26
CHAPTER5 PRECEDENCE DIAGRAM

CHAPTER5 PRECEDENCE DIAGRAM

  • Upload
    others

  • View
    15

  • Download
    0

Embed Size (px)

Citation preview

Page 1: CHAPTER5 PRECEDENCE DIAGRAM

CHAPTER5

PRECEDENCE

DIAGRAM

Page 2: CHAPTER5 PRECEDENCE DIAGRAM

Advantages of using Precedence Diagram:1. No dummy activities are required.2. A single number can be assigned to identifyeach activity.3. Analytical solution is simpler

Page 3: CHAPTER5 PRECEDENCE DIAGRAM

DIFFERENCE BETWEEN ARROW DIAGRAMAND PRECEDENCE DIAGRAM

1 2A

Arrow

A

Precedence Diagram

Arrow diagram

Page 4: CHAPTER5 PRECEDENCE DIAGRAM

T.E Sub base

Lay pipe

Back fill compact

Precedence diagram

Page 5: CHAPTER5 PRECEDENCE DIAGRAM

CON.

The project can be represented in Other way which called The stair type relationship.

In this method each activity divided into many parts as shown below

Page 6: CHAPTER5 PRECEDENCE DIAGRAM
Page 7: CHAPTER5 PRECEDENCE DIAGRAM

A B

Page 8: CHAPTER5 PRECEDENCE DIAGRAM

A B

Page 9: CHAPTER5 PRECEDENCE DIAGRAM

A B

Page 10: CHAPTER5 PRECEDENCE DIAGRAM

A B

Page 11: CHAPTER5 PRECEDENCE DIAGRAM
Page 12: CHAPTER5 PRECEDENCE DIAGRAM
Page 13: CHAPTER5 PRECEDENCE DIAGRAM
Page 14: CHAPTER5 PRECEDENCE DIAGRAM

What it does mean?

Page 15: CHAPTER5 PRECEDENCE DIAGRAM
Page 16: CHAPTER5 PRECEDENCE DIAGRAM
Page 17: CHAPTER5 PRECEDENCE DIAGRAM
Page 18: CHAPTER5 PRECEDENCE DIAGRAM
Page 19: CHAPTER5 PRECEDENCE DIAGRAM

Four time values associated with eachactivity:

1.ESD (Early Start Date)is the earliest point in time that any activity bursting from its beginning node can start.

2.EFD (Early Finish Date)

is the earliest point in time that any activity can be finshed

Page 20: CHAPTER5 PRECEDENCE DIAGRAM

3.LSD (Late Start Date)Is the latest point of time that any activity can be start.

4.LFD Late (Finish Date)

is the latest point in time that any activity is the latest point in time that any activity which merges at the activity’s endingnode can finish.

Page 21: CHAPTER5 PRECEDENCE DIAGRAM

Forward Pass RulesRule 1The initial project event is assumed to occur at time zero

Rule 2All activities are assumed to start as soon as possible,that is , as soon as all the predecessor activities arecompleted.completed.

Rule 3The early finish time of an activity is merely the sum ofits early start date and the estimated activity duration.EFD = ESD + T

Page 22: CHAPTER5 PRECEDENCE DIAGRAM

Rule 4

The late start date LSD is found by subtractingthe activity duration T from the late finish dateLFDLSD = LFD - T

Page 23: CHAPTER5 PRECEDENCE DIAGRAM

1. Total Float

Total float may be defined as that time spanin which the completion of an activity mayoccur and not delay the termination of theproject.TF = LFDij - EFD= LSD - ESD= LSD - ESD

Page 24: CHAPTER5 PRECEDENCE DIAGRAM

2. Free Float� Free float may be defined as the time spanin which the completion of an activity mayoccur and not delay the finish of the projectnor delay the start of any following activity.FF = ESDB - EFDA

3. Interfering Float3. Interfering FloatThat part of the total float which remains after freefloat has been deducted is the interfering float.It may be defined as: the time span in which thecompletion of an activity may occur and not delaythe termination of the project but within whichcompletion will delay the start of some otherfollowing activity.INTF= TF - FF

Page 25: CHAPTER5 PRECEDENCE DIAGRAM

Precedence NetworkPrecedence NetworkCalculations

Page 26: CHAPTER5 PRECEDENCE DIAGRAM