39
Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

Cetek Technology for Coal-fired Power Plants:

Ceramic Coatings

Page 2: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

Cetek Agenda• Challenges/Solutions in the Coal-Fired

Power Industry• Introduction to Cetek • Case Study I:

– 820 MW Supercritical Boiler– 420 MW Subcritical Boiler– 420 MW Subcritical Boiler

• Case Study II: 650 MW Supercritical Boiler• Cetek Coating Benefit Summary

Page 3: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

Challenges in the Coal-Fired Power Industry: Slagging

• Inefficiency – $20 billion USD in North America

• Current Solutions– SS tubes

• Very expensive, Cl attack– Online Cleaning

• Soot Blowing– Erosion, Cost

• Water Blasting– Tube Quenching

• Explosive Blasting– Boiler Damage

Page 4: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

– Increases thermal transfer to boiler tubes

– Lowers maintenance costs

• Eliminates damage to slope or other components due to large falling clinker

Slagging Solution: Ceramic Coating

Page 5: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

Challenges in the Coal-Fired Power Industry: Corrosion

• Primary cause of 50% of forced outages

• Current Solutions– High Alloy Tubes

• Very expensive, cycling issues– Overlay

• Weld Overlay– Cost, Cracking, Application Time

• Thermal Spray– Cost, Porosity, Hazards

Page 6: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

• Minimizes Forced Outages

• Increases reliability • Lowers

maintenance costs– Increased run

times– Longer boiler tube

life

Corrosion Solution: Ceramic Coating

Page 7: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

Cetek’s Ceramic Coating Technology

• 15 years industrial experience• Multiple industries

– Power Generation– Refining– Chemical Processing– Steel

• Thousands of coating applications• Benefits delivered

– Corrosion Prevention– Fouling Prevention– Fuel Savings– NOX Reduction– Production Increases

Page 9: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

Case Study I: 820 MW Supercritical Boiler 420 MW Subcritical Boiler 420 MW Subcritical Boiler

Trials to Full Scale Projects

Page 10: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

Spring 2006 Unit 4

March 27, 2006

Page 11: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

Spring 2006 Unit 4Unit Properties

• 820 MW CE Supercritical• T-fired, 8-corner• Commissioned 1973 • 2004

• Low NOx Burner use initiated• Eastern Bituminous Coal 2.5% Sulfur

• WashedObjectives

• Test Cetek’s Ceramic Coating in a high corrosion environment– Minimize the corrosion rate

• ~500 µm per year• Show a slag reduction

Page 12: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

833'-8"

804'807'810'-6"

845'-6"

840'

837'-8"

841'

117

#4

221

98

80

862'-8"

858'

854'850'-4"

224

73

#1

183

155

Bottom Bend of Lower Slope

163

127

202

198

169

Top Bend of Lower Slope

Unit 4: “A” Front Wall

= March 2001 Weld Overlay= April/May 2004 Weld Overlay=8.0m2 of aluminum metal spray= 2 waterwall panels installed = Cetek installed 2006 1m wide by 4m high

Areas Treated1m x 4m’ area “A” Furnace

Right of burner #4Top Burner

elevation

Page 13: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

Spring 2006 Unit 4• 6 month Inspection

– Coating Intact • Thickness readings taken by Plant and Cetek were

in proper coating range– No visible damage to coating– Slag on coated area is significantly less

Page 14: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

Spring 2006 Unit 4

Per Plant Management: Per Plant Management: ““Coating still has a green hue to it Coating still has a green hue to it and there is no visible slag build up on the tubes.and there is no visible slag build up on the tubes.””

Page 15: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

Spring 2006 Unit 4• Spring 2008

– 2 years in service– Significant slag reduction– No wastage in areas of coating vs.

~500 µm per year in region around coating

Page 16: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

Fall 2006 Unit 5

November 1, 2006

Page 17: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

Fall 2006 Unit 5Unit Properties

• 420 MW CE Sub-critical Drum, T-fired• Commissioned 1976 • 2003: Low NOx Burner use initiated• Eastern Bituminous Coal 3.5% - 4.5% Sulfur

– 30% WashedObjectives

• Minimize the corrosion rate– 711 µm average per year over the last outage cycle (up

to 1.27mm per year)• Minimize slag

Page 18: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

Fall 2006 Unit 5Front Wall

Page 19: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

Fall 2006 Unit 5Rear Wall

Page 20: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

Fall 2006 Unit 5Side Walls

Page 21: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

Fall 2006 Unit 5• One year later, Sept 2007 forced outage

note from Plant Management stated:– The walls looked very clean where the Cetek

coating had been applied. – There were sheets of slag above the coated

areas on the waterwalls. – The coating was still visible.

