Form CC-0090 Page 1 of 11 Rev.1.23.2010
LOS ANGELES COMMUNITY COLLEGE DISTRICT
DEPARTMENTOFFACILITIESPLANNINGANDDEVELOPMENT
SUSTAINABLEBIUILDINGPROGRAM
LEED POINT SUMMARY
CreditNo.
Credit/Prerequisite Description
onsu
an
Responsible
Supportfrom
Section
Submittals Required
(S)Sustainable Sites
SPR1 Erosion and Sedimentation Control
CreditsS1 Site Selection
Do not build on land falling underany of 5 criteria
S2 Urban Redevelopment
Minimum density 60,000 sf/acre
S3 Brownfield Redevelopment
S4 Alternative transportation
4.1 1/2 mile to rail station or within 1/4mile 2 bus lines
4.2 Bicycle facilities and showers for 5%
occupants4.3 Alternative fueling station for 3%
vehicles4.4 Minimum parking by zoning, or no
new parkingS5 Reduced Site Disturbance
5.1 Limit site disturbance of naturalareas
5.2 Exceed local open spacerequirements by 25%
S6 Stormwater Management
8/10/2019 CC-0090 LEED Point Summary
2/11
Form CC-0090 Page 2 of 11 Rev.1.23.2010
LOS ANGELES COMMUNITY COLLEGE DISTRICT
DEPARTMENTOFFACILITIESPLANNINGANDDEVELOPMENT
SUSTAINABLEBIUILDINGPROGRAM
LEED POINT SUMMARY
CreditNo.
Credit/Prerequisite Description
onsu
an
Responsible
Supportfrom
Section
Submittals Required
6.1 No net increase of water runoff fromexisting or if >50% imperviousness,decrease 25% stormwater runoff
6.2 Treatment system 80% tss, 40% tp
S7 Landscape and Design to reduce Heat Islands
7.1 Non-roof surfaces - Shade or low-albedo
02751
Cut sheet showing reflectance value of sidewalkpavement
OR
02700cut sheets for the pervious paving system,demonstrating that it is at least 50% pervious
7.2 Energy-Star compliant roof
07313,
07511,07620
Cut sheet for roofing material, highlighting theemissivity, the initial reflectance and the reflectanceafter 3 years.
OR
cut sheets highlighting the green vegetated roof system
S8 Light Pollution Reduction
Do not exceed IESNA footcandlelevels and zero direct-beamillumination leaves site
(W)Water Efficiency
CreditsW1 Water Efficient Landscaping
8/10/2019 CC-0090 LEED Point Summary
3/11
Form CC-0090 Page 3 of 11 Rev.1.23.2010
LOS ANGELES COMMUNITY COLLEGE DISTRICT
DEPARTMENTOFFACILITIESPLANNINGANDDEVELOPMENT
SUSTAINABLEBIUILDINGPROGRAM
LEED POINT SUMMARY
CreditNo.
Credit/Prerequisite Description
onsu
an
Responsible
Supportfrom
Section
Submittals Required
1.1
high efficiency irrigation technology,OR, use captured rain or recycledsite water for 50% reduction
02810
Cut sheets for high-efficiency irrigation equipment
1.2
Use only captured rain or recycledsite water for an additional 50%reduction (100% total reduction) ofpotable water for site irrigationneeds, OR, do not install permanentlandscape irrigation systems.
W2 Innovative Wastewater Technologies
Reduce the use of municipallyprovided potable water for buildingsewage conveyance by a minimumof 50%, OR, treat 100% ofwastewater on site to tertiarystandards.
W3 Water Use Reduction
3.1
Employ strategies that in aggregate
use 20% less water than the wateruse baseline calculated for thebuilding (not including irrigation)after meeting Energy Policy Act of1992 fixture performancerequirements.
15050
Cut sheets for all water consuming fixtures necessary
for the occupancy use of the building, with waterconservation specifications highlighted to show that thefixtures meet or exceed fixture performancerequirements of the Energy Policy Act of 1992 - forbaseline, refer to table 1 in 01101.1.03
8/10/2019 CC-0090 LEED Point Summary
4/11
Form CC-0090 Page 4 of 11 Rev.1.23.2010
LOS ANGELES COMMUNITY COLLEGE DISTRICT
DEPARTMENTOFFACILITIESPLANNINGANDDEVELOPMENT
SUSTAINABLEBIUILDINGPROGRAM
LEED POINT SUMMARY
CreditNo.
Credit/Prerequisite Description
onsu
an
Responsible
Supportfrom
Section
Submittals Required
3.2
Exceed the potable water usereduction by an additional 10% (30%total efficiency increase).
(E) Energy and Atmosphere
PrerequisitesEPR1 Fundamental Building Systems Commissioning 01810 refer to the commissioning specEPR2 Minimum Energy Performance
Meet ASHRAE 90.1-1999 or localcode, whichever is more stringent.
EPR3 CFC Reduction in HVAC & R
EquipmentUse no CFC refrigerants in newconstruction. Phase out in reusedsystems.
