings shared with Contractor
3D Model
for Design
19
New Superstructure Plan
Straight beams / modules. Bridge curvature accommodated using
overhangs with variable widths 20
Precast Cap Elevation
24
• Steel shims used to achieve proper seat elevations• Gap around shims filled with rapid set grout -- through
grout ports in cap
Slide In Bridge Construction:
20-Hour Weekend Closure
Twin NYSDOT Bridges on I-84
SHRP2 R04 Demonstration Project
• Bridge design: HNTB (2013)
• Highway design: NYSDOT Region8
• Contractor: Yonkers Contracting
• Precaster: Dailey Precast, Vermont
• Slide Contractor: Barnhart / Marino
• Design funding:
• Construction funding: NYSDOT
Quick Facts
Slide-In Bridge Construction
• 20 Hr closure on two weekend nights
• Bridges too narrow for cross-over
Weekend Replacement of NY I-84 Twin Bridges
• Over 75,000 ADT; 16% trucks
• Existing bridges are too narrow for cross-overs
• Elevation differences between EB & WB roadways
• Under-passing road at 16% grade
NYSDOT Original Replacement Plan
•Build new temporary bridge in the median to maintain traffic
•Additional cost of approximately $2.0 M
•One construction season for each bridge
• Significant traffic impact; Environmental impact
ABC Approach
• Build new substructures working below existing bridges
• Build new superstructures adjacent to existing
• Slide in new superstructures using 20 Hr closure for each slide
ABC Design: Slide-In Replacement
• Slide-In replacement over two weekend nights
• Traffic disruption on I-84 reduced from two years to two Saturday nights (20 hr closures).
• Eliminates need for a temporary bridge & cross-overs –over; $2 M savings.
• Incentive/disincentive clause: $10,000 per hour for early or late completion ($50 K max incentive)
BID / ABC Schedule
• Low Bid: Yonkers Contracting, New York
• $10.2 M (Total Cost); (Bridge cost $6.1 M)
• Contract award January 2013
• Replaced Westbound bridge: 9/21/13
• Replaced Eastbound bridge: 10/19/13
• ABC window: 4 PM Saturday to 1 PM Sunday
55
10 months
Traffic Control During Construction
• Detour during Saturday night -- Sunday morning
• Route 6/202, parallel to I-84, will be used as the detour.
5757
ABC Design & Roadway Tie-in
• Single span 80’; three lanes at 12’
• Bridge width 33’-4” 57’-0”
• Under passing road on 16% grade
• Minimize structure depth with NEXT beams
• Still, the new bridges needed to be two feet higher than the existing to provide 14’-6” under-clearance.
➢ How do you raise the approaches on an Interstate by 2 ft & place approach slabs within the overnight closure period
➢ Roadway tie-in was on the critical path for ABC
Falsework
• Temporary Bents on H piles• Contractor designed• Attach the temp support to
the permanent structure for lateral restraint
• Provide for vertical adjustment by jacking
• Provide soil borings
Precast Approach Slabs Temporary End Spans Carrying Traffic
Flowable fill pumped thru holes in the approach slab to make it ground supported later
Slide Bearings & JacksStainless Steel on Elastomeric Bearings w/PTFE
PTFE bonded to Elastomeric Bearing Push/Pull Jacks
SLIDING FRICTION
• Design of slide system needs a good estimate of static and dynamic friction. Use a trial slide to verify friction, jack capacity
Raising The Approaches
• Raised by 2 feet using warm asphalt in 6” lifts• Takes time: On critical path for closure period
Cost Savings with ABC
80
• Over $ 1.2 M in user delay cost savings by using ABC (Source: NYSDOT)
• $ 2 m cost savings from elimination of cross-overs, temporary bridge (Source: NYSDOT)
• Savings in work-zone accidents costs from reduced work zone traffic control
• Reduced contract administration costs
Lessons Learned
• Focus on Roadway Approaches as much as Structure slide-in. Roadway not the slide was on critical path.
• Need for displacement control at each abutment during slide
• Importance of camber control in P/S beams
• Contractor chose to use permanent bearings for the slide. Use of temporary slide bearings is advantageous