Upload
vish5610
View
217
Download
0
Embed Size (px)
Citation preview
8/13/2019 CEP-Construction of Railwayoverbridge
1/45
Thanks For Choosing www.engineeringcivil.com
We hope that this presentation is useful to you.If you also have any presentation which can beuseful to other civil engineers then pleasecontact us via our website.
Thanks
KJS
http://www.engineeringcivil.com/http://www.engineeringcivil.com/8/13/2019 CEP-Construction of Railwayoverbridge
2/45
CONSTRUCTION OF RAILWAY OVERBRIDGE
AT DOMORIA PULL, JALANDHAR
BY ISHAN KAUSHAL
ROLL NO. 1040252
8/13/2019 CEP-Construction of Railwayoverbridge
3/45
ROB AT DOMORIA PULL, JALANDHAR
8/13/2019 CEP-Construction of Railwayoverbridge
4/45
Details of the Project
Client Municipal Corporation, Jalandhar
Construction agency M/S Gammon India Ltd.
Type of contract Item rate
Total length of ROB 1.65 Km
Cost of the project Rs 20 crores
Contract period 15 months
Starting date 28-06-2004
Due to some technical and financial constraints it is being delayed.
8/13/2019 CEP-Construction of Railwayoverbridge
5/45
Key Plan Of the Project
8/13/2019 CEP-Construction of Railwayoverbridge
6/45
Company Profile
Gammon India Limited is one of the leading constructioncompanies in India today.
The company was established by late Mr. J. C. Gammon in1919 as a firm of Civil Engineers & Contractor.
From arch and bowstring girder bridges to balancedcantilever, prestressed concrete and latest cable-stayed
bridges, Gammon's capabilities cover the entire spectrum oftechnological advances in bridge engineering.
Besides designing and building bridges, Gammon has
achieved perfection in the techniques of launching,underwater concreting development of supporting equipmentlike pneumatic caissons, winches, cables, groutingmachinery etc., and building of enabling structures.
8/13/2019 CEP-Construction of Railwayoverbridge
7/45
When I joined.
All the piling work was over.
All the pile caps were cast except the one at location DPG7.
All the pier, pier caps, pedestals were cast except at the
location DPG7.
Filling of the backfill in the ramp portions had been done.
8/13/2019 CEP-Construction of Railwayoverbridge
8/45
Training Schedule
11 June to 16 June Understood the Work
Culture.
18 June to 21 June Started Collecting Data
about the Project
21 June to 21 July Estimation Work And
Supervision of Site (Pile
cap)23 July to 10 dec Casting yard (Supervision
Of pretensioned I-Girders)
8/13/2019 CEP-Construction of Railwayoverbridge
9/45
Some Important Specifications
Number of arms : 7(A,B,C,D,E,FO AND FI)
Total number of piles : 248 Type of piles : Bored cast in-situ
Diameter and depth of piles : 1000 mm and 20 m resp.
Total number of piers : 51
Number of abutments : 6 Type of superstructure : In-situ deck with pre-
tensioned I girders andRCC/post-tensioned boxgirders
Number of box girders spans : 10 Earth work involved : 10,000 m
Steel used : Fe 415 and Fe 500
High Tension strands (HT strands) : 15.2 mm diameter (7 ply)
Bearings : POT PTFE
Number of I girders : 144
8/13/2019 CEP-Construction of Railwayoverbridge
10/45
Equipments Used at Site
Needle type vibrator(60 mm dia) Concrete pump (56 m/hr)
Gantry girder( 60 ton) Transit mixer (7 m capacity)
8/13/2019 CEP-Construction of Railwayoverbridge
11/45
Equipments Used at Site
Slump Cone JCB
Batching Plant
PrestressingPump
8/13/2019 CEP-Construction of Railwayoverbridge
12/45
Equipments Used at Site
Pipeline Bucket (0.5 m capacity)
Hydra crane( 3 ton)
8/13/2019 CEP-Construction of Railwayoverbridge
13/45
PROJECT NO. 1
SUPERVISION OF SUBSTRUCTURE
8/13/2019 CEP-Construction of Railwayoverbridge
14/45
Foundation : Piles
Piles are long slender members that carry and transfer the
load of the structure to the ground located at some depth
below the ground and the earth surrounding the piles.
Bored cast in-situ friction RCC piles of diameter 1000 mm.
M35 grade of concrete was used at our site.
Average depth of the piles was 20 m.
8/13/2019 CEP-Construction of Railwayoverbridge
15/45
Estimation of Steel in Piles
Steel quantity
Dia of one pile = 1000 mm
Clear cover = 75 mm
Dia of the bar used for pile rings = 10 mm
Dia of pile ring, d = 1000- 2*75 = 850 mm
Circumference of pile ring = *d = *850 =2.669 mNo. of rings in the pile = 100
So total length of 10 mm bar = 100*2.669 = 266.9 m
Vertical bars
Diameter = 20 mm
Length of one single bar from top to bottom of the pile = 20.9 mNumber of the bars = 15
So total length = 15*20.9 = 313.5 m
Total weight of steel used in one pile = 10/162266.9 + 20/162*313.5
= 938.8 kg
For pile group having 4 piles total weight of steel = 4*938.8 = 3755.3 kg
For pile group having 6 piles total weight of steel = 6*938.8 = 5632.96 kg
8/13/2019 CEP-Construction of Railwayoverbridge
16/45
Pile Cap
Structural elements that tie a group of piles together.
Used to transmit forces from piers to the pile foundations.
At my site I studied the construction of the pile cap namedDPG7.
It was constructed to connect 9piles.
Concrete mix of M35was used in the pile cap.
Total of 93.2 mof concrete was used in this pile cap.
Height of the pile cap was 1.75 m.
8/13/2019 CEP-Construction of Railwayoverbridge
17/45
Plan of the pile cap DPG7
8/13/2019 CEP-Construction of Railwayoverbridge
18/45
Reinforcement Detailing of the Pile Cap
8/13/2019 CEP-Construction of Railwayoverbridge
19/45
Elevation of the Pile Cap
8/13/2019 CEP-Construction of Railwayoverbridge
20/45
Bar bending Schedule
Sr. no. Bar
mark
Bar
dia(mm)
Specifications Type
1 b1 25 150 c/c
2 b2 25 110 c/c
3 b3 16 110 c/c
4 b4 16 150 c/c
5 b5 12 sets of 7 stirrups @250 c/c
6 b6 16 2 sets of 6 bars
8/13/2019 CEP-Construction of Railwayoverbridge
21/45
Estimation of the Pile Cap DPG7
Shuttering quantity of pile cap
Dimensions of the pile cap are shown in the figure
Height of the pile cap = 1.75 m
Area of shuttering = 2*1.75*(3388+3388+847+847+2998+3000+790)
= 54.403 m
Concrete quantity
Volume of concrete to be used = ((7.693*7)-0.5929)*1.75
= 93.2 m
8/13/2019 CEP-Construction of Railwayoverbridge
22/45
Concrete Mix Proportion for Pile Cap
Different grades of concrete were used for the bridgeconstruction.
M35was used for the pile cap.
Steel used : Fe 415.
Cement used : Vikram cement (OPC 53 grade)
Aggregates used : 10 mm, 20 mm and sand.
Admixture used : FORSOC CONPLAST SP 430.
Cement : Sand : Coarse Aggregate = 1 : 1.36 : 3.24
Cement W/C
Ratio
Water Sand 20 mm 10 mm Admixture
400
kg/m
0.37 148
kg/m
684
kg/m
592.5
kg/m
592.5
kg/m
0.4
1 0.37 1.36 1.94 1.3 0.001
8/13/2019 CEP-Construction of Railwayoverbridge
23/45
Pier Cap
8/13/2019 CEP-Construction of Railwayoverbridge
24/45
Estimation of the pier cap
All dimensions in mm
Concrete quantity
Ar1 = 9477600 mm = 9.477 m
Ar2 = 5.4882 m
Total area = 9.477+5.4882 = 14.96 m
Thickness of the pier cap = 3600 mm
So total volume of concrete to be used = 14.96*3.6 = 53.8 m
8/13/2019 CEP-Construction of Railwayoverbridge
25/45
All dimensions in mm
Shuttering quantity
A1 = 2*14.96 = 29.92 m
A2 = 4203.4*3600 = 15.132 mA3 = 600*3600*2 = 4.32 m
A4 = 3018.87*3600 = 10.868 m
A5 = 100*3600*2 = 0.72 m
Total surface area for shuttering = A1+A2+A3+A4+A5 = 60.96 m
8/13/2019 CEP-Construction of Railwayoverbridge
26/45
PROJECT NO. 2
SUPERVISION OF THE
SUPERSTRUCTURE
8/13/2019 CEP-Construction of Railwayoverbridge
27/45
Pretensioned I-Girder
8/13/2019 CEP-Construction of Railwayoverbridge
28/45
Cross section of the I-girder
8/13/2019 CEP-Construction of Railwayoverbridge
29/45
Methodology for the construction of I-Girder:
1. Preparing the shuttering:
Bearing plates Dowel bars
Groove made for bearings
Bearing
plate
dowels
grease
Dowel bars200 mm length
Outer dia 50 mm
Inner dia 22 mm
8/13/2019 CEP-Construction of Railwayoverbridge
30/45
2. Lowering of the reinforcement cage:
Gantry girder : 60 ton and 35 ton
3. Cable threading:
Reinforcement
cage
cables
Wedges
and
barrels
8/13/2019 CEP-Construction of Railwayoverbridge
31/45
4. Stressing:
Least count of the pump : 5 kg/cm.
5. Closing of the side shutters
6. Concreting:
Automatic batching plant
Needle type vibrator : 60 mm dia
Concrete pump : 56 m/hr
7. Deshuttering:
After 24 hrs
Concrete coming out of
the pipe line
Cement W/C
Ratio
Water Sand 20 mm 10 mm Admixture
435
kg/m
0.30 130.5
kg/m
652
kg/m
741
kg/m
494
kg/m
0.8%
Deshuttered beam
8/13/2019 CEP-Construction of Railwayoverbridge
32/45
8. Destressing
Using the grinder.
9. Lifting of the girders10. Curing
For next 25 days at least.Hessian
clothCables
after
cutting at
top
Cables after
cutting at bottom
8/13/2019 CEP-Construction of Railwayoverbridge
33/45
Prestressed Concrete
Prestressed concrete is basically concrete in which internal stresses of a
suitable magnitude and distribution are introduced so that the stresses
resulting from external loads are counteracted to a desired degree.
Concrete is strong in compression but weak in tension. The tensile strength
of concrete is about one-tenth of its compressive strength. Since concrete is
weak in tension, an R.C.C beam at times develops minute cracks in concrete
on tension side of the beam, even when the stress developed in tensile steel
is much less than its permissible value.
8/13/2019 CEP-Construction of Railwayoverbridge
34/45
Prestressing has two types:-
1. Pre-tensioning.
2. Post-tensioning.
Pre-tensioning:
In the pretensioning the tendons are first tensioned between rigid anchor
blocks cast on the ground or in a column or unit mould type tensioning bed,
prior to the casting of concrete in the moulds. The tendons comprising
individual wires or strands are stretched with constant or variable
eccentricity with tendon anchorage at one end and jacks at the other end.
With the forms in place, the concrete is cast around the stressed tendon.
Post-tensioning:
In post tensioning the concrete units are first cast by incorporating ducts orgrooves to house the tendons. When the concrete attains sufficient strength,
the high tensile wires are tensioned by means of means of jack bearing on
the end face of the member and anchored by wedges or nuts
8/13/2019 CEP-Construction of Railwayoverbridge
35/45
Methodology for pre-tensioning of the I-girder:
1. Laying of cables2. PVC pipes are used for debonding of the cables.
3. Cables are locked using the wedges and barrels. These wedges and
barrels provide such arrangement that cable can come out of it, but
cant go back.
