Chapter 8- Project Management

Embed Size (px)

Citation preview

  • 8/13/2019 Chapter 8- Project Management

    1/65

    Chapter 8: Project Management

    Dr. Angela de Oliveira

    RES EC 313

    QUANTITATIVE METHODS

  • 8/13/2019 Chapter 8- Project Management

    2/65

    HOUSEKEEPING

    You will get exams back on Thursday

    Where we are in the term:

    Exam 1: Linear and Nonlinear programming. Some of ourmost powerful analytical tools!

    New Material: We will cover a number of popular ways

    numbers help managers to make better decisions.

    Our 1stway: Project management using networks.

  • 8/13/2019 Chapter 8- Project Management

    3/65

    TODAYS GAME PLAN

    The Elements of Project Management

    CPM/PERT

    Probabilistic Activity Times

    Project Crashing and Time-Cost Trade-Off

    Formulating the CPM/PERT Network as a Linear

    Programming Model

  • 8/13/2019 Chapter 8- Project Management

    4/65

    Network representation is useful for project analysis.

    Networks show how project activities are organized and are used

    to determine time duration of projects.

    Network techniques used are:

    CPM (Critical Path Method) PERT (Project Evaluation and Review Technique)

    Now called CPM/PERT

    Developed independently during late 1950s.

    Build upon the Gantt Chart

    Overview

  • 8/13/2019 Chapter 8- Project Management

    5/65

    Elements of Project Management

    Management is generally perceived as concerned withplanning, organizing, and control of an ongoingprocess

    or activity.

    Project management is concerned with control of an

    important activity for a relatively short per iod of time

    after which management effort ends.

  • 8/13/2019 Chapter 8- Project Management

    6/65

    Elements of Project Management

    Project Planning

    Objectives

    Project scope

    Contract requirements

    Schedules

    Resources

    Personnel

    Control

    Risk and problem analysis

  • 8/13/2019 Chapter 8- Project Management

    7/65

    Elements of Project Management

    Project Planning

    Objectives

    Detailed project statement

    Include what will be accomplished

    How it feeds into the strategic plan Time, cost, and return estimates

    Project scope

    Contract requirements

    Schedules

    Resources

    Personnel

    Control

    Risk and problem analysis

  • 8/13/2019 Chapter 8- Project Management

    8/65

    Elements of Project Management

    Project Planning

    Objectives

    Project scope

    Approach to the project

    Project justification & benchmark for success

    Technological and resource feasibility

    Major tasks and schedule

    Contract requirements

    Schedules

    Resources

    Personnel

    Control

    Risk and problem analysis

  • 8/13/2019 Chapter 8- Project Management

    9/65

    Elements of Project Management

    Project Planning

    Objectives

    Project scope

    Contract requirements

    Structure of managerial, reporting, & performance

    responsibilities

    Include staff, suppliers, subcontractors,

    Include projected organizational structure

    Schedules

    Resources

    Personnel

    Control

    Risk and problem analysis

  • 8/13/2019 Chapter 8- Project Management

    10/65

    Elements of Project Management

    Project Planning

    Objectives

    Project scope

    Contract requirements

    Schedules

    List of all major tasks, events and subschedulesuse to make a

    master schedule

    Resources

    Personnel Control

    Risk and problem analysis

  • 8/13/2019 Chapter 8- Project Management

    11/65

    Elements of Project Management

    Project Planning

    Objectives

    Project scope

    Contract requirements

    Schedules

    Resources Project budget

    Procedures for budget control

    Personnel

    Control

    Risk and problem analysis

  • 8/13/2019 Chapter 8- Project Management

    12/65

    Elements of Project Management

    Project Planning

    Objectives Project scope

    Contract requirements

    Schedules

    Resources

    Personnel

    Identify and recruit project team

    Be sure to list special skills and training needed

    Control

    Risk and problem analysis

  • 8/13/2019 Chapter 8- Project Management

    13/65

    Elements of Project Management

    Project Planning

    Objectives Project scope

    Contract requirements

    Schedules

    Resources

    Personnel

    Control

    Procedures for monitoring and evaluating progress and

    performance

    Include schedules and cost

    Risk and problem analysis

  • 8/13/2019 Chapter 8- Project Management

    14/65

    Elements of Project Management

    Project Planning

    Objectives Project scope

    Contract requirements

    Schedules

    Resources

    Personnel

    Control

    Risk and problem analysis

    Anticipate uncertainties, potential problems

  • 8/13/2019 Chapter 8- Project Management

    15/65

    Project Return

    Lots of projects could be chosen. They are often selected based on ROI Return on investment (ROI) is a measure used to evaluate

    projects calculated by dividing the dollar gain minus the

    dollar cost by the dollar cost.

    gain from project - cost of projectROI

    cost of project

    ROI can be used to rank projects

    Caution: Not all project benefits can be measured in dollars

  • 8/13/2019 Chapter 8- Project Management

    16/65

    Project team typically consists of a group of individuals from various

    areas in an organization and often includes outside consultants.

    Project team may include workers.

    Members of engineering staff often assigned to project work.

    Most important member of project team is theproject manager.

    Project manager is often under great pressure because of

    uncertainty inherent in project activities and possibility of failure.

    Potential rewards, however, can be substantial.

    Project manager must be able to coordinate various skills of team

    members into a single focused effort.

    The Project Team

  • 8/13/2019 Chapter 8- Project Management

    17/65

    Scope Statement

    Scope Statement Document providing common understanding of project.

    Justification describing the factors giving rise to need forproject.

    Expected results and what constitutes success.

    List of necessary documents and planning reports.

    Statement of work (SOW)

    Planning document for individuals, team members, groups,

    departments, subcontractors and suppliers

    Describes what is required for successful, on time

    completion.

  • 8/13/2019 Chapter 8- Project Management

    18/65

    ELEMENTS OF PROJECT MANAGEMENT

    WORK BREAKDOWN STRUCTURE (WBS)

    Organizational chart

    WBS breaks down project into major components (modules).

    Modulesare further broken down into activitiesand, finally, into

    individual tasks.

    Identifies activities, tasks, resource requirements and relationships

    between modules and activities. Helps avoid duplication of effort.

    Basis for project development, management, schedule, resources and

    modifications.

    Approaches for WBS development:

    1. Top down process

    What components constitute this level?

    2. Brainstorm entire project

    Put everything on sticky notes and then organize.

  • 8/13/2019 Chapter 8- Project Management

    19/65

    Sample Work Breakdown Structure

  • 8/13/2019 Chapter 8- Project Management

    20/65

    Responsibility Assignment Matrix

    WBS is very big. It gives you the big picture, but not very

    manageable.

    Use an organizational breakdown structure (OBS).

    OBS is a table or a chart showing which organizational units

    are responsible for work items. OBS leads to the responsibility assignment matrix (RAM)

    RAM helps organize smaller elements

    RAM shows who is responsible for doing the necessary work in

    the project

    This can include overall responsibility, who actually does the

    work, and who acts in a support capacity

    Project manager assigns work elements to organizational units,

    departments, groups, individuals or subcontractors.

  • 8/13/2019 Chapter 8- Project Management

    21/65

    Sample Responsibility Assignment Matrix

    j S i

  • 8/13/2019 Chapter 8- Project Management

    22/65

    Project Scheduling

    Project schedule evolves from planning documents, with focus on

    timely completion.

    Critical element in project managementsource of most conflicts and

    problems.

    Schedule development steps:

    1. Define activities,

    2. Sequence activities,

    3. Estimate activity times,4. Develop schedule.

    Gantt chart and CPM/PERTtechniques can be useful.

    Computer software packages available, e.g. Microsoft Project.

    G Ch

  • 8/13/2019 Chapter 8- Project Management

    23/65

    Gantt Chart

    Popular, traditional technique, also known as a bar chart -developed

    by Henry Gantt (1914).

    A visual display of project schedule showing activity start and finish

    times and where extra time is available.

    Suitable for projects with few activities and precedence

    relationships.

    Drawback: precedence relationships are not always discerniblewhich limits charts use to smaller projects

    S l G Ch

  • 8/13/2019 Chapter 8- Project Management

    24/65

    Sample Gantt Chart

    Takes 3 months. Nothing else can happen until completed.

    Start at same time Slack

    P j t C t l

  • 8/13/2019 Chapter 8- Project Management

    25/65

    Project Control

    Process ofensuring progress toward successful completion.

    Monitoring project to minimize deviations from project plan and

    schedule.

    Corrective actions necessary if deviations occur.

    Key elements of project control

    Time managementfrequent monitoring and updates

    Cost managementsome cost estimates are wrong. May have

    extra costs if behind schedule Performance managementmonitoring progress and

    developing status updates

    Earned value analysis (EVA)standard for numerically

    measuring a projects progress

    CPM/PERT

  • 8/13/2019 Chapter 8- Project Management

    26/65

    There are two main presentation styles:

    1stPresentation style: Activity-on-Arc (AOA) Network

    2ndPresentation style: Activity-on-Node (AON) Network

    I will follow the conventions used in your text

    BUTeven with just these two styles, you can see these networks

    drawn a LOT of different ways.

    They will all contain the same pieces of information But they may look very different from each other

    CPM/PERT

    Th P j t N t k

  • 8/13/2019 Chapter 8- Project Management

    27/65

    Copyright 2013 Pearson Education, Inc. Publishing as Prentice Hall

    1stPresentation style: Activity-on-Arc (AOA) Network

    A branch reflects an activityof a project.

    A node represents the beginning and end of activities, referred to as

    events.

    Branches in the network indicate precedence relationships. When an activity is completed at a node, it has been realized.

    The Project Network

    CPM/PERT

  • 8/13/2019 Chapter 8- Project Management

    28/65

    EXAMPLE PROJECT NETWORK:

    HOUSE BUILDING PROJECTNumber Activity Predecessor Duration

    1 Design house and obtain financing -- 3 months

    2 Lay foundation 1 2 months

    3 Order and receive materials 1 1 month

    4 Build house 2,3 3 months

    5 Select paint 2, 3 1 month

    6 Select carpet 5 1 month7 Finish work 4, 6 1 month

    Activity on Arc (AOA) : The Project Network

  • 8/13/2019 Chapter 8- Project Management

    29/65

    Activities can occur at the same time (concurrently).

    Network aids in planning and scheduling.

    Time duration of activities shown on branches.

    Activity-on-Arc (AOA) : The Project Network

    Activities are located on

    the arrows, known as

    branches

    Time

    The nodes are events

    They indicate the beginning and

    end of activities

    Dummy activities are

    placeholders: see next slide

    Dummy Activities

  • 8/13/2019 Chapter 8- Project Management

    30/65

    Two or more activities cannot share the same start and end nodes.

    So, how do you handle two separate activities that start and end at

    the same time??

    Use a dummy activity

    A dummy activity shows a precedence relationshipbut reflectsno passage of time.

    It is represented on the network with a dashed line.

    Dummy Activities

    A ti it N d (AON) P j t N t k

  • 8/13/2019 Chapter 8- Project Management

    31/65

    Activity-on-Node (AON) - Project Network

    for the House Building Project

    2nd

    Presentation style: Activity-on-Node (AON) Network A node represents an activity, with its label andtime shown

    on the node

    The branches show the precedence relationships

    Convention used in Microsoft Project software

    Activity on Node (AON) Project Network

  • 8/13/2019 Chapter 8- Project Management

    32/65

    Activity-on-Node (AON) - Project Network

    for the House Building Project

    Everything is on the node: Branches (arrows) only show precedence

    Label,

    Not always included

    Activity number

    from the table

    Timeneeded

    This says that activity 5, which is to

    select paint, can begin after both

    activity 2&3 are finished. It will take1 period.

    The Project Network

  • 8/13/2019 Chapter 8- Project Management

    33/65

    The Project Network

    Paths Through a Network

    Path Events

    A 1247

    B 12567

    C 1347

    D 13567

    We need to identify the paths through the network Helps figure out how long the project will take

    Also identify the most crucial activities to finishing on time

    What to do:

    Trace out all of the ways you can get from start to finish

    Then, figure out how long it takes (next slide).

    The Project Network

  • 8/13/2019 Chapter 8- Project Management

    34/65

    Add up the times (the bottom number on each node) along the path

    The cri tical pathis the longest path through the network; the

    minimum time needed to complete the network.

    Path A: 1 2 4 7 3 + 2 + 3 + 1 = 9 months ***

    Path B: 1 2 5 6 7 3 + 2 + 1 + 1 + 1= 8 months

    Path C: 1 3 4 7 3 + 1 + 3 + 1 = 8 months

    Path D: 1 3 5 6 7 3 + 1 + 1 + 1 + 1 = 7 months

    The Project Network

    The Critical Path

  • 8/13/2019 Chapter 8- Project Management

    35/65

    ACTIVITY SCHEDULING IN ACTIVITY-ON-NODE

    CONFIGURATION

    This part is

    what we had

    before:

    This is new:

    Helps with overall planning

    The Project Network

  • 8/13/2019 Chapter 8- Project Management

    36/65

    ES (Earliest start) is the earliest time an activity can start:

    (Earliest finish) is the earliest start time plus the activity time:

    The Project Network

    Activity Scheduling : Earliest Times

    EF ES t

    { }ES Maximum EF immediate predecessors

    ES=0 since this is the

    1stactivity

    EF = 0 + 3 = 3

    ES=3 since that is EF of

    activity 1EF = 3 + 1 = 4

    ES = 5 because that is the longest EF

    time of the activities before this one (2

    & 3)

    EF = 5 + 3 = 8

    The Project Network

  • 8/13/2019 Chapter 8- Project Management

    37/65

    WorkBACKWARDS

    LS is the latest time an activity can start without delayingcritical path time:

    LF is the latest finish time:

    The Project Network

    Activity Scheduling : Latest Times

    LS LF t

    { }LF Minimum LS following activities

    LF=9, no later

    activities.LS = 9-1 = 8LF = min{8} = 8LS = 8-1 = 7

    LF = min{8} = 8

    LS = 8-3 = 5

    LF = min{5, 6} = 5

    LS = 5-2 = 3

    On the critical path, the

    ES & LS times will be

    the same!

    The Project Network

  • 8/13/2019 Chapter 8- Project Management

    38/65

    Slackis the amount of time an activity can be delayed without

    delaying the project: S = LSES = LF - EF Slack Time exists for those activities not on the critical path for

    which the earliest and latest start times are not equal.

    Shared Slack is slack available for a sequence of activities.

    The Project Network

    Activity Slack Time (1 of 2)

    *Critical path

    Activity LS ES LF EF Slack, S*1 0 0 3 3 0

    *2 3 3 5 5 0

    3 4 3 5 4 1

    *4 5 5 8 8 0

    5 6 5 7 6 1

    6 7 6 8 7 1

    *7 8 8 9 9 0

    Probabilistic Activity Times

  • 8/13/2019 Chapter 8- Project Management

    39/65

    Activity time estimates usually cannot be made with certaintyhow

    to we account for this?

    PERT used for probabil istic activity times.

    In PERT, threetime estimates are used:

    most l ikelytime (m), the optimistictime (a), and the pessimistictime (b).

    You will write out the nodes of your network with all 3 times

    instead of 1 time (next slide)

    Probabilistic Activity Times

    Probabilistic Activity Times:

  • 8/13/2019 Chapter 8- Project Management

    40/65

    Probabilistic Activity Times:

    Southern Textile Company example

    Activity #

    3 Activity

    times

    Probabilistic Activity Times

  • 8/13/2019 Chapter 8- Project Management

    41/65

    To get mean and variance, we need a distribution: Beta distribution.

    1streason: convention

    2nd reason: can approximate mean and variance with only 3

    estimates

    3rdreason: continuous distribution but no predetermined shape(takes on shape of our estimates)

    Recall: most likely(m), optimistic (a), &pessimistic(b).

    To estimate the mean and variance of a Beta PERTdistribution:

    Mean (expected time):

    Variance:

    a 4m bt6

    2b - a

    6v

    Probabilistic Activity Times

    Calculating Probabilistic Activity Times

  • 8/13/2019 Chapter 8- Project Management

    42/65

    Calculating Probabilistic Activity Times

    =(6 + (4*8) + 10)/6

    =(3 + (4*6) + 9)/6

    =((5-3)/6)2

    = (2/6)2

    = (1/3)2= 1/9

    =((7-1)/6)2

    = (6/6)2

    = (1)2= 1

    Probabilistic Activity Times

  • 8/13/2019 Chapter 8- Project Management

    43/65

    Probabilistic Activity Times

    Activity #

    MEAN time

    ES & EF

    LS & LF

    Indicates slack

    EXPECTED completion time

    Probabilistic Activity Times

  • 8/13/2019 Chapter 8- Project Management

    44/65

    Expected project time is the sum of the expected times of the

    critical path activities. Project var iance is the sum of the critical path activities variances

    This assumes activity times are statistically independent

    The expected project time is assumed to be normally distr ibuted

    (based on central limit theorem: caution warranted here).

