Upload
karangrover
View
227
Download
0
Embed Size (px)
Citation preview
8/4/2019 Chapter 5 Updated
1/26
5.MARKET ANALYSIS
5.1. POWER SECTOR SCENARIO IN INDIA: A PERSPECTIVE
5.2. THERMAL POWER IN INDIA
5.2.1. Introduction
5.3. PERFORMANCE AT A GLANCE
5.3.1. Power Supply
Despite significant growth in electricity generation over the years, the shortage of
power continues to exist primarily on account of growth in demand for power
outstripping the capacity additions in generation. The problem of the shortage in supply
becomes worse during peak hours leading to load shedding by many utilities to
maintain the demand-supply balance. The power supply position is characterized by
shortages both in terms of the demand met during peak time and overall energy
supply.
5.3.1.1.Peak Demand & Deficit Position
The demand-supply situation for Peak Power requirement in India for the past few
years is as follows:
(Source: CEA)
(9252) (9945)(9508) (10254)
(11463)(13897)
(18073) (13124 )(15748 )
(12151)
0 MW
20000 MW
40000 MW
60000 MW
80000 MW
100000 MW
120000 MW
140000 MW
160000 MW
9th Plan
End
2002-03 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11
Peak Supply (MW) Peak Deficit (MW)
Graph 5-1: Peak Supply & Deficit Position as of 31st March, 2011
8/4/2019 Chapter 5 Updated
2/26
5.3.1.2.Total Energy Requirement& DeficitPosition
The total Energy requirement in India for the past few years is as follows:
(Source: CEA)
The energy shortage has increased from 7.5 % in 2001-02 to 10.1 % during 2009-10;
the peaking shortage has reduced from 11.8 % in 2001-02 to 8.5 % in 2010-11.
5.3.1.3.Regionwise Peak DemandandEnergy Requirement& Shortages
The region wise power situation for the five regions in India is given below:
Peak Energy
Peak Demand
(MW)Gap (MW)
Shortage
(%)
Energy Requirement
(MU)Gap (MU)
Shortage
(%)
Northern 37431 -3330 -8.9% 258780 -20795 -8.0%
Western 40798 -5979 -14.7 % 268488 -35617 -13.3%
Southern 33256 -2135 -6.4 % 229904 -11923 -5.2%
Eastern 13767 -682 -5.0 % 94558 -4032 -4.3%
3918748093
39866 43258
52735 6609273336 86001
83950
73236
0
100000
200000
300000
400000
500000
600000
700000
800000
900000
1000000
9th Plan
End
2002-03 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11
Peak Supply (MU) Deficit (MU)
Graph 5-2: Total Energy Availability & Deficit Position as of 31st
March, 2011
Table 5-1: Region-wise power situation 2010-2011
8/4/2019 Chapter 5 Updated
3/26
N Eastern 1913 -353 -18.5 % 9861 -869 -8.8%
All India 1222287 -15418 -12.1 861591 -73236 -8.5%
(Source: CEA)
Major shortage in terms of energy and peak power is observed in Western Region of
India which comprises of Maharashtra, Gujarat, Madhya Pradesh, Chattisgarh and Goa.
5.3.2. Installed Capacity
The Indian power sector has grown significantly since 1947 and the power generating
capacity has increased from 1,362 MW in 1947 to about 1,73,626.40 MW as on March
31, 2011.
5.3.2.1.Sector-wise installedcapacity
The existing Sector-wise installed capacity (MW) as on 31stMarch, 2011 is given below:
Graph 5-3:Installed Capacity (MW) as on April 30, 2011: Sector-wise
(Source: CEA)
The State sector still dominates the power sector in terms of installed capacity.
Western region comprising Maharashtra, Chhattisgarh, Madhya Pradesh, Gujarat and
Goa has the maximum generating capacity in the country followed by Southern and
Northern Region.
State
Sector, 82452.58
MW, 48%
Central
Sector, 54412.63
MW, 31%
Private
Sector, 36761.19
MW, 21%
8/4/2019 Chapter 5 Updated
4/26
5.3.2.2.Regionwise installedcapacity(MW)
Existing region wise installed capacity (MW) as on 30th April, 2011 is depicted below:
(Source: CEA)
Chhattisgarh, Maharashtra and Madhya Pradesh have coal reserves and most of thepower plants are located on the bed-head in these States. The land fall of HBJ pipeline
carrying natural gas from Bombay High is located at Hazira, Gujarat and no. of gas
based thermal units are located in Gujarat. Besides, Gujarat has lignite and thermal
power plants based on lignite are also located at the pithead in Gujarat.
5.3.2.3.Fuel wise installedcapacity(MW)
The fuel wise installed capacity (MW) as on 31stMarch, 2011 is depicted below:
46988.55 MW
53697.25 MW
48073.30 MW
23196.34 MW
2329.34 MW
76.12 MW
Northern
Western
SouthernEastern
North Eastern
Islands
Graph 5-4: Existing Installed Capacity (MW) as on 30th April, 2011 : Region-wise
Graph 5-5: Existing Installed Capacity (MW) as on 30th April, 2011: Fuel-wise
8/4/2019 Chapter 5 Updated
5/26
(Source: CEA)
Thermal power still continues to be the backbone of the power supply in India. GoI is
contemplating to increase capacity addition in nuclear power by 2030 so as to reduce
carbon emission and to reduce dependability on coal as the reserve would be depleting.
5.3.2.4.Regionwise andFuel wise installedcapacity(MW)
The region wise and fuel wise installed capacity is given below:
RegionThermal
Nuclear Hydro R.E.S. TotalCoal Gas DSL Total
Northern 24232.50 4134.76 12.99 28380.25 1620.00 13822.75 3165.55 46988.55
Western 31130.50 7903.81 17.48 39051.79 1840.00 7447.50 5357.96 53562.25
Southern 20482.50 4690.78 939.32 26112.60 1320.00 11299.03 9341.67 47473.30
Eastern 18747.88 190.00 17.20 18955.08 0.00 3882.12 359.64 23196.84
N.Eastern 60.00 787.00 142.74 989.74 0.00 1116.00 223.60 2329.34
Islands 0.00 0.00 70.02 70.02 0.00 0.00 6.10 76.12
Hydro, 22%
Nuclear, 3%
R.E.S., 11%
Coal, 54%
Gas, 10%Oil, 1%
Thermal, 65%
Table 5-2: Existing Installed Capacity (MW) as on 30th April, 2011
8/4/2019 Chapter 5 Updated
6/26
Total 94653.38 17706.35 1199.75 113559.48 4780.00 37567.40 18454.52 174361.40
(Source: CEA)
Western region has the maximum installed capacity with majority contribution from
Thermal Generation.
The major capacity additions during 11th Plan would be in thermal accounting for 76%
of the total capacity addition and the capacity addition in hydro would be 15,627 MW
(20% of the total capacity addition).
5.3.2.5.Growthratesininstalledcapacity(MW)
Growth rates in installed capacity are depicted in the following graph:
(Source: CEA)
From the above graph, it is observed that in the recent, past generating capacity has
been growing at a pace much below the required levels. However, during the last 2-3
years due to some focused efforts in the power sector, there have been some
improvements in the growth rates and the sector is expecting major initiatives in terms
of capacity additions.
0.00%
1.00%
2.00%
3.00%
4.00%
5.00%
6.00%
7.00%
8.00%
9.00%
10.00%
0 MW
20000 MW
40000 MW
60000 MW
80000 MW
100000 MW
120000 MW
140000 MW
160000 MW
180000 MW
200000 MW
Installed Capacity YoY Growth(%)
Graph 5-6: Historical Growth in Installed Capacity
8/4/2019 Chapter 5 Updated
7/26
5.4. FUTURE OUTLOOK
5.4.1. Capacity Addition Program
The capacity addition scenario had been dismal in all previous 5 year plans despite the
Government of India (GoI) taking aggressive measures to push the capacity additions.The capacity additions in the earlier two plans missed the targets by nearly 50 per cent.
GoI had set aggressive targets every time but achievement figures painted a dismal
picture.
5.4.1.1.Actual capacityadditionvis-a-visthe targetin last5 yearplans
The actual capacity addition vis-a-vis the target in last four 5 year plans is as under:
(Source: CEA)
A number of Eleventh Plan projects are already behind schedule; CEA has revised the
capacity addition in Eleventh Plan to 62,488 MW as against the Planning Commission
target of 78,700 MW. As of 31st
March, 2011, capacity addition of about 41GW hasbeen achieved.
5.4.2. Demand Forecast (All India 17th EPS)
CEA in its 17th EPS has given detailed estimates of the growth in power demand,
region-wise and for the country as a whole. The summary is given below:
0%
10%
20%
30%
40%
50%
60%
70%
80%
0
10000
20000
30000
40000
50000
60000
70000
8th Plan 9th Plan 10th Plan 11th Plan (underway)
Target Achieved Percentage Achieved
Graph 5-7: Actual Capacity Addition Vs Target Capacity Addition
8/4/2019 Chapter 5 Updated
8/26
RegionPeak Load ( MW ) Energy Requirement ( MU )
2011-12 2016-17 2021-22 2011-12 2016-17 2021-22
Northern 48,137 66,583 89,913 2,94,841 4,11,513 5,56,768
Western 47,108 64,349 84,778 2,94,860 4,09,805 5,50,022
Southern 40,367 60,433 80,485 2,53,443 3,80,068 5,11,659
Eastern 19,088 28,401 42,712 1,11,802 1,68,942 2,58,216
North Eastern 2,537 3,760 6,180 13,329 21,143 36,997
All India 1,52,746 2,18,209 2,98,253 9,68,659 13,92,066 19,14,508
(Source: 17th EPS)
According to the 17th EPS, India's peak demand will reach 152,746 MW with an energy
requirement of 968 billion units (BUs) by the year 2012. By the year 2016-17, the peak
demand will reach 218,209 MW and energy requirement will touch nearly 1,392 BUs.
5.4.3. Supply Forecast for All India at the end of the XIth Plan
To cater to this demand, huge capacity addition is being planned. As of now, nearly
78,700 MW of new power plants are under various stages of implementation /
conceptualisation.
5.4.3.1.Likelycapacityadditionsduring the XIth planperiod(2007-12)
A brief summary of the likely capacity additions fuel wise, sector wise and region
wise, during the XIth plan period (2007-12) is given in the graph:
Table 5-3: Long-term Projected Energy Requirement
Graph 5-8: Likely capacity additions during the XIth plan - Fuel wise
8/4/2019 Chapter 5 Updated
9/26
(Source: CEA)
5.4.3.2.Sectorwise capacityadditioninthe XIthPlan
Sector wise capacity addition in the XIth Plan is as follows:
(Source: CEA)
Hydro, 15627, 20%
Nuclear, 3380, 4%
Wind, 0%
Coal, 52850, 67%
Gas, 6843.4, 9%
Diesel, 0%
Coal, 59693.4, 76%
Hydro
Nuclear
Wind
Coal
Gas
Diesel
State
26,783
34%
Private
15,043
19%
Central
36,874
47%
State
Private
Central
Graph 5-9: Likely capacity additions during the XIth plan - Sector wise
8/4/2019 Chapter 5 Updated
10/26
The Central Sector envisaged major capacity additions comprising 47% of the total
followed by State Sector comprising 34%. The major capacity additions would be by
NTPC, NHPC and DVC in the Central Sector.
5.4.3.3.Region-wise, Fuel-wise capacityadditioninthe XI
th
Plan
The Region-wise, Fuel-wise capacity addition in the XIth Plan is as follows:
(Source: CEA)
In case the above planned capacity additions come up as per the envisaged schedule,
the total installed capacity of the country will nearly reach 2,11,029 MW at the end of
XIth plan. However, as witnessed in the past, the capacity addition targets were never
achieved. Rather in the last two five year plans, the capacity addition targets were
missed by nearly 50%. However, there could be some improvement in achieving the
capacity addition targets during the current XIth plan, still it is felt that the same would
be much below the targeted level and India would continue to be in power deficit
assuming a capacity addition target of 60% during XIth Plan.
Based on the above, it is expected that the total capacity addition during the XI th five
year plan would be 47,220 MW (60% of the envisaged capacity for XIth plan, as against
50% added during Xth plan). Accordingly, the total available capacity at the end of FY
2012 would be 179,549 MW.
7,488
1,170 1,094
3,151 2,724
13,000
20,210
10,886
14,060
1,537440 0
2,940
0 0-
5,000
10,000
15,000
20,000
25,000
Northern Western Southern Eastern North Eastern
Hydro
Thermal
Nuclear
Graph 5-10: Likely capacity additions during the XIth plan - Region wise
8/4/2019 Chapter 5 Updated
11/26
5.4.3.4.CapacityUtilizationof existing InstalledCapacity
Total available Energy and available Peak Load against installed capacity for the period
Oct08 to Sep09 has been tabulated below:
MonthInstalled
Capacity (MW)Energy
Availability (MU)PLF
Peak LoadAvailability (MW)
Peak LoadAvailability
Sep '09 1,52,360 62,201 56.70% 1,01,852 66.85%
Aug '09 1,52,148 65,287 59.60% 99,277 65.25%
July '09 1,51,073 62,685 57.63% 96,282 63.73%
June '09 1,50,323 62,126 57.40% 96,871 64.44%
May '09 1,49,392 62,477 58.08% 95,033 63.61%
Apr '09 1,48,265 60,377 56.56% 97,355 65.66%
Mar '09 1,47,965 61,997 58.19% 96,785 65.41%Feb '09 1,47,715 54,677 51.41% 94,896 64.24%
Jan '09 1,47,457 58,342 54.95% 93,198 63.20%
Dec '08 1,47,402 56,945 53.66% 91,022 61.75%
Nov '08 1,46,902 55,268 52.25% 91,068 61.99%
Oct '08 1,46,752 59,510 56.32% 94,634 64.49%
Average 56.08% 64.23%
(Source: CEA)
Based on above data, it is evident that the total available Energy and total available
Peak Power is 56.08% and 64.23% of the installed capacity. However, considering GoI
impetus on improving operation and maintenance, reduction in Transmission and
Distribution loss and encouragement to Private players in Power sector, available
Energy and available Peak Power considered for arriving at supply position by the end
of XIth plan is 60% and 70% of the installed capacity respectively.
5.4.3.5.Projecteddemandandsupplyatthe endof XIth five yearplan(2011-12)
Taking into consideration the above, the projected demand and supply position at the
end of eleventh five year plan (2011-12) after factoring available Energy and available
Peak Power at 57% and 70% of the installed capacity respectively is given below:
Table 5-4: Total Energy & Peak Load Availability Vs Installed Capacity
8/4/2019 Chapter 5 Updated
12/26
Region(in MW)
%(in MU)
%PeakDemand
PeakSupply
DeficitEnergy
DemandEnergySupply
Deficit
All India 1,52,746 142765 -9981 -6.5 968659 948836 -19823 -2.0
(Source: CEA)
The country shall face a peak power deficit of 27,000 MW and 72,536 million units in
terms of energy supply at the end of XIth five year plan.
5.4.3.6.Region-wise demandandsupplyatthe endofthe XIth five yearplan
Following is the region-wise demand and supply position at the end of the XIth five year
plan:
Region(in MW)
%(in MU)
%PeakDemand
PeakSupply
DeficitEnergy
DemandEnergySupply
Deficit
All India 1,52,746 1,25,684 -27,062 -17.72% 9,68,659 9,43,709 -24,949 -2.64%
Northern 48,137 34,357 -13,780 -28.63% 2,94,841 2,57,974 -36,867 -14.29%
Western 47,108 36,312 -10,796 -22.92% 2,94,860 2,72,649 -22,210 -8.15%
Southern 40,367 32,419 -7,948 -16.69% 2,53,443 2,43,421 -10,021 -4.12%
*Data for Eastern & North-eastern states not depicted.(Source: CEA)
The western region as well as the northern region together would have deficit ofapproximately 24,000 MW and 88,000 million units by the end of 11th Plan.
5.5. POWER SCENARIO REGION WISE
5.5.1. Power Scenario in Northern India
5.5.1.1.Installed capacity-Sector Wise
The total installed capacity in the northern region as on 31stMarch, 2010 is 42,189 MW.
Details of the installed capacity in Northern region are given below:
Table 5-5: Projected Demand & Supply Position at the end of XIth Five Year Plan
Table 5-6: Projected Demand & Supply Position at the end of XIth Five Year Plan
8/4/2019 Chapter 5 Updated
13/26
Most of the generating capacity is in the State Sector and the Private sector comprises
only 9% of the total installed capacity.
5.5.1.2.Installedcapacity-FuelWise
(Source: CEA)
Most of the generating capacity in the northern region is based on Thermal Power
Plants, which comprises 51% of coal and gas comprises 9%, followed by Hydro (30%).
State, 23902
MW, 51%
Private, 4079
MW, 9%
Central, 19007
MW, 40%
Nuclear, 3.45%
Hydro, 29.42%
R.E.S., 6.74%Coal, 51.57%
Gas, 8.80%Diesel, 0.03%
Coal, 60.40%
Graph 5-11: Installed Capacity as on 3th April, 2011: Sector-wise
Graph 5-12: Installed Capacity as on 30th April, 2011: Fuel-wise
8/4/2019 Chapter 5 Updated
14/26
5.5.1.3.Demand-supplypositionofpeakpower
The demand-supply position of peak power in Northern India over the last tan years is
given below:
(Source: CEA)
The peak power requirement during April- December, 2010 was 37,431 MW and the
deficit was 3,330 MW.
5.5.1.4.Demand-supplypositionofpeakpower
The demand-supply position of total energy in Northern India over the last nine years is
given below:
(1854) (2203) (1546)
(2709)(2954)
(4872)(2967) (3530)
(5720)
(3330)
0
5000
10000
15000
20000
25000
30000
35000
40000
45000
9th Plan
End
2002-03 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11
Energy Supply (MW) Energy Deficit (MW)
Graph 5-13: Historical Demand-Supply of Peak Power
Graph 5-14: Historical Demand-Supply of Total Energy
8/4/2019 Chapter 5 Updated
15/26
The energy deficit during April, 2010- March, 11 was 20,795 MU.
