Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Cetek Technology for Coal-fired Power Plants:
Ceramic Coatings
Cetek Agenda• Challenges/Solutions in the Coal-Fired
Power Industry• Introduction to Cetek • Case Study I:
– 820 MW Supercritical Boiler– 420 MW Subcritical Boiler– 420 MW Subcritical Boiler
• Case Study II: 650 MW Supercritical Boiler• Cetek Coating Benefit Summary
Challenges in the Coal-Fired Power Industry: Slagging
• Inefficiency – $20 billion USD in North America
• Current Solutions– SS tubes
• Very expensive, Cl attack– Online Cleaning
• Soot Blowing– Erosion, Cost
• Water Blasting– Tube Quenching
• Explosive Blasting– Boiler Damage
– Increases thermal transfer to boiler tubes
– Lowers maintenance costs
• Eliminates damage to slope or other components due to large falling clinker
Slagging Solution: Ceramic Coating
Challenges in the Coal-Fired Power Industry: Corrosion
• Primary cause of 50% of forced outages
• Current Solutions– High Alloy Tubes
• Very expensive, cycling issues– Overlay
• Weld Overlay– Cost, Cracking, Application Time
• Thermal Spray– Cost, Porosity, Hazards
• Minimizes Forced Outages
• Increases reliability • Lowers
maintenance costs– Increased run
times– Longer boiler tube
life
Corrosion Solution: Ceramic Coating
Cetek’s Ceramic Coating Technology
• 15 years industrial experience• Multiple industries
– Power Generation– Refining– Chemical Processing– Steel
• Thousands of coating applications• Benefits delivered
– Corrosion Prevention– Fouling Prevention– Fuel Savings– NOX Reduction– Production Increases
Case Study I: 820 MW Supercritical Boiler 420 MW Subcritical Boiler 420 MW Subcritical Boiler
Trials to Full Scale Projects
Spring 2006 Unit 4
March 27, 2006
Spring 2006 Unit 4Unit Properties
• 820 MW CE Supercritical• T-fired, 8-corner• Commissioned 1973 • 2004
• Low NOx Burner use initiated• Eastern Bituminous Coal 2.5% Sulfur
• WashedObjectives
• Test Cetek’s Ceramic Coating in a high corrosion environment– Minimize the corrosion rate
• ~500 µm per year• Show a slag reduction
833'-8"
804'807'810'-6"
845'-6"
840'
837'-8"
841'
117
#4
221
98
80
862'-8"
858'
854'850'-4"
224
73
#1
183
155
Bottom Bend of Lower Slope
163
127
202
198
169
Top Bend of Lower Slope
Unit 4: “A” Front Wall
= March 2001 Weld Overlay= April/May 2004 Weld Overlay=8.0m2 of aluminum metal spray= 2 waterwall panels installed = Cetek installed 2006 1m wide by 4m high
Areas Treated1m x 4m’ area “A” Furnace
Right of burner #4Top Burner
elevation
Spring 2006 Unit 4• 6 month Inspection
– Coating Intact • Thickness readings taken by Plant and Cetek were
in proper coating range– No visible damage to coating– Slag on coated area is significantly less
Spring 2006 Unit 4
Per Plant Management: Per Plant Management: ““Coating still has a green hue to it Coating still has a green hue to it and there is no visible slag build up on the tubes.and there is no visible slag build up on the tubes.””
Spring 2006 Unit 4• Spring 2008
– 2 years in service– Significant slag reduction– No wastage in areas of coating vs.
~500 µm per year in region around coating
Fall 2006 Unit 5
November 1, 2006
Fall 2006 Unit 5Unit Properties
• 420 MW CE Sub-critical Drum, T-fired• Commissioned 1976 • 2003: Low NOx Burner use initiated• Eastern Bituminous Coal 3.5% - 4.5% Sulfur
– 30% WashedObjectives
• Minimize the corrosion rate– 711 µm average per year over the last outage cycle (up
to 1.27mm per year)• Minimize slag
Fall 2006 Unit 5Front Wall
Fall 2006 Unit 5Rear Wall
Fall 2006 Unit 5Side Walls
Fall 2006 Unit 5• One year later, Sept 2007 forced outage
note from Plant Management stated:– The walls looked very clean where the Cetek
coating had been applied. – There were sheets of slag above the coated
areas on the waterwalls. – The coating was still visible.