    For our example, expected project time (tp) and variance (vp)

    interpreted as the mean () and variance (2) of a normal

    distribution:

    = 25 weeks

    2= 62/9

    = 6.9 weeks2

    Probabilistic Activity Times

    Expected Project Time and Variance

    Probability Analysis of a Project Network

  • 8/13/2019 Chapter 8- Project Management

    45/65

    We can use this information to figure out our chances of

    finishing within a specified timeframe

    Use the normal distribution

    probabilities are determined by computing the number

    of standard deviations (Z) a value is from the mean.

    A standard deviation, , is the square root of variance

    You get the Z by: =

    The Z value is used to find the corresponding

    probability in Table A.1, Appendix A.

    This should be VERY familiar from stats!! Here is one

    wa it is useful for mana ers!

    Probability Analysis of a Project Network

    Example 1: What is the probability that the

  • 8/13/2019 Chapter 8- Project Management

    46/65

    We will use the table to find this part.Then, add them together to get our answer.

    Example 1: What is the probability that the

    network will be completed in 30 weeks or less

    This is p = 0.5000

    Probability Analysis of a Project Network

  • 8/13/2019 Chapter 8- Project Management

    47/65

    What is the probability that the new order processing

    system will be ready by 30 weeks?

    Probability Analysis of a Project Network

    Example 1

    2

    25

    6.9

    6.9 2.63

    30 251.90

    2.63

    weeks

    xZ

    Z

    Z value of 1.90 corresponds to

    probability of .4713 in Table A.1,

    Appendix A. Go down to the 1.9 row and over

    to the 0.00 column

    The probability of completing

    project in 30 weeks or less:(.5000 + .4713) = .9713.

    Example 2: What is the probability the network

  • 8/13/2019 Chapter 8- Project Management

    48/65

    Example 2: What is the probability the network

    will be completed in 22 weeks or less?

    This is p = 0.5000 The table tells us this probability.So, take 0.5000the probability in the table

    Probability Analysis of a Project Network

  • 8/13/2019 Chapter 8- Project Management

    49/65

    A customer will trade elsewhere if the new ordering system is notworking within 22 weeks. What is the probability that she will be

    retained?

    First, convert the problem to a Z:

    =

    Z = (22 - 25)/2.63 = -1.14

    Z value of 1.14 (ignore negative) corresponds to probability of .3729in Table A.1, Appendix A.

    1.1 row, 0.04 column

    Probability that customer will be retained is .1271= .5000 - .3729

    Probability Analysis of a Project Network

    Example 2

    Project Crashing and

  • 8/13/2019 Chapter 8- Project Management

    50/65

    What if you are in a hurry? Project duration can be reducedby assigning more

    resources to project activities.

    However, doing this increases project cost. Decision is based on analysis of trade-off between time

    and cost.

    Project crashingis a method for shortening projectduration by reducing one or more cr itical activities to a

    time less than normal activity time.

    Project Crashing and

    Time-Cost Trade-Off Overview

    Project Crashing and Time-Cost Trade-Off

  • 8/13/2019 Chapter 8- Project Management

    51/65

    Project Crashing and Time Cost Trade Off

    Example: Building a House (from start of lecture)

    Activity #

    Time in weeks

    Lets assume that activity 1 costs $3000 for a 12 week completion time

    It can be completed in 7 weeks (crash time) for $5000 (crash cost).

    So, 5 weeks costs us $2000.

    Project Crashing and Time-Cost Trade-Off

  • 8/13/2019 Chapter 8- Project Management

    52/65

    Project Crashing and Time Cost Trade Off

    $2000 $400 / 5

    Total Crash Costweek

    Total Crash Time weeks

    127 = 5

    50003000 = 2000

    Project Crashing and Time-Cost Trade-Off:

  • 8/13/2019 Chapter 8- Project Management

    53/65

    Project Crashing and Time Cost Trade Off:

    You can do the same thing for each activity

    You get these estimates from a contractor, someone else

    =12-7 =2000/5

    Network with normal activity times and weekly

  • 8/13/2019 Chapter 8- Project Management

    54/65

    Ne wo w o c v y es d wee y

    crashing costs

    As activities are crashed, the critical path may change and several pathsmay become critical.