5.5.1.5.State-wise demand-supplypositioninNorthernRegion
The state-wise demand-supply position in Northern Region for the period FY2010-11 is
shown in the table below:
Peak
Demand(MW)
Peak
Gap(MW)
Peak
Gap(%)
Energy
Requirement(MU) Gap(MU) Gap(%)
Chandigarh 301 0 0.0% 1,519 0 0%
Delhi 4,810 -71 -1.5% 25,559 -66 -0.3%
Haryana 6,142 -568 -9.2% 34,552 -1,926 -5.6%
Himachal Pradesh 1,278 -91 -7.1% 7,626 -262 -3.4%
Jammu and Kashmir 2,369 -798 -33.7% 13,571 -3,390 -25.0%
Punjab 9,399 -1,461 -15.5% 44,484 -2,685 -6.0%
Rajasthan 7,729 -287 -3.7% 45,261 -425 -0.9%
Uttar Pradesh 11,082 -410 -3.7% 76,292 -11,446 -15.0%
(7973) (12392)
(8852)(16140)
(19980)(22139)
(23650)(25153)
(29570) (20795)
0
50000
100000
150000
200000
250000
300000
9th Plan
End
2002-03 2003-04 2004-05 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11
Energy Supply (MU) Energy Deficit (MU)
Table 5-7: State-wise Demand-Supply Position for the Period 2010-11
8/4/2019 Chapter 5 Updated
16/26
Uttarakhand 1,520 0 0% 9,850 -595 -6.0%
(Source: CEA)
The northern region is facing peak power deficit of 3,330 MW while the energy shortage
was 20,795 MU. The major States where the shortfall is occurring are Haryana, J&K,Punjab and Uttar Pradesh. The reason is due to industrialization and development
around Delhi and extensive use of power in agriculture.
5.5.1.6.The demandforecastforNothernRegionasper17th EPS
As per 17th EPS, in 2011-12 Northern Region will have a peak demand of 48,137 MW
while the energy requirement is expected to touch 2,94,892 MU. The State-wise
demand forecast for Northern India is given below:
Peak Load (MW) Energy Requirement (MU)
2011-12 2016-17 2011-12 2016-17
Delhi 6,092 8,729 36,293 52,762
Haryana 6,839 9,375 38,417 54,305
Himachal Pradesh 1,611 2,194 9,504 13,136
Jammu & Kashmir 2,063 2,790 11,202 15,272
Punjab 11,000 14,441 60,489 82,572
Rajasthan 8,482 11,404 48,916 67,767
Uttar Pradesh 13,947 19,623 79,268 1,10,665Uttarankhand 1,533 2,085 8,445 11,668
Chandigarh 420 602 2,308 3,367
Total 48,137 66,583 2,94,842 4,11,514
(Source: 17th EPS)
The State of Uttar Pradesh, Punjab and Haryana would be the demand centres for peak
power as well as energy.
5.5.1.7.CapacityAdditionduring the XIth five yearplan:
Likely capacity addition sector-wise and state-wise in the northern region during the XIth
five year plan is given below:
HydroThermal
Nuclear Wind TotalCoal Gas Diesel Total
Table 5-8: State-wise Demand Forecast for Northern India
Table 5-9: Likely capacity Addition During the XIth Plan
8/4/2019 Chapter 5 Updated
17/26
State 964 5,870 1,720 0 7,590 0 0 8,554
Private 1,792 2,680 0 0 2,680 0 0 4,472
Central 4,732 2,730 0 0 2,730 440 0 7,902
Total 7,488 11,280 1,720 0 13,000 440 0 20,928
(Source: CEA)
The likely capacity addition during 11th Plan in Northern Region would be mainly in
hydro and coal and the most of the additions would be in the State and Central Sector.
Demand supply forecast for the Northern Region is based on success rate of 60% of the
envisaged capacity addition in XIth Plan.
5.5.1.8.Demand-supplyforecastforthe NothernRegionin2011-12
The demand-supply forecast for the Nothern Region in 2011-12 is depicted below:
RegionPeak
Demand(MW)
PeakSupply(MW)
Deficit %EnergyNeed(MU)
EnergySupply(MU)
Deficit %
Northern 48,137 43790 --4347 -9.0% 2,94,841 293501 -1340 -0.5%
(Source: CEA)
It may be observed from table above that Northern Region will have deficit in peak
power as well as energy requirements at the end of eleventh five year plan (2012) to
the tune of 9% and 0.5% respectively.
