Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Chapter Six
( E1472 v3)FEDERAL REPUBLIC OF NIGERIA
RURAL ACCESS AND MOBILITY PROJECT
(RAMP I, KADUNA)
CR 4408
ENVIRONMENTAL MANAGEMENT PLAN (EMP)
FOR THE
PROPOSED OPRC ROADS PROJECT
(MOW&T/KADRAMP/C/12/10)
Final Report
TABLE OF CONTENTS
Table of Contents2
List of Tables3
List of Figures and Plates3
Acronyms and Abbreviations4
Executive Summary6
Section OneBackground and Introduction13
1.1Introduction and Overview13
1.2Objectives of this EMP14
1.3Report Structure14
Section TwoLegal and Administrative Framework16
2.1Introduction16
2.2Overview of Pertinent National Regulations16
2.3Relevant Kaduna State Regulation20
2.4Relevant International Regulations21
Section ThreeProject Description and Environmental Conditions
around Kaduna22
3.1Project Location22
3.2Scope and Description of the Project22
3.3Summary of Existing Environmental Conditions
around Kaduna26
Section FourEnvironmental Management Plan (EMP)30
4.1Introduction30
4.2Objectives of the EMP30
4.3General Environmental Management Planning,
Training and Responsibilities31
4.4Specific Environmental Management Practices32
4.5Environmental Monitoring40
Section FiveCost Estimates and Institutional Framework Requirement for EMP42
5.1Introduction42
5.2Cost Estimates for Mitigation measures and Monitoring Activities42
5.3Institutional Framework for Implementation of the EMP48
Section SixConclusions and Recommendations51
LIST OF TABLES
Page
Table ES 1:Cost Estimates for the Relevant Mitigation Measures8
Table ES 2:Cost Estimates for Monitoring Activities11
Table 2.1:National Environmental legislations Lists11
Table 3.1:Overview of Road Network in Northern Lot 1 of the RAMP Project19
Table 3.2:Overview of Road Network in Northern Lot 2 of the RAMP Project19
Table 3.3:Overview of Road Network in Southern Lot 1 of the RAMP Project20
Table 3.4:Overview of Road Network in Southern Lot 2 of the RAMP Project20
Table 4.1:Monitoring Requirement36
Table 5.2:Cost Estimates for the Relevant Mitigation Measures38
Table 5.2:Cost Estimates for Monitoring Activities42
LIST OF FIGURES AND PLATES
Figure 3.1:Administrative map of Kaduna State showing the lots covered by the project18
Plate 3.1:Farmlands in the Area24
Plate 3.2:Farmlands in the Area24
Plate 3.3:Avian Species Observed in the Area24
Plate 3.4:Avian Species Observed in the Area24
ACRONYMS AND ABBREVIATIONS
ABBREV.
FULL MEANING
AIDS
Acquired Immune Deficiency Syndrome
APC
Air Pollution Control
BAT
Best Available Technology
BP
Bank Policy
BPT
Best Practicable Technology
CCMP
Contractor Camp Management Plan
CET
Contractor Environmental Team
CO
Carbon Monoxide
CSP
Contractors Safety Plan
dB
Decibels
EA
Environmental Assessment
EIA
Environmental Impact Assessment
EIS
Environmental Impact Statement
EM & A
Environmental Management and Audit
EMP
Environnemental Management Plan
EMS
Environmental Management Systems
EPB
Environmental Project Brief
EPC
Engineering Procurement and Construction
ER
Engineers Representative
ESMF
Environmental and Social Management Framework
ESIA
Environmental and Social Impact Assessment
EMP
Environmental Management Plan
ET
Environmental Team
FEPA
Federal Environmental Protection Authority
FGN
Federal Government of Nigeria
FMEnv
Federal Ministry of Environment
FRSC
Federal Road Safety Corps
GEF
Global Environment Facility
GPS
Global Positioning System.
HIV
Human Imuno-defficiency Virus
HSE
Health Safety and Environment
IDA
International Development Agency
IEC
Independent Environmental Consultant
ISO
International Organization for Standardization
ITCZ
Inter-tropical Convergence Zone
KEPA
Kaduna State Environmental Protection Agency
LFN
Law of the Federation of Nigeria
LGA
Local Government Authority
LTI
Lost Time Injury
NO2
Nitrogen Oxide
NPE
National Policy on Environment
OD
Operational Directive
OP
Operational Policy
OPRC
Output Performance-based Road Contracts
PC
Project Coordinator
PCF
Prototype Carbon Fund
PASP
Project Activity Safety Plan
PHS
Public Health Safety
PPE
Personnel Protective Equipment
PRC
Public Road Construction
QA
Quality Assurance
QC
Quality Control
RAMP
Rural Access and Mobility Project
RCEMP
Roads Construction Environmental Management Plan
ROW
Right of Way
RTTP
Rural Travel and Transport
SEA
Site Environmental Audit
SI
Special Instrument
SO2
Sulphur Dioxide
SPIU
State Project Implementation/Coordinating Unit
TSP
Total Suspended Particulates
UES
Uniform Effluent Standards
WB
World Bank
EXECUTIVE SUMMARY
1.0 Introduction
The FGN applied for, and received funds from the World Bank (WB), through its international development agency (IDA), to support and finance its policy on Rural Travel and Transport. Kaduna state is one of the states of the federation designated to benefit from this planned Rural Travel and Transport projects, and its implementation in Kaduna State is coordinated by the State Project Implementation Unit (SPIU) under the Kaduna State Ministry of Works and Transport. In compliance with regulatory requirements, a contract was awarded for the preparation of an all-encompassing EMP for the implementation of RAMP projects in Kaduna state.
2.0 Legal and Administrative Framework
Local regulations for the construction/transportation sector, under the jurisdiction of the Federal Ministry of Environment (FMEnv), and the Kaduna State Environmental Protection Agency (KEPA) were considered in this section. In addition, regulations from international agencies such as the World Bank were considered.
3.0 Project Description and Summary of Environmental Conditions
The Rural Access and Mobility Project (RAMP) is divided into two main components namely;
· Transport Infrastructure and
· Institutional strengthening.
Kaduna State lies between latitude 90 02′N – 110 32′N and longitude 60 15’E – 80 50′E. With a lot of rock outcrops which vary in height up to 1370m above sea level and an undulating landscape. Kaduna State has a dense network of drainages with Rivers Kaduna and Gurara being the two major rivers. Generally the soil is made up of reddish brown to reddish yellow lateritic soils, in the upland areas the soils are rich in red clay and sand, but poor in organic matter. The soils generally are freely drained in rocky, hilly areas, and well-drained in the plains. Kaduna State has basically two vegetation zones; the Guinea Savannah and Sudan Savannah. Each zone has the southern and northern fringes.
In the northern part of Kaduna State comprising about ten (10) local governments, Hausa is the predominant tribe and language spoken, followed by Fulani. Other minority tribes include Gbagyi, and settlers like Yoruba, Igbos and others. The southern part of Kaduna is made up of eleven (11) local governments and has over 35 different tribes and languages. The predominant ones are Bajju, Atyap, Jaba and Ninzo Agorok. Hausas and Fulanis are also found in the south, but as minorities.
4.0 Environmental Management Plan
The EMP highlights the required activities and commitments of the Kaduna State Project Implementation Unit (SPIU) to the implementation of mitigation measures built into project design as well as the monitoring requirements for the entire project phase, starting from implementation, through operation and maintenance, to decommissioning. The specific areas focused on by this EMP are:
· Traffic and Traffic Management
· Air Quality and Noise
· Flood Waters, Runoff and Soil Management
· Hydrological Issues
· Waste Management
· Hazardous Materials Storage
· Fire Safety and Emergency Management Plans
· Health and Safety
Environmental monitoring requirements and plans were also identified for each of these various components identified above. A summary of the various impacts and their relative severity is presented in Table ES1 below:
S/N
ASSOCIATED IMPACT
RELATIVE SEVERITY OF IMPACT
MITIGATION MEASURES
1.
Routine traffic movement may be impeded by construction activities and lead to traffic build up in the vicinity
Negligible
Enlist the support of traffic management agencies such as FRSC
Dust from construction activities could lead to elevated suspended materials levels in ambient air and affect the health of project workers and nearby communities
Minor
Provide respiratory protection for project personnel
Undertake periodical sprinkling of road surface during the dry season particularly, to minimize dust impact
Noise from construction vehicles and machinery could lead to increased ambient noise levels
Minor
Provide hearing protection for project personnel in high noise areas
Ensure personnel do not work for more than the regulatory 8-hr shift
Waste generation, especially solid and domestic/sanitary wastes could become an issue, if not properly handled
Minor
Ensure collection and segregation at source
Provide for collection and disposal of oily wastes in approved state facilities
If road construction activities block existing natural drainages, it could lead to enhanced inundation, flooding upstream and drying up downstream
Moderate
Road alignments shall take this into consideration
Alternative flow routes shall be provided, where road works tamper with natural drainage and flow regimes
Possible fire outbreak in fuel storage areas if adequate care is not taken during various operational activities
Moderate
Provide muster points;
Provide fire-fighting equipment
Provide fire breaks around stacking areas
Undertake regular fire drills and train personnel on fire fighting
5.0 Cost Estimates and Institutional Framework Requirement for the EMP
An overview of the estimated costs for the implementation of the various mitigation measures indicated and the costs of carrying out environmental monitoring was estimated. Generally, many of the mitigation measures are routine and do not require financial inputs. However some of them require financial investments and these are indicated in Table ES 1 of this report. Also, Table ES 2 indicates the cost requirements for environmental monitoring activities. However, a summary of the costs associated with mitigation, monitoring and capacity building training is presented below
1
ES 1: Cost Estimates for the Relevant Mitigation Measures
S/N
ENVIRONMENTAL/SOCIAL ISSUES
COST OF MITIGATION MEASURES
TOTAL COSTS FOR FOUR (4) LOTS
RESPONSIBLE PARTIES
1
Traffic and Traffic Management
Traffic is not a serious issue in virtually all of the designated roads, since they are mostly rural feeder roads, subject to minimal traffic normally.
1. Provision of Alternative routes will be required only at river/stream crossings. For Seasonal streams, if construction is undertaken in the dry season, only minimal grading and filling of alternative crossings will be required. This is estimated to cost =N=300,000/crossing and estimating about 5 crossings per lot
2. Estimates for involvement of traffic management agencies is put at =N=250,000 in each lot
=N=6,000,000.00
=N=1,000,000.00
Alternative routes will be provided by construction contractors, while contractors will work in conjunction with RAMP SPIU to involve traffic control agencies for traffic control
2
Air Quality and Noise Levels
A. Air Quality
The primary concern in terms of air quality is the health of project workers, and nearby communities, who are designated as sensitive receptors for this project. Generally, dust from construction activities will lead to elevated suspended particulate matter levels in ambient air. This, in turn, could predispose project workers and host communities to respiratory infections and ailments.
Noise
Noise from vehicles associated with construction activities and subsequently, those that will ply the roads, will lead to an increase in ambient noise level. However, because noise during operations will be intermittent, rather than continuous, therefore, effort will need to be paid to construction period noise levels. This is in order to ensure that regulatory limits are not exceeded
Cost of monitoring is provided in Table 5.2.
Provision of respiratory protection (masks) will cost an estimate of =N=250,000/lot
Provision of water tankers to sprinkle the roads will cost an estimate of =N=100,000/km and estimated that 10km per lot will need to be sprinkled over the period of construction
Noise monitoring costs are provided in Table 5.2
Hearing protection will cost an estimated =N=250,000/lot
=N=1,000,000.00
=N=4,000,000.00
=N=1,000,000.00
Respiratory protection will be provided by contractors, and they will work in conjunction with RAMP Environmental Officers to ensure the appropriate usage of these equipment
Water sprinklers shall be provided by construction contractors
Hearing protection will be provided by contractors
Regular maintenance of machinery shall be undertaken by construction contractors
3
Waste Management
Different categories of wastes will typically be generated around the project area. These will include domestic/food wastes, sanitary waste and some level of oil wastes. These need to be properly handled to prevent environmental degradation
Provision of waste bins at construction sites shall cost an estimated =N=120,000/lot
Contracting of hazardous waste disposal contractors will cost =N=250,000/lot/month
=N=480,000.00
=N=1,000,000.00
Provision of waste bins and contracting of waste management contractors shall be undertaken by contractors but will be monitored by RAMP SPIU Safety Officer attached to the lot.
4
Hazardous Materials Storage
The main hazardous materials that are likely to be stored within and around the project area include diesel fuels for powering generating sets and for running machinery and equipment to be used for the project; paints and lubricants. Because these materials are highly flammable, they need to be carefully handled.
Provision of signage and cordoning of stacking sites will cost an estimate of =N=200,000/lot
PPE per personnel will cost an estimate of =N=50,000/personnel. Assuming 20 personnel per lot
Personnel training will cost =N=45,000/person; assuming 5 key personnel per lot
=N=800,000.00
=N=4,000,000.00
=N=900,000.00
This will be the responsibility of the construction contractors per lot
5
Hydrological Issues
Generally, some portions of the project location, especially in the southern lots, are quite susceptible to inundation and water logging during the rainy season. Therefore, in the event that road construction activities block existing natural drainage routes, it could exacerbate inundation in upstream areas and cause drying up in downstream areas, leading to negative modifications in existing hydrological regimes.
No cost is associated with these measures as these options are expected to have been taken into consideration by the contractor
Contractor will be responsible for these actions but will be monitored by RAMP
6
Fire Safety and Emergency Management
Fire outbreak is a major possibility in the storage area, where flammable materials like diesel, petrol and engine oil is stored. It is therefore necessary that a comprehensive fire safety and emergency management option be provided as part of overall project environmental management plans.
Fire fighting equipment per lot is estimated to cost =N=350,000
Construction of fire breaks around stacking areas is expected to cost =N=150,000/lot
=N=1,400,000.00
=N=600,000.00
Contactor will be responsible for these actions but will be monitored by RAMP
7
Health and Safety
The health and safety of personnel working in the project area is important.
Cost of quarterly fire drills and health checks prior to employment should already be incorporated into contractors HSE plan for the project and as such, no costs are associated with these measures
Contractor will be responsible for this, but will be monitored by RAMP’s Environmental officer
8
Accidents/Incidents
An accident is an unplanned, uncontrolled or undesired event that could result in personal injury, property damage or loss of time. Since they are not planned, specific mitigation measures cannot be provided for accidents/incidents. However, preventive plans and palliative measures must be put in place
The cost of preparing a detailed and comprehensive Emergency Response Plan for each lot is estimated at =N=500,000.00
=N=2,000,000.00
Contractor shall handle the preparation of Emergency Response Plans and will share these with RAMP SPIU
Total Cost of Mitigation in the Four (4) Lots
=N=11,180,000.00
Table ES 2: Cost Estimates for Monitoring Activities
S/N
ENVIRONMENTAL/SOCIAL ATTRIBUTE
RELEVANT PARAMETERS
FREQUENCY OF MONITORING
LOCATIONS TO BE MONITORED
COST ESTIMATE FOR MONITORING
RESPONSIBLE PARTY
1
Air Quality and Noise Levels
· NO2,
· SO2,
· CO,
· SPM,
· Noise Levels
Monitoring shall be carried out monthly during construction and quarterly during operations and maintenance, for the first 3years.
Monitoring shall be undertaken within construction areas and control points
=N=250,000/month/lot
Assume 6 months for construction
=N=18,000,000 for the 4 lots over the 3yr period
· RAMP SPIU
· EMP Consultant
· KEPA
2
Soil
· pH;
· Conductivity;
· Heavy Metals;
· Total Organic Carbons and Total Nitrogen
· Hydrocarbons
· Anions and cations
· Microbiology
Monitoring shall be carried out monthly during construction and quarterly during operations and maintenance, for the first 3years.
Monitoring shall be undertaken within construction areas and control points
=N=300,000/lot/month
=N=21,600,000 over the entire period
· RAMP SPIU
· EMP Consultant
· KEPA
3.
Occupational Health and Safety
· Personnel health
· Health of nearby communities
Monitoring shall be carried out half yearly during construction and yearly during operations
Monitoring shall cover project workers and communities within construction areas
=N=250,000/lot/monitoring
=N=4,000,000.00
· RAMP SPIU
· EMP Consultant
· KEPA
4
Traffic Management
Traffic situation within and around construction sites shall be regularly monitored to ensure that construction activities do not negatively affect baseline traffic situations
Monitoring shall be undertaken half yearly during construction
Construction areas will be covered during each monitoring
=N=325,000/lot/monitoring
=N=1,300,000.00
· RAMP SPIU
· EMP Consultant
· KEPA
Total Cost of Monitoring for the four (4) lots over construction and operation monitoring period
=N=44,900,000
Stakeholders for the RAMP project and their roles were also identified. These stakeholders are:
The stakeholders in the KADRAMP project are:
· International institutions – World Bank
· National institutions: Federal Ministry of Agriculture and Rural Development
· State Institutions : Kaduna State Ministry of Works ; Kaduna State Environmental Protection Agency (KEPA)
· Local Government Institutions : The LGA Authorities of the various road projects
· Community – Traditional rulers, village heads of all the areas covered in the project
· Others – Private sector (Contractors, Consultants) NGOs.
6.0 Conclusion and Recommendations
The conclusions drawn from the foregoing are:
· The planned project is a good project, with a number of associated positive benefits;
· The environmental sustainability of the project is premised on the implementation of a sound and cost-effective environmental management program (EMP)
· The EMP presented above is comprehensive and is deemed adequate to ensure the sustainability of the project;
· It is the responsibility of the RAMP SPIU in Kaduna, and its contractors to ensure that the EMP is properly implemented;
· Monitoring reports and other environmental compliance activities shall be periodically reported to the Federal Ministry of Environment (FMEnv),the Kaduna State Environment Protection Authority (KEPA) and the World Bank.