Page 22: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

Fall 2006 Unit 5• Spring 2008 Inspection

– Coating Intact– Minimal WW loss of +/- 75 µm

• Inspected every 67cm vertical ; every 5 tubes– Slag still not attaching to tubes

Page 23: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

Unit 5 vs. Unit 6 Comparison Fall 2006-18 month run

Unit 5• 370 m2 of coating applied

• No tube leaks in coated areas

• No Slagging on coated surfaces– Increase in Heat

Absorption

• Max of 75 µm loss in waterwall tubes

Unit 6• No coating applied due to

shortened outage

• 2 tube leaks in targeted areas– Result 2 Forced Outages

• 6.5 Days offline

• 711 µm avg per year loss in targeted areas (up to 1.27mm per year)

Page 24: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

Spring 2008 Unit 6

May 1, 2008

Page 25: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

Spring 2008 Unit 6Unit Properties

• 420 MW CE Sub-critical Drum, T-fired• Commissioned 1978 • 2003: Low NOx Burner use initiated• Eastern Bituminous Coal 3.5% - 4.5% Sulfur

– 30% Washed

Objectives• Minimize slag

– Decrease Furnace Exit Gas Temperature• Minimize the corrosion rate

– ~711 µm average per year over the last outage cycle (up to 1.27mm per year)

Page 26: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

Spring 2008 Unit 6• Areas Treated

– Front Wall, 247 Tubes– Rear Wall, 247 Tubes– Side Wall, 194 Tubes

• All tubes are 5.1cm on 6.4cm center.– El. 803 to El. 845 (12.8 m)– Total surface area 1,050 m2

• Additional Outage Work Completed– New Final Reheat Section Installed

• Stainless steel• Reduced surface area

– Not related to a performance issue

Page 27: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

Spring 2008 Unit 6• Initial Benefits to date

– Slag Reduction > Increased Boiler Efficiency• Economizer Exit Gas Temp reduced by 17°C

– Pre vs. Post Outage: 382°C vs. 365°C• Boiler Heat Rate Improvements (vs. pre outage)

– July 15th: 11.3 KCal/kWh– August 5th : 19.6 KCal/kWh– $575,000 annual savings

• NOx Reduction– Estimated 4.3% under same pre outage firing

conditions.– Estimated 72,350 Kg/year

Page 28: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

Unit 6 – Boiler Heat Rate Improvement

Source: Plant Management, using HRDR system.

Page 29: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

Spring 2008 CVU6• Project tracking

– Per Plant Management: • “We have seen a 18.1 KCal/kWh reduction in

these 3 parameters in August compared to pre-outage.”

• “The results of the testing showed a drop in FEGT of 62.0°C on Unit 6.” (Testing completed by third party)

• “This year the Unit 6 NOx is 22.6% below our target. 345 tons of NOx less than the target.”

Page 30: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

Case Study II 650 MW CE Supercritical Boiler

Page 31: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

Case Study II: 650 MW C-E Supercritical Boiler

Unit Properties• Currently operated at 700-

720 MW• T-fired, 8-corner• Double Reheat Unit• Commissioned 1969 • 2001

• Low Nox Burners• March 2007

• Fluidized Gas Desulfurization

• Intelligent soot blowing system

Results after 6 Months• Coated Areas require 93%

less soot-blowing frequency than uncoated areas to achieve same results

• Coated unit projected soot blowing steam utilization savings of $130,000/yr (side benefit of coating)

• Reduced furnace exit gas temp.

• Minimized waterwall cycling

Page 32: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

Case Study II

Cerak M870

Cerak M670

Total Area of 405m2

Cerak M870 = 362m2

Cerak M670 (Chemical Set Coating) = 43m2

13m

5.5m

3m

Page 33: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

Case Study II

Cerak M670

Cerak M870

Page 34: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

Case Study II

Uncoated Area

Coated Area

Front-wall after 3 months of boiler operation

Page 35: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

3 WALL BLOWER D13 NOT AT REST3 WALL BLOWER D14 NOT AT REST3 Tube Crown Temp Right D133 Tube Crown Temp Right D14Gross Load, EXDESC=Gross Load

ZS3BS01D13

ZS3BS01D14

TE3BS01D13D

DEG FTE3BS01D14D

DEG F3LOAD

MW

3 Temp WB D Lev el 13&14

7/16/2007 9:26:44.881 AM 7/23/2007 9:26:44.881 AM7.00 day s

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

0

1

0

1

700

800

700

800

650

900

709.18

734.80

751.25

FALSE

FALSE

Case Study II

Uncoated Area Delta T: 50°C Frequency: 14 Times

Page 36: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

3 WALL BLOWER D17 NOT AT REST3 WALL BLOWER D18 NOT AT REST3 Tube Crown Temp Right WB D173 Tube Crown Temp Right WB D18Gross Load, EXDESC=Gross Load

ZS3BS02D17

ZS3BS02D18

TE3BS02D17D

DEG FTE3BS02D18D

DEG F3LOAD

MW

3 Temp WB D Lev el 17 & 18

7/16/2007 9:11:13.614 AM 7/23/2007 9:11:13.614 AM7.00 day s

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

0

1

0

1

650

750

650

750

650

800

709.77

704.07

703.63

FALSE

FALSE

Case Study II

Coated Area Delta T: 18°C Frequency: 7 Times

Page 37: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

Cetek Coating Benefit Summary• Cetek Ceramic Coatings proven to significantly

reduce slag and increase efficiency– Improve heat transfer– Minimize thermal cycling– Minimize soot blowing– Lower FEGT

• Cetek Ceramic Coatings proven to minimize corrosion– Extend tube life– Decrease tube leaks

Page 38: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

Cetek Coating Benefit Summary• Improves heat rate• Lowers NOx

• Reduces maintenance costs• Increases asset life• Increases reliability• Increases efficiency• Decreases forced outages

Page 39: Cetek Technology for Coal-fired Power Plants: Ceramic Coatings

20600 Sheldon Road, Brook Park, OH 44142Telephone: 216/362-3900 Fax: 216/362-3901Internet: http://www.ceteklimited.com

The Cetek Service Portfolio includes Ceramic Coatings,

High Temperature Inspections& Hot Refractory Repairs

For More Information Contact: