Upload
agnes-curtis
View
216
Download
0
Tags:
Embed Size (px)
Citation preview
Challenges of DualHarmonic RF Systems
ISIS Synchrotron Group
John Thomason
Second Target Station
50 pps
40 pps
Increased Beam Intensity
1) The RFQ Accelerator
• 4-rod 202.5 MHz RFQ accelerates 35 keV H− beam from ISIS ion source to 665 keV• Focuses and bunches with ~ 95% transmission efficiency (compared with ~ 60% for the old pre-injector)
• Fundamental RF system of six cavities (1.3 – 3.1 MHz) gives up to 140 kV/turn • Four additonal RF cavities (2.6 – 6.2 MHz) give up to 80 kV/turn
Increased Beam Intensity
2) The Dual Harmonic RF System
Increased Phase Stable Regions
• Increased phase stable regions, enhanced bunching factors and smaller beam loss• Potentially increase accelerated intensity from 2.5x1013 ppp (200 µA) to 3.75x1013 ppp (300 µA)
LPRF Controls: Amplitude,Phase & Cavity Tuning
Driver Amplifier
Anode Power Supply
2nd Harmonic high power RF
Frequency Law
Summing Amplifier
Frequency Law
Generator
Master Oscillator
1.3 MHz - 3.1 MHz
Dipole Search
Coil
Beam Phase Loop
Radial
Loop
Trim
Function
Bunch Length Loop
Existing Fundamental RF System
Phase Shifter
Super-period Phase Splitter
To Other 2nd Harmonic Cavity LPRF Systems
Phase
Modulator
2 RF Level Controller
Func Gen.
2nd Harmonic Cavity Voltage Loop
Func. Gen
Phase Detector (Cavity Lock)
Cavity Lock LPF
2
RF
Detector
RF
Limiters
Phase Detector (Cavity Tune)
2
Gated Summing Amplifier
Delay
Unit
RF Summing Amplifier
Phase
Networks
2
2nd Harmonic Cavity Phase Loop
2nd Harmonic Cavity
Tuning Loop
Digital Signal
Processor
2nd Harmonic Beam Compensation Loop
Sum Electrode
Func. Gen.
Func.
Gen.
LPF
Variable Delay
Variable Gain
Frequency Doubler 2.6 MHz – 6.2 MHz
2nd Harmonic low power RF
HPDCavity
Cavity Bias Regulator
Cavity Bias RegulatorLow Voltage Power Supply
Cavity Lock Servo
Cavity Gap A Voltage Monitor
Summing Amplifier
Phase Modulation and Delay Chassis
1RF 2RF
A single Burle 4648VI tetrode is used to drive
the 2RF cavity
2RF System Overview
OperatingRegime
Trappedbeam
intensity(protons
)
Totalbeamloss
(protons)
Equivalent current
to TS-1 (µA)
50 pps 40 pps
1RF(50 pps)
2.30×1013 2.76×1012 184 148
+2 × 2RF(50 pps)
2.65×1013 1.60×1012 212 170
+2 × 2RF(50/32 pps)
2.93×1013 2.70×1012 234 187
2 × 2RF Cavity Running to TS-1
2RF Hardware Failures
Anode Power Supplies
• But also significant problems with intermediate amplifiers, bias regulators, cavity interlocks, LPRF modules, etc.
• Problems not evident on test rig, only with beam• User cycles limited to 2 × 2RF cavities to give some spares capacity
2RF Challenges
• Installation has to contend with very stringent space constraints, particularly in the ISIS ring, but also in cable trenches and RF hall• Additional 2RF systems are notoriously difficult to get working at all on proton machines (see experiences of IPNS team at Argonne)• System is very complex• Reliability of equipment can only be proved under limited conditions on test rigs• Very little dedicated commissioning time with beam available• Much of this has had to be spent repairing hardware rather than actually setting up the systems• Because ISIS can continue to run without 2RF (unlike any other of the accelerator systems) so far whenever 2RF systems have failed during a run operational/user pressure has dictated that it is left until the end of the run to mend them, hence compounding the lack of running with beam and having to use machine physics sessions to mend hardware• Target constraints on TS-1 have limited achievable intensity during some user runs
2 × 2RF Cavity Running to TS-1 and
TS-2
End of Cycle 2008/4Synchrotron average current 210 µA
Beam to TS-1 Beam to TS-2
• 2 × 2RF cavities have been run for most of the time duringthe last 10 ISIS user cycles (starting with Cycle 2006/3), admittedly
with some reliability issues and problems with mid-cycle (~ 5 ms) beam loss
• TS-1 began routine running at 40 pps in Cycle 2008/3 with beam to TS-2 being phased in during Cycles 2008/3 and 2008/4
3.27×1013 ppp injected (96%)2.90×1013 ppp accelerated (93%)2.90×1013 ppp extracted (100%)
Average horizontal position
R2BLM3
BLM sum
BLM sum –(SP1+SP2)
20 December 2008
2 × 2RF Cavity Machine Physics (@
MS1/32)
• Losses were well controlled and we ran for the majority of the 8 hour shift at this intensity
• Well within BLM trip tolerances, but inhibiting on intensity
• Linac pulse length was 290µs, so in theory we could operate up to this level for next user run
Future Work
• Install new Master Oscillator: new FPGA unit provides the RF frequency sweep for 1RF & 2RF cavities. Applies all phase modulation (delta, anti-phasing, geometrical offset)
• Try to start Cycle 2008/5 (10 February 2009) with 180 µA to TS-1 at 40 pps and 45 µA to TS-2 at 10 pps using 2 × 2RF cavities• Gradually improve intensity and reliability running 2 × 2RF systems during user cycles• Optimise running with 3 × 2RF cavities and 4 × 2RF cavities during machine physics sessions• Eventual optimised running with 4 × 2RF cavities during user cycles (when we have a spare 2RF APS again)
2RF Feed-forwardBeam Compensation
• Now – Fixed Band Pass• Tried – 2 x “switch-in”• Later – Tuneable
Bunch 1
Bunch 2
TetrodeAmplifiers
IntermediateAmplifier Subtracter
-
Variablegain
Variabledelay2RF Filter
2RFdemand
FunctionGenerator
FunctionGenerator
Induced 2RF gap volts:- No beam compensation- Single (low frequency)- Switched (low and high frequency)