Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
Case study
ChallengeThe aging chiller at the Kohlwes Education Center was
inefficient, and replacement parts for the unit were no longer
available. Continuous maintenance, required to keep the
chiller operational, was resulting in considerable expense for
the district. In addition, a large number of servers in the
computer room were running at a low percentage of capacity,
taking up space that could be better utilized as a server room
and separate Information Management Services (IMS)
development lab. Believing in the critical importance of
technology in running its schools and providing its students
with a high-quality education, Renton School District sought
to obtain more efficient and reliable server room capacity.
SolutionWhen funds became available through the State of
Washington’s Energy Savings Performance Contracting
(ESPC) grant program and the voter-approved 2009
Technology Levy, Renton School District took advantage of
the opportunity to initiate its much needed data center
upgrades. The district’s IMS department collaborated with the
Office of Resource Conservation Management to begin
transforming and updating its server room. Selected as its
Energy Services Company (ESCO), Trane supported the Office
of Resource Conservation Management in their efforts to also
upgrade mechanical systems, controls and install a new Trane
chiller with enough capacity to cool the entire building.
Renton School District Kohlwes Education CenterServer room transformation reduces load 50 percent, lowers maintenance costRenton, Washington
Renton School District envisions classrooms where technology is a tool used to boost student achievement. The district’sInformation Management Services (IMS), located in its Kohlwes Education Center, is charged with implementation andsupport of technology. Services provided include network and desktop support, software and hardware purchasingstandards, training computer labs, videoconferencing, and telecommunications / telephone services.
Virtualization technology transforms server room
Server room power supplies, network switches and servers
were upgraded to provide more efficient computing power for
the entire district. The IMS project included the use of
“virtualization” technology, reducing a couple hundred
physical servers to six physical servers hosting hundreds of
virtual servers, with capacity to grow. The reduction in servers
has resulted in a reduction in both the amount of energy
consumed to power the servers and the power required to
dissipate the heat generated by the servers.
The upgraded Kohlwes Education Center server room provides more
efficient computing power for the entire district.
September 2012
State-of-the-art data center better serves district needs
Once the new server room reconfiguration was begun, plans
were drawn up to enclose the 20 ft by 30 ft room within a
state-of-the-art data center that would better meet the
needs of the district, while increasing system reliability, and
energy efficiency of complex direct digitally controlled (DDC)
mechanical systems. The new server room includes unique
features, such as special fire suppression and air handling
units, and expandable hot and cold aisle racks, designed to
roll in the event of an earthquake.
HVAC systems increase efficiency and energy savings
The building’s aging chiller was replaced with a 130-ton
Trane high-efficiency, air cooled chiller. The new chiller
improves part-load efficiency and has to-date eliminated
costly repairs. The data center’s 5-ton rooftop cooling unit
was replaced with a more energy efficient Trane 7.5-ton dual
compressor, air-cooled packaged unit. The unit is equipped
with an economizer, which allows it to take advantage of
"free cooling", using 100 percent outside air when
temperatures are below 65 degrees. "Trane removed the old
units on Saturday morning, then installed the new chiller and
rooftop unit," said J. Stine, Renton School District resource
conservation and safety manager. "By Monday, systems were
100 percent, with zero issues and no cooling interruptions."
Energy Management System provides real time control
The existing Energy Management System (EMS) was
upgraded to provide monitoring, control and performance
trending of the new server room and development lab within
the direct digital control system. The energy management
tool is utilized daily by district staff.
ResultsAs a result of technology and mechanical system upgrades,
energy usage at Renton School District Kohlwes Education
Center has decreased dramatically. The data center’s electric
load has been reduced by 50 percent, resulting in utility cost
savings of $12,000 per year.
"The data center modernization was successful due to several
partnerships including the Washington ESPC grant, Trane -
our ESCO, Renton School District’s Resource Conservation
Manager, the IMS Infrastructure team, a supportive school
board and superintendant, and our community," said Stosh
Morency, director of Information Management Services. "The
upgrades allow the district to offer robust technology
resources to support student learning for the next decade,
while reducing costs."
"We’re saving energy, preventative maintenance visits are
taking place, our data center is more reliable and we’re using
economizer cooling 90% of the time," added Stine. "This
allows us to redirect operating funds back into the classrooms
to support our primary mission - Education!"
Shown above: Server room before transformation. Virtualization
technology reduced a couple hundred physical servers to six physical
servers hosting hundreds of virtual servers.
industrial markets. Our people and our family of brands—including Club Car®, Ingersoll Rand®, Schlage®, Thermo King® and Trane®—work together to Ingersoll Rand (NYSE:IR) is a world leader in creating and sustaining safe, comfortable and efficient environments in commercial, residential and
enhance the quality and comfort of air in homes and buildings, transport and protect food and perishables, secure homes and commercial properties,
company and for our customers. For more information, visit www.ingersollrand.com.and increase industrial productivity and efficiency. We are a $14 billion global business committed to sustainable business practices within our
trane.com ingersollrand.com
We are committed to using environmentally conscious print practices that reduce waste.
© 2012 Trane All rights reserved
CASE-SLX323-EN September 14, 2012