1 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
Civil Engineering Practices, Quality
and LegislationLecture 4
Procurement of Construction Works
Asoka Perera
Professor of Civil Engineering
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
2/54
2 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
ObjectiveTo learn on methods and tools for
management of procurement in projects.Content
Theory related procurement management,
Lecture objective and content
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
3/54
3 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
Project Procurement Managementincludes the processes to purchase oracquire the products, services, orresults needed from outside theproject team to perform the work.
Overview of lecture
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
4/54
4 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
Two perspectives of procurement.The organization can be either the buyer
or seller of the product, service, orresults under a contract.
Project Procurement Managementincludes the contract managementand change control processesrequired to administer contracts orpurchase orders issued by authorizedproject team members.
Overview of lecture
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
5/54
5 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
Project Procurement Management alsoincludes administering any contract
issued by an outside organization (thebuyer) that is acquiring the projectfrom the performing organization (theseller), and administering contractualobligations placed on the project teamby the contract.
Overview of lecture
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
6/54
6 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
Project Procurement Management alsoincludes administering any contract
issued by an outside organization (thebuyer) that is acquiring the projectfrom the performing organization (theseller), and administering contractualobligations placed on the project teamby the contract.
Overview of lecture
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
7/547 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
Overview of lecture
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
8/54
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
9/549 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
The Plan Purchases and Acquisitions processalso includes consideration of potentialsellers, particularly if the buyer wishes toexercise some degree of influence or controlover contracting decisions.Consideration should also be given to who is
responsible for obtaining or holding anyrelevant permits and professional licenses thatmay be required by legislation, regulation, ororganizational policy
1. Plan Purchases and Acquisitions
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
10/5410 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
1. Plan Purchases and Acquisitions
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
11/5411 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
Tools and TechniquesMake-or-Buy Analysis
• a general management technique• The analysis includes both indirect as well as
direct costs.• In a make-or-buy analysis, if a buy decision is to
be made, it also reflects the perspective of theproject team’s organization as well as theimmediate needs of the project.
Expert Judgment
1. Plan Purchases and Acquisitions
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
12/5412 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
Tools and TechniquesExpert Judgment
• To assess the inputs to and outputs from thisprocess.
• To develop or modify the criteria that will be usedto evaluate offers or proposals made by sellers.
• Expert legal judgment may involve the services ofa lawyer to assist with nonstandard procurementterms and conditions.
1. Plan Purchases and Acquisitions
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
13/5413 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
Tools and TechniquesContract Types
• Fixed-price or lump-sum contracts.• Cost-reimbursable contracts - This category of
contract involves payment (reimbursement) to theseller for seller’s actual costs, plus a fee typicallyseller profit.
– Cost-Plus-Fee (CPF) or Cost-Plus-Percentage of Cost(CPPC).
– Cost-Plus-Fixed-Fee (CPFF). – Cost-Plus-Incentive-Fee (CPIF).
•
Time and Material (T&M) contracts.
1. Plan Purchases and Acquisitions
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
14/5414 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
OutputsProcurement Management Plan
• The procurement management plan describeshow the procurement processes will be managedfrom developing procurement documentationthrough contract closure. Several items
Contract Statement of Work• Each contract statement of work defines, for
those items being purchased or acquired, just theportion of the project scope that is includedwithin the related contract.
1. Plan Purchases and Acquisitions
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
15/5415 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
OutputsMake-or-Buy Decisions
• The documented decisions of what projectproducts, services, or results will be either beacquired or will be developed by the project team.
Requested Changes
1. Plan Purchases and Acquisitions
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
16/5416 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
2. Plan Contracting
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
17/5417 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
Inputs – as given in the FigureTools and Techniques
Standard Forms• Standard forms include standard contracts,standard descriptions of procurement terms, non-disclosure agreements, proposal evaluationcriteria checklists, or standardized versions of allparts of the needed bid documents.
Expert Judgment
2. Plan Contracting
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
18/5418 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
OutputsProcurement Documents
• Can use ICTAD, FIDIC – Covered in detail form inthe Procurement and law module
Evaluation CriteriaContract Statement of Work (Updates)
2. Plan Contracting
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
19/54
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
20/5420 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
InputsOrganizational Process Assets
• Organizational process assets, maintain lists orfiles with information on prospective andpreviously qualified sellers, sometimes calledbidders, who can be asked to bid, propose, orquote on work.
Procurement Management PlanProcurement Documents
3. Request Seller Responses
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
21/5421 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
Tools and TechniquesBidder Conference
• Know and bid meeting, pre-bid meeting
Advertising• Very common any news paper
Develop qualified seller list• Registered suppliers list, etc.
3. Request Seller Responses
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
22/5422 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
OutputsQualified Sellers List
Procurement Document PackageProposals
3. Request Seller Responses
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
23/5423 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
The Select Sellers process receives bids orproposals and applies evaluation criteria, asapplicable, to select one or more sellers whoare both qualified and acceptable as a seller.Many decisions
Price or cost can be the primary determinant
Proposals – Technical and FinancialMultiple sources could be required for criticalproducts, servicesSelect a single seller
Establish a negotiating sequence
4. Select Sellers
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
24/54
24 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
4. Select Sellers
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
25/54
25 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
InputsAs indicated in the Figure
Tools and techniquesWeighting System
• A weighting system is a method for quantifyingqualitative data to minimize the effect of personalprejudice on seller selection. Most such systemsinvolve assigning a numerical weight to each ofthe evaluation criteria,
Independent Estimates• Prepare its own independent estimates –
Generally know as “Engineer’s Estimate”
4. Select Sellers
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
26/54
26 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
Tools and techniques Screening System
• Involves establishing minimum requirements ofperformance for one or more of the evaluationcriteria, and can employ a weighting system andindependent estimates.
Contract negotiation• Contract negotiation clarifies the structure and
requirements of the contract so that mutualagreement can be reached prior to signing thecontract.
4. Select Sellers
http://e/Videos/VTC%20-%20PMI%20PMBOK/VTC.PMBOK.Part.4/19.Select%20Sellers/19.02.Tools%20&%20Techniques.movhttp://e/Videos/VTC%20-%20PMI%20PMBOK/VTC.PMBOK.Part.4/19.Select%20Sellers/19.02.Tools%20&%20Techniques.mov
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
27/54
27 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
Tools and techniquesSeller Rating Systems
• Seller rating systems are developed by manyorganizations and use information such as theseller’s past performance, quality ratings,delivery performance, and contractualcompliance.
Expert JudgmentProposal Evaluation Techniques
4. Select Sellers
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
28/54
28 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
OutputsSelected SellersContractContract Management PlanResource AvailabilityProcurement Management Plan (Updates)
Requested Changes
4. Select Sellers
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
29/54
29 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
Both the buyer and the seller administer the contractfor similar purposes.The Contract Administration process ensures that the
seller’s performance meets contractual requirementsand that the buyer performs according to the terms ofthe contract.The legal nature of the contractual relationship makes
it imperative that the project management team isacutely aware of the legal implications of actions takenwhen administering any contract.
5. Contract Administration
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
30/54
30 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
Direct and Manage Project Execution to authorize thecontractor’s work at the appropriate time Performance Reporting to monitor contractor cost,
schedule, and technical performancePerform Quality Control to inspect and verify theadequacy of the contractor’s product Integrated Change Control to assure that changes are
properly approved, and that all those with a need toknow are aware of such changesRisk Monitoring and Control to ensure that risks aremitigated.
5. Contract Administration
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
31/54
31 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
The Contract Administration process reviews anddocuments how well a seller is performing or hasperformed based on the contract and established
corrective actions.Contracts can be amended any time prior to contractclosure by mutual consent, in accordance with thechange control terms of the contract.
