Upload
others
View
14
Download
0
Embed Size (px)
Citation preview
[email protected] - May 9, 2019 – CBETA Advisory Committee Meeting, Cornell
CBETA RF Systems
Peter Quigley
[email protected] - May 9, 2019 – CBETA Advisory Committee Meeting, Cornell
CBETA RF Systems:Overview
• RF Hardware
• Cryogenic Systems
• Warmup/Cooldown
• Tuning
• RF Control
• Future Plans
[email protected] - May 9, 2019 – CBETA Advisory Committee Meeting, Cornell
CBETA RF Systems: RF HardwareInjector Cryomodule (ICM)
1.3 GHz 2-cell SRFcavity, blade tuner.
HOM load at 80Kbetween cavities
Twin Input PowerCoupler
Number of 2-cell cavities 5 Number of HOM loads 6
Energy gain per cavity 1 – 3 MeV HOM Power per cavity 40 W
Gradient 4.3 – 13.0 MV/m Couplers per cavity 2
R/Q (Linac definition) 222 Ω RF power per cavity 120 kW
Qext 4.6 x 104 – 4.1 x 105 Amplitude/phase stability 10-4/0.1º (rms)
Total 2K / 5K/ 80K loads 30 W / 60 W / 700 W Module Length 5 m
CBETA Operating Temperature 2K Current Temperature 80K
HGRP with three sections
Support Posts300K to 2K
Isolation
µ-metal “Lunch Box”around cavities
Wire Position Monitor (WPM) tube
WPM, (one on each cavity)
[email protected] - May 9, 2019 – CBETA Advisory Committee Meeting, Cornell
CBETA RF Systems: RF HardwareMain LINAC Cryomodule (MLC)
6 7-cell Cavities• ΔE = 6 MeV• σA/A ~ 10-4, σφ ~ 0.1°
7 HOM Absorbers(Max 400 W)
Based on TESLA cryomodule designwith important differences:• Optimized for CW operation.• Designed for ERLs.• Cavities hang from the HGRP which is
used to align them.
Helium Gas Return Pipe (1 section)Input Power Coupler(Max 10 kW)
2K 2-PhaseHelium Line
[email protected] - May 9, 2019 – CBETA Advisory Committee Meeting, Cornell
SSAs
5 kW
5 kW
5 kW
10 kW
10 kW
10 kW
RF Power Isolators
• Status:• MLC is currently at 1.2 K (12.5 Torr Helium Pressure).• Vacuum:
• Insulation: 8.0x10-6 Torr• Cavity Beamline: 1.8x10-11 Torr• Input Power Couplers: 6.0x10-10 Torr (average of six couplers)
Stiffened CavityStiffening Rings
Unstiffened Cavity
Input Power Coupler
40K Flange and cooling
Warm Ceramic Window
BellowsCavity
Flange (1.8)
Antenna 5K Intercept
Cold Ceramic WindowInstrumentation Port
Air Cooling
Waveguide Flange
Pump Port
300K Flange
Slow Cavity Tuner
3- Stub WGTuner
Piezo Tuner
2K TunerMotor
CBETA RF Systems: RF HardwareMain LINAC Cryomodule (MLC), Input Coupler, Tuner, Solid State Amplifiers (SSA)
[email protected] - May 9, 2019 – CBETA Advisory Committee Meeting, Cornell
CBETA RF Systems: RF HardwareWhat Happened Since 2018 AC
• ICM
• Klystron #3 needed solenoid current adjustment.
• ICM delivers 6 MeV reliably.• MLC
• SSA firmware upgrade: 1/20/2019.
• SSA power up with shorted waveguide and interlocks bypassed.
• Tuned cavities with network analyzer. Motors are vulnerable.• CM2, SECOND 1.3 GHZ CRYOMODULE FABRICATION AT FERMILAB* T. Arkan, PAC2013
• Connected RF power to cavities, all initially tested for operation at 6 MeV, no
issues.
[email protected] - May 9, 2019 – CBETA Advisory Committee Meeting, Cornell
CBETA RF Systems: RF HardwareWhat Happened Since 2018 AC
• MLC (continued)
• SSA operating condition
• Firmware update introduced new bug.
• External interlock trip requires AC power cycle to reset.
• Put external interlocks in series with PPS. Works well enough.
• Working with manufacturer to resolve.
• SSA #6 48 VDC power supply interlock false failure indication.
• Measurements show power supply is working.
• Interlock is bypassed. Checking with manufacturer to see if operating in
this state is ok.
• Ordering spare supply
[email protected] - May 9, 2019 – CBETA Advisory Committee Meeting, Cornell
CBETA RF Systems:MLC SSA Test After RF Power Circulator Repair
All isolators were repaired: (Slide From October 2018 AC)1. Tuning screws were removed and the resistive load were disassembled.
2. Broken ferrite tiles were removed and the load surface was cleaned.3. Plastic residue was blown out with dry nitrogen.4. The isolator was reassembled and the tuning screws were adjusted to optimize isolation using
a network analyzer.5. All SSAs and isolators were tested to full power CW!
Ferrite damage on 10 kW loads Damage to load surface on 5 kW loads
Loads damaged due to arcing triggered by damaged plastic on tuning screws.
Results of SSA Nominal Power Test After Isolator Repair
Cavity # 1 2 3 4 5 6
Max Pf (kW) 10 5 10 5 10 5
Max Pr (W) 130 18 118 75 13 3.5
[email protected] - May 9, 2019 – CBETA Advisory Committee Meeting, Cornell
CBETA RF Systems: RF HardwareRF Power Circulators
• RF Power Circulators• AFT refuses to warranty RF power circulator damage.
• Concern is water leak on cooling plate in pitted locations.
• Adding automatic valve for cooling water ON/OFF.
• Agreed to fix at factory but confidence in a timely turn around is low.
• Requesting that AFT send new ferrite plates for repairs to be done at Cornell.
Port 1
Port 2Port 3
Water Cooled Ferrite Load InsideTapered Waveguide
Tuning Screws
Arc Detector Port
New
Damaged • Isolators tuning screw insulatordisintegrated on the initial testdepositing a power-like substanceon the interior surface.
• No Arcing detected at any timeduring RF operations.
[email protected] - May 9, 2019 – CBETA Advisory Committee Meeting, Cornell
CBETA RF Systems:Cryogenics
• Cryogenic Systems:
• Added sleeves to all MLC cryogenic valves (microphonics suppression).
• Modified MLC cryogenic pumping lines to mitigate oil flow between skids.
• Checking microphonics impact when using different pump skids.
• 2K 2-Phase Helium Level Control:
• RF OFF: JT regulates helium level.
• RF ON: Either 2K 2-Phase heater or the JT regulates helium level.
• Working on optimizing both.
[email protected] - May 9, 2019 – CBETA Advisory Committee Meeting, Cornell
CBETA RF Systems:Warmup/ Cooldown
• Warmup/Cooldown:• ICM
• Idle at 80K since 6/14/2018 through 2/28/2019.
• Cooldown to 2K 3/4/2019, no issues.• MLC
• (Warmed to room temperature 5/23/2018.)
• MLC Beamline height correction: 3/4/2019
• Beam based measurements show beam line is ~4 mm too high.
• Survey could only account for 2 mm offset.
• Beamline thermal shrinkage ~1 mm.
• Lowered MLC vacuum vessel 2mm, beamline 1.2mm (Next Slide).
[email protected] - May 9, 2019 – CBETA Advisory Committee Meeting, Cornell
CBETA RF Systems:MLC Vertical Offset
Lowered MLC vacuum vessel 2mm
• Thermal shrinkage is~1.2 mm. Notaccounted for duringMLC assembly.
Two room temperatureheight adjustmentscrews on each supportpost.
• Survey shows ~ 1mmerror on the BPMposition.
BPM just downstream of theMLC exit flange.
MLC Support Stand
• Beam based measurements show beam line is ~4 mmtoo high.
• Survey could only account for 2 mm offset.• Beamline thermal shrinkage ~1 mm• Lowered MLC vacuum vessel 2mm, beamline 1.2mm
[email protected] - May 9, 2019 – CBETA Advisory Committee Meeting, Cornell
CBETA RF Systems:MLC Cooldown March 2019
[email protected] - May 9, 2019 – CBETA Advisory Committee Meeting, Cornell
CBETA RF Systems:Cavity Tuning
• Tuning
• ICM Cavity #2 cannot be tuned to 1299.9 MHz, detuned, Klystron HVdisconnected.
• MLC cavity #6 mechanical tuner limit forces the CBETA operatingfrequency to be 1299.9 MHz.
• This tuner is not easily accessible in-situ. Risky, Time consuming.
[email protected] - May 9, 2019 – CBETA Advisory Committee Meeting, Cornell
MLC Tuner Motor Harmonic Drive
[email protected] - May 9, 2019 – CBETA Advisory Committee Meeting, Cornell
• ICM
• Cavities require occasional tuning otherwise operation is reliable.
• Field stability is optimized
• MLC
• Microphonics and LDF compensation is working well.
CBETA RF Systems:Cavity Tuning
[email protected] - May 9, 2019 – CBETA Advisory Committee Meeting, Cornell
CBETA RF Systems:RF Control
• RF Control
• MLC cavity field stability.
• Measured noise/crosstalk on LLRF cavity field signal.
• ICM ~1 kV rms.
• MLC ~10 kV rms.
• Likely source being on the RF high power side.
• Waveguide is a likely source.
• Flanges.
• Directional couplers.
• RF leak checking on the schedule.
• Cavity #5 is not operating in klystron or cavity loop.
• Investigating.
[email protected] - May 9, 2019 – CBETA Advisory Committee Meeting, Cornell
MLC Microphonics
Cavity Stiffened Old PeakDetuning (Hz)
New PeakDetuning (Hz)
Major VibrationFrequencies (Hz)
Field (MV)
1 No 30 40 41, 59 6
2 Yes 25 29 41, 100 6
3 No 50 45 41, 59, 100 6
4 Yes 20 19 100 6
5 No 41 41 8, 41, 59 6
6 Yes 18 25 8, 41 6
Slight increase in peak microphonics detuning on most cavities, but we are still within ourRF power budget for 36 MeV operations. Slide By Nilanjan Banerjee
[email protected] - May 9, 2019 – CBETA Advisory Committee Meeting, Cornell
CBETA RF Systems:Future Plans
• RF• Continue to optimize loop parameters as conditions require.• Measure and characterize RF noise/vibration sources
• Mechanical• New vibration sources added since FAT.
• Added additional cryogenic valve sleeves.• Cause return of the 41 Hz vibration?
• Cooling ventilation duct work.• Cooling water systems.• New equipment platform.• New cable tray and conduits.
• Clamp waveguides with Sorbothan.• Decouple SSA waveguide from Klystron mezzanine.• Measure 2K Helium pumping line vibrations, (using different skids).
• Electrical:• Locate and isolate RF leaks.• Shield electronics if necessary.• Check for ground currents/loops.
• A fair amount of ground connections were made according to electricalcode requirements.
• Cryogenics• Continue to optimize loop parameters as operating conditions require.• Automating Skid bypass control valves.
[email protected] - May 9, 2019 – CBETA Advisory Committee Meeting, Cornell
CBETA RF Systems:Conclusion
• CBETA RF Systems have delivered up to 59 MeV energy gain, (during FAT) and can
reliably deliver 42 MeV.
• CBETA RF system Team continues to work system optimization and address issues
both current and as they arise.
[email protected] - May 9, 2019 – CBETA Advisory Committee Meeting, Cornell
Extra Slides Follow
[email protected] - May 9, 2019 – CBETA Advisory Committee Meeting, Cornell
Initial Test of Solid State RF Power Amplifiers (SSA)(Power is not applied to cavity, See test setup)
SSA NominalPower
SSA SerialNumber
MLCCavity
PeakForward
Power (Pf)(kW)
Peak ForwarPower (Pr)
(kW)
SSA DisipatedPower(kW)
RF PowerIsolator
DissipatedPower (kW)
RF PowerIsolator HighTemperature
(°C)
Comments
10 kW0001 #5 9.03 0.31 15.40 8.90 62 Cable Over heated on SSA power module #20002 #3 9.52 0.15 13.20 9.00 74 Trip on high Pf high Pr
0003 #1 10.00 0.43 12.50 11.40 72 No Issues
5 kW0001 #6 4.55 0.31 5.10 8.90 90 High isolator temperature0002 #4 3.00 0.30 2.90 No Data 35 Trip cause unknown. Pulse operation to 5 kW0003 #2 5.02 0.15 5.20 7.00 37 No Issues
Port 1
Port 2Port 3
Water Cooled FerriteLoad Inside TaperedWaveguide
Tuning ScrewsArc Detector Port
Isolator (AFT)
SSA (SigmaPhi)
3 Stub Tuner
DirectionalCoupler
Short install atwaveguide output
SSA Test Setup
New
Damaged
CBETA RF Systems: MLCSolid State Amplifier (SSA) Initial Test
• Isolators tuning screw insulatordisintegrated on the initial testdepositing a power-like substanceon the interior surface.
