Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
i
Chittagong Water and Sewerage Authority (CWASA)
“To be the most efficient Water and Sewerage Authority in Bangladesh”
Chittagong Water Supply Improvement & Sanitation Project
(CWSISP)
Utility Modernization Umbrella Consultancy (CWSISP/S-31)
MANAGEMENT INFORMATION SYSTEM PLAN
JULY 2016 – JUNE 2018
July 2016
Prepared by: NWSC- External Services, Uganda
in association with M/s Devcon, Bangladesh and
UNESCO IHE, The Netherlands
Plot 39 Jinja Road, P. O. Box 7053, Kampala, Uganda
Tel: +256 313 315 100/111/715
Email:[email protected] Website: www.nwsc.co.ug
i | P a g e
TABLE OF CONTENTS List of Abbreviations and Acronyms ....................................................................................................... ii
List of Tables .......................................................................................................................................... iv
List of Figures ......................................................................................................................................... iv
1.0 INTRODUCTION ........................................................................................................................... 1
1.1 Preamble ................................................................................................................................. 1 1.2 Background to the Assignment ............................................................................................... 1 1.3 Structure of the Report ........................................................................................................... 1 1.4 The Chittagong Water Supply and Sewerage Authority (CWASA) .......................................... 2 1.5 The Status of Information Management in CWASA ............................................................... 3 1.6 Objectives and Scope of the Assignment ................................................................................ 4
2.0 APPROACH AND METHODOLOGY ............................................................................................... 5
2.1 Sub-Tasks/Steps Undertaken in Executing the Assignment ................................................... 5 2.2 Review of Background Literature ............................................................................................ 5 2.3 Interviews with Key Informants .............................................................................................. 6 2.4 Visits to Key Facilities .............................................................................................................. 6 2.5 Audit and Assessment of CWASA’s Key Business Processes ................................................... 6
2.5.1 Water Treatment & Production ...................................................................................... 7
2.5.2 Water Distribution and Network O&M ........................................................................... 8
2.5.3 New Connection Implementation ................................................................................... 8
2.5.4 Meter Reading & Billing .................................................................................................. 9
2.5.5 Revenue Management .................................................................................................... 9
2.5.6 Accounts & Finance Management ................................................................................ 10
2.5.7 Customer Complaints Handling .................................................................................... 10
2.5.8 Human Resource Management .................................................................................... 11
2.5.9 Monitoring & Evaluation (Management Reporting) ..................................................... 11
2.5.10 Customer Mapping & GIS .............................................................................................. 12
2.5.11 ICT Support Provision .................................................................................................... 12
2.5.12 Procurement & Transport ............................................................................................. 13
2.5.13 Public Relations Management ...................................................................................... 13
2.5.14 Project Management .................................................................................................... 13
2.6 Identification of Information Requirements for Key Business Processes ............................. 14 2.7 Information Management Gap Analysis ............................................................................... 14 2.8 Formulation of Information Management Improvement Strategies ................................... 18
3.0 THE CWASA MANAGEMENT INFORMATION SYSTEMS (MIS) PLAN (2016-2018) ..................... 21
4.0 FRAMEWORK FOR AN INTEGRATED MANAGEMENT INFORMATION SYSTEM ......................... 24
4.1 Functional Relationships between Processes ....................................................................... 24 4.2 Required Functionality for Integrated MIS Core Modules .................................................... 25
ii | P a g e
5.0 REQUIREMENTS FOR ESTABLISHMENT OF PRIORITY IT INFRASTRUCTURE .............................. 27
5.1 Network Infrastructure ......................................................................................................... 27 5.2 Server Hardware ................................................................................................................... 27 5.3 Email Solution ....................................................................................................................... 28 5.4 Hardware and Data Security ................................................................................................. 28
6.0 STAFF CAPACITY DEVELOPMENT AND ON-THE-JOB TRAINING REQUIREMENTS ..................... 30
APPENDICES .......................................................................................................................................... 32
Appendix 1: List of Persons Met and Interviewed ............................................................................ 33 Appendix 2: Summary of Process Audit and Assessment for CWASA’s Key Business Processes ..... 36 Appendix 3: Sample Management Information Systems (MIS) Report for CWASA (April 2016) ..... 47 Appendix 4: Sources of Data for MIS Report .................................................................................... 50 Appendix 5: Summary of Critical Data and Information Generated and Managed for each Key Business Process ............................................................................................................................... 52 Appendix 6: The CWASA Management Information Systems (MIS) Plan 2016-2018 ...................... 64 Appendix 7: Assumptions and Accompanying Notes to MIS Plan Cost Estimates ........................... 76
List of Abbreviations and Acronyms AE Assistant Engineer
AIM Asset Information Management
AMR Automated Meter Reading
APA Annual Performance Agreement
BPDB Bangladesh Power Development Board
CCC Chittagong City Corporation
CE Chief Engineer
CHS Complaints Handling System
CM Commercial Manager
CSR Corporate Social Responsibility
CTS Complaints Tracking System
CUG Closed User Group
CWASA Chittagong Water Supply and Sewerage Authority
CWSISP Chittagong Water Supply Improvement and Sanitation Project
CWSISP-S31 Chittagong Water Supply Improvement and Sanitation Project, Package 31
DMD Deputy Managing Director
DMD (A) Deputy Managing Director (Administration)
DMD (E) Deputy Managing Director (Engineering)
DMD (F) Deputy Managing Director (Finance)
DR Disaster Recovery
DTW Deep Tube Well
EE Executive Engineer (also abbreviated XEN)
ERP Enterprise Resource Planning
FY Financial Year
GIS Geographic Information Systems
GoB Government of the People's Republic of Bangladesh
GWTP Groundwater Treatment Plant
iii | P a g e
HOD Head of Department
HQ Headquarters
HR Human Resources
HRMIS Human Resources Management Information System
IAM Infrastructure Asset Management
ICT Information and Communication Technology
IDA International Development Agency
IS Information Systems
IT Information Technology
JICA Japanese International Cooperation Agency
KPI Key Performance Indicators
KSA Karnaphuli Service Area
KWSP Karnaphuli Water Supply Project
LAN Local Area Network
MD Managing Director
MIS Management Information System(s)
MLD Mega litres per day
MMS Meter Management System
MOD Maintenance, Operation and Distribution
O&M Operation and Maintenance
OJT On-the-Job Training
PANI Project for Advancing Non-Revenue Water Reduction Initiative
PBX Private Branch Exchange
PC Personal Computer
PD Project Director
PDU Procurement and Disposal Unit
PF Personal File
PID Planning and Infrastructure Development
PM&E Performance Monitoring and Evaluation
PMU Project Monitoring Unit
PPM Planned Preventive Maintenance
PRO Public Relations Officer
PVC Polyvinyl Chloride
RfP Request for Proposal
SA Systems Analyst
SAE Sub Assistant Engineer
SCADA Supervisory Control and Data Acquisition
SE Superintending Engineer
SLA Service Level Agreement
SM Social Media
SMART Strategic, Measurable, Achievable, Realistic, and Time-bound
SMS Short Message Service
SOP Standard Operating Procedure
SQL Structured Query Language
SWIFT Sustainable Water Supply Services Improvement and Financial Tenacity
SWTP Surface Water Treatment Plant
iv | P a g e
TBD To Be Determined
TCD Training and Capacity Development
TIA Training Impact Assessment
Tk Taka
TNA Training Needs Assessment
UPS Uninterruptible Power Supply
URL Universal Resource Locator
VoIP Voice over Internet Protocol
VPN Virtual Private Network
WAN Wide Area Network
WASA Water and Sewerage Authority
Wi-Fi Wireless Fidelity
WTP Water Treatment Plant
WUM Water Utility Maturity
XEN Executive Engineer (also abbreviated EE)
List of Tables Table 1: Identified Gaps in Information Management Practices for Key Business Processes within
CWASA
Table 2: Categorization of Issues to be addressed for Information Management Improvement in CWASA
Table 3: Summary of MIS Plan Objectives and Improvement Strategies
Table 4: Summary of Expected Outputs and Deliverables of the CWASA MIS Plan
Table 5: Required Functionality for Core Modules of Integrated MIS Solution for CWASA
List of Figures Fig. 1: Map of Bangladesh, showing the location of Chittagong City
Fig. 2: Functional Relationship Diagram for CWASA’s core and support processes
Fig. 3: CWASA’s Maturity Scorecard 2015
1 | P a g e
1.0 INTRODUCTION
1.1 Preamble This report describes and details a Management Information Systems (MIS) Plan that has been
formulated for Chittagong Water Supply and Sewerage Authority (CWASA), for implementation over
the period 2016-2018. The MIS Plan is one of the deliverables under the Utility Modernization
Umbrella Consultancy (Ref. CWSISP-S31), which is itself part of the Chittagong Water Supply
Improvement and Sanitation Project (CWSISP).
1.2 Background to the Assignment The Government of the People’s Republic of Bangladesh (GoB) has received financing from the
International Development Association (IDA) toward the cost of Chittagong Water Supply
Improvement & Sanitation Project (CWSISP). The project objective is to increase sustainable access to
safe water and improved sanitation, and to support the establishment of a longer term water supply,
sanitation and drainage capital development and operational management program for the city of
Chittagong. CWSISP entails aspects of infrastructure investments for water production facilities and
the water distribution network, as well as aspects of supporting the comprehensive institutional
development of CWASA.
Package 31 of CWSISP, the Utility Modernization Umbrella Consultancy (code-named CWSISP-S31), is
part of the institutional development program for CWASA under CWSISP. The main objective of
CWSISP-S31 is to develop and improve the capacity of CWASA in the operation and management of
water utility services, and support the modernization of CWASA’s operational structure, systems and
processes. The CWSISP-S31 assignment consists of eleven main components and tasks, with
associated deliverables.
Under Task 5 of the Utility Modernization Umbrella Consultancy, the Consultant is required develop a
Management Information Systems (MIS) Plan for CWASA. The primary objective of the task is to
enhance and streamline CWASA’s capacity for operational data capture & storage, data analysis &
information synthesis, information sharing & management, and application of operational
information for strategic planning and management decision-making on a sustained basis. This report
describes activities that have been undertaken towards implementation of this Task, as well as the
outputs and deliverables obtained as a result.
1.3 Structure of the Report This report is structured as follows. This Chapter introduces and briefly describes the project area
(CWASA), and outlines the objectives and scope of activities under Task 5 of the CWSISP-S31
assignment. Chapter 2 presents the approach and outlines the steps taken in implementing Task 5 of
the assignment. This is followed in Chapter 3 by an audit and assessment of CWASA’s key business
processes. In Chapter 4, the specific information requirements for each business process are
identified, followed by an analysis of gaps in existing information management practices in CWASA.
Chapter 5 describes the formulation of improvement strategies to address the identified information
management gaps, leading to the compilation of a Management Information Systems (MIS) Plan for
CWASA. This is followed in Chapter 6 by a specification of requirements for establishment of priority
2 | P a g e
IT infrastructure. The report concludes in Chapter 7 with recommendations for staff training and
capacity development activities with regard to the improved, modern information management
systems and practices prescribed under this assignment.
1.4 The Chittagong Water Supply and Sewerage Authority (CWASA) Located in the Bay of Bengal 214 km southeast of
the capital, Dhaka (Fig. 1), Chittagong is the second
largest city, the main port city, and the commercial
capital of the People’s Republic of Bangladesh. The
city, including its suburban areas, covers an area
of around 550 km2, and has a population of 3.75
million. It is estimated that the city’s population
will grow to 5.2 million by the year 2021.
The Chittagong Water Supply and Sewerage
Authority (CWASA) was first established in 1963
under the East Pakistan Water Supply and
Sewerage Ordinance 1963, for the purpose of
providing water supply, sewerage and storm
water services to the city of Chittagong. The Water
and Sewerage Authority Act of 1996 repealed the
1963 Ordinance and provided for the
establishment of Water and Sewerage Authorities
to provide water supply, sewerage and drainage
services to cities and towns in Bangladesh, beginning with Dhaka and Chittagong. CWASA is currently
administered by a Board formed under the WASA Act 1996. The first board meeting under this Board
was held in September, 2012.
There is an Annual Performance Agreement (APA) between CWASA and the GoB which was first made
in 2011 and has been revised twice since. The initial APA spells out a number of Key Performance
Indicators and the strategies that must be formulated and pursued to increase CWASA’s capabilities.
More recently, the parent ministry has prepared a new performance agreement which has been called
the Annual Performance Memorandum of Understanding. Monthly performance reports (MIS reports)
are routinely prepared and form the basis for an annual performance report that is submitted to the
GoB.
Although CWASA is legally mandated to provide water supply, sewerage and drainage services, it
currently only provides water services to the residents of Chittagong. There are no piped sewerage
systems in Chittagong, and drainage services are currently provided by the Chittagong City
Corporation (CCC). The current water demand for Chittagong is estimated to be about 500 MLD,
compared to a total installed production capacity of only 210 MLD. This demand is projected to
increase to 1,241 MLD by 2021. As of April 2016, CWASA had a total of 62,613 customer connections
(Source: CWASA MIS Report for April 2016). Of these, 57,337 (or 91.6 %) were on supply and being
billed.
Fig. 1: Map of Bangladesh, showing the
location of Chittagong City.
3 | P a g e
CWASA’s water supply system consists of two water treatment plants i.e. the Mohara Surface WTP
(90 MLD) and the Kalurghat Groundwater Iron Removal Plant and Booster Station (68 MLD). A new
surface water treatment plant, the Karnaphuli WTP, with an initial phase design capacity of 143 MLD,
is scheduled for commissioning by the end of 2016. In addition to the Surface and Ground WTPs,
CWASA operates 95 (ninety-five) deep tube wells installed to augment the water supply to the city.
There are 14 (fourteen) service reservoirs in the system, with a total storage capacity of 46 MLD. The
water transmission and distribution pipelines, amounting to a total length of 687 km, consist of various
pipe materials such as ductile iron, asbestos cement and PVC. A significant part of the CWASA water
distribution network is old and requires rehabilitation.
CWASA, with assistance from the GoB and development partners (the World Bank and the Japanese
International Cooperation Agency (JICA)), is implementing a number of projects to rehabilitate and
expand its water supply systems. The projects which are currently under implementation include: The
Karnaphuli Water Supply Project (KWSP1 & KWSP2), under JICA assistance; The Emergency Water
Supply & Deep Tube Well Rehabilitation Project, funded by the GoB; and the Chittagong Water Supply
Improvement and Sanitation Project (CWSISP), funded by the World Bank. In addition, there is the
ongoing Project for Advancing Non-Revenue Water Reduction Initiative (PANI1 & PANI2), also funded
by JICA.
1.5 The Status of Information Management in CWASA A preliminary appraisal of the status of information management in CWASA was carried out as part of
Task 10 under the CWSISP-S31 assignment, which undertook a review of the utility maturity scorecard
for CWASA to confirm its baseline performance, and to develop mechanisms for periodic review and
monitoring of the outcomes of implementing capacity development measures under the CWSISP
project. Findings indicated, among other things, that data is collected on a regular basis from various
operational units and primarily used by the Design Division to produce monthly quantitative
performance reports (termed MIS Reports), which utilize Key Performance Indicators (KPIs) from the
Annual Performance Agreement signed with GoB as a basis for reporting on CWASA’s performance.
These monthly MIS Reports subsequently form the basis for compilation and submission of annual
reports to GoB in compliance with the APA.
Beyond fulfilling this statutory obligation, however, the practice of data collection and analysis for
purposes of generating information for day-to-day management decision-making is not prevalent
within CWASA. Furthermore, there is no proper system in place for monitoring and evaluating the
performance of individual employees and business units, nor for tracking progress towards
achievement of set performance targets. In fact, there is currently no dedicated unit tasked with the
performance monitoring and evaluation function within CWASA. The Design Division simply performs
the role of collating and compiling data that is used to populate the MIS Reports mentioned above.
A considerable amount of data is generated through the daily activities of CWASA. Water production
data (quantity, quality and power consumption) is recorded daily. Customer meters are read regularly
and used for billing. However, meter readings are still captured using manual meter reading sheets
and the data entered into the billing system manually, and no subsequent analysis is made of the
meter reading field data, beyond its use for purposes of billing. The GIS system run by the Design
Division is supposed to update new connection information such as customer locations and
connection sizes, but this in not being done, and there is no interface between the GIS and the billing
4 | P a g e
system. There is, however, an online billing platform where customers can check their bills and
statements.
Document control, which includes creation, storage, updating, maintenance and retrieval of official
documents, is predominantly manual. As a result, information flow is sporadic and cumbersome,
which hinders ease of access to information by different business units that may need it. The existing
internal and external communication infrastructure, too, is quite limited. There is a Local Area
Network (LAN) in place at the CWASA HQ, but no Wide Area Network (WAN) linking the HQ to other
key facilities and locations. There is no functional, organization-wide email system in use. Most staff
use their personal mobile phones for communicating amongst themselves and externally with
customers, though the organization does not provide airtime for this.
1.6 Objectives and Scope of the Assignment The main objective of Task 5 of the CWSISP-S31 project is to develop a Management Information
Systems (MIS) Plan for CWASA, aimed at improving CWASA’s data capture & storage, information flow,
internal communications, and data analysis and use for management decision-making. The specific
objectives are:
To carry out an audit and assessment of CWASA’s key and critical business processes, with a
view to identifying information management requirements and gaps;
Based on the identified gaps in information management systems and practices, to formulate
improvement strategies, and identify tasks and activities necessary to implement these
strategies;
To develop a framework for an appropriate integrated information management system for
CWASA, and specify requirements for procurement and roll-out of critical components of the
prescribed system.
The expected outputs and deliverables under Task 5 of the CWSISP-S31 assignment include the
following:
A Management Information Systems (MIS) Plan for CWASA
Requests for Proposals (RfPs) for procurement of IT systems as required
On-the-job training reports on good information management practices
This report describes and elaborates activities undertaken to date in implementing Task 5, and in
particular, the formulation of a MIS Plan for CWASA. In executing Task 5 under the CWSISP-S31 project,
the focus has been on providing information management support for identified key and critical
business processes, while ensuring that proposed activities and interventions are harmonized with
relevant tasks, undertakings and deliverables under parallel ongoing projects such as the JICA funded
PANI project. Furthermore, a process-based approach to the assignment has been adopted, as
described in the next Chapter.
5 | P a g e
2.0 APPROACH AND METHODOLOGY
2.1 Sub-Tasks/Steps Undertaken in Executing the Assignment In executing this assignment, a process-based approach was adopted. This approach involved
considering each of CWASA’s key business processes in turn, and appraising these processes with
respect to their information management requirements and current practice. Prior to the appraisal, a
review of project reports and other relevant documents pertaining to CWASA was carried out, as a
way of gaining a clearer context and understanding of the prevailing conditions within the project
area. Information gained from this review was subsequently validated and augmented through
interviews with key informants and visits to key facilities and installations.
In summary, the approach involved the following sub-tasks/steps:
A desk review of background literature
Interviews with key informants
Visits to key facilities
Audit and assessment of CWASA’s key business processes
Identification of data and information requirements pertaining to each business process
A gap analysis of information management practices within each business process
Formulation of information management objectives and improvement strategies to address
the identified gaps
2.2 Review of Background Literature In order to gain a clearer understanding of CWASA’s organizational setup and the status quo pertaining
to CWASA’s information management systems and practices, a desk review of available and relevant
reports and background literature was conducted. During this exercise, the following reports and
documents were reviewed:
1. The Institutional Assessment for CWASA, Final Report, May 2012
2. CWASA Strategic Plan 2012/13-2016/17
3. CWASA Strategic Plan 2015-2020
4. CWASA Annual Performance Agreement (APA) with Government of Bangladesh (GoB)
(English-translated version)
5. CWASA Rolling Five-Year Business Plan (July 2013-June 2018)
6. CWASA Go-Ahead Programme (Rolling Annual Plan, 2015-2016)
7. CWASA MIS Report (April 2016)
8. CWSISP/S-31 SWIFT PIP 90-Day Action Plan, Mar-May 2016
9. CWSISP/S-31 Review of Organogram and Decentralisation Options (Task 1)
10. CWSISP/S-31 Report on SOPs, O&M manuals, and Maintenance Management Programme
for CWASA facilities and equipment (Task 3)
11. CWSISP/S-31 Commercial Management Plan (Task 4)
12. CWSISP/S-31 Staff Training and Capacity Development Report (Task 6)
13. CWSISP/S-31 CWASA Revised Maturity Scorecard 2015 (Task 10)
14. JICA Final Report on Organisational Restructuring (July 2013)
15. JICA PANI Annual Progress Report (June 2015)
16. CWASA Organogram 2016 (English-translated version)
6 | P a g e
2.3 Interviews with Key Informants In parallel with the desk review of relevant background literature, interviews were scheduled and held
with identified key personnel from different business units across CWASA. The purpose of the
interviews was as follows:
To apprise the interviewees of the aim and objectives of the specific task at hand
To obtain first-hand information on the functions, responsibilities and inner workings of the
respective Wing/Circle/Division/Section, including a description of the key processes handled
by the business unit
To identify the information requirements of the business unit, and the available sources for
this information
To identify the data generated by the business unit, and the subsequent use to which this data
is put
To identify the current tools and systems in use (manual or computerised) for handling data
and information within the business unit
To identify and elicit challenges faced and proposals for improvement in information
management tools and practices within the business unit
A detailed list of persons interviewed, and the specific areas of interest discussed, is contained in
Appendix 1.
2.4 Visits to Key Facilities During the project inception mission in August 2015, as well as the subsequent mission in July 2016
that was focused on Task 5, the Consultant was able to visit a number of key installations and witness
first-hand the physical condition and operating environment at these facilities and installations. Places
visited and assessed included the following:
Mohara Surface Water Treatment Plant, located at Mohara
Kalurghat Groundwater Iron Removal Plant and Booster Station, located at Kalurghat
Dampara Water Works, located at Dampara
CWASA Head Office, located at Dampara (various Sections and Divisions, including the
Computerised Billing Section and the ICT Server Room)
MOD2 Zonal Office, located at Dampara
Following the background literature reviews, interviews with key personnel, and field visits to key
facilities, the Consultant engaged in a number of activities as earlier outlined, geared towards
generating the required outputs and deliverables under Task 5. These activities are described in detail
in the Sections that follow.
2.5 Audit and Assessment of CWASA’s Key Business Processes For purposes of this assignment, the primary focus has been on an identified set of business processes
that have been considered to be key and critical for the proper functioning of CWASA, in fulfilling its
mandate of providing water and sanitation services for the City of Chittagong. The key business
processes that have been identified and assessed are:
1. Water Treatment & Production
2. Water Distribution and Network O&M
3. New Connection Implementation
7 | P a g e
4. Meter Reading & Billing
5. Revenue Management
6. Accounting & Financial Management
7. Customer Complaints Handling
8. Human Resource Management
9. Monitoring & Evaluation (Management Reporting)
In addition to these key business processes, the following support processes have been identified and
appraised as well:
• Customer Mapping & GIS
• ICT Support Provision
• Procurement & Transport
• Public Relations Management
• Project Management
In the sub-sections that follow, each of the above key and support business processes is briefly
described. A summary assessment of the different business processes within the context of their
current information management systems and practices is contained in Appendix 2. Identified gaps in
the various processes, as they relate to information management practices within CWASA, are further
explored in Section 2.7.
2.5.1 Water Treatment & Production
Responsibility for water treatment and production in CWASA falls under the Treatment & Production
Circle of the Engineering Wing. Currently, CWASA has two functional water treatment plants (WTPs),
namely the Mohara Water Treatment Plant (Surface Water) and the Kalurghat Iron Removal Plant and
Booster Station (Groundwater). A third water treatment plant, the Karnaphuli Water Treatment Plant,
is nearing completion and is expected to be commissioned later this year. There are also plans to
construct a fourth surface WTP at Modunaghat by the end of 2017. In addition to the WTPs, there are
94 to 96 Deep Tube Wells (DTWs) that have been established to augment supply to the CWASA service
area. Of these, about 54 DTWs supply water into direct distribution, while the remainder channel their
water to the Kalurghat Iron Removal Plant for further treatment.
At Mohara, raw water is abstracted from River Halda and is initially channeled through a desilting
basin. From there, it goes to a rapid mixing chamber, where chlorine and alum are added.
Subsequently, it goes through the traditional treatment processes of clarification, filtration and
disinfection, and the treated water is finally pumped to network storage and subsequent distribution.
At Kalurghat, groundwater from 27 DTWs (those considered to be high in iron levels) goes through a
pair of aerator tanks, and is subsequently channeled through two sedimentation basins and into a
clear water well, from where it is disinfected with chlorine and pumped to network storage and
distribution. Groundwater from the remaining 14 DTWs does not go through aeration and
sedimentation, but instead is directly channeled to the clear water well for subsequent disinfection
and distribution.
Under the Karnaphuli Water Supply Project (KWSP), a SCADA system is being implemented to link the
new Karnaphuli WTP to the storage reservoir located at Nasirabad, and subsequently to District
8 | P a g e
Metered Areas (DMAs) located within the Karnaphuli Supply Area (KSA). The control room for the
SCADA system is planned to be located at Nasirabad. Progress towards implementation of the SCADA
system has been slow to date; however, the Karnaphuli WTP itself has been designed and constructed
in such a way that fully manual operation is possible.
Most data management activities at the WTPs and DTW locations are manual. Daily water production,
water quality and electricity consumption measurements are recorded in manual registers, and the
data is submitted daily using physical copies and by telephone to the Design Division, from where it is
compiled and conveyed (by telephone and SMS) to various key officials, including the Superintendent
Engineer (MODs), The Chief Engineer, The Deputy Managing Director (Engineering) and the Managing
Director. In general, WTP and DTW maintenance is outsourced to annual (“yearly”) contractors.
2.5.2 Water Distribution and Network O&M
Water distribution and network operation & maintenance (O&M) in CWASA are the responsibility of
the Maintenance, Operation and Distribution (MOD) Zones, which together constitute the MOD Circle
under the Engineering Wing. There are four MOD Zones provided for within the CWASA organizational
structure, namely MOD1 (Agrabad), MOD2 (Dampara), MOD3 (Kalurghat) and MOD4 (Jubilee Road).
Of these, MOD1 and MOD2 are currently operational. Key functions handled by the MOD Zones
include: Water production from DTWs; Water distribution to customers; Network maintenance;
Overseeing water bowser sales; Responding to customer complaints. Associated with the MOD Zones
are MOD Revenue Zones, which handle functions such as: Meter reading; Bill distribution; Revenue
collection; Disconnections & reconnections; Meter servicing.
DTW production data, including both flow and electricity meter readings, is recorded daily and a
physical copy of the records is dispatched to the CWASA Head Office (for the attention of EE-Design
Division, SE-MOD, CE, DMD-Eng and MD). Customer complaints are received either by phone or by
physical visits to the zonal office by customers. Complaints are logged in manual registers, and are
subsequently assigned to field staff for follow up. Leakages and other small pipeline maintenance jobs
are handled by CWASA zonal staff, while in general DTW electromechanical equipment maintenance
is outsourced to yearly contractors. There are frequent breakdowns of the DTWs, sometimes caused
by power outages from the Bangladesh Power Development Board (BPDB).
2.5.3 New Connection Implementation
Implementation of new customer connections in CWASA is a function and responsibility of the Sales
Division under the Finance Wing. The process starts with a customer purchasing and submitting an
application form. A site visit to ascertain connection feasibility follows. Once the application is
approved, a demand note is issued to the customer, who pays the required connection fees together
with a security deposit. A work order is issued to field staff. Upon connection implementation, a
completion report is sent to the Revenue Division, which in turn submits customer details to the
Computerized Billing Section for account creation in the Billing System.
The Sales Division is responsible for maintenance of customer service lines for the first six months
following connection, after which their maintenance becomes the responsibility of the respective
MOD Zone. The Sales Division also receives and handles requests for relocation of service lines, as well
as applications for connection enlargement.
9 | P a g e
Currently, the new connection process takes on average 7 to 15 days to complete. Delays in the
process are associated with the numerous approval levels at various stages of the process, and the
manual nature of the process itself. There are also delays between connection implementation and
account opening. Currently, it takes approximately two months from connection to submission of
customer details to the Revenue Division. Current staffing levels, too, are inadequate to meet
CWASA’s monthly new connection targets. On average, only 250 to 300 new connections are made
per month. As a result, the Sales Division is considering outsourcing (sub-contracting) the new
connection process as a way of meeting annual targets.
2.5.4 Meter Reading & Billing
Meter reading in CWASA is a function of the MOD Revenue Zones of the Revenue Circle, under the
Finance Wing. Billing, on the other hand, is carried out by the Computerized Billing Section, under the
ICT Division of the Finance Wing. The two processes are directly related, however, as the former
provides critical input into the latter.
As earlier outlined, new connection details from the Sales Division are used to create customer
accounts in the billing system. Subsequently, meter readings collected by meter inspectors from the
respective MOD Revenue Zones are used to generate monthly bills for water consumed. Physical bills
are printed out and distributed to customers by the meter inspectors. Additionally, SMS notifications
are sent to customers upon billing. Customers can also access their bill information online through the
CWASA website.
Customers make bill payments through participating banks and/or mobile service providers. There are
currently 34 participating banks and three participating mobile service operators. Internet VPN
connectivity is used to upload billing data to mobile operator servers daily. Likewise, bill payment data
is transferred to CWASA’s online billing server from the participating banks daily. However, a common
complaint is that customers sometimes make payments but the banks delay to post these payments,
which results in delayed updates to the CWASA billing server.
The meter reading process is fully manual, and utilizes manual meter reading sheets for field collection
of meter readings. The billing system is not coupled to the meter reading process, and there are no
system defined meter reading walks or cycles. Readings from the field are manually entered into the
billing system. There are no processes in place for auditing of meter readings, nor of generation and
analysis of meter reading anomalies prior to billing.
There is no Help Desk at the CWASA Head Office dedicated to handling of billing-related complaints.
It is common to find customers with billing-related complaints physically moving from desk to desk
within the Computerized Billing Section, seeking to have their complaints resolved. The same thing
applies to customers with other kinds of complaints. In general, there is lack of a centralized unit to
receive and coordinate the handling of customer complaints.
2.5.5 Revenue Management
Revenue management in CWASA is a function and responsibility of the Revenue Circle, under the
Finance Wing. Tasks and duties include: Billing preparation (provision of metering data to the ICT
Division); Bill delivery (distribution of physical bills); Follow up and collection of payment arrears;
Disconnections and reconnections; Meter servicing and replacement of faulty meters; Licensing of
10 | P a g e
Deep Tube Wells; and Customer complaints handling relating to requests for phased (instalment)
payments, connection status, and changes in service and tariff categories.
Whereas the meter installation function is handled by the Sales Division, meter servicing,
disconnection and reconnection are done by the Revenue Division. However, there are reported
staffing shortages for this function. There are supposed to be five disconnection squads in place, but
these are not readily evident on the ground. Meter inspectors, too, are insufficient in number. There
is a tender process currently underway to sub-contract/outsource the activity of bulk replacement of
faulty customer water meters to an external contractor.
2.5.6 Accounts & Finance Management
The accounts and finance management functions in CWASA are the responsibility of the Accounts
Circle, under the Finance Wing. The Accounts Circle consists of four Sections (located on different
floors of the CWASA Head Office building). These are:
• The Accounts Management Section, which handles the following functions:
- Preparation of final accounts
- Management of fixed assets
- Tracking of project works in progress
- Inventory management
• The Revenue Accounts Section, which handles the revenue tracking function, and tracks
revenues from:
- Water sales at customer connections and street hydrants
- New connection fees
- DTW licensing fees
- Water bowser sales
• The Accounts Finance Section, which handles payments to suppliers and service providers
• The Budget Section, which deals with budget preparation, including both estimation and
rectification of budgets.
An accounting software solution named “Dheraaj” (made in India) was previously acquired for use in
CWASA’s accounting function. However, it was never fully implemented. In 2003, another software
solution named Tally (also made in India) was procured, and is currently in use in the Accounts Circle.
Support for the Tally software is provided by a local Tally supplier.
There are some staffing inadequacies reported within the Accounts Circle. Out of the 12 staff of the
Accounts Management Section, only 3 staff are trained to, and work with, Tally. As a result, there is a
significant backlog in data entry into Tally, with entry of data for the 2013-2014 FY only 60% completed
to date. Out of the three staff available for the Revenue Accounts function, two are set to retire. There
is only one staff in the Accounts Circle (the Budget Officer) who handles the budgeting process. This
staff currently also holds an additional charge as Revenue Officer (Accounts).
2.5.7 Customer Complaints Handling
As earlier mentioned, handling of customer complaints of a technical (engineering) nature in CWASA
is primarily the responsibility of the respective MOD Zones, under the MOD Circle of the Engineering
Wing. Complaints are received and logged at Customer Help Desks set up at various locations.
Currently, there are four complaint handling centres: One at Dampara Water Works (MOD2); two at
Jubilee Road (Mod4); and one at Agrabad (Mod1).
11 | P a g e
The process typically starts with a customer either walking in or calling the Zonal office with a
complaint. The most common categories of customer complaints are leakages, dirty water, and no
water. Complaint details are captured in a manual complaints register, following which they are
assigned to field teams for follow-up. A field team typically consists of two staff (a plumbing mistry
and a helper), equipped with appropriate tools and riding on a tempu (a three-wheeled motorized
vehicle). However, there is a reported shortage of trained manpower (mistry) within CWASA.
Supervision of field works is by physical inspection, and is carried out by pipeline supervisors, the Sub-
Assistant Engineer, and Assistant Engineer. Difficult cases and/or delayed jobs are sometimes
escalated to the Executive Engineer. Monthly reports are compiled and submitted to the Chef
Engineer, the SE-MOD, and the DMD (Engineering). Typical report contents include: Total complaints
received; Leakages reported; Leakages repaired; Water shortage complaints received; Water
shortages solved; Total cases attended to.
As indicated above, the complaints handling process in CWASA is manual from start to finish. There
are no IT software solutions deployed to support this function. The Systems Analyst has made
attempts to develop a computerized Complaints Tracking System (CTS); however, so far there seems
to be little interest within the Finance Wing regarding the implementation and adoption of this
system.
2.5.8 Human Resource Management
Human resource management in CWASA is a function of the Secretariat, under the Administration
Wing. Currently, there are 20 grades of staff (excluding the top two grades), divided into four classes,
as follows (numbers as per the CWASA organogram for 2016):
Class 1 Officers (68 No.)
Class 2 Officers (32 No.)
Class 3 Staff (488 No.)
Class 4 Staff (371 No.)
CWASA employs staff on either full-time or temporary basis. Categories of temporary staff consist of
either work charge (monthly basis), master role (daily basis), or project staff (contract basis). A
Personal File (PF) is maintained for each staff.
Staff payroll management is currently handled by the Computerized Billing Section. The section utilizes
a Foxpro-based system (a stand-alone database application which is near-obsolete), for computation
of staff monthly salaries and emoluments and generation of pay slips. All other HR management
processes are manual.
2.5.9 Monitoring & Evaluation (Management Reporting)
Currently, CWASA does not have a dedicated Performance Monitoring & Evaluation (PM&E) unit.
However, the Design Division of the Construction Circle, under the Engineering Wing, is tasked with
the role of collecting and collating performance data from the various business units, and compiling it
into a monthly “MIS Report” which is circulated to key officers within CWASA. The MIS Reports so
generated are subsequently used as a basis for an annual performance report which CWASA submits
to the GoB, as required under the Annual Performance Agreement or MoU signed with the latter.
12 | P a g e
To compile the MIS Report, the Draftsman in the Design Division calls up relevant officers in the various
units/departments and asks them to furnish their respective performance data. The performance data
is submitted in hard-copy format to the Draftsman, who enters and compiles the data using the MIS
Report template developed under the JICA-funded PANI project. The MIS Report is subsequently
reviewed and subjected to the following chain of approvals: EE-Design; SE-Construction; DMD-
Engineering; MD. Thereafter, the approved report is circulated to 38 different personnel/officers
across CWASA.
The MIS Report contains the following categories of performance data: Connection data; Tariff rates;
Billing & collection data; Financial data; Water supply data; Personnel data; and Customer services
data. A sample MIS Report for the month of April 2016 is shown in Appendix 3, while Appendix 4
indicates the specific sources (persons/business units) of data contained in the MIS Report. It is
reported, however, that delayed submission of data by the different business units is common, which
has resulted in a time lag of about two months in report preparation (the latest circulated MIS Report
usually applies to a period about two months prior to the current month). It is also reported that errors
in the submitted data also contribute to delays in getting the report ready.
As earlier indicated, in addition to the key business processes described above, a number of support
processes have been appraised as well, and these are described below.
2.5.10 Customer Mapping & GIS
According to the CWASA organizational structure, the customer mapping and GIS function is supposed
to be performed by the Design Division, under the Construction Circle of the Engineering Wing.
However, the only activity currently taking place in respect this function is being done within the JICA-
funded PANI project, and specifically for customers located within the project area, i.e. the Karnaphuli
Service Area (KSA), which constitutes 60-70% of CWASA’s service area. Under the PANI project,
customer field surveying is carried out by five engineers (project staff), while 2-3 engineers from
CWASA seconded to the PANI project have been trained to handle the GIS function. Training of CWASA
survey staff is reported to be ongoing, and the mainstreaming of the GIS function into CWASA
operations and integration with activities of the Billing and Sales Divisions is planned to take place this
year.
To date, between 50,000 and 60,000 customer connections located within the KSA have been
surveyed and captured in the GIS database. However, this GIS data has not yet been utilized by CWASA
in its day-to-day commercial operations. Another 27,000 or so connections located outside the KSA
are expected to be mapped and updated as well. In addition to customer data, the piped water
distribution network within the project (KSA) area has been mapped. No mapping of the piped water
network outside the KSA has been done, however.
2.5.11 ICT Support Provision
Provision of Information and Communication Technology (ICT) support in CWASA is the responsibility
of the ICT Circle, under the Finance Wing. There are approximately 50-60 desktop PCs deployed across
CWASA, although a significant number of them are reported to be out of service. In addition to the
desktop PCs, the ICT Circle also maintains three servers (online, offline and internal backup) for the
Billing function, as well as a server for the Accounts function. The servers are housed in a server room
located within the Computerized Billing Section in the CWASA Head Office at Dampara. There is a
13 | P a g e
limited Local Area Network (LAN) coverage implemented for the CWASA Head Office, both wired and
wireless.
For internal communication, there is a traditional switch (PBX) intercom system in use at the CWASA
Head Office, which also facilitates external landline communication for key offices. There is no Voice
over Internet Protocol (VoIP) based communication system in use within the CWASA Head Office or
for communication across the various CWASA facilities and locations.
CWASA does not currently maintain an official Social Media presence (Facebook, Twitter, Instagram
or the like). However, CWASA has a website (URL: www.ctg-wasa.org.bd), which is maintained and
updated by the Computerized Billing Section. Furthermore, position-based corporate email addresses
(e.g. [email protected]) have been created on the CWASA domain for 30-40 key
positions; however, these email addresses have not been adopted for effective use by their intended
beneficiaries. Instead, the use of personal email addresses for official communication is prevalent.
2.5.12 Procurement & Transport
According to the CWASA organizational structure, Procurement & Transport are functions supervised
by the Office of the Secretary, under the Administration Wing. However, in practice, the procurement
function in CWASA is not a centralized function, but rather carried out directly by the individual
business units. The only procurement handled by the Administration Wing is for items such as
stationery and related office requirements. As a result, it is currently not easy to monitor and track
data and information relating to procurement activities within CWASA.
2.5.13 Public Relations Management
Public Relations Management in CWASA is a function carried out by a Public Relations Officer (PRO)
who reports to the Secretary, under the Administration Wing. Responsibilities include the following:
Liaising with print and electronic media on behalf of CWASA; Monitoring public views and sentiments
towards CWASA operations as expressed through print and electronic media; Advising CWASA
management on media related issues; Arranging press conferences and dispatching press releases to
print and electronic media; Publishing tender notices and adverts (e.g. supplementaries); Managing
the allocation of telecommunication lines/facilities within CWASA (including ensuring that key staff
are equipped with landlines, and following up resolution of reported faults with telephone lines);
Running school/community awareness campaigns; and Designing and implementing Corporate Social
Responsibility (CSR) initiatives and drives.
In addition to the responsibilities outlined above, the PRO has been nominated as CWASA’s
Information Officer under the “Right to Information Act 2009”. Under this Act, citizens can request for
information on a wide range of issues using a prescribed type of form, following which the Information
Officer must process requests, refer the requests to relevant officers in CWASA for provision of the
required information, and ensure that feedback is provided to the concerned citizens within the
duration prescribed under the law (20 working days).
2.5.14 Project Management
There is no dedicated unit within the CWASA organizational setup responsible for coordinating and
supervising the implementation of internally and externally funded capital projects. Instead, there are
officers from various business units, mainly under the Engineering Wing, who have been delegated
responsibility as Project Directors (PDs) for the various ongoing projects, on top of the day-to-day
14 | P a g e
duties and responsibilities under their mainstream dockets. For example, the DMD (Engineering) is
the PD for the JICA funded PANI Project, while the Chief Engineer is the PD for the Karnaphuli Water
Supply Project (KWSP), also under JICA funding.
2.6 Identification of Information Requirements for Key Business Processes In this activity, the critical types of data and information that must be managed for the proper
execution of the key business processes described above were identified and compiled. For each
business process, the data generated at various stages of the process was determined. The source and
repository of each dataset was identified, and the information outputs at each stage, and in particular
those outputs that constitute the performance measures that are currently tracked in the CWASA
monthly MIS Report, were specified. Appendix 5 summarizes the findings in this regard.
From this compilation, it is evident that CWASA’s information management requirements are quite
considerable. A potentially huge amount of data is routinely generated as part of the day-to-day
operations of the different business units within the organization. Much of this data, if well managed,
can act as a source of valuable information for performance analysis and operational decision-making
in the short term, as well as for more long-term strategic planning and organizational policy-making.
Unfortunately, this vast resource is not being fully harnessed in CWASA at present, owing to existing
gaps in information management practices within the Authority, as discussed in the Section that
follows.
2.7 Information Management Gap Analysis In this step, a number of gaps in terms of information management requirements for the proper
and/or effective execution of CWASA’s key business processes were identified and highlighted. These
gaps are outlined in Table 1 for each business process.
Table 1: Identified Gaps in Information Management Practices for Key Business Processes within
CWASA
Key Business Process
Identified Gaps relating to Information Management
Water Treatment & Production
There is hardly any computerisation of record-keeping in the water production process. Most records within the Surface and Ground WTPs (Mohara and Kalurghat respectively) are maintained in manual registers.
Whereas under the KWSP project there is a SCADA system designed to link the new Karnaphuli WTP with DMAs in the distribution network, this system has not yet been fully implemented and operationalized.
Water Distribution and Network O&M
Record keeping for complaints handling involves the use of manual complaints registers which, in the majority of cases, are not even used for their intended purposes.
There is no mechanism in place for tracking progress of complaints handling, for escalating delayed or unfinished tasks, and for providing feedback to customers upon job completion.
There are no explicit performance targets for MOD engineering operations, and neither is there a mechanism for tracking progress towards target achievement.
There is no effective system in place to monitor the compliance of DTW maintenance yearly contractors to expected performance standards, and to document maintenance activities of these contractors.
15 | P a g e
Key Business Process
Identified Gaps relating to Information Management
New Connection Implementation
Lack of a computerised information management system to handle the new connection process. The process is largely manual, with almost no ICT applied.
Lack of automated reporting on new connections. The Executive Engineer Sales produces a monthly but manually prepared report. There are no other operational and management reports available.
Lack of a new connection payments bank interface for confirming genuine payments made by customers.
JICA staff under the PANI project have made efforts to translate and digitise the New Connection form for online (digital) use; however, the challenge with this is that there are no computers in the Sales Division to facilitate and mainstream the use of the online application form.
Meter Reading & Billing
The Computerised Billing System in its current form does not provide support for key commercial processes such as new connections, meter reading, customer inquiry, customer account maintenance, and service changes.
The billing system is only a repository of meter reading history, and is not optimized for meter reading service efficiency. Meters are not linked to any Book, Walk, Sequences and Reading Cycles definable and updated from the billing system. As a result, meter readers utilise manual meter reading books, which is an inefficient meter reading approach.
Meter reading practices are manual and outdated. No meter reading technologies such as hand-held meter reading devices, Automated Meter Reading (AMR), or On-Spot Field Billing have been adopted. The meter reading process is entirely manual and thus prone to error.
There is no anomalies generation and handling process in place to address meter reading anomalies prior to billing.
Lack of meter reading analysis for improved reading accuracy. No meter reading audits are carried out, and neither are meter reading exceptions produced and reviewed to guarantee a higher meter reading accuracy.
There is lack of a meters inventory/database, disaggregated for meters in the store, meters in the field, and meters returned from the field. This limits the capability to validate meters and track their location, status and age.
Revenue Management
Account maintenance across the commercial cycle is manual and tedious right from meter reading management, journals & adjustment to service maintenance. Manual files are maintained for each customer. The Revenue Division office is cluttered with piles and piles of files as a result.
There is insufficient IT equipment to support the revenue management function. The Computerised Billing System itself in its current form is not robust enough to support the revenue management function.
With the Computerised Billing System, it is not possible to view revenue collection information from the WASA bank based at the CWASA HQ (Janatha Bank), as well as the mobile service providers, in real time on a daily basis.
No reports/data are generated by the Revenue Division regarding revenue collection; instead, reporting on revenue is done by the ICT Division.
There is limited use of debt management tools such as Debt Age reports, Arrears Payment Agreements, etc.
Accounting & Financial Management
There is an insufficient number of computers in the Revenue Division to handle the Accounting and Financial Management function.
The Tally accounting software in use requires customisation in order for it to suit the accounting requirements of CWASA. There is no interface with the Sales,
16 | P a g e
Key Business Process
Identified Gaps relating to Information Management
Billing and Revenue functions. There is no budgeting functionality, no stores/inventory management functionality, and no payroll management functionality.
Out of the 12 staff of the Accounts Management section, only 3 staff have access to and work with Tally.
There is a backlog of data entry into Tally, with entry of data for the 2013-2014 FY only 60% complete to date.
Customer Complaints Handling
There is no Call Centre, nor is there a toll-free line for customers to use in reporting issues and lodging complaints. Customers often have to physically visit the CWASA offices in order to lodge their complaints.
There is no electronic system in place for logging customer complaints. There are manual complaints registers to be found at the Customer Help Desks located at the various MOD offices and at the CWASA HQ. However, in many cases these registers are not used for their intended purpose.
There is no mechanism in place for tracking progress of resolution of reported cases. There are no escalation mechanisms in the event that tasks remain unattended to or unresolved. As a result, delays in customer complaints handling are commonplace.
There is no dedicated customer help desk for billing related complaints handling. Often, customers with billing-related issues/complaints come right up to the individual officers in the Computerised Billing Section seeking solutions to their complaints, thereby causing a lot of disruption/distraction to the billing staff.
Likewise, for other types and categories of complaints, customers often have to physically move from desk to desk in order to have their issues resolved.
Human Resource Management
All HR management processes are manual. There is no computerised HRM system to document and manage staff related records, including staff scheduling and shift management.
There is no proper system in place for monitoring and evaluating the performance of individual employees.
Monitoring & Evaluation (Management Reporting)
Lack of a dedicated Monitoring & Evaluation Unit within the corporate structure. This function (in its present form) is currently being carried out by the Design Division of the Construction Circle, under the Engineering Wing.
Lack of an ICT Strategy for upscaling adoption and utilization of ICT for improving performance monitoring and management reporting.
Delayed data submission, which leads to a time lag of about two months in report preparation (the latest circulated MIS report usually applies to a period about two months prior).
Frequently, there are errors in submitted data resulting from the manual way in which this data is compiled and maintained.
The MIS Report lacks information on stock/inventory levels, as well as on CWASA support processes such as Customer mapping & GIS, ICT support services, Procurement, Transport, Public relations, Training & staff capacity development, and Project management.
Customer Mapping & GIS
The CWASA water supply service area and customer base is yet to be mapped and fully digitized into an effective GIS. This limits comprehensive validation of new connections and existence of a structured new connection database.
There is a disconnect between GIS under the JICA funded PANI project and CWASA’s Sales Division. The implementation and institutionalization of the GIS system remains at the PANI project level, yet CWASA could have taken
17 | P a g e
Key Business Process
Identified Gaps relating to Information Management
advantage of the significant data cleaning and mapping measures undertaken to date to improve efficiency of its commercial operations.
Under the PANI project, there is scope for upscaling the survey and mapping of customer connections to areas outside of the KSA project area. However, this has not yet been done.
CWASA mainstream staff have not been trained in customer surveying and mapping.
The available computer facilities and equipment are insufficient. For example, there are no computers within the Sales Division to handle the GIS/mapping function. Likewise, the available licenses for the GIS software in use are limited (e.g. there are only four ArcGIS desktop licenses, and no ArcGIS server license).
ICT Support Provision
Computer Hardware & Networking Infrastructure:
The existing Local Area Network (LAN) within the CWASA HQ is implemented in a haphazard, disorganised manner, and is not easy to maintain and secure.
There is no Wide Area Network (WAN) connectivity to other CWASA facilities/installations outside the HQ.
There is no IT infrastructure performance monitoring software in place.
The existing system security measures are insufficient. There are insufficient backup servers and insufficient power backup (UPS) systems. Whereas a server firewall software solution was procured, it was not properly configured and implemented by the software vendor.
The existing server room housing the CWASA online billing server and other servers is poorly constructed, insecure, and not well ventilated.
There is no off-shore Disaster Recovery (DR) site.
There are no Service Level Agreements (SLAs) in place with computer hardware/software suppliers for routine and preventive system maintenance.
IT Support Services:
There is no dedicated IT support team in place in CWASA. In general, unless necessary structural changes are implemented, CWASA may not ready for the business expansion anticipated after full completion and commissioning of the KWSP. The current organisational setup requires review to manage and support an ICT-driven organization.
There are low levels of computer literacy amongst CWASA staff, with only approximately 20% of staff reported to have basic computer knowledge. There is a general apathy towards the use of ICT systems. Most staff think it is personnel from the ICT Division alone who should use ICT systems, and not they themselves within their respective departments/units.
Procurement & Transport
The procurement function is currently directly performed by the various units, and is not a centralised function. This makes it difficult to monitor and control procurement activities within the Authority.
Public Relations Internal and External Communication:
There is a fixed phone intercom system in place at the CWASA HQ, with maintenance support provided by MOD2. However, this system is not a VoIP based system, and does not extend/connect to fixed phones in other CWASA offices/facilities outside of the HQ.
Communication with field staff is by use of personal mobile phones. There are no company owned mobile phones or lines in use for field operations. Instead,
18 | P a g e
Key Business Process
Identified Gaps relating to Information Management
field staff end up having to use their personal mobile phones to communicate with office staff and with customers, because there are no office mobile lines.
Most office processes are still manual. The culture of electronic communication is not yet prevalent among staff. Computers themselves are fairly available, but their adoption and use for internal communication is quite low.
The corporate email addresses that were established on the CWASA domain have not been widely adopted for use by the officers for whom they were set up.
Use of Social Media:
Social Media has not been adopted within CWASA as a practical medium for internal or external communication. In general, use of Social Media is regarded as being a preserve of teenagers.
In general, access and use of the internet is not widespread within CWASA.
Project Management
There is no centralised Project Monitoring Unit (PMU) coordinating the activities of various ongoing projects within CWASA. As such, it is difficult to track and report on progress and outputs of the various project activities.
Documentation of engineering works (including as-built drawings, resources applied, equipment used, money spent etc.) is not readily accessible.
2.8 Formulation of Information Management Improvement Strategies The prevailing information management gaps identified in the previous Section may be clustered into
five problem categories, namely:
IT infrastructure and equipment challenges
Software and information systems shortcomings
Human resource capacity issues and staffing gaps
Performance monitoring and management reporting gaps
Technology transfer gaps
Table 2 outlines the issues to be addressed within each problem category.
Table 2: Categorization of Issues to be addressed for Information Management Improvement in
CWASA
PROBLEM CATEGORY ISSUES TO BE ADDRESSED
1. IT infrastructure and
equipment challenges
Insufficient computer hardware
Insufficient networking infrastructure
Insufficient system security measures
Insufficient IT support systems and practices
Insufficient internal and external communication systems
2. Software and information
systems shortcomings
Lack of systems to computerize and optimize key
processes
Gaps in existing computerized systems
19 | P a g e
PROBLEM CATEGORY ISSUES TO BE ADDRESSED
3. Human resource capacity
issues and staffing gaps
Gaps in the organizational structure
Insufficiencies in staffing levels and capacities
Lack of an information systems culture amongst staff
4. Performance monitoring
and management reporting
gaps
Insufficient performance monitoring framework
Insufficient data analysis and reporting practices
Process-related gaps
Gaps in information sharing and information flow
5. Technology transfer gaps Gaps in mainstreaming of project outputs
Staff training, knowledge transfer and capacity building
gaps
Based on the identified categories of problem issues, five information management improvement
objectives have been identified. The five objectives are:
1. Ensure that CWASA’s IT infrastructure is sufficient to meet the Authority’s information
management requirements in the immediate and long term, particularly taking into
consideration the anticipated growth in business subsequent to commissioning of KWSP1 and
KWSP2.
2. Ensure that adequate, appropriate and effective information management systems and
software solutions are in place to support CWASA’s core business processes.
3. Ensure that CWASA’s organizational structure, staffing levels, staff culture, attitude, mindset
and capabilities are adequate to meet CWASA’s information management requirements.
4. Improve the efficiency and effectiveness of CWASA’s performance monitoring and
management reporting.
5. Ensure that relevant outputs from various ongoing projects are harmonized and
mainstreamed, and that technology transfer and staff capacity development is fully achieved
as planned.
For each of these improvement objectives, a set of improvement strategies have been formulated, as
outlined in Table 3.
Table 3: Summary of MIS Plan Objectives and Improvement Strategies
OBJECTIVE IMPROVEMENT STRATEGIES
1.0 Ensure that CWASA’s IT infrastructure is sufficient to meet the Authority’s information management requirements in the immediate and long term, particularly taking into consideration the anticipated growth in business subsequent to commissioning of KWSP1 and KWSP2.
1.1 Equip CWASA’s business units with sufficient computer hardware equipment and core basic software applications.
1.2 Establish an adequate IT network infrastructure backbone for CWASA.
1.3 Implement robust IT systems security measures. 1.4 Institute appropriate IT support mechanisms and
practices. 1.5 Improve internal and external communication
systems.
20 | P a g e
OBJECTIVE IMPROVEMENT STRATEGIES
2.0 Ensure that adequate, appropriate and effective information management systems and software solutions are in place to support CWASA’s core business processes.
2.1 Modify, improve and upgrade CWASA’s existing computerised information management systems and solutions.
2.2 Introduce new computerized information management systems and solutions.
2.3 Utilize improved, modern tools and technologies for field data collection and management.
3.0 Ensure that CWASA’s organizational structure, staffing levels, staff culture, attitude, mindset and capabilities are adequate to meet CWASA’s information management requirements.
3.1 Make necessary modifications to the organizational structure to cater for the information management and performance monitoring requirements of CWASA.
3.2 Re-orient staff culture and mindsets towards adoption of information systems and computerized information management practices.
3.3 Undertake Business Process Re-engineering for critical business processes, with a view to phasing out manual methods of data management to the extent possible and replacing them with more streamlined, computerized methods.
4.0 Improve efficiency and effectiveness of CWASA’s performance monitoring and management reporting.
4.1 Review and revise CWASA’s performance monitoring framework to ensure that it is ICT enabled, process oriented, target driven, and that it encompasses all key and support business processes.
4.2 Improve CWASA’s data analysis and report generation practices.
4.3 Streamline and address gaps in key business processes hindering effective information management and efficient process flows.
4.4 Improve and streamline information sharing and information flow.
5.0 Ensure that relevant outputs from various ongoing projects are harmonized and mainstreamed, and that technology transfer and staff capacity development is fully achieved as planned.
5.1 Follow up the effective completion, operationalization and mainstreaming of undertakings under the JICA PANI project that impact on information management practices in CWASA.
5.2 Follow up the training and knowledge transfer to mainstream CWASA staff of specialised skills and competencies in information management practices from project partners/consultants/counterparts.
These strategies, and the specific tasks and activities necessary to implement them, together
constitute the Management Information Systems (MIS) Plan for CWASA, which is the primary output
of this assignment. The MIS Plan is presented in detail in the Chapter that follows.
21 | P a g e
3.0 THE CWASA MANAGEMENT INFORMATION SYSTEMS (MIS) PLAN
(2016-2018) Based on the information management improvement objectives derived in the previous Chapter, a
Management Information Systems (MIS) Plan for CWASA has been formulated, to be implemented
over the period 2016-2018. The CWASA MIS Plan (2016-2018) prescribes a set of tasks and activities
necessary to implement improvement strategies that have been formulated to address the identified
problem issues. It allocates primary responsibility for each task or activity to specific
Wing/Circle/Division Heads within CWASA, and also sets a time frame within which each task or
activity should be implemented. An estimate of the cost of implementing each activity is also provided,
where applicable. Furthermore, expected outputs and deliverables for each set of strategies, tasks
and activities are specified.
Table 4 summarizes the expected outputs/deliverables of the MIS Plan corresponding to each
objective. The detailed MIS Plan is contained in Appendix 6, while Appendix 7 outlines the assumptions
made in costing the activities within the MIS Plan.
Table 4: Summary of Expected Outputs and Deliverables of the CWASA MIS Plan
MIS PLAN OUTPUTS/DELIVERABLES CORRESPONDING TO EACH IMPROVEMENT OBJECTIVE
Objective 1: Ensure that CWASA’s IT infrastructure is sufficient to meet the Authority’s information management requirements in the immediate and long term, particularly taking into consideration the anticipated growth in business subsequent to commissioning of KWSP1 and KWSP2.
Outputs/Deliverables:
A comprehensive inventory of IT equipment.
New computer hardware (Servers, PCs, printers & accessories) procured as required.
Basic and specialized software applications (both desktop and server software) and
licenses procured as required.
Improved and expanded LAN at each core facility/location.
Corporate-wide WAN linking core facilities and locations.
A network infrastructure performance monitoring solution.
An upgraded server room at CWASA HQ.
Backup servers for mission-critical software systems.
An effective Uninterruptible Power Supply (UPS) solution.
An off-site Disaster Recovery (DR) site.
Effective firewall and user access control solutions.
Service-Level Agreements (SLAs) with hardware and software vendors.
A computerized corporate-wide IT Support Requests handling system.
A functional Call Centre, preferably served by toll-free line(s).
A VoIP or IP PBX internal telephony solution.
Staff equipped with company mobile phone lines on a Closed User Group (CUG).
A functional corporate-wide email system.
Social Media (SM) platforms to enhance both internal and external information sharing.
Functional internet access for core offices.
Objective 2: Ensure that adequate, appropriate and effective information management systems and software solutions are in place to support CWASA’s core business processes.
22 | P a g e
MIS PLAN OUTPUTS/DELIVERABLES CORRESPONDING TO EACH IMPROVEMENT OBJECTIVE
Outputs/Deliverables:
The existing Computerized Billing System remodelled and modified to provide functionality for: - New connection processing & implementation - Meter reading management - Revenue & debt management - Customer inquiry - Report generation - Meter exchanges - Tariff & service changes
The interface with partnering banks and mobile service providers modified to cater for: - Real time data synchronization and access - SMS confirmations to customers upon payment - Handling of non-consumption related payments
The existing Tally accounting software modified and customized to cater for: - Budgeting - Procurement, logistics, stores and inventory management - Payroll management - Interface with sales, billing and revenue management functions
A computerized Human Resource Management Information System (HRMIS) procured and implemented.
A computerized Complaints Handling System (CHS) developed and implemented.
A computerized Meter Management System (MMS) procured and implemented.
An integrated data management system for water production & treatment and plant maintenance developed and implemented.
