5.1 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Chapter 5: CPU Scheduling
5.2 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Chapter 5: CPU Scheduling
Basic Concepts
Scheduling Criteria
Scheduling Algorithms
Thread Scheduling
Multiple-Processor Scheduling
Operating Systems Examples
Algorithm Evaluation
5.3 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Objectives
To introduce CPU scheduling, which is the basis for multiprogrammed operating systems
To describe various CPU-scheduling algorithms
To discuss evaluation criteria for selecting a CPU-scheduling algorithm for a particular system
5.4 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Basic Concepts
Maximum CPU utilization obtained with multiprogramming
CPU–I/O Burst Cycle – Process execution consists of a cycle of CPU execution and I/O wait
CPU burst distribution
5.5 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Histogram of CPU-burst Times
5.6 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Alternating Sequence of CPU And I/O Bursts
5.7 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
CPU Scheduler
Selects from among the processes in memory that are ready to execute, and allocates the CPU to one of them
CPU scheduling decisions may take place when a process:
1. Switches from running to waiting state
2. Switches from running to ready state
3. Switches from waiting to ready
4. Terminates
Scheduling under 1 and 4 is nonpreemptive
All other scheduling is preemptive
5.8 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Dispatcher
Dispatcher module gives control of the CPU to the process selected by the short-term scheduler; this involves:
switching context
switching to user mode
jumping to the proper location in the user program to restart that program
Dispatch latency – time it takes for the dispatcher to stop one process and start another running
5.9 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Scheduling Criteria
CPU utilization – keep the CPU as busy as possible
Throughput – # of processes that complete their execution per time unit
Turnaround time – amount of time to execute a particular process
Waiting time – amount of time a process has been waiting in the ready queue
Response time – amount of time it takes from when a request was submitted until the first response is produced, not output (for time-sharing environment)
5.10 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Scheduling Algorithm Optimization Criteria
Max CPU utilization
Max throughput
Min turnaround time
Min waiting time
Min response time
5.11 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
First-Come, First-Served (FCFS) Scheduling
Process Burst Time
P1 24
P2 3
P3 3
Suppose that the processes arrive in the order: P1 , P2 , P3
The Gantt Chart for the schedule is:
Waiting time for P1 = 0; P2 = 24; P3 = 27
Average waiting time: (0 + 24 + 27)/3 = 17
P1 P2 P3
24 27 300
5.12 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
FCFS Scheduling (Cont.)
Suppose that the processes arrive in the order:
P2 , P3 , P1
The Gantt chart for the schedule is:
Waiting time for P1 = 6; P2 = 0; P3 = 3
Average waiting time: (6 + 0 + 3)/3 = 3
Much better than previous case
Convoy effect short process behind long process
P1P3P2
63 300
5.13 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Shortest-Job-First (SJF) Scheduling
Associate with each process the length of its next CPU burst. Use these lengths to schedule the process with the shortest time
SJF is optimal – gives minimum average waiting time for a given set of processes
The difficulty is knowing the length of the next CPU request
5.14 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Example of SJF
Process Arrival Time Burst Time
P1 0.0 6
P2 2.0 8
P3 4.0 7
P4 5.0 3
SJF scheduling chart
Average waiting time = (3 + 16 + 9 + 0) / 4 = 7
P4 P3P1
3 160 9
P2
24
5.15 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Determining Length of Next CPU Burst
Can only estimate the length
Can be done by using the length of previous CPU bursts, using exponential averaging
:Define 4.
10 , 3.
burst CPU next the for value predicted 2.
burst CPU of length actual 1.
1n
thn nt
.1 1 nnn t
5.16 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Prediction of the Length of the Next CPU Burst
5.17 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Examples of Exponential Averaging
=0
n+1 = n
Recent history does not count
=1
n+1 = tn
Only the actual last CPU burst counts
If we expand the formula, we get:
n+1 = tn+(1 - ) tn -1 + …
+(1 - )j tn -j + …
+(1 - )n +1 0
Since both and (1 - ) are less than or equal to 1, each successive term has less weight than its predecessor
5.18 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Priority Scheduling
A priority number (integer) is associated with each process
The CPU is allocated to the process with the highest priority (smallest integer highest priority)
Preemptive
Nonpreemptive
SJF is a priority scheduling where priority is the predicted next CPU burst time
Problem Starvation – low priority processes may never execute
Solution Aging – as time progresses increase the priority of the process
5.19 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Round Robin (RR)
Each process gets a small unit of CPU time (time quantum), usually 10-100 milliseconds. After this time has elapsed, the process is preempted and added to the end of the ready queue.
If there are n processes in the ready queue and the time quantum is q, then each process gets 1/n of the CPU time in chunks of at most q time units at once. No process waits more than (n-1)q time units.
Performance
q large FIFO
q small q must be large with respect to context switch, otherwise overhead is too high
5.20 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Example of RR with Time Quantum = 4
Process Burst Time
P1 24
P2 3
P3 3
The Gantt chart is:
Typically, higher average turnaround than SJF, but better response
P1 P2 P3 P1 P1 P1 P1 P1
0 4 7 10 14 18 22 26 30
5.21 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Time Quantum and Context Switch Time
5.22 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Turnaround Time Varies WithThe Time Quantum
5.23 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Multilevel Queue
Ready queue is partitioned into separate queues:foreground (interactive)background (batch)
Each queue has its own scheduling algorithm
foreground – RR
background – FCFS
Scheduling must be done between the queues
Fixed priority scheduling; (i.e., serve all from foreground then from background). Possibility of starvation.