5.6. POWER SCENARIO IN UTTARAKHAND
5.6.1. The installed capacity in Uttarakhand
The installed capacity in Uttarakhand was 2455.24 MW as on 31st March, 2010. The
break-up of the same is given below:
Sector HydroThermal
Nuclear R.E.S. TotalCoal Gas Diesel
STATE 1252.15 0.00 0.00 0.00 0.00 134.12 1386.27
PRIVATE 400.00 0.00 0.00 0.00 0.00 12.05 412.05
Table 5-10: Demand-Supply Forecast for the Northern Region in 2011-12
Table 5-11: Installed Capacity as on 31st April, 2011
8/4/2019 Chapter 5 Updated
18/26
CENTRAL 304.03 261.26 69.35 0.00 22.28 0.00 656.92
Total 1956.18 261.26 69.35 0.00 22.28 146.17 2455.24
(Source: CEA)
Uttarakhand has an installed capacity of 2455.24 MW which is entirely in the State and
Central Sector as of now and number of projects are being developed by private sector
players which is likely to be commissioned in XIth Plan.
5.6.2. Demand and Supply position in Uttarakhand
The historical demand and supply position of peak power and energy in Uttarakhand for
the year 2005-06 onwards is given below:
Time
Peak
Demand
(MW)
Peak Deficit
/Surplus
(MW)
Peak Deficit
/Surplus (%)
Energy
Requirement
(MU)
Energy Deficit
/Surplus (MU)
Energy Deficit
/Surplus (%)
2006 991 -134 -13.5% 5155 -147 -2.9%
2007 1108 -117 -10.6% 5957 -358 -6.0%
2008 1200 -50 -4.2% 7047 -202 -2.9%
2009 1267 0 0.0% 7762 -93 -1.2%
2010 1397 -84 -6.0% 8904 -583 -6.5%
2010-11 1,520 0 0 9,850 -595 -6.0%
(Source: CEA)
The energy requirement has gone up from 5155 MU in the FY 2005-06 to 8921 MU in
FY 2009-10. Sikkim is a net exporter of energy from April to October while it is an
importer of energy for the balance period.
5.6.3. Peak load demand and energy requirement forecasts
The forecasts for the peak load demand and energy requirement for the state of Sikkim
are given below:
Table 5-12: Historical Demand-Supply Position of Peak Power & Energy in
Uttarakhand
Table 5-13: Demand-Supply Forecast for the Northern Region in 2011-12
8/4/2019 Chapter 5 Updated
19/26
PeakDemand
(MW)
PeakSupply(MW)
Deficit %Energy
Need (MU)
EnergySupply(MU)
Deficit %
1533 2305 772 50.4% 8445 12789 4344 51.4%
(Source: CEA)
The above forecast was done by CEA in its report on Seventeenth Electric Power Survey
of India published in the month of March, 2007. The actual data used for forecast was
for the period 2004-05 only and balance projections were done by extrapolation,
however, vigorous industrial development has happened after the aforesaid period.
Hence, despite the rise in demand for energy, the shortfall in peak power and energy
availability shall prevail to continue in the state of Sikkim.
In view of the foregoing, the peak power requirement by the end of 2011-12 would be
much above 93 MW and the corresponding energy requirement would be above 320
MU. State of Sikkim would be power deficit State once the industrial development
activities peak up. However, the power generation trend in the State indicates that
Sikkim is a net exporter from April October and net importer during November -
March on account of low generation of hydro in winter and increase in demand of
power for heating during winter.
5.7. POWER TRADING IN INDIA
The power requirement of a region can be gauged from the power transactions done
through bilateral trading, energy exchange and unscheduled interchange. The power
transactions done by the various regions are depicted below:(million units)
Month Northern Western Southern EasternNorth
EasternTotal
Aug '08 280 207 669 -360 -302 494
Sep '08 745 131 494 -510 -230 630
Oct '08 723 373 347 -526 -180 738
Nov '08 215 754 532 -587 -97 817
Dec '08 90 652 939 -768 -53 860
Jan '09 889 -179 650 -410 -25 924Feb '09 376 -205 874 -384 2 663
Mar '09 191 -482 1,084 -181 57 669
April '09 -10 -562 1,215 -320 40 364
May '09 521 -486 832 -138 -11 718
June '09 1,126 -6 -125 -530 -51 413
(Source: CERC)
Table 5-14: Actual Net Power Position in India - Export (-) / Import (+)
8/4/2019 Chapter 5 Updated
20/26
From the table above, it emerges that all regions are importing power throughout the
period of August 08 to June 09.
