Gwadar Port AuthorityPak- China Friendship Road
Gwadar
TENDER DOCUMENTS
Preparation of DetailedGPA Accounts and Complete
AuditingBy Chartered Accountants
c) At outset, the operations of Gwadar Port were transferred to a private party under
a Concession Agreement w.e.f February 2007 and almost all assets created under2
b) III the beginning the project accounts of GPA were prepared on single entry
system; however, during 2006, the accounts were converted on Double-entry
system and accounting software was developed, taking the balances of accounts of
previous period. At present, all accounting entries are being made through the
Accounting Soft ware and the same is running satisfactorily.
2002 with the assistance of China and 'wascompleted 011 30th June 20 J O.The cost
of project amounting to approx Rs. ]7 Billion was jointly financed by
Governments of China and Pakistan. The part Iof project works namely Marine
Works were completed by the Chinese Finn MIS CIlEC, whereas part II namely
Shore civil works were done by Pakistani firms. The foreign currency financing
was arranged frOI11 China under some financing agreement and all payments to
Chinese contractor as well as consultants were released directly through Chinese
bank. The payments to Chinese firms were made in ]2 installments on the basis of
milestones achieved and certified by the Project Director GPA. The mentioned
project worth Rs. ]7 Billion had already been audited satisfactory.
1.1.2 Profile:
a) The Gwadar Port Authority is the 3,d Port of Pakistan, located at Gwadar coast on
the western Balochistan having a road distance of approx 630 KM from Karachi.
The project i.e. Gwadar Deep Water Port Project (GD\VPP) was started during
1.1.1 Offers arc invited from reputable nccountin]; und uudit films for SUbmitting technical
and financial proposals lor prcpnrntion of' detailed uccounts or Gwadar Port Authority and
complete auditing by Chartered Accountants registered with ICAP. This document will form
the basis of contract between the OrA and the selected accounting and audit firm.
1.1 General
I. Letter of Iuvitntlon (LOJ)
Preparation ofddnil('d CPA "0 \ (','()uJlL'l uud auditing by
Chartered Accounts
3
1.1.3 The interested parties shall have sufficient knowledge and experience for such works
and should have sufficient knowledge of the area. It is suggested that before submitting
proposals a visit of the area and the organization may be helpful in understanding the tasks,
the location and other aspects. GPA will however, take no responsibility for such visits, but
wouJd be available for any background and necessary data and information.
i) East Bay Express Way Project
ii) Up- gradation GPA Housing Complex Project
Iii) Mullah Band Port Allied Project (OPA Business Service Complex)
iv) Pak-China Vocational Training Institute Project
v) CPEC Support Unit
vi) Feasibility Study of Break Water Project
vii) Feasibility Study of Petroleum / Petro-chemical Terminal & Dirty dry Bulk
Terminal Project
viii) Rehabilitation of Auction Hall of Gwadar Mini Port
d) The interested parties shall audit the following project accounts which are
functioning under the supervision ofGPA accordingly.
the project except a few ones were transferred to the company for a certain period
of time on BOT basis. Meanwhile the said agreement was breached and entered a
new Concession Agreement w.e.f. May 2013 to Mis China Oversea Ports Holding
Company (COPHC).
4
1.2.8 Financial proposals of only those firms who have been declared as technically
qualified wiU be opened publicly at a time, date and venue which
will be announced by OPA and notified to all successful bidders. The financial
proposals of the Firms who were not technically qualified will be returned unopened
to respective bidders.
1.2.7 The firms scoring 70% or above points will be declared technically qualified.
t .2.6 The technical proposals will be evaluated in accordance with the specified evaluation
criteria given in these documents by the "Tender Evaluation Committee" appointed
by OPA.
1.2.5 After the deadline for submission of proposals, the technical proposals wiUbe opened
immediately by the "Tender Evaluation Committee".
1.2.4 The completed proposals must be delivered at the submission date given in the Tender
Notice. Any proposals received after the closing date and time for submission of
proposals shall be returned unopened.
1.2.3 An authorized representative of the firm shall initial all pages of the finanoial
proposal. The representative's authorization is to be confirmed by an "Authorization
Letter" accompanying the proposal.
l.2.2 The proposal shall be prepared in indelible ink, It shall contain no overwriting, except
as necessary to correct errors made by the Finn itself. Any such corrections must be
initialed by the authorized person (s) of the firm.
1.2.1 The "Single stage two envelopes" bidding procedure will be adopted for receipt,
opening, and evaluation of the proposals, as given in the succeeding paragraphs. The
envelopes shall be marked as "TECHNICAL PROPOSAL" and "FINANCIAL
PROPOSAL" in bold and legible ink to avoid confusion. Both envelopes shall be
sealed and the two envelopes shall be placed in a single package, also sealed.