15050
Cut sheets from all HVAC&R equipment, highlightingrefrigerant data
CreditsE1 Energy Efficiency
1.1
Exceed ASHRAE 90.1-1999 by 20%new, 10% old
1.2 by 30% new, 20% old
1.3 by 40% new, 30% old
1.4 by 50% new, 40% old
1.5 by 60% new, 50% old
E2 Renewable Energy
2.1
5% total building energy load
16200Provide cut sheets for on-site renewable energysystems
8/10/2019 CC-0090 LEED Point Summary
5/11
Form CC-0090 Page 5 of 11 Rev.1.23.2010
LOS ANGELES COMMUNITY COLLEGE DISTRICT
DEPARTMENTOFFACILITIESPLANNINGANDDEVELOPMENT
SUSTAINABLEBIUILDINGPROGRAM
LEED POINT SUMMARY
CreditNo.
Credit/Prerequisite Description
onsu
an
Responsible
Supportfrom
Section
Submittals Required
2.2
10% total building energy load
16200Provide cut sheets for on-site renewable energysystems
2.3
20% total building energy load
16200 Provide cut sheets for on-site renewable energysystems
E3 Additional Commission 01810 refer to the commissioning spec
E4 Elimination of HCFC's and Halons
15050cut sheets for all HVAC&R equipment, highlightingrefrigerant data
E5 Measurement and VerificationSee USDOE IPMVP Standards.
15050
cut sheets of sensors and the data collection systemused to provide continuous metering per IPMVPstandards
E6
Green Power 2 year contract with green-e labeledpower
(M) Conserving Materials and Resources
PrerequisitesMPR1 Storage & Collection of Recyclables
Credits
M1 Existing building rehabilitation
1.1Maintain 75% of original structuralshell
1.2Maintain 100% of original structuralshell
8/10/2019 CC-0090 LEED Point Summary
6/11
Form CC-0090 Page 6 of 11 Rev.1.23.2010
LOS ANGELES COMMUNITY COLLEGE DISTRICT
DEPARTMENTOFFACILITIESPLANNINGANDDEVELOPMENT
SUSTAINABLEBIUILDINGPROGRAM
LEED POINT SUMMARY
CreditNo.
Credit/Prerequisite Description
onsu
an
Responsible
Supportfrom
Section
Submittals Required
1.3
Maintain 100% of original structuralshellAND 50% non-shell
M2 Construction waste management
2.1
Waste plan plus recycle or salvageat least 50% (by weight) ofconstruction, demolition, and landclearing waste.
alldivisions
Sellen construction waste management plan, refer tosection 01505
2.2
Recycle or salvage an additional25% (by weight) of construction,demolition, and land clearing waste. all
divisions
Sellen construction waste management plan, refer tosection 01505
M3 Resource reuse
3.1
Specify 5% salvaged or refurbishedmaterials
Divs 2-
12
Cut sheets or submittals shall clearly indicate whether
the material is a salvaged or reused material
3.2
Specify additional 5% salvaged orrefurbished materials
GC to provide LEED Calculator spreadsheet
M4 Recycled content
4.1
Specify a minimum of 25% ofbuilding materials that contain inaggregate, a minimum of 20%postconsumer recycled contentmaterial, OR, a minimum 40% post-industrial recycled content material.
Divs 2-12
Cut sheets shall clearly indicate whether the materialcontains post-consumer or post-industrial recycledmaterials or both.
GC to provide LEED Calculator spreadsheet
8/10/2019 CC-0090 LEED Point Summary
7/11
Form CC-0090 Page 7 of 11 Rev.1.23.2010
LOS ANGELES COMMUNITY COLLEGE DISTRICT
DEPARTMENTOFFACILITIESPLANNINGANDDEVELOPMENT
SUSTAINABLEBIUILDINGPROGRAM
LEED POINT SUMMARY
CreditNo.
Credit/Prerequisite Description
onsu
an
Responsible
Supportfrom
Section
Submittals Required
4.2
Specify an additional 25% (50%total) of building materials thatcontain in aggregate, a minimum of
20% post-consumer recycledcontent material, OR, a minimum40% post-industrial recycled contentmaterial.
Divs 2-12
Cut sheets shall clearly indicate whether the materialcontains post-consumer or post-industrial recycledmaterials or both.
M5 Local / Regional Materials
5.120% materials manufactured within500 miles
5.2
50% of the above 20% that areextracted, harvested, or recovered
within 500 miles.
Divs 2-12
Cut sheets shall clearly indicate location ofmanufacture, highlighting those materials manufactured
within a 500-mile radius.
M6 Rapidly Renewable MaterialsSpecify rapidly renewable buildingmaterials for 5% of total buildingmaterials. Divs 2-
12Cut sheets shall clearly indicate rapidly renewablematerials contained in the product
M7 Certified Wood
8/10/2019 CC-0090 LEED Point Summary
8/11
Form CC-0090 Page 8 of 11 Rev.1.23.2010
LOS ANGELES COMMUNITY COLLEGE DISTRICT
DEPARTMENTOFFACILITIESPLANNINGANDDEVELOPMENT
SUSTAINABLEBIUILDINGPROGRAM
LEED POINT SUMMARY
CreditNo.
