Upload
orlando-spires
View
215
Download
0
Tags:
Embed Size (px)
Citation preview
CERT UPDATE TO GUILFORD COUNTY
ENERGY AUDITS OF
•BELLE MEADE BUILDING•BB&T BUILDING•HIGH POINT COURTHOUSE & DETENTION CENTER•HIGH POINT PUBLIC HEALTH BUILDING
APRIL 7, 2009
WORK TO DATE
• GATHERED ENERGY USE DATA
• REVIEWED EXISTING BUILDING CONDITIONS
• IDENTIFIED AND ANALYZED SEVERAL ENERGY CONSERVATION MEASURES
NORTH ELEVATION
GREENSBORO MENTAL HEALTH GREENSBORO MENTAL HEALTH BUILDINGBUILDING
• Building location Greensboro
• Built year 1991
• Total Area 99,935 ft2
SOUTHEAST CORNER
• In terms of operations the building is divided into three section:
– Main building: 87,421ft2;
12hr/6 days/week
– Computer: 6030ft2; 24hr/7days/week
– North Wing : 6030ft2; 24hr/7days/week
• Each sector has its own AC which runs 24hr/7days/week
Energy Source
Amount Consumed (BTU)
Cost ($)
Electricity 9,966,588,480 149,443.98
Natural gas 1,882,800,000 25,887.94
Energy Cost Index =$1.75/ft2/year
Energy Use Index =118.57/kBTU/ft2/year
ANNUAL ENERGY CONSUMPTIONANNUAL ENERGY CONSUMPTION
20082008
RETROFIT SAVINGS OPTIONSRETROFIT SAVINGS OPTIONS
Fixture Type # of Fixtures # of Lamps/FixtureA 567 3-T12 40 wattB 161 2-T12 40 wattC 83 2-T12 40 watt
COMMON LIGHTING FIXTURESCOMMON LIGHTING FIXTURES
Current Practice: T12, 40 watt, magnetic ballast; 3 different fixtures: A, B, and C Recommended: T8 32 watts; Electronic ballast
OPTION 1:OPTION 1: REPLACE EXISTING LAMP REPLACE EXISTING LAMP
WITH ENERGY EFFICIENT LAMPWITH ENERGY EFFICIENT LAMP
Implementation CostFixture type A = $49.00/fixtureFixture types B & C =$32.00/fixtureTotal implementation cost = $35,737.00Simple payback period = 4.5 yearsDollar Savings from Lamp Type A, B, &
C =$7,867/yr
RETROFIT SAVINGS FROM HVACRETROFIT SAVINGS FROM HVAC
Option 2B: Changing from Fixed to Variable Frequency Drive
•Estimated Savings: $ 4,335/year
•Estimated Cost: $ 10,500•Simple payback period: 2.4 yearsThis analysis assumed that the City will
provide their own labor.
Option 2A: Turn of Main Building AC from 10:00pm to 6:00am Weekends & Holidays•Estimated Savings: $ 12,315/year•Estimated Cost: $ 0.00•Simple payback period: Immediate paybackThis analysis assumed that the City will provide their own labor.
Current practice: The fan is being driven by 75 hp motor, efficiency of 0.925 Recommended: Replace the 75 hp motor with efficient motor of efficiency 0.955 Assume an average load factor (LF) of 0.8, operate for 8,760hrs/year
•Estimated Savings: $983/year•Estimated Cost: $4,505•Simple payback period: 4.6years•This analysis assumed that the City will provide their own labor.
OPtion2C: Replace the Existing Motor with OPtion2C: Replace the Existing Motor with Energy Efficient MotorEnergy Efficient Motor
SAVINGS FROM RESET CHILLED WATER SAVINGS FROM RESET CHILLED WATER TEMPERATURETEMPERATURE
Option 3: R eset Chilled Water Temperature
Estimated Savings: $ 2,937/yearEstimated Cost: $ 3,000Simple payback period: 1 yearThis analysis assumed that the City will provide
their own labor.
Conservation Measure Cost Savings(KWh)/yr Savings/yr
Replacing T12 with T8 Lamps
$ 35,737 131,117 $ 7,867
*Replacing 75 hp motor with energy efficient motor
$ 4,505* 16,383* $ 983*
*Using VFD for 75hp motor instead of fixed drive
$ 10,500* 72250* $ 4,335*
Shutting AC unit for the Main building from 10pm-6pm and weekends
205250 $ 12,315
Reset Chiller water temperature
$ 3,000 48,950 $ 2,937
Total 38,737 385,317 $ 23,119
Percentage Savings per year = 13%
SUMMARYSUMMARY
GREENSBORO BB&T BUILDINGGREENSBORO BB&T BUILDING
• Building location Greensboro
• Built year 1973• Total Area 64,301 ft2
Energy Source Cost ($)Electricity $95,000Natural gas $43,000
Energy Cost Index =$2.15/ft2/year
•Estimated Savings: $ 10,884/year•Estimated Cost: $ 58,140•Simple payback period:
5.3 years
Floor Total Number of bulbs
Fixtures
Basement 236 155First 522 300Second 742 306Third 770 201Forth 978 511Total 3230 1,473
OPTION 1: REPLACE EXISTING LAMP OPTION 1: REPLACE EXISTING LAMP
WITH ENERGY EFFICIENT LAMPWITH ENERGY EFFICIENT LAMP
RETROFIT SAVINGS OPTIONSRETROFIT SAVINGS OPTIONS
Option2: Reset chilled water temperatureEstimated Savings: $ 2,670/yearEstimated Cost: $ 3,000Simple payback period: 1.2 yearsOption 3:Reset Hot water
temperatureEstimated savings: $750Estimated cost: $3,000 Estimated pay back: 4 years
RETROFIT SAVINGS FROM HVACRETROFIT SAVINGS FROM HVAC
Conservation Measure Cost Savings(KWh)/yr
Dollar Savings/yr
Replacing T12 with T8 Lamps
$58,140 181,400 $ 10,884
Reset Chiller water temperature
$ 3,000 44,500 $ 2,670
Reset Hot water temperature
$ 3,000 15,500 $ 750
Total $67,140 241,400 $14,304
SUMMARYSUMMARY
Percentage Savings per year = 8%
HIGH POINT COURTHOUSE & JAIL HIGH POINT COURTHOUSE & JAIL BUILDINGBUILDING
High-Point Courthouse Front View
• Building location High Point• Built year 1988• Total Area 227,044 ft2
• Annual Energy use 21,454MBTU
• Annual Energy Cost $346,612.29
Building Energy and Building Energy and Cost IndexCost Index•94.5 kBTU/SF/YR •1.5 $/kBTU/SF/YR
RETROFITSAVINGS OPTIONSRETROFITSAVINGS OPTIONS
Option 1: Replace the Existing Lamp with T8 25 wattEstimated Savings: $ 29,534Estimated Cost: $ 142,528Simple payback period: 4.8 yearsThis analysis assumed that the City will provide their own labor.
