CEP-Construction of Railwayoverbridge

Embed Size (px)

Citation preview

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    1/45

    Thanks For Choosing www.engineeringcivil.com

    We hope that this presentation is useful to you.If you also have any presentation which can beuseful to other civil engineers then pleasecontact us via our website.

    Thanks

    KJS

    http://www.engineeringcivil.com/http://www.engineeringcivil.com/
  • 8/13/2019 CEP-Construction of Railwayoverbridge

    2/45

    CONSTRUCTION OF RAILWAY OVERBRIDGE

    AT DOMORIA PULL, JALANDHAR

    BY ISHAN KAUSHAL

    ROLL NO. 1040252

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    3/45

    ROB AT DOMORIA PULL, JALANDHAR

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    4/45

    Details of the Project

    Client Municipal Corporation, Jalandhar

    Construction agency M/S Gammon India Ltd.

    Type of contract Item rate

    Total length of ROB 1.65 Km

    Cost of the project Rs 20 crores

    Contract period 15 months

    Starting date 28-06-2004

    Due to some technical and financial constraints it is being delayed.

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    5/45

    Key Plan Of the Project

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    6/45

    Company Profile

    Gammon India Limited is one of the leading constructioncompanies in India today.

    The company was established by late Mr. J. C. Gammon in1919 as a firm of Civil Engineers & Contractor.

    From arch and bowstring girder bridges to balancedcantilever, prestressed concrete and latest cable-stayed

    bridges, Gammon's capabilities cover the entire spectrum oftechnological advances in bridge engineering.

    Besides designing and building bridges, Gammon has

    achieved perfection in the techniques of launching,underwater concreting development of supporting equipmentlike pneumatic caissons, winches, cables, groutingmachinery etc., and building of enabling structures.

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    7/45

    When I joined.

    All the piling work was over.

    All the pile caps were cast except the one at location DPG7.

    All the pier, pier caps, pedestals were cast except at the

    location DPG7.

    Filling of the backfill in the ramp portions had been done.

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    8/45

    Training Schedule

    11 June to 16 June Understood the Work

    Culture.

    18 June to 21 June Started Collecting Data

    about the Project

    21 June to 21 July Estimation Work And

    Supervision of Site (Pile

    cap)23 July to 10 dec Casting yard (Supervision

    Of pretensioned I-Girders)

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    9/45

    Some Important Specifications

    Number of arms : 7(A,B,C,D,E,FO AND FI)

    Total number of piles : 248 Type of piles : Bored cast in-situ

    Diameter and depth of piles : 1000 mm and 20 m resp.

    Total number of piers : 51

    Number of abutments : 6 Type of superstructure : In-situ deck with pre-

    tensioned I girders andRCC/post-tensioned boxgirders

    Number of box girders spans : 10 Earth work involved : 10,000 m

    Steel used : Fe 415 and Fe 500

    High Tension strands (HT strands) : 15.2 mm diameter (7 ply)

    Bearings : POT PTFE

    Number of I girders : 144

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    10/45

    Equipments Used at Site

    Needle type vibrator(60 mm dia) Concrete pump (56 m/hr)

    Gantry girder( 60 ton) Transit mixer (7 m capacity)

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    11/45

    Equipments Used at Site

    Slump Cone JCB

    Batching Plant

    PrestressingPump

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    12/45

    Equipments Used at Site

    Pipeline Bucket (0.5 m capacity)

    Hydra crane( 3 ton)

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    13/45

    PROJECT NO. 1

    SUPERVISION OF SUBSTRUCTURE

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    14/45

    Foundation : Piles

    Piles are long slender members that carry and transfer the

    load of the structure to the ground located at some depth

    below the ground and the earth surrounding the piles.

    Bored cast in-situ friction RCC piles of diameter 1000 mm.

    M35 grade of concrete was used at our site.

    Average depth of the piles was 20 m.

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    15/45

    Estimation of Steel in Piles

    Steel quantity

    Dia of one pile = 1000 mm

    Clear cover = 75 mm

    Dia of the bar used for pile rings = 10 mm

    Dia of pile ring, d = 1000- 2*75 = 850 mm

    Circumference of pile ring = *d = *850 =2.669 mNo. of rings in the pile = 100

    So total length of 10 mm bar = 100*2.669 = 266.9 m

    Vertical bars

    Diameter = 20 mm

    Length of one single bar from top to bottom of the pile = 20.9 mNumber of the bars = 15

    So total length = 15*20.9 = 313.5 m

    Total weight of steel used in one pile = 10/162266.9 + 20/162*313.5

    = 938.8 kg

    For pile group having 4 piles total weight of steel = 4*938.8 = 3755.3 kg

    For pile group having 6 piles total weight of steel = 6*938.8 = 5632.96 kg

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    16/45

    Pile Cap

    Structural elements that tie a group of piles together.

    Used to transmit forces from piers to the pile foundations.

    At my site I studied the construction of the pile cap namedDPG7.

    It was constructed to connect 9piles.

    Concrete mix of M35was used in the pile cap.

    Total of 93.2 mof concrete was used in this pile cap.

    Height of the pile cap was 1.75 m.

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    17/45

    Plan of the pile cap DPG7

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    18/45

    Reinforcement Detailing of the Pile Cap

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    19/45

    Elevation of the Pile Cap

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    20/45

    Bar bending Schedule

    Sr. no. Bar

    mark

    Bar

    dia(mm)

    Specifications Type

    1 b1 25 150 c/c

    2 b2 25 110 c/c

    3 b3 16 110 c/c

    4 b4 16 150 c/c

    5 b5 12 sets of 7 stirrups @250 c/c

    6 b6 16 2 sets of 6 bars

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    21/45

    Estimation of the Pile Cap DPG7

    Shuttering quantity of pile cap

    Dimensions of the pile cap are shown in the figure

    Height of the pile cap = 1.75 m

    Area of shuttering = 2*1.75*(3388+3388+847+847+2998+3000+790)

    = 54.403 m

    Concrete quantity

    Volume of concrete to be used = ((7.693*7)-0.5929)*1.75

    = 93.2 m

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    22/45

    Concrete Mix Proportion for Pile Cap

    Different grades of concrete were used for the bridgeconstruction.

    M35was used for the pile cap.

    Steel used : Fe 415.

    Cement used : Vikram cement (OPC 53 grade)

    Aggregates used : 10 mm, 20 mm and sand.

    Admixture used : FORSOC CONPLAST SP 430.

    Cement : Sand : Coarse Aggregate = 1 : 1.36 : 3.24

    Cement W/C

    Ratio

    Water Sand 20 mm 10 mm Admixture

    400

    kg/m

    0.37 148

    kg/m

    684

    kg/m

    592.5

    kg/m

    592.5

    kg/m

    0.4

    1 0.37 1.36 1.94 1.3 0.001

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    23/45

    Pier Cap

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    24/45

    Estimation of the pier cap

    All dimensions in mm

    Concrete quantity

    Ar1 = 9477600 mm = 9.477 m

    Ar2 = 5.4882 m

    Total area = 9.477+5.4882 = 14.96 m

    Thickness of the pier cap = 3600 mm

    So total volume of concrete to be used = 14.96*3.6 = 53.8 m

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    25/45

    All dimensions in mm

    Shuttering quantity

    A1 = 2*14.96 = 29.92 m

    A2 = 4203.4*3600 = 15.132 mA3 = 600*3600*2 = 4.32 m

    A4 = 3018.87*3600 = 10.868 m

    A5 = 100*3600*2 = 0.72 m

    Total surface area for shuttering = A1+A2+A3+A4+A5 = 60.96 m

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    26/45

    PROJECT NO. 2

    SUPERVISION OF THE

    SUPERSTRUCTURE

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    27/45

    Pretensioned I-Girder

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    28/45

    Cross section of the I-girder

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    29/45

    Methodology for the construction of I-Girder:

    1. Preparing the shuttering:

    Bearing plates Dowel bars

    Groove made for bearings

    Bearing

    plate

    dowels

    grease

    Dowel bars200 mm length

    Outer dia 50 mm

    Inner dia 22 mm

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    30/45

    2. Lowering of the reinforcement cage:

    Gantry girder : 60 ton and 35 ton

    3. Cable threading:

    Reinforcement

    cage

    cables

    Wedges

    and

    barrels

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    31/45

    4. Stressing:

    Least count of the pump : 5 kg/cm.

    5. Closing of the side shutters

    6. Concreting:

    Automatic batching plant

    Needle type vibrator : 60 mm dia

    Concrete pump : 56 m/hr

    7. Deshuttering:

    After 24 hrs

    Concrete coming out of

    the pipe line

    Cement W/C

    Ratio

    Water Sand 20 mm 10 mm Admixture

    435

    kg/m

    0.30 130.5

    kg/m

    652

    kg/m

    741

    kg/m

    494

    kg/m

    0.8%

    Deshuttered beam

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    32/45

    8. Destressing

    Using the grinder.

    9. Lifting of the girders10. Curing

    For next 25 days at least.Hessian

    clothCables

    after

    cutting at

    top

    Cables after

    cutting at bottom

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    33/45

    Prestressed Concrete

    Prestressed concrete is basically concrete in which internal stresses of a

    suitable magnitude and distribution are introduced so that the stresses

    resulting from external loads are counteracted to a desired degree.

    Concrete is strong in compression but weak in tension. The tensile strength

    of concrete is about one-tenth of its compressive strength. Since concrete is

    weak in tension, an R.C.C beam at times develops minute cracks in concrete

    on tension side of the beam, even when the stress developed in tensile steel

    is much less than its permissible value.

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    34/45

    Prestressing has two types:-

    1. Pre-tensioning.

    2. Post-tensioning.

    Pre-tensioning:

    In the pretensioning the tendons are first tensioned between rigid anchor

    blocks cast on the ground or in a column or unit mould type tensioning bed,

    prior to the casting of concrete in the moulds. The tendons comprising

    individual wires or strands are stretched with constant or variable

    eccentricity with tendon anchorage at one end and jacks at the other end.

    With the forms in place, the concrete is cast around the stressed tendon.

    Post-tensioning:

    In post tensioning the concrete units are first cast by incorporating ducts orgrooves to house the tendons. When the concrete attains sufficient strength,

    the high tensile wires are tensioned by means of means of jack bearing on

    the end face of the member and anchored by wedges or nuts

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    35/45

    Methodology for pre-tensioning of the I-girder:

    1. Laying of cables2. PVC pipes are used for debonding of the cables.

    3. Cables are locked using the wedges and barrels. These wedges and

    barrels provide such arrangement that cable can come out of it, but

    cant go back.

    4. Stressing

    Monostrand

    hydraulic

    jack

    Cables

    Wedges and

    barrels

    Prestressing pump

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    36/45

    Stressing report:

    GIRDER MARK P1-P2 (10 AND 11)For strand NO. 1 TO 21

    ELONGATION (mm) MIN. = 292 MODIFIED= 307 MAX. = 322

    PRESSURE (kg/cm) MIN. = 382 MODIFIED= 402 MAX. = 422

    For strand No. 22 and 23ELONGATION (mm) MIN. = 273 MODIFIED= 287 MAX. = 301

    PRESSURE (kg/cm) MIN. = 382 MODIFIED= 402 MAX. = 422

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    37/45

    PRESSURE

    (kg/cm)

    0 50 100 150 200 250 300 350 402 Elg Reqd 100 reading Total Elg Zero correction Net Elg

    Strand no. 1 20 40 75 115 160 190 235 265 300 307 75 225 85 310

    2 20 50 75 120 160 190 240 270 310 307 75 225 85 310

    3 15 50 85 120 160 195 235 270 315 307 85 230 75 305

    4 20 48 80 120 155 190 220 270 310 307 80 230 75 305

    5 10 25 65 105 145 180 225 260 300 307 65 235 80 315

    6 20 45 80 120 160 200 245 225 320 307 80 240 80 320

    7 20 80 120 160 200 235 280 320 360 307 120 240 80 320

    8 20 70 100 140 175 225 265 310 360 307 100 260 65 325

    9 20 65 105 145 180 225 260 305 350 307 105 245 75 320

    10 32 70 115 150 185 230 280 320 365 307 115 250 70 320

    11 25 75 110 155 195 230 275 310 345 307 110 235 85 320

    12 25 50 90 125 165 200 245 285 320 307 90 230 75 305

    13 20 55 75 130 155 200 245 280 315 307 75 240 80 320

    14 20 40 75 115 150 190 230 265 305 307 75 230 75 305

    15 25 55 100 135 175 210 250 285 330 307 100 230 75 305

    16 10 50 90 130 175 200 240 280 315 307 90 225 85 310

    17 25 65 100 140 180 215 255 295 330 307 100 230 80 310

    18 20 80 120 155 200 240 280 320 355 307 120 235 80 315

    19 35 80 115 155 190 235 275 310 350 307 115 235 75 310

    20 25 75 115 150 190 230 270 310 350 307 115 235 75 310

    21 25 65 105 145 185 225 265 300 335 307 105 230 80 310

    22 25 50 82 120 150 185 220 255 305 287 85 220 68 288

    23 25 40 75 105 140 175 210 245 295 287 75 220 65 285

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    38/45

    Box Girder

    I-girders can be used only for the spans smaller than 20-25 m or which are

    not curved. For curved spans and spans which are greater than 20-25 m, box

    girders are used.

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    39/45

    Cross-section of the box girder near the support

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    40/45

    Methodology for the construction of post-tensioned box girder:

    1. Constructing the temporary foundation for the temporary structure forsupporting the box girder shuttering.

    2. Erecting the trestles.

    3. Placing the shuttering.

    4. Placing the reinforcement.

    5. Passing the cables through sheathing pipes.

    6. Concreting.

    7. Curing.

    8. Constructing the deck slab.

    9. Post-tensioning.10. Grouting.

    11. Removing the trestles.

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    41/45

    Safety Requirements

    1. Training the workers.

    2. Providing the first aid.

    3. List of nearby hospitals.

    4. Safety manual.5. Banners.

    6. Using the safety equipments.

    7. Providing the vehicle.

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    42/45

    Problems Faced at Site

    1. Sometime the strength of the girders didnt come on time.

    Remedy:

    First off all, aggregates were washed before using them. It would

    increase the rate of bond formation between the aggregates and

    cement.

    also if use a higher grade of cement, I will help in early achievement

    of strength.

    2. While transporting the concrete by transit mixers, traffic created a big

    problem.Remedy:

    Three transit mixers were used at time to reduce the time gap.

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    43/45

    Problems Faced at Site

    3. Power failure and batching plant failure delayed the processes.

    Remedy:

    Proper and regular maintenance helped to reduce this problem.

    4. While shifting the I-girders, traffic was a problem.Remedy:

    the girders were shifted at night to avoid this problem.

    5. In summer days, water for curing dried too early.

    Remedy:

    Hessian cloth was used to retain water for longer period. Continuous

    curing was also done.

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    44/45

    TH NKS

  • 8/13/2019 CEP-Construction of Railwayoverbridge

    45/45

    End Note This presentation is for educational use

    can use this as part of reference material

    and it should not be used directly as yourown presentation.

    For more such presentation log on to www.engineeringcivil.com

    http://www.engineeringcivil.com/http://www.engineeringcivil.com/