Credit/Prerequisite Description
onsu
an
Responsible
Supportfrom
Section
Submittals Required
50% certified materials per FSC
06105,06150,06402,08211,09640,
Cut sheets highlighting certified wood-based materialsinstalled. Provide wood certification documentationfrom manufacturer declaring conformance with FSC
guidelines for certified wood building components.
(Q)Indoor Environmental Quality
PrerequisitesQPR1 Minimum IAQ Performance
minimum requirements of voluntaryconsensus standard ASHRAE 62-1999.
QPR2 Environmental Tobacco Smoke (ETS) Control
CreditsQ1 Carbon Dioxide (CO2) Monitoring
15050 Cut sheets for CO2 sensors and monitoring system
Q2 Increase Ventilation Effectiveness
Provide for the effective delivery andmixing of fresh air to buildingoccupants to support their health,safety, and comfort.
Q3 Construction IAQ management plan
8/10/2019 CC-0090 LEED Point Summary
9/11
Form CC-0090 Page 9 of 11 Rev.1.23.2010
LOS ANGELES COMMUNITY COLLEGE DISTRICT
DEPARTMENTOFFACILITIESPLANNINGANDDEVELOPMENT
SUSTAINABLEBIUILDINGPROGRAM
LEED POINT SUMMARY
CreditNo.
Credit/Prerequisite Description
onsu
an
Responsible
Supportfrom
Section
Submittals Required
3.1
Prevent indoor air quality problemsresulting from theconstruction/renovation process, tosustain long term tradesman andoccupant health and comfort.
1 & 15
Cut sheets for all filtration media used duringconstruction, highlighting MERV values of at least 13.Provide photographs of construction IAQ managementmeasures such as protection of ducts and on-site storedor installed absorptive materials
3.2
Advanced Plan - reduce constructioncontaminants specify flush out
Q4 Low-Emitting Materials
4.1
Meet VOC limits for adhesives,sealants
allsections Cut sheet and MSDS for each adhesive and eachsealant used in the building, highlighting the VOC limits.
4.2
Meet VOC limits for paints andcoatings - green seal
09900Cut sheet and MSDS for each coating used, highlightingVOC and Chemical component limits.
4.3
Meet CRI's green label for carpetsystems
09681Cut sheets for each carpet system element installed,highlighting VOC limits.
4.4
No added urea-formaldehyde inglues for composite wood products
06402
Cut sheets for each composite wood or agrifiber product
used, highlighting urea-formaldehyde resin limits
8/10/2019 CC-0090 LEED Point Summary
10/11
Form CC-0090 Page 10 of 11 Rev.1.23.2010
LOS ANGELES COMMUNITY COLLEGE DISTRICT
DEPARTMENTOFFACILITIESPLANNINGANDDEVELOPMENT
SUSTAINABLEBIUILDINGPROGRAM
LEED POINT SUMMARY
CreditNo.
Credit/Prerequisite Description
onsu
an
Responsible
Supportfrom
Section
Submittals Required
Q5 Indoor Chemical and Pollutant Source Control
Design to minimize cross-contamination of general occupancy
areas by chemical pollutants. 12484 Cut sheet for the doorway walk off matsQ6 Controllability of Systems
6.1
Provide a minimum of one operablewindow and one lighting controlzone per 200 s.f. for all occupiedareas within 15 feet of the perimeterwall.
08520,08800,13800
Cut sheets for operable windows and lighting controls
6.2
Provide controls for each individualfor airflow, temperature, and lightingfor 50% of the non perimeter,regularly occupied areas.
13800,15050 cut sheets for airflow, temperature, and lighting controls
Q7 Thermal Comfort
7.1
Comply with ASHRAE Standard 55-1992, Addenda 1995 for thermalcomfort
7.2
Install a permanent temperature andhumidity monitoring systemconfigured to provide operatorscontrol over thermal comfortperformance and effectiveness ofhumidification and/ordehumidification systems in thebuilding. 15050
cut sheets for the elements of the permanenttemperature and humidity monitoring system
Q8 Daylight and Views
8/10/2019 CC-0090 LEED Point Summary
11/11
Form CC-0090 Page 11 of 11 Rev.1.23.2010
LOS ANGELES COMMUNITY COLLEGE DISTRICT
DEPARTMENTOFFACILITIESPLANNINGANDDEVELOPMENT
SUSTAINABLEBIUILDINGPROGRAM
LEED POINT SUMMARY
CreditNo.
Credit/Prerequisite Description
onsu
an
Responsible
Supportfrom
Section
Submittals Required
8.1
Diffuse sunlight to reach 75% of allregularly occupied spaces
8.2
Direct line of sight to vision glazing
while seated from 90% of allregularly occupied spaces
TOTAL CORE CREDIT POINTS
(D)
D1 InnovationD2 Innovation
D3 InnovationD4 InnovationD5 LEED Certified Designer