•Replacing T12, 34 watt fluorescence tubes with T8 25 watt and electronic ballast:•Number of fixtures in Detention Center = 780; burning continuously throughout the year•Number of fixtures in Courthouse = 1316; burning 12 hour/day and 5days a week
Option 2A: Repair/Replace controls in CourthouseEstimated Savings: $ 19,825/yrEstimated Cost: $ 129,600Simple payback period: 6.5 years
Option 2B: Repair/Replace Controls in Detention CenterEstimated Savings: $ 4,637/yrEstimated Cost: $ 204,750Simple payback period: 44.2yearsOption 2C: Add VFD to AHUs in the CourthouseEstimated Savings: $ 12,253Estimated Cost: $ 60,000/yrSimple payback period: 4.9 years
RETROFITSAVINGS FROM HVACRETROFITSAVINGS FROM HVAC
Option 2E: Install Water Side EconomizerEstimated Savings: $2000-3000Estimated Cost: $ 35,000Simple payback period: 17.5-11.7years
Option2D: ReplaceVAV with Terminal Reheat in Courthouse with FPVAV Estimated Savings: $ 4,749Estimated Cost: $ 160,000Simple payback period: 33.7 years
*Option3 Installing Solar Panel in the Detention CenterEstimated Savings: $ 12,800.00/yr @ 65% efficiencyEstimated Cost: $250,000 and $300,000 ***Simple payback period: 19.5yearsThis system will offset 50 tons of CO2 per year.
Option2F : HVAC Re-Commissioning Estimated Savings: $1,413Estimated Cost: $60,000.00(DC)/
$82,500.00(CH)Simple payback period: years
Conservation Measure Cost Savings (kWh)/yrDollar
Savings/yr1. Replace Existing Lamps 142,528 492233 29,5342A. Repair/Replace Controls in Courthouse 129,600 330417 19,8252B. Repair/Replace Controls in Detention Center 204,750 77283 4,6372C. Add VAV to AHUs 60,000 204217 12,2532D Replace VAV with FPVAV 160,000 79150 4,7492E Install Water Side Economizer 35,000 33,333-50,000 2000-3000
2 F Re-commissioning HVAC60,000(DC)82,500(CH) 23550 1,413
SUMMARYSUMMARY
• Building location High Point
• Built year 1990• Total Area 34,446 ft2
HIGH POINT PUBLIC HEALTH BUILDINGHIGH POINT PUBLIC HEALTH BUILDING
Building Energy and Building Energy and Cost IndexCost Index•190.81 kBTU/SF/YR •$3.32/kBTU/SF/YR
Option 1: Replace T12, 34 watt fluorescence tubes with T8 25 watt and electronic ballast:Estimated Savings: $ 5,647.00/yearEstimated Cost: $ 21,119.00Simple payback period: 4.0 years
Option 2: Reset Chilled Water from Outside AirEstimated Savings: $ 1446.00/yearEstimated Cost: $ 3,000.00Simple payback period: 2.1yearsThis analysis assumed that the City will provide their own labor
SAVINGS FROM RETROFITSAVINGS FROM RETROFIT
•Repair and Use the Existing Solar Water Heaters Estimated Savings: $ 983/yearEstimated Cost: $ 4505.00Simple payback period: 4.6yearsThis analysis assumed that the City will provide their own labor
SAVINGS FROM RETROFITSAVINGS FROM RETROFIT
Conservation Measure CostSavings (kWh)/yr
Dollar Savings/yr
1. Replace Existing Lamps 21,119 94117 5,6472. Reset Chilled Water from OA 3000 24100 14463.Repair and Used the Existing Solar Thermal System 4,505 16383 983
SUMMARYSUMMARY
NEXT STEPS
• COMPLETE FINAL REVIEW OF IDENTIFIED MEASURES
• SELECT MEASURES TO BE IMPLEMENTED
• IDENTIFY FUNDING SOURCES
• OBTAIN DESIGN ASSISTANCE WHERE NEEDED TO IMPLEMENT MEASURES