Time slice – each queue gets a certain amount of CPU time which it can schedule amongst its processes; i.e., 80% to foreground in RR
20% to background in FCFS
5.24 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Multilevel Queue Scheduling
5.25 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Multilevel Feedback Queue
A process can move between the various queues; aging can be implemented this way
Multilevel-feedback-queue scheduler defined by the following parameters:
number of queues
scheduling algorithms for each queue
method used to determine when to upgrade a process
method used to determine when to demote a process
method used to determine which queue a process will enter when that process needs service
5.26 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Example of Multilevel Feedback Queue
Three queues:
Q0 – RR with time quantum 8 milliseconds
Q1 – RR time quantum 16 milliseconds
Q2 – FCFS
Scheduling
A new job enters queue Q0 which is served FCFS. When it gains CPU, job receives 8 milliseconds. If it does not finish in 8 milliseconds, job is moved to queue Q1.
At Q1 job is again served FCFS and receives 16 additional milliseconds. If it still does not complete, it is preempted and moved to queue Q2.
5.27 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Multilevel Feedback Queues
5.28 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Thread Scheduling
Distinction between user-level and kernel-level threads
Many-to-one and many-to-many models, thread library schedules user-level threads to run on LWP
Known as process-contention scope (PCS) since scheduling competition is within the process
Kernel thread scheduled onto available CPU is system-contention scope (SCS) – competition among all threads in system
5.29 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Pthread Scheduling
API allows specifying either PCS or SCS during thread creation
PTHREAD SCOPE PROCESS schedules threads using PCS scheduling
PTHREAD SCOPE SYSTEM schedules threads using SCS scheduling.
5.30 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Pthread Scheduling API
#include <pthread.h>#include <stdio.h>#define NUM THREADS 5int main(int argc, char *argv[]){
int i;pthread t tid[NUM THREADS];pthread attr t attr;/* get the default attributes */pthread attr init(&attr);/* set the scheduling algorithm to PROCESS or SYSTEM */pthread attr setscope(&attr, PTHREAD SCOPE SYSTEM);/* set the scheduling policy - FIFO, RT, or OTHER */pthread attr setschedpolicy(&attr, SCHED OTHER);/* create the threads */for (i = 0; i < NUM THREADS; i++)
pthread create(&tid[i],&attr,runner,NULL);
5.31 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Pthread Scheduling API
/* now join on each thread */
for (i = 0; i < NUM THREADS; i++)
pthread join(tid[i], NULL);
}
/* Each thread will begin control in this function */
void *runner(void *param)
{
printf("I am a thread\n");
pthread exit(0);
}
5.32 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Multiple-Processor Scheduling
CPU scheduling more complex when multiple CPUs are available
Homogeneous processors within a multiprocessor
Asymmetric multiprocessing – only one processor accesses the system data structures, alleviating the need for data sharing
Symmetric multiprocessing (SMP) – each processor is self-scheduling, all processes in common ready queue, or each has its own private queue of ready processes
Processor affinity – process has affinity for processor on which it is currently running
soft affinity
hard affinity
5.33 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
NUMA and CPU Scheduling
5.34 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Multicore Processors
Recent trend to place multiple processor cores on same physical chip
Faster and consume less power
Multiple threads per core also growing
Takes advantage of memory stall to make progress on another thread while memory retrieve happens
5.35 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Multithreaded Multicore System
5.36 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Operating System Examples
Solaris scheduling
Windows XP scheduling
Linux scheduling
5.37 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Solaris Dispatch Table
5.38 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Solaris Scheduling
5.39 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Windows XP Priorities
5.40 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Linux Scheduling
Constant order O(1) scheduling time
Two priority ranges: time-sharing and real-time
Real-time range from 0 to 99 and nice value from 100 to 140
(figure 5.15)
5.41 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Priorities and Time-slice length
5.42 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
List of Tasks Indexed According to Priorities
5.43 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Algorithm Evaluation
Deterministic modeling – takes a particular predetermined workload and defines the performance of each algorithm for that workload
Queueing models
Implementation
5.44 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Evaluation of CPU schedulers by Simulation
5.45 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
End of Chapter 5
5.46 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
5.08
5.47 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
In-5.7
5.48 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
In-5.8
5.49 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
In-5.9
5.50 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Dispatch Latency
5.51 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Java Thread Scheduling
JVM Uses a Preemptive, Priority-Based Scheduling Algorithm
FIFO Queue is Used if There Are Multiple Threads With the Same Priority
5.52 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Java Thread Scheduling (Cont.)
JVM Schedules a Thread to Run When:
1. The Currently Running Thread Exits the Runnable State
2. A Higher Priority Thread Enters the Runnable State
* Note – the JVM Does Not Specify Whether Threads are Time-Sliced or Not
5.53 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Time-Slicing
Since the JVM Doesn’t Ensure Time-Slicing, the yield() Method May Be Used:
while (true) {
// perform CPU-intensive task
. . .
Thread.yield();
}
This Yields Control to Another Thread of Equal Priority
5.54 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Thread Priorities
Priority Comment
Thread.MIN_PRIORITY Minimum Thread Priority
Thread.MAX_PRIORITY Maximum Thread Priority
Thread.NORM_PRIORITY Default Thread Priority
Priorities May Be Set Using setPriority() method:
setPriority(Thread.NORM_PRIORITY + 2);
5.55 Silberschatz, Galvin and Gagne ©2009Operating System Concepts with Java – 8th Edition
Solaris 2 Scheduling