Scope ManagementChapter 5
2
1. Understand the importance of scope management for project success.
2. Construct a Work Breakdown Structure for a project.
3. Develop a Responsibility Assignment Matrix for a project.
4. Describe the roles of changes and configuration management in assessing project scope
Learning Goals
3
Project Scope
Project scope is everything about a project – work content as well as expected outcomes, which should include- activities to be performed- resources consumed- end product result- quality standard expected
Scope management is the function of controlling a project in terms of its goals and objectives and consists of:
1) Conceptual development 4) Scope reporting2) Scope statement 5) Control systems3) Work authorization 6) Project closeout
See Table 5.1 for details
4
The process that addresses project objectives by finding the best ways to meet them.
Collect data and develop information: Problem or need statement Information gathering and baselining Constraints and restrictions Alternative solution analysis Project objectives with a clear statement of
expectations
Conceptual Development
5
Sets the stage for the project
Successful conceptual development requires: Goals and objects are clearly stated
◦ Should be specific and measureable◦ i.e. Create goals such as “Improve gas mileage
from 12 mpg to 16 mpg by June 30th” not “Improve gas mileage”
Complete understanding of the problem Use the SMART model
Problem Statements
6
SMART Model
7
Poorly written objective:◦ Seminar delivered via electronic media.
Improved:◦ The project management seminar will be
delivered via Web conference at 10:00 a.m. central time, on January 15th. The host, John Schneider, will discuss the ethics of project management for 50 minutes, followed by a 10-minute question-and-answer session at the conclusion of the session.
SMART Example
8
Statement of Work (SOW)
A SOW is a detailed narrative description of the work required for a project.
Effective SOWs contain1. Key objectives for the project2. A brief and general description of the work to be
performed3. Background or history of why this is a project4. Expected outcomes5. Funding and schedule constraints6. Timeline and milestones7. Signatures of acceptance
See UPMM_IIL_Project Charter.doc and Table 5.2
9
The Scope Statement Process1. Establish the project goal criteria
a) costb) schedulec) performanced) deliverablese) review/approval gates
2. Develop the management plan for the project
3. Establish a work breakdown structure4. Create a scope baseline
10
Work Breakdown StructureA process that sets a project’s scope by breaking down its overall mission into a cohesive set of synchronous, increasingly specific tasks.
What does the WBS accomplish?1. It echoes project objectives. 2. It is the organization chart for the project. 3. Creates the logic for tracking costs, schedule, and
performance specifications for each element in the project.
4. May be used to communicate project status. 5. May be used to improve overall project communication. 6. Demonstrates how the project will be controlled.
11
Work Breakdown Structure and Codes
Work packages are individual project activities
1.0
1.2 1.3 1.4
1.2.1
1.2.2
1.2.3
1.3.1
1.3.2
1.2.3.1
1.2.3.2
Deliverables are major project components
Sub-deliverables are supporting deliverables
The project is the overall project under development
12
Defining a Work Package
Lowest level in WBS
Deliverable result
One owner
Miniature projects
Milestones
Fits organization
Trackable
13
Sample WBS in MS Project
14
Organizational Breakdown StructureOrganizational Breakdown Structure (OBS)
allows Define work definition Owner assignment of work packages Budget assignment to departments
OBS links cost, activity & responsibility
15
Intersection of the WBS and OBS
16
Cost Account Rollup Using OBS
Identify personnel who will be directly responsible for each work package
17
Responsibility Assignment Matrix
Notification Responsible SupportApproval
LEAD PROJECT PERSONNEL
BobIS
Dave SueHR
AnnR&D
JimR&D
Task & CodeDeliverable IS
Match IT toOrg. Tasks
proposalPrepare
1.3
1.1
Identify ISuser needs
1.2
ProblemAnalysis
Developinfo
Interview
users
showDevelop
Gain user “buy in”
Find cost/benefit info
1.1.1
1.1.2
1.2.1
1.2.2
1.2.3
1.3.1
See UPMM_IIL_Responsibility Assignment Matrix (RAM).doc
18
Work Authorization
Let the work begin!!
The formal “go ahead” to begin working the project.
Follows the approval of scope management steps:
1. scope definition2. planning documents3. management plans4. contractual documents
19
Contractual DocumentationMost contracts contain:
RequirementsValid considerationContracted terms
Contracts range from:
Lump Sum Cost Plusalso called “Turnkey”
20
Scope Reporting
Determines what types of information is reported, who receives copies, when, and how information is acquired and disseminated.
Typical project reports contain1. Budget performance status2. Schedule status3. Technical performance status
Solid communication between all parties is one of the most important task to be accomplished.
21
Scope Reporting
22
Reasons Why Projects Fail Politics Naïve promises Naïve optimism Startup mentality of fledging entrepreneurial
companies “Marine Corps” mentality Intensive competition caused by globalization Intense competition caused by appearance of new
technologies Intense pressure caused by unexpected government
regulations Unexpected and/or unplanned crises#1 Reason
Poor Scope Statements!
23
Control systems are vital to ensure that any changes to the project baseline are conducted in a systematic and thorough manner.
Configuration – same scope? Design – same scope, schedule and cost? Trend monitoring – same cost, schedules and
resources? Document – documentation compiled and circulated? Acquisition – monitors resources Specification – monitors requirements and change
control
How does a project become a year late? One day at a time!
Types of Control Systems
See UPMM_IIL_Project Change Request Form.doc
24
Project CloseoutThe job is not over until the paperwork is done…
Closeout documentation is used to:Resolve disputesTrain project managersFacilitate auditing
Closeout documentation includes:Historical recordsPost project analysis – post-mortem processFinancial closeout
25
1. What are the primary benefits of developing a comprehensive project scope analysis?
2. What are the key characteristics of a work package?
3. Create a Work Breakdown Structure for a term paper project or another school-related project you are working on. What are the steps in the WBS? Can you identify any sub-steps for each step?
Chapter 5 Review and Discussion
26
4. What are the benefits of designing a Responsibility Assignment Matrix (RAM) for a project?
5. Develop an argument for scope reporting mechanisms. At a minimum, what types of reports do you consider necessary for document control of a project? Why?
6. What is the chief purpose of configuration management? In your opinion, why has it become increasingly popular in recent years as part of the project management process?
7. What is the logic behind developing a plan for project closeout prior to even beginning the project?
Chapter 5 Review and Discussion
27
Customer RequestIma Prez says, “I want a phone system like the company downstairs.”
Your Task1. Starting with Ima’s stated want/need,
develop a set of questions so that project objectives and functional and technical requirements can be established.
2. Based on Ima’s stated want/need, rewrite it as a SMART objective in a functional format.
Case Study 2: Working with Customers to Develop Good Requirements