SECTION ONE
BACKGROUND AND INTRODUCTION
1.1Introduction and Overview
The Federal Government of Nigeria (FGN) recognizes that rural access and mobility is a critical requirement towards the improvement of the lives and living conditions of rural dwellers in the country. This is particularly critical for agrarian communities, considering that there is a need for them to transport farming inputs like fertilizers, etc, to their farms and to ferry out their bulky and, quite often, perishable produce to the markets.
Towards this end, the FGN, applied for, and received funds from the World Bank (WB), through its International Development Agency (IDA), to support and finance its policy on Rural Travel and Transport. Rural Access and Mobility Projects (RAMP) are seen as a major way of fostering and achieving the FGN’s Rural Travel and Transport policy. The RAMP is aimed at improving and enhancing accessibility and mobility in rural areas. Kaduna state is one of the states of the federation designated to benefit from this planned RAMP projects, and the implementation of RAMP in Kaduna State is coordinated by the State Project Implementation Unit (SPIU) under the Kaduna State Ministry of Works and Transport.
The Kaduna State RAMP projects currently include a total of forty (40) rural feeder roads, based on priority. These 40 roads have been subdivided into four (4) lots. Each of the Northern and Southern parts of Kaduna State has two (2) lots. The 40 rural roads selected are of three categories; paved (tarred), unpaved (untarred with standard and uniform carriageway) and unpaved tracks/paths (rough and irregular carriageway). 17 of the 40 roads are in the north while 23 are in the southern part of the state.
In compliance with national regulations and the requirements of the World Bank’s safeguard policies, there is a need for proper and enhanced, environmental management plans and programs, in the course of implementing these projects. Therefore, this document has been prepared to present a concise but all-encompassing Environmental Management Plan (EMP) for the implementation of the RAMP project in Kaduna state.
1.2Objectives of this EMP
In broad terms, the objectives of this EMP report include the following:
· to monitor compliance with all the mitigation measures and commitments as discussed in the ESMF report prepared for this project;
· to ensure best practices management as a commitment for continuous improvement in environmental performance;
· to monitor compliance with legal standards and limits for wastes discharges;
· to identify monitoring requirements, allocate responsibilities and identify areas where institutional strengthening is required;
· to provide early warning signals on potential environmental degradation for appropriate actions to be taken so as to prevent or minimize environmental consequences;
1.3Report Structure
This EMP has been put together to meet the objectives stated above, for the successful and sustainable implementation of RAMP projects in Kaduna state. The EMP is organized as follows:
Section One: Background and Introduction: This section presents background information on the proposed project and an overview of the objectives of this EMP report.
Section Two: Legal and Administrative Framework: An overview and summary of relevant regulations at the State, Federal and International levels are presented in this section of the report.
Section Three: Overview of the Project and Existing Environment in Kaduna State: This section of the report presents a concise description of the planned projects in the four (4) lots and a summary of the biophysical and socio-economic conditions of the project environment.
Section Four: The Environmental Management Plan: In this section of the report, an overview of the pertinent environmental and social issues relating to the planned RAMP projects, mitigation measures for negative impacts, as well as a monitoring schedule for the project phases is presented
Section Five: Cost Estimates and Institutional Framework Requirement for the EMP: This section of the report presents an overview of cost-estimates for the implementation of the mitigation measures and the monitoring requirements identified for the project phases. It also presents the institutional framework required for the effective implementation of the EMP
Section Six: Conclusion and Recommendations: A summary of the conclusions drawn from the EMP and recommendations on the optimal steps to be undertaken in implementing the EMP during various phases of the project is presented in this section.
SECTION TWO
LEGAL AND ADMINISTRATIVE FRAMEWORK
2.1Introduction
In Nigeria, several legislation and regulations guide the operations of various sectors of its industries, including oil and gas, transportation, infrastructure, and food and drugs. These regulations include local laws as well as some international treaties, acts and conventions. In this section, an overview of the laws that closely or remotely relate to the RAMP project is presented.
Local regulations for the construction/transportation sector are under the jurisdiction of the Federal Ministry of Environment (FMEnv)[footnoteRef:1], and the Kaduna State Environmental Protection Agency (KEPA). FMEnv regulations applicable to current project are briefly discussed here. The pertinent regulations are listed in Table 2.1. [1: Formerly the Federal Environmental Protection Agency (FEPA).]
Table 2.1
National Environmental Legislations list
APPLICABLE REGULATIONSYEAR
Federal Environmental Protection Agency Act
1988/91/92
Environmental Impact Assessment Act No. 86
1992
Guidelines and Standards for Environmental pollution Control in Nigeria
Effluent Limitation Regulations (S.I.8)
Pollution Abatement in Industries and Facilities Producing Waste (S.I.9)
Management of Solid Hazardous Wastes (S.I.15)
1991/ 2002
Harmful Waste Act
1988
Oil in Navigable Waters Regulation
1968
2.2Overview of Pertinent National Regulations
2.2.1The Federal Ministry of Environment (FMEnv), formerly the Federal Environmental Protection Agency (FEPA) Regulations 1988, 1991 and 1992.
Act 58 of 1988 established the Federal Environmental Protection Agency (FEPA) as the chief regulatory body for environmental protection in Nigeria with the responsibility of ensuring that all industries meet the limits prescribed in the national guidelines and standards and associated regulations for environmental pollution management. From time to time, the FMEnv (formerly FEPA) may update the national guidelines and standards. Relevant specific standards and other environmental requirements are outlined as follows.
FMEnv has put in place statutory documents to aid the control and abatement of industrial wastes and indiscriminate pollution of the environment. Statutory documents include:
· EIA Act No 86 of 1990;
· S.I.8 - National Environmental Protection (Effluent Limitations) Regulations of 1991;
· S.I.9 - National Environmental Protection (Pollution Abatement in Industries and Facilities Generating Wastes);
· S.I.15 - National Environmental Protection Management of Solid and Hazardous Wastes Regulations of 1991;
· The Harmful Wastes (Criminal Provisions) Act No. 42 of 1988;
· The 1989 National Policy on the Environment;
These statutory documents clearly spell out the restrictions imposed on the release of toxic substances into the environment and the responsibilities of all industries whose operations are likely to pollute the environment. Such responsibilities include provision of anti-pollution equipment, adequate treatment of effluent before discharge into the environment, etc. (S.I.8 & 9). For example, paragraph 15(2) of S.I.9 states that no oil in any form shall be discharged into public drains, rivers, lakes, seas, atmosphere or underground injection without a permit being issued by FMEnv or any organisation designated by the ministry. Also paragraph 17 states that an industry or a facility which is likely to release gaseous, particulate, liquid or solid untreated discharges shall install into its system, appropriate abatement equipment in such a manner as may be determined by the FMEnv.
Specifically, S.I.15 provides a comprehensive list of wastes that are classified as being dangerous to the environment. It also gives detail on the contingency planning and emergency procedure to be followed in case of sudden release of any of these hazardous wastes into the environment.
2.2.2National Policy on Environment (1989, Revised 1999). Issued by Federal Environmental Protection Agency (FEPA)
The goal of the National Policy on the Environment is to achieve sustainable development in Nigeria, and in particular to:
· Secure a quality of environment adequate for good health and well-being;
· Conserve and use the environment and natural resources for the benefit of present and future generations;
· Restore, maintain, and enhance the ecosystem and ecological processes essential for the functioning of the biosphere to preserve biological diversity and the principle of optimum sustainable yield in the use of living natural resources and ecosystems;
· Raise public awareness and promote understanding of the essential linkages between the environment, resources, and development, and encourage individual and community participation on environmental improvement efforts; and
· Co-operate in good faith with other countries’ international organizations and agencies to achieve optimal use of Trans-boundary natural resources and effective prevention or abatement of Trans-boundary environmental degradation (Article 2.0).
2.2.3National Guidelines and Standards for Environmental Pollution Controlin Nigeria, 1991
Effluent Limitations Regulations
This regulation was made pursuant to Section 37 of the FEPA Act Cap 131 LFN, to regulate ways and manners of treating effluent as well as installation of anti-pollution equipment by industries operating in Nigeria.
The regulation mandates every industry to install anti-pollution equipment for the detoxification of effluent and chemical discharges emanating from the industry (Regulation 1(1)). Such installed anti-pollution equipment shall be based on Best Available Technology (BAT), BPT or the Uniform Effluent Standards (UES) (Regulation 1(2)). An industry which discharges effluent shall treat the effluent to a uniform level as specified in the schedule to the receiving water into which the effluent is discharged (Regulation 3(1)).
2.2.4Pollution Abatement in Industries and Facilities Generating Wastes
This regulation is made pursuant to FEPA Act, CAP 131 LFN Section 37, to designate and regulate the management of solid and hazardous wastes generated from facilities in Nigeria.
Unless with the approval of the Agency (FEPA, now FMEnv), no industry or facility shall release hazardous or toxic substances into the air, water or land of Nigeria’s ecosystem and such limits approved by the Agency shall not be exceeded. Storage, treatment, and transportation of harmful toxic waste without permit is also prohibited (Regulations 1, 10, and 15).
It mandates that an industry or facility has a pollution monitoring unit within its premises, sets up a machinery for combating pollution hazard and maintains equipment in the event of an emergency, and assigns the responsibility for pollution control to a person or corporate body accredited by the Agency (Regulations 2 and 8).
Solid waste generated by an industry or facility, including sludges and all by-products resulting from the operation of pollution abatement equipment shall be disposed of in an environmentally safe manner, and no industry solid waste shall be disposed of in any municipal landfill (Regulation 16).
It further enjoins every industry or facility which is likely to release gaseous particles or solid untreated discharges to install into its system prescribed abatement equipment by the Agency (Regulation 17).
It also empowers the Agency to demand environmental audit from existing industries and environmental impact assessment from new industries and major development projects and the industries shall comply within 90 days of the receipts of the demand (Regulation 21).
2.2.5Management of Hazardous Waste Regulation
This regulation designates those solid wastes, which are dangerous or extremely hazardous to the public health and environment.
In order to determine if the waste generated is to be designated as “dangerous i.e. hazardous waste” or “extremely hazardous waste” in accordance with the stipulations under Part II of the Regulations, the generator or operator has to consult the dangerous waste list, characteristics and criteria set out under schedules 6-13 and follow the detailed cross checking procedures established there.
It provides for surveillance and monitoring of dangerous and extremely hazardous waste and substances, until they are detoxified, reclaimed, neutralized, or disposed of safely.
It also provides the form and rules necessary to establish a system for manifesting, tracking, reporting, monitoring, record keeping, sampling and labeling dangerous, and extremely hazardous wastes.
It further encourages recycling, reuse, reclamation, and recovery to the maximum extent possible.
2.3Relevant Kaduna State Regulation
Kaduna State Environment Protection Authority (KEPA) Amendment Edict 1997
The Kaduna State Environment Protection Authority (KEPA) Edict came into operation on the 1st day of January, 1997. Under the edict, the Authority (KEPA) has the general responsibility for all matters relating to environment. Its main duties are to:
· Enact and enforce State regulations control criteria, procedures, guidelines and environmental standards for effective prevention, remediation, control and prevention of point and non-point sources of pollution and degradation;
· Formulate, implement, and review environmental policy in the State and in particular to demand and review Environmental Impact Assessment and Statements for new development projects and to also demand and review environmental audit reports for existing developments and such other operations which are deemed to have significant impact on the environment;
· Prepare, in accordance with the State Policy and Edict on the environment, periodic master plans for the development and the financial requirements for implementation of such plans;
· Prevent, stop any act of omission or commission which consequences are likely to adversely affect the environment and to generally deal with any discharge solid, liquid or gaseous, deposited willfully or otherwise in the environment and to deal generally with any violations which the Authority may deem hazardous to the environment and ecosystem.
2.4Relevant International Regulations
2.4.1World Bank OP/BP 4.01; Environmental Assessment (EA)
This is one of the 10+1 Environmental and Social Safeguard Policies of the World Bank. It is used in the Bank to examine the potential environmental risks and benefits associated with Bank lending operations. Under OP/BP 4.01, Bank lending operations are broadly defined to include investment lending, sector lending, rehabilitation lending through financial intermediaries, and investment components of hybrid lending. Prototype Carbon Fund (PCF) and Global Environment Facility (GEF) co-financed projects are also subject to the provisions of OP/BP 4.01.
Under this guideline, The Bank requires environmental assessment (EA) of projects proposed for Bank financing to help ensure that they are environmentally sound and sustainable, and thus to improve decision making. EA evaluates a project's potential environmental risks and impacts in its area of influence; examines project alternatives; identifies ways of improving project selection, siting, planning, design, and implementation by preventing, minimizing, mitigating, or compensating for adverse environmental impacts and enhancing positive impacts; and includes the process of mitigating and managing adverse environmental impacts throughout project implementation. The Bank favours preventive measures over mitigatory or compensatory measures, whenever feasible.
SECTION THREE
PROJECT DESCRIPTION AND ENVIRONMENTAL CONDITIONS AROUND KADUNA
3.1Project Location
The project is located in Kaduna State of Nigeria. The project covers four (4) lots, two each in northern and southern ends of the state. Figure 3.1 shows an administrative map of Kaduna state, with the various roads and the affected Local Government Areas (LGAs).
3.2Scope and Description of the Project
The Rural Access and Mobility Project (RAMP) is divided into two main components namely;
· Transport Infrastructure and
· Institutional strengthening.
Component A: Transport Infrastructure
This component, which has to do with more of civil works, is made up of River crossing (A2) and Output Performance based Road Contracts (A1). The River Crossing makes up 40% of this component A and is aimed at rehabilitating rivers crossings, culverts, etc. On the other hand, the Output Performance based Road Contracts (OPRC) makes up 60% and is aimed at improving and/or upgrading the existing rural feeder roads and tracks. There are two categories of roads under OPRC, namely; existing paved roads which are degraded and require re-sealing, and existing unpaved roads and tracks which would be upgraded to laterite surface dressed roads.
The improvement of the existing rural roads will be carried out using the Output and Performance Based Road Contracts (OPRC). The OPRC means that the contractors will be paid based on the quantity of actual work done, and the payment would be fee per kilometer (km) per month only if the defined (contract) service levels have been achieved.
Figure 3.1: Administrative map of Kaduna State showing the lots covered by the project
A total of forty (40) rural feeder roads have been selected under the RAMP in Kaduna State based on priority. These 40 roads have been subdivided into four (4) lots. The Northern part of Kaduna State has two (2) lots while the Southern part has two (2) lots. The 40 rural roads selected are of three categories; paved (tarred), unpaved (untarred with standard and uniform carriageway) and unpaved tracks/paths (rough and irregular carriageway). 17 of the 40 roads are in the north while 23 are in the southern part of the state.
Tables 3.1 to 3.4 show the various lots of roads in the northern and southern parts of the state and the estimated distance and scope of works to be carried out
Table 3.1: Overview of Road works in Northern Lot 1 of the RAMP Project
LOT N 1
Surface
Scope of works
Road #
Name
LGA
Total km
paved
Unpaved
Construct to gravel 7.3m
Upgrade to paved 7.3m
Patch and reseal 7.3m
R1-1
Dogon Dawa – U/Danko-Kwashi
Birnin Gwari
13.8
13.8
13.8
R1-2
Kidanda – S/Gari Yadi and Galadimawa – Gamba
Giwa
24
24
24
R1-3
Gwada-Sabon Birnin
Giwa
6.5
6.5
6.5
R1-12
U/Liman-Fatika-U/Kanawa
Giwa
27.4
27.4
27.4
R1-24a
Unguwan Fari - Bugai
Birnin Gwari
12
12
12
R1-24b
Bugai (End of Village) – U’n Alhaji Shehu
Birnin Gwari
12.8
12.8
12.8
R1-26
Nasarawa – Gangara - Dundubus
Giwa
12.4
12.4
12.4
R1-27
Giwa town - Yakawada
Giwa
12.2
12.2
12.2
Total
131.7
27.4
104.3
104.3
0
27.4
Table 3.2: Overview of Road works in Northern Lot 2 of the RAMP Project
LOT N 2
Surface
Scope of works
Road No.