    Here we can crash activity 1 without changing the path because all paths

    will be equally affected.

    This is normally done using a computer.

    Project Crashing and Time-Cost Trade-Off

  • 8/13/2019 Chapter 8- Project Management

    55/65

    j g

    General Relationship of Time and Cost (1 of 2)

    Another reason to crash a project is to lower indirectcosts

    Project crashing costs and indirect costs have an inverse

    relationship.

    Crashing costs are highest when the project is

    shortened.

    Indirect costs increase as the project duration

    increases.

    The optimal project time is at the minimum point on the

    total cost curve.

    General Relationship of Time and Cost

  • 8/13/2019 Chapter 8- Project Management

    56/65

    p

    The CPM/PERT Network

  • 8/13/2019 Chapter 8- Project Management

    57/65

    General linear

    programming model

    with AOA convention

    Lets look at an

    example

    The objective is to minimize the project duration (critical path time).

    Formulating as a Linear Programming Model

    minimize

    subject to

    , for all activities

    , 0

    earliest event time of node

    earliest event time of node

    time of activity

    i

    i

    j i ij

    i j

    i

    j

    ij

    Z x

    x x t i j

    x x

    where

    x i

    x j

    t i j

    Example Problem Formulation and Data

  • 8/13/2019 Chapter 8- Project Management

    58/65

    p

    AOA Network

    Recall: The activity is on the arc (arrow/branch) Activity 1 2: The activity starting at 1 and ending at 2

    ET: EarliestEvent Time. The earliest a node can be realized.

    We know ET of last node equals critical path time

    Letxibe the ET at each node. Then, set up the LPM.

    ET = max(12 + 4, 12 + 8)

    =max(16, 20) = 20

    ET = max(20 + 12, 24 + 4)

    =max(32, 28) = 32

    ET = 32 + 4 = 36

    The CPM/PERT Network

  • 8/13/2019 Chapter 8- Project Management

    59/65

    Minimize Z = x1+ x2 + x3+ x4+ x5 + x6+ x7subject to:

    x2 - x112

    x3- x2 8x4- x2 4

    x4- x30

    x5- x44

    x6- x

    412

    x6- x54

    x7- x64

    xi, xj0

    Example Problem Formulation and Data (2 of 2)

    This is the sum of all the earliest event times

    It does not have a useful interpretation

    It is used because it will give us the earliest event

    time at each node, which is what we want.

    We have a minimum time for each activity Look at Activity 12

    ET at node 2, x2= 12

    ET at node 1, x1= 0 (it is the beginning)

    Minimum time for 12 = x2x1= 12 - 0 = 12

    To formulate the constraint, we realize that it is

    possible to go over time, but not under time.

    Do the same thing for each activity, including

    dummy activities

    Dont forget to include the non-negativity

    constraints

    You can then use solver or QM for Windows

    Exhibit 8.10: Example Problem Solution with

  • 8/13/2019 Chapter 8- Project Management

    60/65

    p

    Excel

    B6:B12 =B7-B6

    Decision variables,

    B6:B12

    The CPM/PERT Network

  • 8/13/2019 Chapter 8- Project Management

    61/65

    Exhibit 8.11

    Example Problem Solution with Excel (2 of 4)

    Set dummy activities = 0

    The CPM/PERT Network

  • 8/13/2019 Chapter 8- Project Management

    62/65

    Example Problem Solution with Excel (3 of 4)

    This is the total project duration

    The CPM/PERT Network

  • 8/13/2019 Chapter 8- Project Management

    63/65

    Example Problem Solution with Excel (4 of 4)

    A shadow price of 1 indicates an activity is on the

    critical path: Just refer back to the referenced cells

    to get the activities

  • 8/13/2019 Chapter 8- Project Management

    64/65

    FOR THURSDAY

    Read Chapter 8

  • 8/13/2019 Chapter 8- Project Management

    65/65

    NOTE ON VARIANCE:

    Variance for the Beta PERT distribution is based on thestatistical concept that there are +-3 standard deviations

    from the mean, or 6 standard deviations

    Since b=most pessimistic and a = most optimistic, b-a is =

    6 standard deviations

    So, (b-a)/6 is one standard deviation

    Then, just square it to get the variance

    v = ((b-a)/6)^2