13
Case Study: Gemina Rice Husk Project Nicaragua (Scenario Analysis and Small-Scale Simplified Methodologies) Carbon Finance Unit The World Bank 22 October 2002 www.CarbonFinance.org (Revised by CCIC, 17 July 2003)

Case Study: Gemina Rice Husk Project Nicaragua (Scenario Analysis and Small-Scale Simplified Methodologies) Carbon Finance Unit The World Bank

  • Upload
    haile

  • View
    37

  • Download
    3

Embed Size (px)

DESCRIPTION

Case Study: Gemina Rice Husk Project Nicaragua (Scenario Analysis and Small-Scale Simplified Methodologies) Carbon Finance Unit The World Bank 22 October 2002 www.CarbonFinance.org (Revised by CCIC, 17 July 2003). Contents. Introduction to the Gemina Rice Husk Project - PowerPoint PPT Presentation

Citation preview

Page 1: Case Study: Gemina Rice Husk Project  Nicaragua (Scenario Analysis and Small-Scale Simplified Methodologies) Carbon Finance Unit The World Bank

                                                                                                                         

Case Study: Gemina Rice Husk

Project Nicaragua

(Scenario Analysis and Small-Scale Simplified Methodologies)

Carbon Finance UnitThe World Bank22 October 2002

www.CarbonFinance.org

(Revised by CCIC, 17 July 2003)

                                      

Page 2: Case Study: Gemina Rice Husk Project  Nicaragua (Scenario Analysis and Small-Scale Simplified Methodologies) Carbon Finance Unit The World Bank

                                                                                                                         

Contents

• Introduction to the Gemina Rice Husk Project

• Elements of the baseline

• Applicability of the Meth Panel’s recommendations for simplified methodologies for Small-Scale CDM projects

Page 3: Case Study: Gemina Rice Husk Project  Nicaragua (Scenario Analysis and Small-Scale Simplified Methodologies) Carbon Finance Unit The World Bank

                                                                                                                         

Introduction to the Project • Current practice

– Gemina produces 18,000 tons of rice husk yearly, increasing to 25,000 tons after expansion in 2003

– Rice husks are dumped in open piles– Periodic burning of piles to reduce

volume

• Rice husk to electricity project– Construction of ~1.6 MW power plant– Plant consumes 2.75 t rice husk per hour– Ash used to substitute for cement

Page 4: Case Study: Gemina Rice Husk Project  Nicaragua (Scenario Analysis and Small-Scale Simplified Methodologies) Carbon Finance Unit The World Bank

                                                                                                                         

Introduction to the Project • Technology: Conventional

boiler/steam turbine– Rice husks are fed to the combustor and

burned to produced to produce heat– Steam generated is passed to steam

turbine which drives an electrical generator

• Rice Husk Power Plant– To cover electricity demand for rice and

flourmill complex– And sell the excess electricity to third

parties

Page 5: Case Study: Gemina Rice Husk Project  Nicaragua (Scenario Analysis and Small-Scale Simplified Methodologies) Carbon Finance Unit The World Bank

                                                                                                                         

Introduction to the Project • Main sources of emission reductions

– Displacement of electricity from fossil fuel

– Methane reduction from avoided rice husk decomposition

– CO2 reduction from substitution of cement

0 / 2,712 t CO2eCO2 cement2,338 / 2,338 t CO2eMethane from husks

7,418 / 11,144 t CO2eCO2 energy

•Projected reduction 21 years: 212,395 t CO2e (low)

•Yearly reductions 2003-2012 (low/optimal)

Page 6: Case Study: Gemina Rice Husk Project  Nicaragua (Scenario Analysis and Small-Scale Simplified Methodologies) Carbon Finance Unit The World Bank

                                                                                                                         

Elements of the Baseline

• Baseline– Electricity would otherwise be produced using

fossil fuels– Dumping of waste husks from Gemina rice

mill in open piles

• Gemina project is small-scale– Renewable energy component less than 15MW– Rice husk power plant directly emits less than