Name
LGA
Total km
paved
Unpaved
Construct to gravel 7.3 m
Upgrade to paved 7.3m
Patch and reseal 7.3m
R2-4
Kerawa-Gedage
Giwa
8.2
8.2
8.2
R2-5b
Dunki –Labar – Jaji
Igabi
11.1
11.1
11.1
R2-6
Kerawa-Sako
Giwa
9.8
9.8
9.8
R2-7
Kakangi-Murai-Karaukarau
Giwa
9
9
9
R2-8a
Wazata-Kwaba-Rafin Yashi-Sabon Birni-Kugu
Giwa/
12.5
12.5
12.5
Zaria
R2-8b
Wazata-Kwaba-Rafin Yashi-Sabon Birni-Kugu
Giwa/
7
7
7
Zaria
R2-10
Tami-Birni-Yaro-Rahama-Kabomo-
Igabi
29.8
29.8
29.8
Kwarakwara-Kasangwari-R/Chikun Rail Crossing
R2-25
Sabon Birni Yero – Dallatu
Igabi
10.1
10.1
10.1
Total
97.6
0
97.6
97.6
0
0
Table 3.3: Overview of Road works in Southern Lot 1 of the RAMP Project
LOT S1
Surface
Scope of works
Road #
Name
LGA
Total km
Paved
Unpaved
Construct to gravel 7.3 m
Upgrade to paved 7.3m
Patch and reseal 7.3 m
R3-3a
F/Kagoma-Jaginidi Tasha
Jema’a
5.8
1.5
4.3
4.3
1.5
R3-3b
F/Kagoma-Jaginidi Tasha
Jema’a
12.5
12.5
12.5
R3-4
Bakinkogi-Godogodo-Dangoma
Jema’a
29.4
22.8
6.6
6.6
22.8
R3-6
Jaginidi Tasha-Kogum
Jema’a
12.7
12.5
0.2
0.2
12.5
R3-8
Jaginidi Tasha-Amere-Gerti
Jema’a
7.0
7.0
7.0
R3-9a
F/Kamantan-Zagon-Anza-Gorasegwaza-Gora Gan-ung Ruhogo-Takanai-U/Wakili
Zangon Kataf
10.5
10.5
10.5
R3-9b
From Federal Rd to Sako Village
Zangon Kataf
6.7
6.7
6.7
R3-9ab
F/Kamantan-Zagon-Anza-Gorasegwaza-Gora Gan-ung Ruhogo-Takanai-U/Wakili
Zangon Kataf
13.3
13.3
13.3
R3-10
Fadan Kamantan-Yangil-Walijo-Kurmi Sidi
Zangon Kataf/Kachia
21.8
21.8
21.8
R3-21
Zonkwa junction – lenak Village – Zuturun Turan Village
Zangon Kataf
8.2
8.2
8.2
R3-21a
Zonkwa Junction – Zuturun Achi Village
Zangon Kataf
4.3
4.3
4.3
Total
132.3
36.8
95.4
73.4
22.0
36.8
Table 3.4: Overview of Road works in Southern Lot 2 of the RAMP Project
LOT S2
Surface
Scope of works
Road #
Name
LGA
Total km
Paved
Unpaved
Construct to gravel 7.3 m
Upgrade to paved 7.3m
Patch and reseal 7.3 m
R4-1
Sabon Gida-Kudiri-Rafan Kimba-kagarko
Kagarko
12.9
12.9
12.9
R4-2
Kagaroko-Akote-Kushe-Kahir-Kasru
Kagarko
36.1
36.1
36.1
R4-2a
Karajan – Kasaru – Junction with Federal Road
Kagarko
15.2
15.2
15.2
R4-13
Sabon Itche-Kuse-U/Dankarami-T/Wada-Kagunyi
Kagarko
6.7
6.7
6.7
R4-14a
Kubacha-A/Madaki-Kukui-Kusam1 Kusam2
Kagarko
7.4
7.4
7.4
R4-14b
Kubacha-A/Madaki-Kukui-Kusam1 Kusam2
Kagarko
10.0
10.0
10.0
R4-16
From state road to Mai Ido Kufai
Kachia
14.7
14.7
14.7
R4-17
From state road to Mai Gora Village
Kachia
2.2
2.2
2.2
R4-18
From state road to U/Fari
Kachia
1.4
1.4
1.4
R4-19
From state road to Kabara Aribi Village
Kagarko
7.9
7.9
7.9
R4-20
From state road to Goraa village
Jaba
3.4
3.4
3.4
Total
127.0
127.0
127.0
Component B: Institutional Strengthening
This will focus on;
· Strengthening the road management as well as planning, procuring and supervising road maintenance contract skills both on State and Local Government levels;
· Assisting with the development and implementation of institutional reform proposals and reporting systems to assist with efficient management of rural transport infrastructure;
· Support with the implementation of RTTP to empower the local government and communities to participate in the management and provision of rural transport infrastructure and services; and
· Capacity building in the procurement, supervision and execution of labour based and small scale contracting.
3.3Summary of Existing Environmental Conditions in Kaduna State
A summary of the general environmental conditions around Kaduna State is presented below:
Geology, Drainage and Hydrology
The state is underlain generally by metamorphic rocks of the Precambrian basement complex, consisting of biotite, gneisses and older granites. Younger granites and batholites predominate in the South-Eastern parts of the state .The Central; North-East and South-Eastern parts of the state are dominated by older granites. Giwa local government and Birnin Gwari areas and some parts of Zaria have undifferentiated meta-sediments. The valleys around Kaduna are extensive up to the watershed areas, having gentle sloping valleys containing moist/marshy alluvial flood plains. These flood plains are the “Fadamas” which are used for dry season crop cultivation. Mineral deposits of the state include; Iron Ore, Manganese, Kyanite, Sillimanite, Graphite, Talc, Feldspar, Gold, Fassiterite, Columbite, various Gemstones, Clay, Sand and Laterite derived from weathered Granite.
Kaduna State has a dense network of rivers/drainages with Rivers Kaduna and Gurara being the two major rivers. The sources of these rivers include Kauru, Lere and Plateau State area which form the source of the biggest river, Kaduna; The Zangon Kataf/Kaura to Plateau state area which form the source of the river Shayu, Kagom, Mada and Sanga; Kachia and Kagarko from where rivers Gurara and Dinya flow; Birnin Gwari areas form the source of rivers Udawa/Baban ,Damari ,Kusheriki, Kwingi and Mairiga; then the Ikara, Kubau and Lere/Plateau areas provide the source for rivers Karami, Galma and Kubani. All of these rivers have their tributaries and distributaries which forms the dense network of drainage in the state.
The state has a lot of surface and groundwater. The large number of rivers, streams and ponds in the state provides surface water. The total reserve for the state is about 8,000m3. About 80% of this comes from surface water, while 20% comes from wells and boreholes. There area no major surface waters that are directly affected by the planned RAMP projects, except for a few seasonal streams and minor streams that need to be crossed in some portions
Climate
Kaduna State experiences a typical tropical continental climate in which pronounced seasonal regimes reflect the influence of tropical continental and equatorial maritime air masses, with a cool to hot dry season November to February, and a rainy season May to October. The spatial and temporal distribution of rain varies from an average of some 1600 mm in the south to less than 700 mm in the north. High storm intensities, ranging from 60-99 mm/hour, and the nature of surface runoff have led to the development of an extensive river system. Rainfall is associated with the northwards movement or the Inter-Tropical Convergence Zone (ITCZ) across Kaduna State. During the rainy season, relative humidity is high and winds are mainly south-westerly. The southward movement of the ITCZ occurs in October-November and indicates the onset of the dry season, with low relative humidity.
Air Quality
The measured air quality parameters (CO, SO2, NO2, TSP etc) of the study area are within the FMEnv regulatory limits. However, the harmattan winds of the dry season are often dust laden and contrive to lead to an increase in ambient levels of suspended particulate matter. Project activities are likely to further exacerbate this, especially if undertaken in the dry season. Noise levels are generally low in the state, ranging between 40 and 65dB(A), except in urban areas like Kaduna metropolis, some parts of Zaria, etc., where traffic and human activities contrive to elevate noise levels to 75dB and above. In all cases however, ambient noise levels are below the Federal limit of 90dB for a maximum of 8 hours exposure.
Soil
The soils of most part of project area are sandy with very low organic content. Anions and cations are within acceptable ranges to support the growth of some plants. Heavy metal contamination has not occurred as records from previous studies in the state recorded low ranges of metals that are within acceptable limits.
Vegetation Study
The entire project area falls within the guinea savannah vegetation type with two basic habitat types; savannah grassland and farmland/grassland mosaic. In the savannah grassland, trees are few and spaced wide apart. Plants recorded within the project area include trees such as Parkia biglobosa, Adansonia digitata and Azadirachta indica. Grassy species such as Panicum maximum, Andropogon gayanus and Imperata cylindrica are also present.
The communities immediately around the project site are primarily agrarian and engage in subsistence and semi-commercial farming of food crops and cash crops. The main food crops include maize, guinea-corn, Hungry rice, rice, cassava, and millet. Some vegetables such as pepper, tomatoes, okra, pumpkin and corchorus are planted along the river course. Livestock farming, especially cattle and sheep is very prominent.
Wildlife
The faunal diversity in the project area presents a wide variation of both vertebrate (amphibians, reptiles, mammals and aves) and invertebrate animals. Birds are typically abundant within the project area, while reptiles such as snakes, crocodiles and monitor lizards, which are very shy animals, were not easily observed. However, the rainbow lizard (Agama agama) is very ubiquitous in the area and is therefore seen regularly all over the project area.
Plates 3.1 to 3.4 show some of the vegetation and wildlife typically associated with the area.
Plates 4.1 and 4.2: Farmlands in the area
Plates 3.3 and 3.4: Avian species observed in the area
SECTION FOUR
ENVIRONMENTAL MANAGEMENT PLAN (EMP)
4.1Introduction
Environmental Management Plan (EMP) is a management application tool used to monitor the effectiveness of mitigation measures and project commitments to environmental protection, especially as may have been contained in the ESIA report. The EMP is incorporated into the project implementation process, to minimize or eliminate identified negative impacts, assess compliance with environmental regulatory standards and corporate safety policies.