Fall 2006 Unit 5• Spring 2008 Inspection
– Coating Intact– Minimal WW loss of +/- 75 µm
• Inspected every 67cm vertical ; every 5 tubes– Slag still not attaching to tubes
Unit 5 vs. Unit 6 Comparison Fall 2006-18 month run
Unit 5• 370 m2 of coating applied
• No tube leaks in coated areas
• No Slagging on coated surfaces– Increase in Heat
Absorption
• Max of 75 µm loss in waterwall tubes
Unit 6• No coating applied due to
shortened outage
• 2 tube leaks in targeted areas– Result 2 Forced Outages
• 6.5 Days offline
• 711 µm avg per year loss in targeted areas (up to 1.27mm per year)
Spring 2008 Unit 6
May 1, 2008
Spring 2008 Unit 6Unit Properties
• 420 MW CE Sub-critical Drum, T-fired• Commissioned 1978 • 2003: Low NOx Burner use initiated• Eastern Bituminous Coal 3.5% - 4.5% Sulfur
– 30% Washed
Objectives• Minimize slag
– Decrease Furnace Exit Gas Temperature• Minimize the corrosion rate
– ~711 µm average per year over the last outage cycle (up to 1.27mm per year)
Spring 2008 Unit 6• Areas Treated
– Front Wall, 247 Tubes– Rear Wall, 247 Tubes– Side Wall, 194 Tubes
• All tubes are 5.1cm on 6.4cm center.– El. 803 to El. 845 (12.8 m)– Total surface area 1,050 m2
• Additional Outage Work Completed– New Final Reheat Section Installed
• Stainless steel• Reduced surface area
– Not related to a performance issue
Spring 2008 Unit 6• Initial Benefits to date
– Slag Reduction > Increased Boiler Efficiency• Economizer Exit Gas Temp reduced by 17°C
– Pre vs. Post Outage: 382°C vs. 365°C• Boiler Heat Rate Improvements (vs. pre outage)
– July 15th: 11.3 KCal/kWh– August 5th : 19.6 KCal/kWh– $575,000 annual savings
• NOx Reduction– Estimated 4.3% under same pre outage firing
conditions.– Estimated 72,350 Kg/year
Unit 6 – Boiler Heat Rate Improvement
Source: Plant Management, using HRDR system.
Spring 2008 CVU6• Project tracking
– Per Plant Management: • “We have seen a 18.1 KCal/kWh reduction in
these 3 parameters in August compared to pre-outage.”
• “The results of the testing showed a drop in FEGT of 62.0°C on Unit 6.” (Testing completed by third party)
• “This year the Unit 6 NOx is 22.6% below our target. 345 tons of NOx less than the target.”
Case Study II 650 MW CE Supercritical Boiler
Case Study II: 650 MW C-E Supercritical Boiler
Unit Properties• Currently operated at 700-
720 MW• T-fired, 8-corner• Double Reheat Unit• Commissioned 1969 • 2001
• Low Nox Burners• March 2007
• Fluidized Gas Desulfurization
• Intelligent soot blowing system
Results after 6 Months• Coated Areas require 93%
less soot-blowing frequency than uncoated areas to achieve same results
• Coated unit projected soot blowing steam utilization savings of $130,000/yr (side benefit of coating)
• Reduced furnace exit gas temp.
• Minimized waterwall cycling
Case Study II
Cerak M870
Cerak M670
Total Area of 405m2
Cerak M870 = 362m2
Cerak M670 (Chemical Set Coating) = 43m2
13m
5.5m
3m
Case Study II
Cerak M670
Cerak M870
Case Study II
Uncoated Area
Coated Area
Front-wall after 3 months of boiler operation
3 WALL BLOWER D13 NOT AT REST3 WALL BLOWER D14 NOT AT REST3 Tube Crown Temp Right D133 Tube Crown Temp Right D14Gross Load, EXDESC=Gross Load
ZS3BS01D13
ZS3BS01D14
TE3BS01D13D
DEG FTE3BS01D14D
DEG F3LOAD
MW
3 Temp WB D Lev el 13&14
7/16/2007 9:26:44.881 AM 7/23/2007 9:26:44.881 AM7.00 day s
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
0
1
0
1
700
800
700
800
650
900
709.18
734.80
751.25
FALSE
FALSE
Case Study II
Uncoated Area Delta T: 50°C Frequency: 14 Times
3 WALL BLOWER D17 NOT AT REST3 WALL BLOWER D18 NOT AT REST3 Tube Crown Temp Right WB D173 Tube Crown Temp Right WB D18Gross Load, EXDESC=Gross Load
ZS3BS02D17
ZS3BS02D18
TE3BS02D17D
DEG FTE3BS02D18D
DEG F3LOAD
MW
3 Temp WB D Lev el 17 & 18
7/16/2007 9:11:13.614 AM 7/23/2007 9:11:13.614 AM7.00 day s
0.1
0.2
0.3
0.4
0.5
0.6
0.7
0.8
0.9
0
1
0
1
650
750
650
750
650
800
709.77
704.07
703.63
FALSE
FALSE
Case Study II
Coated Area Delta T: 18°C Frequency: 7 Times
Cetek Coating Benefit Summary• Cetek Ceramic Coatings proven to significantly
reduce slag and increase efficiency– Improve heat transfer– Minimize thermal cycling– Minimize soot blowing– Lower FEGT
• Cetek Ceramic Coatings proven to minimize corrosion– Extend tube life– Decrease tube leaks
Cetek Coating Benefit Summary• Improves heat rate• Lowers NOx
• Reduces maintenance costs• Increases asset life• Increases reliability• Increases efficiency• Decreases forced outages
20600 Sheldon Road, Brook Park, OH 44142Telephone: 216/362-3900 Fax: 216/362-3901Internet: http://www.ceteklimited.com
The Cetek Service Portfolio includes Ceramic Coatings,
High Temperature Inspections& Hot Refractory Repairs
For More Information Contact: