Upload
mala
View
30
Download
0
Tags:
Embed Size (px)
DESCRIPTION
Central MA Transmission Study. Long-term Needs and Solutions. Central MA Infrastructure Study. Study Initiated in 2001 Identified Short-term and Long-term Upgrades to ensure reliability of service Study area covers region bounded by: Sandy Pond (NE) Pratts Jct (NW) Carpenter Hill (SW) - PowerPoint PPT Presentation
Citation preview
Central MA Transmission Study
Long-term Needs and Solutions
Central MA Infrastructure Study Study Initiated in 2001 Identified Short-term and Long-term
Upgrades to ensure reliability of service
Study area covers region bounded by: Sandy Pond (NE) Pratts Jct (NW) Carpenter Hill (SW) Northboro Rd (SE)
Geographic Location of Central MA
Short-term Upgrades 18.4 applications approved in
February 2002 63 MVAr Capacitor Bank at Millbury 54 MVAr Capacitor Bank at
Northboro Road Also adjusted taps on Ayer 115-69 kV
transformers In-service for Summer 2002
Long-term Needs in Central MA Needs identified in three main areas
Millbury– 115-69 kV transformer loading– 115 kV voltage
Sandy Pond – 345-115 kV transformer loading
Ayer– 115-69 kV transformer loading– 69 kV voltage
Existing Problems
1. Millbury T1 & T2 Overload for loss of each other
3. Ayer T4 & T6 Overload for loss of each other
2. Sandy Pd T1 & T2 overload for loss of each other
5. Shrewsbury 69 kV Breaker overdutied
4. Ayer 69 kV Area voltage drops below 0.9 pu for K-137 + L-138W DCT contingency
Millbury 115-69 kV Transformers
Loss of either T1 or T2 overloads the remaining small transformer
Recommended Solution to Millbury T1 and T2 Overload
Millbury Station – Replace T1 and T2 (115-69 kV)w/ Larger Transformers Cost: $1.5MIn-Service Year: 2004
Millbury – Replace Two (2) 115-69 kV Autotransformers
Replace T1 and T2 (50 MVA) w/ 56 MVA Transformers
56 MVA
Millbury Substation
56 MVA
Millbury Alternatives Recommendation:
Replace existing T1 and T2 with larger transformers ($1.5M)
Alternatives: Add fourth 115-69 kV transformer into
dedicated bus position ($3.8 M) Add fourth 115-69 kV transformer tapped
off Q-143, relocate I-35 ($2.1 M) Convert 69 kV line X-24 to 115 kV to
unload existing transformers ($14.9 M)
Millbury Solution The recommendation is based on:
Lowest cost Simpler construction compared to
adding a 4th transformer Less permitting risk than 69 kV line
conversion to 115 kV Existing Millbury transformers can
be relocated to Wachusett substation
Ayer 115-69 kV Transformers Loss of either T1 or T2 overloads the
remaining transformer
Recommended Solution to Ayer T4 & T6 Overload
Transfer 69 kV Load from Ayer to Pratts Jct,
and Install two additional 115-69 kV transformers at Pratts Jct
Cost: $1.4M
In-Service Year: 2004
Pratts Jct Sub – Install Two (2) Additional 115-69 kV Autotransformers
56 MVA
56 MVATwo Additional 115-69 kV Autos at PJ
Transfer ½ of Prospect St Load from V-22E to U-21S
Ayer Alternatives Recommendation:
Transfer Prospect Street from 69 kV line V-22E to U-21S; install two (2) 115-69 kV transformers at Pratts Jct and replace eight (8) 69 kV breakers ($2.46 M)
Alternatives: Install (2) 115-69 kV transformers at Ayer
($4.5 M) Convert 69 kV line V-22 to 115 kV to
unload existing transformers ($13.7 M)
Ayer Solution The recommendation is based on:
Lowest cost Simpler construction at Pratts
Junction compared to Ayer Less permitting risk than 69 kV line
conversion to 115 kV
Sandy Pond 345-115 kV Transformers Loss of either T1 or T2 overloads the
remaining transformer Considered installation of new 345-115 kV
transformers at: Sandy Pond Tewksbury Pratts Junction Millbury Wachusett Quinsigamond Junction
Sandy Pond Alternatives Preliminary analysis indicates:
Tewksbury location– not effective at unloading Sandy Pond transformers– does not support Central MA voltage
Millbury location– not effective at unloading Sandy Pond transformers
Sandy Pond 3rd transformer– does not support Central MA voltage– design challenges to prevent loss of two
transformers for a breaker failure contingency Pratts Junction, Wachusett, and
Quinsigamond Junction locations– off-load Sandy Pond transformers– support Central MA voltage – these alternatives identified for further analysis
Sandy Pond 345-115 kV Transformers
The Pratts Junction, Wachusett, and Quinsigamond Junction sites were fully evaluated to provide: A list of associated upgrades based
on thermal and voltage analysis Study grade estimates for all
upgrades associated with each option
Sandy Pond Alternatives Install two (2) 345-115 kV transformers
at existing Pratts Junction substation and associated upgrades
Install two (2) 345-115 kV transformers at existing Wachusett substation and associated upgrades
Install two (2) 345-115 kV transformers at new Quinsigamond Junction substation and associated upgrades
Pratts Jct Alternative - Costs Woodside 69 kV Breaker 2004 0.700 M Pratts Jct Substation 345-115 kV 2006 10.400 M Pratts Jct Substation 115-69 kV 2006 4.390 M Replace Pratts J 115 kV Breakers 2006 1.628 M Replace Pratts J 69 kV Breakers 2006 0.840 M Reconductor N-40 2006 1.180 M Reconductor O-141N 2008 0.750 M Replace W-23E Disconnect 2008 0.020 M Pratts Jct Substation 345 kV 2010 2.700 M Convert N-40/W-23 to 115 kV 2012 18.300 M
Wachusett Alternative - Costs Woodside 69 kV Breaker 2004 0.700 M Wachusett 345-115 Substation 2006 25.750 M Wachusett 115-69 kV 2006 2.530 M Reconductor O-141N 2006 1.500 M Reconductor M-39 2006 1.000 M Reconductor N-40 2006 1.000 M Replace Rolfe Ave Breaker 2006 0.600 M Reconductor W-175 2006 0.475 M W. Boylston Upgrades 2006 0.670 M Replace W-23E Disconnect 2008 0.020 M Reconductor P-142N 2008 0.175 M
Quinsigamond Jct Alternative - Costs
Woodside 69 kV Breaker 2004 0.700 M Quinsigamond Jct Sub 2006 27.700 M Wachusett 115-69 kV Upgrades 2006 4.400 M Replace O-141S Terminal Equip. 2006 0.500 M Reconductor M-39 2006 1.180 M Replace Rolfe Avenue Breaker 2006 0.366 M Reconductor W-175 2006 0.475 M Replace Pratts J 69 kV Breakers 2006 0.840 M Reconductor N-40 2006 1.180 M Replace W-23E Disconnect 2008 0.020 M
Recommended Solution to: Sandy Pd T1 and T2 OverloadLow Voltage in Central MA
Wachusett Station – Install two new 345-115 kV Transformers (448 MVA)
Cost: $25.75M
In-Service Year: 2006
Wachusett – Install Two 345-115 kV Autotransformers (448 MVA)
Wachusett115 kV
P-142
G
G
G
G
G
G
O-141
P-142N
O-141N
A-53
Install 345-115 kV Transformers and Substation at Wachusett
G
G
G
G
G
M-39B-54 G
G
50 MVA
50 MVA
448 MVA
448 MVA
69 kV
Pratts Jct
Greendale Boylston
ReplaceBreakers
345 kV
Sandy Pd
Millbury
343N 314N
G
G
G
G
G
G
Associated Thermal and Voltage Upgrades
Reconductor N-40 & M-39 w/ 795 ACSR
Replace all 69 kV breakers at Pratts Jct for Short Ckt Duty.
Replace Rolfe Ave 115 kV Breaker
Reconductor O-141N [Quinsigimond Jct – Nashua St] w/ 636 ACSS
Reconductor P-142 [Wachusett – W Boylston] w/ 1113 ACSR in 2008
Preferred Sandy Pond Solution The Wachusett alternative was
identified as the preferred alternative based on: Lowest cost Better system performance
compared to Pratts Junction option Less permitting risk than Pratts
Junction option (W-23 conversion) or Quinsigamond Junction (new substation)
Transient Stability Analysis Analysis conducted for the preferred
alternative West Boylston substation becomes
a bulk power system substation High-Speed pilot protection
required for P-142 line from Wachusett to West Boylston
Incremental Cost = $0.890 M Does not change recommendation
Recommended Sandy Pond Solution Wachusett recommended as the preferred
alternative based on: Lowest cost
– Wachusett PW = $32.2 M– Pratts Junction PW = $32.3 M– Quinsigamond Junction PW = $36.1 M
(all estimates are study grade – ±25%) Better system performance compared to
Pratts Junction option Less permitting risk than Pratts Junction
option (W-23 conversion) or Quinsigamond Junction (new substation)
Wachusett Construction Issues Construction Grade estimate
developed for the preferred alternative
Identified wetland issues that limit use of existing Wachusett site
Requires construction of Gas Insulated Substation
Wachusett GIS Layout
Revised Wachusett Cost GIS design increases cost of
Wachusett substation by $5 M (+19%) Revised Comparison of Project Costs
Wachusett (Air): PW = $32.2 M Pratts Junction: PW = $32.3 M Quinsigamond Junction: PW = $36.1 M Wachusett (GIS): PW = $37.2 M
Assessment of Alternatives Wachusett Alternative
PW = $37.2 M NEP land at existing substation Balanced system flows Supports Millbury/Northboro Rd
voltage
Assessment of Alternatives Quinsigamond Junction Alternative
PW = $36.1 M Requires purchase of land
– Higher permitting risk
Balanced system flows Supports Millbury/Northboro Rd voltage Transient Stability analysis and detailed
site engineering may identify additional costs
Assessment of Alternatives Pratts Junction Alternative
PW = $32.3 M NEP land at existing substation Requires conversion of N-40/W-23 circuit from 69
kV to 115 kV– Higher permitting risk– Requires construction of a new 345-115 kV substation
near Millbury if line cannot be permitted Unbalanced system flows
– Eight (8) 115-69 kV transformers at Pratts Junction– Heavy reliance on converted N-40/W-23 circuit to
Northboro Road Support for Millbury/Northboro Rd voltage Transient Stability analysis and detailed site
engineering may identify additional costs
Recommendation The Wachusett location is still the
recommended option Technically superior and less permitting
risk than Pratts Junction option Similar cost and less permitting risk than
Quinsigamond Junction option Changing recommendation will delay
installation by at least one year Additional engineering minimizes
uncertainty with the Wachusett option compared to Pratts Junction or Quinsigamond Junction