• No Arcing detected at any timeduring RF operations.
Circulating Ferrites(Slide From October 2018 AC)
[email protected] - May 9, 2019 – CBETA Advisory Committee Meeting, Cornell
25
27
29
31
33
35
37
39
41
0 2000 4000 6000 8000 10000 12000
Tem
pera
ture
(°C)
Time (seconds)
AFT Isolator Tuning Screw TemperatureDuring SSA Nominal Power Test
SN-1040621 SN-1040195SN-1040620 SN-1040196SN-1040619 SN-1040194
Pf = 5kW
Pf = 10kW Peak
10kWIsolator
5kWIsolator
AFT Isolator tuning screw temperature during high power test followingtuning screw insulator replacement. Tests were not simultaneous andduration of tests varied for arbitrary reasons.
CBETA RF Systems: MLCSSA Test After Isolator Repairs
Temperature monitoredat this location
Port 1
Port 2Port 3
Water Cooled FerriteLoad Inside TaperedWaveguide
Tuning ScrewsArc Detector Port
(Slide From October 2018 AC)
[email protected] - May 9, 2019 – CBETA Advisory Committee Meeting, Cornell
Energy Scan
The MLC successfully reached an energy gain of 53.2 MeV during operations.
• Isolator screw temperatures werebelow 30 C at all times!
• Peak blower speed was 67.5% forboth skids.
Exceeded design energy gain by 50%!
TimeCavity #1 Cavity #2 Cavity #3 Cavity #4 Cavity #5 Cavity #6
Field(MV) Pf (W) Pr (W) Field
(MV)Pf
(W) Pr (W) Field(MV) Pf (W) Pr (W) Field
(MV) Pf (W) Pr (W) Field(MV) Pf (W) Pr (W) Field
(MV) Pf (W) Pr (W)
19:45 6 260 385 6 208 198 6 180 161 6 195 319 6 240 35 11 790 1000 47
19:32 6 260 385 6 208 198 6 180 161 8 353 579 6 241 36 11 791 1001 49
19:58 6 260 385 8 375 356 6 180 161 8 353 579 6 242 37 11 792 1002 51
20:00 6 260 385 8 375 356 6 180 161 8 353 579 8 446 62 11 793 1003 53
21:20 9.25 609 900 8 375 356 7.5 288 257 8.5 399 652 8.5 503 70 11.25 833 1115 59
21:31 9.45 614 900 8 375 356 7.5 288 257 8.4 390 638 8.5 503 70 11.35 849 1135 59.2
Total Energy Gain (6 MeV from ICM)
SSA Isolator Temperature30
29
27
26
28
Kelv
ins
Time (Hours)-20 -15 -10 -5 22:45:16
May 18, 2018
(Slide From October 2018 AC)
[email protected] - May 9, 2019 – CBETA Advisory Committee Meeting, Cornell
CBETA RF Systems:MLC Tuning
• Tuner assembly mounted on unstiffened cavity.
[email protected] - May 9, 2019 – CBETA Advisory Committee Meeting, Cornell
Waveguide motion showing effect of strikingthe structure in the “wrong” spot.
Slide By Tom Powers, LLRF Microphonics Workshop Oct. 201826
• I made the mistake of striking the waveguide at point 2 which made it look like the secondwaveguide from the left was more sensitive than all of the rest.
• I should have struck it on the insulating vessel at one end of in the center in order to excite allof the waveguides about the same.
• Even still we got the information that we needed as this design had a beam between all of thewaveguides and we found a 20 Hz mode of that structure which would have been “amplified”to the 21 Hz half string mode when it got to the cavities.