15,000 t CO2e

If biomass is counted as renewable energy direct emissions from the project are zero

Page 7: Case Study: Gemina Rice Husk Project  Nicaragua (Scenario Analysis and Small-Scale Simplified Methodologies) Carbon Finance Unit The World Bank

                                                                                                                         

Elements of the Baseline• Approach for calculating baseline

emissions selected by Gemina– Marrakech Accord 48 a): Existing or

historical emissions, as applicable• Justification of selected approach

– 48 a) defines Business-as-usual as baseline scenario

– PCF interpretation: BAU can be justified by(a) using historic or current information

(control group) or (b) showing that barriers impede other options.

- especially relevant for small scale investments

Page 8: Case Study: Gemina Rice Husk Project  Nicaragua (Scenario Analysis and Small-Scale Simplified Methodologies) Carbon Finance Unit The World Bank

                                                                                                                         

Elements of the Baseline

Barriers to investment identified for Geminaa) Regulatory barriers to access the market for

electricity- Smallest block of electricity that can be

offered on the Nicaragua wholesale market is 5 MW (Gemina 1.6 MW)

b) Competitive disadvantage of non-traditional projects- Lack of precedents regarding integration of

small generators of renewable energy created problems with concessionaire

c) Limited access to credit- Gemina could not attract financing due to

inter alia absence of long-term PPA, high country risk for Nicaragua

Page 9: Case Study: Gemina Rice Husk Project  Nicaragua (Scenario Analysis and Small-Scale Simplified Methodologies) Carbon Finance Unit The World Bank

                                                                                                                         

Elements of the Baseline

• Indicator for restrictive nature of identified barriers:– Gemina rice husk generator is first-of-a-

kind technology in all Central America

• PCF assistance to overcome the barriers– Carbon purchase agreement is secure

revenue stream– World Bank involvement may trigger the

interest of other financial institutions

Page 10: Case Study: Gemina Rice Husk Project  Nicaragua (Scenario Analysis and Small-Scale Simplified Methodologies) Carbon Finance Unit The World Bank

                                                                                                                         

Applicability of Meth Panel’s recommendation for simplified methodologies

• Gemina project falls under category I. D. “Renewable Electricity Generation for a Grid”

• Recommended simplified methodology:– Technology/Measure:

25. Biomass combined heat and power (co-generation) systems that supply electricity to a grid

– Boundary:26. Physical, geographical site of the

renewable generation source

Page 11: Case Study: Gemina Rice Husk Project  Nicaragua (Scenario Analysis and Small-Scale Simplified Methodologies) Carbon Finance Unit The World Bank

                                                                                                                         

Applicability of Meth Panel’s recommendation for simplified methodologies

• Recommended simplified methodology:– Baseline:

28. For a system where all fossil fuel fired generating units use fuel oil or diesel oil, the baseline is the annual kWh generated by the renewable unit times an emission coefficient for a modern diesel generating unit of the relevant capacity operating at optimal load

– Leakage:30. If the renewable energy technology is

new equipment being installed for the first time, no leakage calculation is required.

Page 12: Case Study: Gemina Rice Husk Project  Nicaragua (Scenario Analysis and Small-Scale Simplified Methodologies) Carbon Finance Unit The World Bank

                                                                                                                         

Applicability of Meth Panel’s recommendation for simplified methodologies

• Recommended simplified methodology:– Monitoring:

31. Shall consist of metering the electricity generated by the renewable technology. In the case of co-fired plants, the amount of biomass input and its energy content shall be monitored.

Page 13: Case Study: Gemina Rice Husk Project  Nicaragua (Scenario Analysis and Small-Scale Simplified Methodologies) Carbon Finance Unit The World Bank

                                                                                                                         

Thank you !

Department of Environment and Natural Resources

CDM Training WorkshopNovember 4-6, 2003

Climate Change Information Center Conference Room