While discussing the peak demand and energy requirement it has been observed that
northern region, western region and southern region are the major power deficit region
and will remain so in future on account of economic development taking place inaforesaid regions.
5.7.1. Sale of Power
The power generated from CHEPP is proposed to be sold as merchant power, i.e.
through short-term PPA. The power trading done under short term PPA is through
Bilateral trade (3.78%), Unscheduled Interchanges (3.05%) and through newly
established Power Exchanges (0.59%). The graphical representation of power traded
through various options available under short term agreements for the period April, 09
to March 10 is depicted below:
(Source: CERC)
0.00% 1.00% 2.00% 3.00% 4.00% 5.00% 6.00%
Apr/09
May/09
Jun/09
Jul/09
Aug/09
Sep/09
Oct/09
Nov/09
Dec/09
Jan/10
Feb/10
Mar/10
% of Generation
UI
Exchange
Bilateral
Graph 5-15: Power traded through various options under short-termagreements
8/4/2019 Chapter 5 Updated
21/26
The average weighted price for power traded through short term agreements works out
to Rs. 5.71 per unit. The average weighted price for transaction through Bilateral Trade,
Energy Exchanges and UI works out to Rs.6.41, Rs.5.73 and Rs. 4.99 respectively.
The detailed graphical presentation for the per-unit rate for short-term transactions for
the year 2009 is depicted below:
It is evident from the graph above that the weighted Weighted Average Price of
Electricity Transacted through Licensees and PXs is Rs. 5.19. Thus, considering the
energy deficit market of India, particularly the Northern, Western Regions and Southern
Region the power generated from the Chuzachen Hydro-electric Project can be easily
traded at a minimum weighted price of Rs. 5.00 per unit.
Recently, CERC, on experimental basis, has introduced a cap of Rs. 8.00 per unit for
sale of power through energy exchanges. However, even after the introduction of the
aforesaid norms the power continues to trade around the Rs. 5.00 mark.
5.7.2. Frequency Spectrum
The maximum, minimum and average frequencies for the NEW (Northern, Eastern &
Western) regions for the period from July 08 to August 09 are depicted below:
0
2
4
6
8
10
12
Bilateral
PX (IEX)
PX (PXIL)
UI (New gRID)
UI (SR Grid)
Graph 5-16: Per-unit rate for short-term transactions
8/4/2019 Chapter 5 Updated
22/26
(Source: WRPC)
The frequency profile in different frequency bands for the NEW regions for the period
July 08 to August 09 is depicted below:
(Source: WRPC)
47.50
48.00
48.50
49.00
49.50
50.00
50.50
51.00
Aug
'09
Jul '09Jun
'09
May
'09
Apr'
09
Mar'
09
Feb
'09
Jan
'09
Dec
'08
Nov
'08
Oct
'08
Sep
'08
Aug
'08
July
'08
Max Min Average
-
10.00
20.00
30.00
40.00
50.00
60.00
70.00
Below
48.50
48.50 -
48.80
48.80 -
49.20
49.20 -
49.50
49.50 -
49.80
49.80 -
50.20
50.20 -
50.30
50.30 -
51.00
51.00 -
51.50
Above
51.50
Aug '09Jul '09
Jun '09
May '09
Apr' 09
Mar' 09
Feb '09
Jan '09
Dec '08
Nov '08
Oct '08
Sep '08
Aug '08
Graph 5-17: Frequency data for the NEW regions
Graph 5-18: Frequency profile for the NEW regions
8/4/2019 Chapter 5 Updated
23/26
The maximum, minimum and average frequencies for the SR (Southern) region for the
period from July 08 to August 09 are depicted below:
(Source: SRLCD)
The frequency profile in different frequency bands for the SR region for the period July
08 to August 09 is depicted below:
47
47.5
48
48.5
49
49.5
50
50.5
51
51.5
Maximum
Minimum
Average
0
10
20
30
40
50
60
70
80
90
100
Below 48.5 48.5 - 49 49 - 49.5 49.5 - 50.2 Above 50.2
Apr-10
May-10
Jun-10
Jul-10
Aug-10
Sep-10
Oct-10
Nov-10
Dec-10
Jan-11
Feb-11
Mar-11
Graph 5-19: Frequency data for the SR region
Graph 5-20: Frequency profile for the SR region
8/4/2019 Chapter 5 Updated
24/26
(Source: SRLCD)
After introduction of Availability Based Tariff (ABT), frequency profile has improved and
frequency lies for most of time in the frequency band of 49.5 Hz to 49.8 Hz for the NEW
Regions. As for the SR Region, the frequency lies mostly in the band of 49.20 Hz to
50.30 Hz.
The discipline in grid operation is due to the deterrent of paying UI charges, however, it
does not imply that the power requirement has been fulfilled and the country is deficit
in energy and peaking power.