4. Stressing
Monostrand
hydraulic
jack
Cables
Wedges and
barrels
Prestressing pump
8/13/2019 CEP-Construction of Railwayoverbridge
36/45
Stressing report:
GIRDER MARK P1-P2 (10 AND 11)For strand NO. 1 TO 21
ELONGATION (mm) MIN. = 292 MODIFIED= 307 MAX. = 322
PRESSURE (kg/cm) MIN. = 382 MODIFIED= 402 MAX. = 422
For strand No. 22 and 23ELONGATION (mm) MIN. = 273 MODIFIED= 287 MAX. = 301
PRESSURE (kg/cm) MIN. = 382 MODIFIED= 402 MAX. = 422
8/13/2019 CEP-Construction of Railwayoverbridge
37/45
PRESSURE
(kg/cm)
0 50 100 150 200 250 300 350 402 Elg Reqd 100 reading Total Elg Zero correction Net Elg
Strand no. 1 20 40 75 115 160 190 235 265 300 307 75 225 85 310
2 20 50 75 120 160 190 240 270 310 307 75 225 85 310
3 15 50 85 120 160 195 235 270 315 307 85 230 75 305
4 20 48 80 120 155 190 220 270 310 307 80 230 75 305
5 10 25 65 105 145 180 225 260 300 307 65 235 80 315
6 20 45 80 120 160 200 245 225 320 307 80 240 80 320
7 20 80 120 160 200 235 280 320 360 307 120 240 80 320
8 20 70 100 140 175 225 265 310 360 307 100 260 65 325
9 20 65 105 145 180 225 260 305 350 307 105 245 75 320
10 32 70 115 150 185 230 280 320 365 307 115 250 70 320
11 25 75 110 155 195 230 275 310 345 307 110 235 85 320
12 25 50 90 125 165 200 245 285 320 307 90 230 75 305
13 20 55 75 130 155 200 245 280 315 307 75 240 80 320
14 20 40 75 115 150 190 230 265 305 307 75 230 75 305
15 25 55 100 135 175 210 250 285 330 307 100 230 75 305
16 10 50 90 130 175 200 240 280 315 307 90 225 85 310
17 25 65 100 140 180 215 255 295 330 307 100 230 80 310
18 20 80 120 155 200 240 280 320 355 307 120 235 80 315
19 35 80 115 155 190 235 275 310 350 307 115 235 75 310
20 25 75 115 150 190 230 270 310 350 307 115 235 75 310
21 25 65 105 145 185 225 265 300 335 307 105 230 80 310
22 25 50 82 120 150 185 220 255 305 287 85 220 68 288
23 25 40 75 105 140 175 210 245 295 287 75 220 65 285
8/13/2019 CEP-Construction of Railwayoverbridge
38/45
Box Girder
I-girders can be used only for the spans smaller than 20-25 m or which are
not curved. For curved spans and spans which are greater than 20-25 m, box
girders are used.
8/13/2019 CEP-Construction of Railwayoverbridge
39/45
Cross-section of the box girder near the support
8/13/2019 CEP-Construction of Railwayoverbridge
40/45
Methodology for the construction of post-tensioned box girder:
1. Constructing the temporary foundation for the temporary structure forsupporting the box girder shuttering.
2. Erecting the trestles.
3. Placing the shuttering.
4. Placing the reinforcement.
5. Passing the cables through sheathing pipes.
6. Concreting.
7. Curing.
8. Constructing the deck slab.
9. Post-tensioning.10. Grouting.
11. Removing the trestles.
8/13/2019 CEP-Construction of Railwayoverbridge
41/45
Safety Requirements
1. Training the workers.
2. Providing the first aid.
3. List of nearby hospitals.
4. Safety manual.5. Banners.
6. Using the safety equipments.
7. Providing the vehicle.
8/13/2019 CEP-Construction of Railwayoverbridge
42/45
Problems Faced at Site
1. Sometime the strength of the girders didnt come on time.
Remedy:
First off all, aggregates were washed before using them. It would
increase the rate of bond formation between the aggregates and
cement.
also if use a higher grade of cement, I will help in early achievement
of strength.
2. While transporting the concrete by transit mixers, traffic created a big
problem.Remedy:
Three transit mixers were used at time to reduce the time gap.
8/13/2019 CEP-Construction of Railwayoverbridge
43/45
Problems Faced at Site
3. Power failure and batching plant failure delayed the processes.
Remedy:
Proper and regular maintenance helped to reduce this problem.
4. While shifting the I-girders, traffic was a problem.Remedy:
the girders were shifted at night to avoid this problem.
5. In summer days, water for curing dried too early.
Remedy:
Hessian cloth was used to retain water for longer period. Continuous
curing was also done.
8/13/2019 CEP-Construction of Railwayoverbridge
44/45
TH NKS
8/13/2019 CEP-Construction of Railwayoverbridge
45/45
End Note This presentation is for educational use
can use this as part of reference material
and it should not be used directly as yourown presentation.
For more such presentation log on to www.engineeringcivil.com
http://www.engineeringcivil.com/http://www.engineeringcivil.com/