1.2 Bidding Procedure
5
1.2.12 The Bids received from the Eligible Bidders shall then be evaluated by the "Technical
Committee / The Technically Member of the Procurement Committee." The
Technical ProposaJ shall be evaluated Package-Wise on technical specification /
requirements in the line of ICAP rules though comparison minimum required
technical qualification (as stated in the Data-Sheet) compared with specifications
mentioned in the Technical Bid. Bids conforming to the required specification /
technical requirements shall stand Responsive, hence will qualify for Financial Bid
opening. All proposals shall be categorized as:
i) Responsive Proposals
ii) Non-Responsive Proposals
1.2.11 Proposals from Ineligible Bidders shall be declared "Non-Responsive", consequently
shall not be accepted for any further evaluation"
i) Their Financial Proposals shall be returned without being opened.
ii) Their Bid security shall be released upon their written request.
i) Eligible Bidders
ii) Ineligible B.idders
1.2.10 Selection of the successful bidder(s) shall be based on the Least-Cost Selection
Method which means, "Technically responsive, lowest financial bid, received from
Eligible Bidder" (as specified under the heading of the "Letter of invitation for Bids
Eligibility Criteria for Bidders" and Bidders shall be categorized as:
1.2.9 The Firm giving lowest rates among technically qualified firms will be considered for
award of contract and will be called for further discussion and necessary action.
6
Assistant Director (Accounts)Gwadar Port AuthorityPh: 0869200426
864200408
1.3.8 The technical and financial proposals should be submitted at the following address to
be received on or before~ up tolv /l<m. Any proposal received after this date and
time will not be accepted. No excuses on account of communication or transportation
problems will be entertained.
1.3.7 The GPA reserves the right to accept any proposal or reject all proposals on genuine
grounds which will be intimated to any participating party on demand.
1.3.6 The firms will be required to certify that they have not been black listed by any
Government agency in the past and also indicate the details of any dispute with any
Government agency, if any.
1.3.4 The remuneration to be received for the subject work will be subject to tax deductions
as per Government rates prevailing at the time of payment.
1.3.5 The earnest money equal to 2% of the quoted rates must be submitted along with
technical proposal in the shape of Pay Order or Bank Draft in the name of Gwadar
Port Authority without which the offers will not be valid for acceptance.
1.3.3 The Financial proposal must be inclusive of all overheads, fees, duties, taxes, profits
and other charges. No amount over and above the quoted rates will be paid by GPA.
1.3.2 Regarding personnel, a certification is required to be submitted conforming that they
are employees of the tendering firm or their services have been acquired for
completion of this assignment. The CVs of the personnel will have to be signed by the
persons themselves, endorsing and confirming their availability for the subject work.
1.3.1 The cost for preparation of proposals including cost of visits etc is not payable
Ireimbursable.
1.3 Instructions to the Tenderers/Bidders
7
e) Study the Financial Agreements entered between Government of Pakistan and
COPRC regardi 9% of Gross Revenue as share ofGPA on port operations and 15%
d) Examine and review all accounting entries recorded in the books to ensure that
these are in line with universally accepted accounting procedures and guidelines
issued by Government through AGPR or other agencies.
c. Examine the Bank statements and other payment documents including local /
foreign transactions on account of aids/grants/loans given by the Government.
-each financial year from l" July and ending at 30th June.
b. Examine and organize all accounting data from July 2016 to June 2018, for
a. Study and review the accounting system adopted by GPA in the past and at
present.
2.2 To accomplish the above tasks the firm would need to study and examine the
following:
b. Carrying complete audit of the accounts through qualified chartered
accounting finn enlisted in ICAP and fulfilling the requirements of chartered
accountants ordinance and keeping in view the requirements of GPA Ordinance 2002
and guidelines provided by AGPR, P&D Division and Finance Division.
a. Preparation of year wise accounts of Gwadar Port Authority from the financial
period July 2016 to June 2018 (It can be extended for further three (03) years). The
Accounts are to be prepared on double entry system as per universally accepted
standards and procedures and keeping in view the instructions and guidelines of the
Government given through AGPR, P&D Division and Finance Division's.
2.1 The scope of work comprises o_fthefollowing main tasks.
2. Scope of Work / Terms Of Reference.
8
-I) Study and examine the PC-IV oftbe projects.
k) Study and examine the original PC-I and PC-IV of the completed / ongoing
projects and revisions made from time to time.
j) Study and examine observations made by various Government agencies on the
accounts of GPA including P&D Division, Finance Division, AGPR, Commercial
Audit and other agencies.
i) Study and examine the main contracts given by GPA for different components
of GPA.
h. Discuss with the concerned officers dealing with projects matters namely P&D
and Finance Directorates.
g) Study the guidelines provided by relevant Government agencies including
P&D Division, Finance Division and AGPR regarding compilation and maintenance
ofGPA's and its related projects accounts
f) Study the Concession Agreement entered between GPA and concession
holder regarding transfer of assets/operations.
of Gross Revenue as GPA Share on Free Zone operations as per Concession Agreement and
would suggest an appropriate accounting system in this regard.
9
•
d)Understanding oftbe work.
The bidding firm may demonstrate its 5 marks
understanding of the work through a concept
paper, enumerating all activities involved in
completing the work, documents/information
to be collected, time period required,
techniques to be applied by them /n
collecting, organizing and compiling/the
minimumof 7 years of experienceof Accountscompilation.
• At least two qualified accounts/auditofficers having qualification of not less thanB.Com with at least 7 years experience of 5 marks for each
workingin the fieldof accounts/Auditing(Note: Minimum 45 points would be thequalifyingcriterion)
Accountant duly registered with ICAP andfulfilling the requirements of CharteredAccountantOrdinance.
• At least one qualified accountingexpert(ICMAIFCMAJCA or equivalent) with 5 marks for each
10 marks
,_
20
10
30At least Two qualified Chartered 15 marks for each
• Two marks for complete ]0
Auditing
• Two marks for Accounts 10compilation
c) QualificationslExperience of personnel
b) Experience ofthe firm
One mark for each year of 5
establishment
a) Establishment ofthe firm
TotalMarking criteriaFactor
3.1 The Technical Evaluations of t_heTendering firms will be carried out on the basis of
following factors.
3. Tecbnical Evaluations oftbe Tendering firms
10
-
3.3 The firm, among the technically qualified firms, submitting lowest rates will be
considered for awarding the work.
3.2 The Technical Evaluations of the Tendering firms will be done by a Technical
Evaluation Committee on the basis of Technical proposals submitted by the firm and firms
securing 70% or more will be declared as qualified and financial proposals submitted by them
will be opened. The firms securing less than 70% marks will not be eligible and their
fmancial proposals will not be opened and returned to them. (Note: The minimum
requirements given at para c above (i.e. minimum 45 points out of 60 points under this factor)
must be met; otherwise the firm will not be technically qualified even if they have secured
total marks of 70%)
data, the accounting reports and statements
to be prepared and the no and quality of
personnel to be deployed by them to.complete the work.
e) Experience of working in similar 5 marks
environment. 5 marks
(The tendering firm may indicate if they
have completed any project of such nature in
Gwadar or in Port Operations in the past.
11
4.7 If the completion of work was delayed, because of unexplainable and unacceptable
reasons, beyond the stipulated completion period of 03 months, LD Charges @ 0.50% of the
contract value or Rs.5000/- per day (whichever is on higher side) for each day of de!ay will
be charged subject to a total of 5% of contract value.
4.6 The General Terms and Conditions of Tendering prescribed by Pakistan Engineering
council I GGRA I ICAP for such tenders shall be applicable.
4.5 Any dispute and difference arising out of this agreement shall be settled amicably
between the two parties to the contract with mutual discussion and consultation. However if
the same was not possible, the matter shall be referred to Chairman GPA for a decision,
whose decision shall be final.
4.4 The officers I staff to be deployed by the firm should be with clear record and may
require prior security clearance from local administration.
4.3 Payment of contract amount will be made on the basis of targets achieved as
stipulated in the financial proposal.
4.2 GPA will not provide accommodation to the team of selected firm and they will be
responsible for meeting cost of food and other expenses.
4.1 The selected firms will be requ_iredto complete the entire work within a period of 03
months after signing the contract or awarding letter, whichever is earlier.
4. Special Terms and Conditions
12
Under this heading list all positions held by staff members since graduation, giving dates,
names of employing organization, title of positions held and locations of assignments.
Indicates experience in Accounting and Software related projects during last 10 years, also
give types of activity performed and client reference, where appropriate.
Experience Record:
Education:
Under this heading, summarize professional qualifications, college / University and other
specialized education, of staff member giving names of school, dates attended and degrees
obtained).
(Under this heading, give outline of staff members experience and training most pertinent to
assigned work on proposed team. Describe degree of responsibility held by staff member on
relevant previous assignment and give dates and location.
Key Qualification:
Nationality Proposed Position of Team: _
Firm:------withYearsProfession:------------------------
Name: ------------------------------
FORMAT OF CURRICULUM VII AE
FOR MEMBERS OF THE TEAM.
APPENDEX - 3
13
5.3 Security Deposit. The successful bidders will need to submit 10% performance
security prior to starting the work which shall be returned 03 months after completion of
work.
50%
c. Complete audit of the accounts (at least two chartered
Accountant) for the FlY July 2016 to June 2018
20%b. Preparation of Financial statements and other
Reports given in the TORI Scope of Work
30%
a. Collection and Compilation of accounts
And preparation of accounting balances
From July 2016 to June 2018
5.2 The payment of contract amount will be made on achieving targets as under:
Terms of Payment.
Total
a. Preparation ofGPA accounts July 2016 to
June 2018 and related works
b. Complete audit ofGPA accounts July 2016 to
June 2018.
Amount
Bill of Quantities
The tendering firm may submit their .financial bids for the following components of work
subject to strictly in the line of lCAP rules (Relevant documents must be attached with Bids
documents).
Financial Proposal