5.8. POWER OFFTAKE ARRANGEMENT
GIL and Tata Power Trading Company Limited (TPTCL) have entered into a Power
Purchase Agreement (PPA) for sale of power from CHEPP with a net tariff of Rs. 4.25
per unit on 05.05.2009.
The brief feature of the PPA is given below and the terms and conditions of the PPA are
provided in Annexure XVIII.
Salient features of the PPA are given below:
Parameter Terms
Capacity tied-up85% of the actual generated power out of the installed capacity of 110MW.
Tariff and tradingmargin
Average annual base tariff of Rs.4.25 per kWh at delivery point for a
block of 5 years Trading margin:--3% of the sales price or trading margin as per CERC whichever is lowerfor electricity sold on short term basis.-2% of the sales price or trading margin as per CERC whichever is lowerfor electricity sold on long term basis Upside Sharing- Any upside from the base tariff for sale on short termbasis to be shared in the ratio of 87.5:12.5 between GIL and TPTCLsubject to CERC regulations.
Term of Agreement 10 years from COD
TPTCLs obligations
No take or pay obligation. Both the parties shall endeavour to promotethe sale of electricity on short term basis. Off-take the contracted capacity for which open access approval hasbeen granted Payment of transmission charges beyond delivery point Obtain and maintain short term open access
TPTCL is a wholly owned subsidiary of India's largest private sector power utility, The
Tata Power Company Limited. It is one of the leading power trading companies in India
catalyzing development of Indian electricity market. TPTCL has been buying and selling
8/4/2019 Chapter 5 Updated
25/26
power from various State Utilities, Captive Power Plants and Independent Power
Producers across all the regions in India by entering into long-term/ medium-term and
short-term Agreements.
TPTCL has grown at a compounded average growth rate exceeding 100% since
inception. It has taken an important position amongst the various trading companies
and is recognized as an efficient and reliable trading company.
The revenue & power sale value for FY 05 to FY 09 is given below:
Particulars Sales (MUs) Revenue (Crs.)
FY05 76 20
FY06 675 208
FY07 1205 604
FY08 1711 896
The detailed profile of TPTCL is given in Annexure XIX.
5.9. CERTIFIED EMIISSION REDUCTION
The CHEPP will produce 484.1MU of electrical energy annually with the net energy to
the grid being 469.5 MU after deducting 0.5% for auxiliary consumption, 0.5% for
transformation losses and 2% for transmission losses.
According to the Tool to calculate the emission factor for an electricity system which is
referred to in the methodology ACM0002, the baseline emissions are the amount of
electricity produced times the grid emission factor which is the Combined Margin (CM),
calculated as the simple average of the Operating Margin (OM) emission factor and the
Build Margin (BM) emission factor.
The CHEPP is expected to export 469.5 MU power to Indias Eastern Power Grid. The
Project will reduce 4,83,526 tonnes of CO2 equivalent of emissions of greenhouse gases
(GHGs) annually at a combined Margin value of 1.0297 tCO2/MWh.
Financial Benefit:
The CER entitlement at 4.83 lakh per year would provide scope of additional funding
through forward selling of the entitlements. The project would be entitled to additional
cash flows of approximately Rs. 25 crore annually calculated at a conservative rate of
Euro 8 per CER (1 Euro @ Rs. 65).
8/4/2019 Chapter 5 Updated
26/26
The revenue from the CER has not been considered in financial analysis, however, it is
imperative to mention that in the event of delay in commissioning of the project beyond
August, 2010, GIL is having provisions for cash flow to meet shortfalls if any.
Current Status
The Project Design Document (PDD) has been duly validated by Designated National
Authority (DNA) and Designated Operational Entity (DOE) and is due to be uploaded on
the site of the Executive Board of the United Nations Framework Convention on Climate
Change (UNFCCC).
Activity wise status is given below:
S.N Activity Agency Status / CompletionDate
01 Appointment of Consultant for CDMRegistration and sale of CERs
M/s Zenith EnergyServices Pvt. Ltd.,Hyderabad
06.09.2007
02 Validation by Designated NationalAuthority (DNA)
MoEF, GoI Completed
03 Appointment of Designated Operational
Entity (DOE)
TUV-Nord CarbonServices, Germany
25.06.2008
04 Validation by DOE TUV-Nord CarbonServices, Germany
Completed
05 Registration at UNFCCC UNFCCC Expected by Jan2010
The CHEPP is expected to be registered at UNFCCC by January, 2010.