5. Contract Administration
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
32/54
32 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
5. Contract Administration
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
33/54
33 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
InputsContractContract Management Plan
Selected SellersPerformance ReportsApproved Change RequestsWork Performance Information
5. Contract Administration
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
34/54
34 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
Tools and TechniquesContract Change Control System
• A contract change control system defines the
process by which the contract can be modified.Buyer-Conducted Performance Review
• A procurement performance review is astructured review of the seller’s progress to
deliver project scope and quality, within cost andon schedule, as compared to the contract.
5. Contract Administration
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
35/54
35 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
Tools and TechniquesInspections and AuditsPerformance Reporting
Payment SystemClaims Administration
• Contested changes and constructive changes are thoserequested changes where the buyer and seller cannot agree
on compensation for the change, or cannot agree that achange has even occurred.
Records Management SystemInformation Technology
5. Contract Administration
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
36/54
36 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
OutputsContract Documentation
• Contract documentation includes, but is not
limited to, the contract, along with all supportingschedules, requested unapproved contractChanges, and approved change requests.
Requested Changes• Requested changes to the project management
plan and its subsidiary plans and othercomponents, such as the project schedule andprocurement management plan, may result from
the Contract Administration process.
5. Contract Administration
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
37/54
37 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
OutputsRecommended Corrective ActionsOrganizational Process Assets (Updates)
• Correspondence• Payment schedules and requests• Seller performance evaluation documentation.
Project Management Plan (Updates)
5. Contract Administration
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
38/54
38 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
The Contract Closure process supports the CloseProject process, since it involves verification that allwork and deliverables were acceptable.
The Contract Closure process also involvesadministrative activities, such as updating records toreflect final results and archiving such information forfuture use.Early termination of a contract is a special case ofcontract closure, and can result from a mutualagreement of the parties or from the default of one ofthe parties.
6. Contract Closure
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
39/54
39 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
6. Contract Closure
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
40/54
40 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
InputsAs indicated
Tools and Techniques Procurement Audits
• A procurement audit is a structured review of theprocurement process from the Plan Purchasesand Acquisitions process through ContractAdministration.
Records Management System
6. Contract Closure
http://e/Videos/VTC%20-%20PMI%20PMBOK/VTC.PMBOK.Part.4/21.Contract%20Closure/21.02.Tools%20&%20Techniques%20-%20Outputs.movhttp://e/Videos/VTC%20-%20PMI%20PMBOK/VTC.PMBOK.Part.4/21.Contract%20Closure/21.02.Tools%20&%20Techniques%20-%20Outputs.mov
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
41/54
41 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
OutputsClosed Contracts
• The buyer, usually through its authorizedcontract administrator, provides the seller withformal written notice that the contract has beencompleted.
Organizational Process Assets (Updates)• Contract file.• Deliverable acceptance.• Lessons learned documentation.
6. Contract Closure
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
42/54
42 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
7.1 IntroductionInstructions to Bidders
Contract and Conditions of Contracts
7 Procurement of Works using ICTAD Standard Contracts
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
43/54
43 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
7 Procurement of Works using ICTAD Standard Contracts
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
44/54
44 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
45/54
45 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
46/54
46 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
47/54
47 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
l l d l
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
48/54
48 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
Ci il E i i P i Q li d L i l i
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
49/54
49 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
Ci il E i i P i Q li d L i l i
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
50/54
50 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
7.2 Instructions to BiddersThe path to form a contract
For invitation for bidsDefinitions
7 Procurement of Works using ICTAD Standard Contracts
Ci il E i i P i Q li d L i l i
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
51/54
51 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
Ci il E i i P i Q li d L i l i
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
52/54
52 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
A. GeneralB. Bidding
Documents
C. Preparation ofbidsD. Submissions of
bids
E. Bid opening andEvaluations
F. Award ofContract
Ci il E i i P ti Q lit d L i l ti
8/18/2019 CE4221 Lecture 4 - Procurement.pdf
53/54
53 © Asoka Perera
Civil Engineering Practices, Quality and Legislation
7.2 Let us see the details from thedocument.
7 Procurement of Works using ICTAD Standard Contracts