This EMP highlights the required activities and commitments of the Kaduna State Project Implementation Unit (SPIU) to the implementation of mitigation measures built into project design as well as the monitoring requirements for the entire project phase, starting from implementation, through operation and maintenance, to decommissioning.
4.2 Objectives of the Environmental Management Plan (EMP)
The objectives of the EMP contained in this Section are as follows:
· to monitor compliance with all the mitigation measures and commitments as discussed in the Environmental and Social Management Framework (ESMF) prepared specifically for this project, during the implementation of the proposed project;
· to ensure best practices management as a commitment for continuous improvement in environmental performance;
· to monitor compliance with legal standards and limits for various environmental requirements, such as wastes discharges, ambient air, occupational exposure limits for workers, etc.;
· to provide early warning signals on potential environmental degradation for appropriate actions to be taken so as to prevent or minimize environmental consequences;
The EMP is in two parts:
· Part 1: General Environmental Management and personnel training issues;
· Part 2: Environmental monitoring requirements and schedule
Details are presented in the following sub-sections.
4.3General Environmental Management Planning, Training and Responsibilities
Environmental Awareness Training and Skills Training for Personnel
All staff and/or contractors involved in work in the project are to be briefed on their obligations towards environmental controls and methodologies in terms of this EMP prior to work commencing. The briefing will usually take the form of an onsite talk and demonstration by the SPIU environmental officer. The education / awareness programme shall be aimed at all levels of management within the operations team.
Personnel
· Working hours must be communicated to all personnel and strictly enforced, so that personnel do not suffer exposure beyond regulatory limits
· No fires shall be permitted within the project area unless for specific activities such as welding and/or temporary illumination during blackouts.
· Personnel shall ensure that waste generation is kept to a barest minimum. Waste bins shall be provided in each booth to handle wastes such as stationers, food wastes, etc.
· Awareness training that includes health programmes containing as a minimum, HIV/AIDS and Malaria awareness training that focuses on the symptoms and effective control mechanisms for early detection and effective control, will be provided.
Record Keeping
All records related to the implementation of this management plan (e.g. site instruction book) must be kept together in an office where it is safe and can be readily retrieved. These records shall be kept throughout project duration and shall at any time be available for scrutiny by any relevant authorities.
Emergency Plan and Contingency Plans
The SPIU shall ensure that contractors handling the different lots prepare and make available emergency plans for the typical emergencies and any other emergencies, as deemed necessary by the Health and Safety Officer. These plans shall include any other contingency plans for events such as Lost Time Injury (LTI), accidental fires from fuel storage facilities; community issues, etc.
4.4Specific Environmental Management Practices
This section contains specific environmental management practices and procedures applicable to the Kaduna RAMP projects. Based on the outcome of the scoping exercise carried out for the purpose of the development of this EMP, it was concluded that the following sections require attention in the EMP:
· Traffic and Traffic Management· Air Quality and Noise· Flood Waters, Runoff and Soil Management
· Hydrological Issues
· Waste Management· Hazardous Materials Storage· Fire Safety and Emergency Management Plans· Health and Safety
The following sub-sections present general environmental management practices that shall be put in place to ensure that the operating environment around the project area is safe and healthy for all personnel and host communities.
4.4.1Traffic and Traffic Management
Traffic is not a serious issue in virtually all of the designated roads, since they are mostly rural feeder roads, subject to minimal traffic normally. However, the occasional vehicular traffic may be impeded by construction activities. Therefore, traffic management schemes shall be put in place to manage traffic in the area, especially during peak periods, which coincide with harvest periods, when farm produce have to be ferried from the local communities to the markets. Thus, traffic management schemes shall be provided by contractors handling the projects. The schemes shall take into consideration, as a minimum, the following:
· Minimization of obstruction to normal traffic flow in the area;
· Provision of temporary alternative routes, in the event that absolute obstruction of traffic is inevitable.
· In addition to the foregoing, RAMP shall work in conjunction with traffic management agencies such as the Federal Road Safety Corps (FRSC), to optimize traffic flow, by minimizing traffic obstruction
.
4.4.2Air Quality and Noise Level
Air Quality
The primary concern in terms of air quality is the health of project workers, and nearby communities, who are designated as sensitive receptors for this project. Generally, dust from construction activities will lead to elevated suspended particulate matter levels in ambient air. This, in turn, could predispose project workers and host communities to respiratory infections and ailments. Therefore, RAMP and its contractors shall ensure that:
· Regular monitoring of air quality around the project area are carried out, on a monthly basis, so that negative trends can be promptly detected and addressed;
· Personnel are not allowed to exceed their regular shift durations
· Adequate respiratory protection is provided for project workers on site, so that their exposure to respiratory irritants is minimized
· In the dry season, there will be need for periodic sprinkling of the road surface with water, especially were road works are taking place within and around communities to minimize suspendable dust levels in ambient air.
A detailed monitoring schedule is presented in subsequent sections of this report.
Noise Control
Noise from vehicles associated with construction activities and subsequently, those that will ply the roads, will lead to an increase in ambient noise level. However, because noise during operations will be intermittent, rather than continuous, therefore, effort will need to be paid to construction period noise levels. This is in order to ensure that regulatory limits are not exceeded.
Therefore, RAMP and its contractors will implement the following measures to protect its workers and nearby host communities from the hazards of high noise levels in the area:
· Provide hearing protection for project personnel, who are in high noise areas, close to the machinery that will be used for project activities;
· Ensure that project personnel do not exceed the normal 8-hr duration of their shifts;
· Provide for regular monitoring of noise levels around the project locations, to facilitate early detection of exceedance of regulatory noise levels
· Undertake regular monitoring of personnel to ensure that they adhere to the relevant health and safety standards pertaining to noise, such as wearing ear protection when noise levels are getting high.
· Ensure that machinery to be used for project construction activities have functional silencers that ensure that noise emissions meet international regulatory standards
4.4.3Waste Management
Different categories of wastes will typically be generated around the project area. These will include domestic/food wastes, sanitary waste and some level of oil wastes. These need to be properly handled to prevent environmental degradation. To this end therefore, the following waste management options shall be instituted:
· Wastes shall be collected and properly segregated at source. Typical segregation options include separation into: food waste; paper and stationeries; and recyclables (plastic and glass).
· Oily wastes shall be collected and disposed in approved facilities in the state;
4.4.4Hazardous Materials Storage
The main hazardous materials that are likely to be stored within and around the project area include diesel fuels for powering generating sets and for running machinery and equipment to be used for the project; paints and lubricants. Because these materials are highly flammable, they need to be carefully handled. Thus hazardous materials storage must make provision for:
· Storage in unobtrusive locations, with restricted access. Access to storage areas shall be limited to only authorized personnel
· Adequate signage must be provided in the storage area. These signage shall warn on the dangers of naked flames in the area as well as need for proper dressing and use of appropriate PPEs
· Areas where flammable materials are stored must be isolated from nearby communities. They must be shaded from the sun.
· Personnel working in such areas shall be provided with necessary PPEs, including oil-proof safety boots and coveralls.
· Personnel must be subject to training on handling of hazardous materials and duly certified. The will also be subject to periodic refresher training
4.4.5Hydrological Issues
Generally, some portions of the project location, especially in the southern lots, are quite susceptible to inundation and water logging during the rainy season. Therefore, in the event that road construction activities block existing natural drainage routes, it could exacerbate inundation in upstream areas and cause drying up in downstream areas, leading to negative modifications in existing hydrological regimes. In order to manage this possibility, the following measures shall be undertaken:
· Road alignments shall take into due cognizance, the existing drainage in the area
· Where it is inevitable to tamper with hydrological flows, alternative flow routes shall be created. This could include the use of underground conduit pipes and/or culverts
4.4.6Fire Safety and Emergency Management Plans
Fire outbreak is a major possibility in the storage area, where flammable materials like diesel, petrol and engine oil is stored. It is therefore necessary that a comprehensive fire safety and emergency management option be provided as part of overall project environmental management plans. Specifically, the following shall be instituted:
· Muster points shall be provided for all personnel to gather in the event of accidental fires
· Adequate fire fighting gadgets shall be made available and distributed around construction sites, especially where flammable materials are stored. These includes:
1)Fire extinguishers (H20, dry powder & CO2)
2)Fire hydrant and foam.
· Instructions shall be readable on the body of the fire extinguisher.
· Personnel should be familiar with the operations of fire extinguishers
· Given the agrarian nature of the project location, and the fact that many of the locations are grasslands, where fire can spread easily. Therefore, adequate fire breaks shall be constructed around project fuel storage sites, to prevent the spread of accidental fires;
· Regular training on fire-fighting and handling shall be provided. The details of such training shall include the following:
· Prevent a fire from starting, by minimising ignition sources, oil/gas leaks, enforcing “no smoking” rules etc
· Protect high fire risk facilities with automatic detectors, early warning devices, and where feasible automatic extinguishers.
· Provide adequate and suitable fire fighting equipments in all installations.
· Train all personnel, especially those on key installation, in the efficient use of equipments and extinguishing of fire.
· Consequently, everyone is expected not only to prevent, but also to fight fires. It is important for every person to:
· Know where the nearest extinguisher is installed, and how to operate and use it.
· Obey “No smoking” signs. Smoke only in designated places and use smoke-extinguishing equipments safely.
· Not obstruct fire exits and extinguishers.
· Dispose of all combustible wastes, rags, papers and other rubbish in proper containers.
· Not to overload power sockets.
· Become familiar with the company’s fire emergency procedures applicable to your workplace.
· Ensure that there are no welding or naked wires in hazardous areas. A written work permit is a must before a source of ignition is introduced into such areas.
· Attend first aid and fire-fighting training to learn how to extinguish fires using the equipments provided in your work area.
4.4.7Health and Safety
The health and safety of personnel working in the project area is important. Therefore, regular safety training and drills must be carried out to enhance the sensitivity of personnel to safety issues. Specifics of drills that have to occur include the following:
· Fire drills must be held at least quarterly. Such drills will include mustering at designated muster points, responding to fire alarms, handling fire-fighting equipment, etc.
· Such drills must be coordinated by the Health and Safety Officer attached to the construction site, who must be a certified safety practitioner.
· Personnel must be subject to comprehensive health checks prior to employment, so that a baseline can be established. Attention shall also be paid to trend of common ailments among toll collection staff, such that any recurrent ailment among the staff that can be remotely or directly related to their work shall be investigated, as the need arises.
4.4.8Accidents/Incidents
An accident is an unplanned, uncontrolled or undesired event that could result in personal injury, property damage or loss of time.
Cause of Accidents
In general, accidents are caused by either unsafe acts, unsafe conditions, or a combination of both. Accidents are rarely as a result of a dramatic failure of equipment; they are mainly due to human failure. Even an apparent failure of equipment may be due to the human factor in failing to recognize signs of impending trouble.
Analyses of accidents have shown that over 80% of accidents are caused by such human factors as persons failing to take proper precautions, ignoring safety regulations or carrying out jobs incorrectly. These are referred to as unsafe acts and may arise in any or combination of the following ways:
· using improper methods
· operating without authority
· failing to use proper mechanical aids
· using improper tools/equipment
· failing to wear personal protective clothing
· over-confidence
· impulsiveness
· horseplay
· impatience
· showing off
· laziness
· ill health
· supervisory failure
· poor training
· lack of discipline
· poor house keeping
To minimize unsafe acts there should be:
· the fullest possible information to the employee regarding the job
· training appropriate to the work
· adequate and effective supervision
The train of events leading up to an accident to personnel or property follows the sequence below:
HUMANUNSAFE ACT PERSONAL UNJURY
ERRORUNSAFE CONDITION ACCIDENT PROPERTY
OR BOTH DAMAGEOR BOTH
Accident Reporting and Investigation
An efficient system of accident investigation and reporting is invaluable in improving safety performance. Prompt investigation is essential; otherwise vital information may be lost, thus preventing the correct remedial measures to be taken.
The reporting of potentially serious accidents (near misses) is valuable in providing a pool of information that can be usefully applied in preventing recurrence and or accidents.
The accident report should begin with a short summary giving the place, date and time of the incident, the damage or injuries sustained to equipment and/or persons and the estimated out-of-production time. A brief note to be given of the cause (or believed cause) and the remedial action proposed.
Accident/Incident Reporting Procedure
· Contact safety officer on site as soon as the incident occurs.
· Safety officer to contact project supervisor who then reports to base.
· However, your knowledge of the response procedures and first aids may have a dramatic positive consequence on your work facilities and on the life of your friend.
· However, always remember the following:
A.DON’T PANIC
B.IMMEDIATELY ALARM/INFORM
· Immediately alarm/inform because help is always required from professional persons.
ACCIDENT INVESTIGATION
Since it is the desire of RAMP to prevent all forms of accidents in her operations, all efforts will be geared towards achieving this policy objective. However, detailed investigation shall be carried out to prevent re-occurrence in case of events that nevertheless occur.
This primary purpose of accident investigation is to establish the circumstances leading to the accident and use the facts to prevent re-occurrence in the future. Consequently, the exercise shall be conducted as a fact-finding and not a fault-finding activity.
The responsibility for accident investigation lies with the SPIU. Supervisors and safety officers are therefore expected to promptly investigate any accident that occurs within and/or around the project work areas.
4.5Environmental Monitoring
This aspect of environmental management is specifically designed in the identification of associated project impacts, equipment malfunction/failure and remedial action. Therefore, for the purpose of monitoring, RAMP shall focus mainly on the aspects highlighted in an earlier section of this report and reiterated below:
· Traffic and Traffic Management
· Air Quality and Noise
· Flood Waters, Runoff and Soil Management
· Hydrological Issues
· Waste Management
· Hazardous Materials Storage
· Fire Safety and Emergency Management Plans
· Health and Safety
Based on the foregoing, and in addition to the management options presented above, it is obvious that regular and periodic monitoring of relevant environmental attributes is necessary. The specific environmental attributes, the relevant parameters, and the regularity of monitoring is presented in Table 4.1 below:
Table 4.1:Monitoring Requirement
S/N
ENVIRONMENTAL/SOCIAL ATTRIBUTE
RELEVANT PARAMETERS
FREQUENCY OF MONITORING
LOCATIONS TO BE MONITORED
RESPONSIBLE PARTY
1
Air Quality and Noise Levels
· NO2,
· SO2,
· CO,
· SPM,
· Noise Levels
Monitoring shall be carried out monthly during construction and quarterly during operations and maintenance, for the first 3years.
Monitoring shall be undertaken within construction areas and control points
· RAMP SPIU
· EMP Consultant
· KEPA
2
Soil
· pH;
· Conductivity;
· Heavy Metals;
· Total Organic Carbons and Total Nitrogen
· Hydrocarbons
· Anions and cations
· Microbiology
Monitoring shall be carried out monthly during construction and quarterly during operations and maintenance, for the first 3years.
Monitoring shall be undertaken within construction areas and control points
· RAMP SPIU
· EMP Consultant
· KEPA
3.
Occupational Health and Safety
· Personnel health
· Health of nearby communities
Monitoring shall be carried out half yearly during construction and yearly during operations
Monitoring shall cover project workers and communities within construction areas
· RAMP SPIU
· EMP Consultant
· KEPA
4
Traffic Management
Traffic situation within and around construction sites shall be regularly monitored to ensure that construction activities do not negatively affect baseline traffic situations
Monitoring shall be undertaken half yearly during construction
· RAMP SPIU
· EMP Consultant
· KEPA
SECTION FIVE
COST ESTIMATES AND INSTITUTIONAL FRAMEWORK REQUIREMENT FOR THE EMP
5.1 Introduction
In this section of the report, an overview of the estimated costs of implementing the various mitigation measures indicated in the previous section of this report, and the costs of carrying out environmental monitoring is presented. Also presented in this section of the report, is an overview of the institutional framework requirement for the implementation of the EMP.
5.2 Cost Estimates for Mitigation Measures and Monitoring Activities
The cost estimates for mitigation measures recommended for the various issues identified in the previous section of this report are presented in Table 5.1 while Table 5.2 presents the cost estimates for the monitoring activities identified as necessary for the various phases of the project implementation, as described in the previous section of this report.
5.1Cost Estimates for the Relevant Mitigation Measures
S/N
ENVIRONMENTAL/SOCIAL ISSUES
MITIGATION OPTIONS
COST OF MITIGATION MEASURES
RESPONSIBLE PARTIES
1
Traffic and Traffic Management
Traffic is not a serious issue in virtually all of the designated roads, since they are mostly rural feeder roads, subject to minimal traffic normally.
Traffic management schemes shall be provided by contractors handling the projects. taking into consideration, as a minimum, the following:
· Minimization of obstruction to normal traffic flow in the area;
· Provision of temporary alternative routes, in the event that absolute obstruction of traffic is inevitable.
· In addition to the foregoing, RAMP shall work in conjunction with traffic management agencies such as the Federal Road Safety Corps (FRSC), to optimize traffic flow, by minimizing traffic obstruction
Provision of Alternative routes will be required only at river/stream crossings. For Seasonal streams, if construction is undertaken in the dry season, only minimal grading and filling of alternative crossings will be required. This is estimated to cost =N=300,000/crossingEstimates for involvement of traffic management agencies is put at =N=250,000 in each lot
Alternative routes will be provided by construction contractors, while contractors will work in conjunction with RAMP SPIU to involve traffic control agencies for traffic control
2
Air Quality and Noise Levels
A. Air Quality
The primary concern in terms of air quality is the health of project workers, and nearby communities, who are designated as sensitive receptors for this project. Generally, dust from construction activities will lead to elevated suspended particulate matter levels in ambient air. This, in turn, could predispose project workers and host communities to respiratory infections and ailments.
Noise
Noise from vehicles associated with construction activities and subsequently, those that will ply the roads, will lead to an increase in ambient noise level. However, because noise during operations will be intermittent, rather than continuous, therefore, effort will need to be paid to construction period noise levels. This is in order to ensure that regulatory limits are not exceeded
RAMP and its contractors shall ensure that:
· Regular monitoring of air quality around the project area are carried out, on a monthly basis, so that negative trends can be promptly detected and addressed;
· Personnel are not allowed to exceed their regular shift durations
· Adequate respiratory protection is provided for project workers on site, so that their exposure to respiratory irritants is minimized
· In the dry season, there will be need for periodic sprinkling of the road surface with water, especially were road works are taking place within and around communities to minimize suspendable dust levels in ambient air.
Noise
RAMP and its contractors will implement the following measures to protect its workers and nearby host communities from the hazards of high noise levels in the area:
· Provide hearing protection for project personnel, who are in high noise areas, close to the machinery that will be used for project activities;
· Ensure that project personnel do not exceed the normal 8-hr duration of their shifts;
· Provide for regular monitoring of noise levels around the project locations, to facilitate early detection of exceedance of regulatory noise levels
· Undertake regular monitoring of personnel to ensure that they adhere to the relevant health and safety standards pertaining to noise, such as wearing ear protection when noise levels are getting high.
· Ensure that machinery to be used for project construction activities have functional silencers that ensure that noise emissions meet international regulatory standards
Cost of monitoring is provided in Table 5.2.
Provision of respiratory protection (masks) will cost an estimate of =N=250,000/lot
Provision of water tankers to sprinkle the roads will cost an estimate of =N=100,000/km
Noise monitoring costs are provided in Table 5.2
Hearing protection will cost an estimated =N=250,000/lot
Respiratory protection will be provided by contractors, and they will work in conjunction with RAMP Environmental Officers to ensure the appropriate usage of these equipment
Water sprinklers shall be provided by construction contractors
Hearing protection will be provided by contractors
Regular maintenance of machinery shall be undertaken by construction contractors
3
Waste Management
Different categories of wastes will typically be generated around the project area. These will include domestic/food wastes, sanitary waste and some level of oil wastes. These need to be properly handled to prevent environmental degradation
the following waste management options shall be instituted:
· Wastes shall be collected and properly segregated at source. Typical segregation options include separation into: food waste; paper and stationeries; and recyclables (plastic and glass).
· Oily wastes shall be collected and disposed in approved facilities in the state;
Provision of waste bins at construction sites shall cost an estimated =N=120,000/lot
Contracting of hazardous waste disposal contractors will cost =N=250,000/lot/month
Provision of waste bins and contracting of waste management contractors shall be undertaken by contractors but will be monitored by RAMP SPIU Safety Officer attached to the lot.
4
Hazardous Materials Storage
The main hazardous materials that are likely to be stored within and around the project area include diesel fuels for powering generating sets and for running machinery and equipment to be used for the project; paints and lubricants. Because these materials are highly flammable, they need to be carefully handled.
Hazardous materials storage must make provision for:
· Storage in unobtrusive locations, with restricted access. Access to storage areas shall be limited to only authorized personnel
· Adequate signage must be provided in the storage area. These signage shall warn on the dangers of naked flames in the area as well as need for proper dressing and use of appropriate PPEs
· Areas where flammable materials are stored must be isolated from nearby communities. They must be shaded from the sun.
· Personnel working in such areas shall be provided with necessary PPEs, including oil-proof safety boots and coveralls.
· Personnel must be subject to training on handling of hazardous materials and duly certified. The will also be subject to periodic refresher training
Provision of signage and cordoning of stacking sites will cost an estimate of =N=200,000/lot
PPE per personnel will cost an estimate of =N=50,000/personnel
Personnel training will cost =N=45,000/person
This will be the responsibility of the construction contractors per lot
5
Hydrological Issues
Generally, some portions of the project location, especially in the southern lots, are quite susceptible to inundation and water logging during the rainy season. Therefore, in the event that road construction activities block existing natural drainage routes, it could exacerbate inundation in upstream areas and cause drying up in downstream areas, leading to negative modifications in existing hydrological regimes.
The following measures shall be undertaken:
· Road alignments shall take into due cognizance, the existing drainage in the area
· Where it is inevitable to tamper with hydrological flows, alternative flow routes shall be created. This could include the use of underground conduit pipes and/or culverts
No cost is associated with these measures as these options are expected to have been taken into consideration by the contractor
Contractor will be responsible for these actions but will be monitored by RAMP
6
Fire Safety and Emergency Management
Fire outbreak is a major possibility in the storage area, where flammable materials like diesel, petrol and engine oil is stored. It is therefore necessary that a comprehensive fire safety and emergency management option be provided as part of overall project environmental management plans.
The following shall be instituted:
· Muster points shall be provided for all personnel to gather in the event of accidental fires
· Adequate fire fighting gadgets shall be made available and distributed around construction sites, especially where flammable materials are stored. These includes:
1)Fire extinguishers (H20, dry powder & CO2)
2)Fire hydrant and foam.
· Instructions shall be readable on the body of the fire extinguisher.
· Personnel should be familiar with the operations of fire extinguishers
· Given the agrarian nature of the project location, and the fact that many of the locations are grasslands, where fire can spread easily. Therefore, adequate fire breaks shall be constructed around project fuel storage sites, to prevent the spread of accidental fires;
· Regular training on fire-fighting and handling shall be provided.
Fire fighting equipment per lot is estimated to cost =N=350,000
Construction of fire breaks around stacking areas is expected to cost =N=150,000/lot
Contactor will be responsible for these actions but will be monitored by RAMP
7
Health and Safety
The health and safety of personnel working in the project area is important.
Regular safety training and drills must be carried out to enhance the sensitivity of personnel to safety issues. Specifics of drills that have to occur include the following:
· Fire drills must be held at least quarterly. Such drills will include mustering at designated muster points, responding to fire alarms, handling fire-fighting equipment, etc.
· Such drills must be coordinated by the Health and Safety Officer attached to the construction site, who must be a certified safety practitioner.
· Personnel must be subject to comprehensive health checks prior to employment, so that a baseline can be established. Attention shall also be paid to trend of common ailments among toll collection staff, such that any recurrent ailment among the staff that can be remotely or directly related to their work shall be investigated, as the need arises.
Cost of quarterly fire drills and health checks prior to employment should already be incorporated into contractors HSE plan for the project and as such, no costs are associated with these measures
Contractor will be responsible for this, but will be monitored by RAMP’s Environmental officer
8
Accidents/Incidents
An accident is an unplanned, uncontrolled or undesired event that could result in personal injury, property damage or loss of time. Since they are not planned, specific mitigation measures cannot be provided for accidents/incidents. However, preventive plans and palliative measures must be put in place
The most critical palliative measure that should be put in place towards preventing accidents/responding promptly, if and when they occur, is the preparation of a site-specific Emergency response plan. Such plans must take into cognizance, as a minimum, the specifics of each project lot
The cost of preparing a detailed and comprehensive Emergency Response Plan for each lot is estimated at =N=500,000.00
Contractor shall handle the preparation of Emergency Response Plans and will share these with RAMP SPIU
Table 5.2: Cost Estimates for Monitoring Activities
S/N
ENVIRONMENTAL/SOCIAL ATTRIBUTE
RELEVANT PARAMETERS
FREQUENCY OF MONITORING
LOCATIONS TO BE MONITORED
COST ESTIMATE FOR MONITORING
RESPONSIBLE PARTY
1
Air Quality and Noise Levels
· NO2,
· SO2,
· CO,
· SPM,
· Noise Levels
Monitoring shall be carried out monthly during construction and quarterly during operations and maintenance, for the first 3years.
Monitoring shall be undertaken within construction areas and control points
=N=250,000/month/lot
· RAMP SPIU
· EMP Consultant
· KEPA
2
Soil
· pH;
· Conductivity;
· Heavy Metals;
· Total Organic Carbons and Total Nitrogen
· Hydrocarbons
· Anions and cations
· Microbiology
Monitoring shall be carried out monthly during construction and quarterly during operations and maintenance, for the first 3years.
Monitoring shall be undertaken within construction areas and control points
=N=300,000/lot/month
· RAMP SPIU
· EMP Consultant
· KEPA
3.
Occupational Health and Safety
· Personnel health
· Health of nearby communities
Monitoring shall be carried out half yearly during construction and yearly during operations
Monitoring shall cover project workers and communities within construction areas
=N=250,000/lot/monitoring
· RAMP SPIU
· EMP Consultant
· KEPA
4
Traffic Management
Traffic situation within and around construction sites shall be regularly monitored to ensure that construction activities do not negatively affect baseline tr