A computerized Asset Information Management (AIM) solution procured and implemented.
Improved, modern field data collection tools and technologies procured and deployed: - Hand-held meter reading devices - Automatic Meter Reading (AMR) enabled meters - Pre-paid meters - Data loggers, pipe locators, portable pressure gauges and leak detection equipment
Objective 3: Ensure that CWASA’s organizational structure, staffing levels, staff culture, attitude, mindset and capabilities are adequate to meet CWASA’s information management requirements.
Outputs/Deliverables:
CWASA’s organization structure modified to create the following units: - A Performance, Monitoring & Evaluation (PM&E) unit under the MD’s office; - A Procurement Monitoring Unit (PMU) under the Administration wing; - An Infrastructure Asset Management (IAM) unit under the Engineering wing; - A Planning & Infrastructure Development (PID) unit under the Engineering wing.
ICT Circle staffing reviewed and strengthened to include capacity for IT support service provision.
Computer appreciation, sensitization and awareness campaigns implemented.
Staff trained in basic and specialized computer software applications.
Key business processes re-engineered to phase out manual methods of data management and introduce streamlined computerized methods.
Objective 4: Improve efficiency and effectiveness of CWASA’s performance monitoring and management reporting.
Outputs/Deliverables:
23 | P a g e
MIS PLAN OUTPUTS/DELIVERABLES CORRESPONDING TO EACH IMPROVEMENT OBJECTIVE
A strategic plan document detailing practical measures for upscaling the application of ICT in CWASA’s performance monitoring and management reporting.
A matrix of Key Performance Indicators (KPIs), with SMART (specific, measurable, achievable, realistic and time-bound) performance targets specified for all key and support business processes.
A robust framework for performance tracking.
System-generated reports developed and implemented for key business processes.
Meter reading audits instituted and operationalized.
Meter reading/billing anomalies handling instituted and operationalized.
Complaints tracking and escalation system instituted and operationalized.
A dedicated help desk for billing related complaints established.
Re-engineered, modernized meter reading practices instituted and operationalized.
Performance data verification and validation mechanisms instituted and operationalized.
Capital works project information sharing mechanisms instituted and operationalized.
Objective 5: Ensure that relevant outputs from various ongoing projects are harmonized and mainstreamed, and that technology transfer and staff capacity development is fully achieved as planned.
Outputs/Deliverables:
The SCADA system for the new Karnaphuli WTP fully operationalized.
All CWASA customer connections mapped and updated in GIS database.
Customer GIS data mainstreamed to CWASA’s technical and commercial operational business units.
CWASA staff trained in GIS data management.
24 | P a g e
4.0 FRAMEWORK FOR AN INTEGRATED MANAGEMENT INFORMATION
SYSTEM In this Chapter, an integrated Management Information Systems (MIS) framework for CWASA is
proposed. The framework outlines the relationships between CWASA’s functional units and core
business processes, and in a sense serves as a blueprint for future implementation of a fully-fledged
Enterprise Resource Planning (ERP) solution for CWASA. A simple definition of an ERP system is that
ERP systems aid the flow of internal business processes and allow for communication between a
business’s departments and its internal functions and data.
4.1 Functional Relationships between Processes An ERP solution for CWASA should, in principle, provide support for all of CWASA’s core business
processes as identified. In addition, support processes and functions must be recognised as playing an
integral role in the smooth functioning of the core business processes. In this respect, CWASA’s core
processes may be summarized as: Produce water; Distribute water; Bill customers; Collect payments.
In support of these core processes, CWASA needs to grow its business through expanding its customer
base and water supply infrastructure, and keep track of where these customers and infrastructure
assets are located. All of this should be done in an efficient, cost-effective manner, utilizing optimal
staffing inputs and supported by the necessary logistics (finances, equipment, supplies and services),
to the satisfaction of internal (management) and external (customers) stakeholders.
Thus, for purposes of proposing an integrated MIS framework for CWASA, the functions played by
CWASA’s business processes have been clustered as follows:
1. Core Functions
Water Treatment & Production
Water Distribution and Network O&M
Meter Reading & Billing
Revenue Management
2. Business Growth Functions
New Connection Implementation
Customer Mapping & GIS
Project Management
3. Efficiency and Effectiveness Functions
Accounting & Financial Management
Human Resource Management
Procurement & Transport
ICT Support Provision
4. Stakeholder Management Functions
Customer Complaints Handling
Public Relations Management
5. Supervisory Functions
Monitoring & Evaluation (Management Reporting)
The inter-relationships between the above functions and processes are illustrated in Fig. 2.
25 | P a g e
Fig. 2: Functional Relationship Diagram for CWASA’s core and support processes
4.2 Required Functionality for Integrated MIS Core Modules From Fig. 2, it is clear that if one were to implement a modular integrated MIS (or ERP) solution for
CWASA, with a core module supporting each of the four identified core processes, then the
functionality that the respective core modules of the MIS would have to support would be as shown
in Table 5.
Table 5: Required Functionality for Core Modules of Integrated MIS Solution for CWASA
Core Process Required Functionality for Corresponding MIS Core Module
Water Production Track water production infrastructure development
Document (map) production infrastructure
Maintain production infrastructure
Allocate financial resources
26 | P a g e
Core Process Required Functionality for Corresponding MIS Core Module
Procure necessary inputs
Control and manage expenditure
Manage water production staff deployment
Manage water production ICT support requests
Monitor and track water production performance
Water Distribution Track water distribution infrastructure development
Handle new connections
Document (map) water distribution infrastructure & customer locations
Maintain water distribution infrastructure
Handle water distribution related complaints
Allocate financial resources
Procure necessary inputs/supplies/services
Control and manage expenditure
Manage water distribution staff deployment
Manage water distribution ICT support requests
Promote and market services to external stakeholders
Monitor and track water distribution performance
Billing Handle new connections
Document (reference) customer locations
Handle billing related complaints
Allocate financial resources
Control and manage expenditure
Track revenue (payments)
Manage billing staff deployment
Manage billing ICT support requests
Promote and market services to external stakeholders
Monitor and track billing performance
Revenue Collection Document (map) and analyze customer locations
Allocate financial resources
Control and manage expenditure
Manage collected revenue
Manage revenue collection staff deployment
Manage revenue collection ICT support requests
Promote and market services to external stakeholders
Monitor and track revenue collection performance
Note, from Table 5 above, that a number of functionalities (shown in italics) are common across
different modules. The implication of this is that, for any proposed integrated MIS (or ERP) solution,
these common functionalities would be catered for by the use of shared (common) databases and/or
modules accessible by the different core modules.
27 | P a g e
5.0 REQUIREMENTS FOR ESTABLISHMENT OF PRIORITY IT
INFRASTRUCTURE In this report, having a basic IT infrastructure backbone has been identified as critical for CWASA to
achieve optimal information management and streamlined internal communication and information
sharing. The specific requirements considered cover the following aspects of IT infrastructure:
Network infrastructure
Server hardware
Hardware and data security
Email systems
Recommendations concerning each of these are briefly outlined in the Sections that follow. It should
be noted that a more detailed assessment of requirements and development of specifications would
of necessity be carried out as part of Tasks 1.1 to 1.5 of the CWASA MIS Plan implementation.
5.1 Network Infrastructure It is recommended that a server room (minimum Tier 2) be established on the ground floor of the
CWASA HQ at Dampara, with a fiber link running in serial to all the floors (from gf to 1st, from 1st to
2nd, 2nd to 3rd etc.). At each floor, a fiber termination panel and a Cisco Catalyst switch or a D-Link
gigabit switch with fiber patch panels will be installed.
Depending on the number of users on each floor, additional Ethernet switches (and therefore a switch
rack) will be installed on each floor, with Cat6 cables running from the switch rack located on the
respective floor to the wall jacks in the offices on that floor. Needless to say, the switch racks will have
to be sited in such a way that their security is guaranteed, considering that they will be located outside
of the server room.
At the off-shore sites (the Zonal offices as well as the Water Treatment Plants), considering that most
networking services including DHCP, AD, DNS and file storage will be implemented and managed at
the Head Office, there will only be need for a Cyberoam installation. The model used will depend on
the number of users at the site, taking into consideration future up-scaling. In addition, there will be
a Cisco Catalyst switch or two installed at each site, again depending on the number of users. Multi-
Protocol Label Switching (MPLS) will be used to connect the different sites to the Head Office, using
an ISP fiber link as the backhaul.
Wireless access points will be established both at the Head Office and at the off-shore sites as
required. For these, the Unifi UAP-AC outdoor enterprise Wi-Fi system is recommended. Alternatively,
as a cheaper alternative, the Unifi APs could be replaced with Linksys, albeit at the cost of efficiency
and centralized management. Likewise, the Cyberoams may be replaced with cheaper MPL enabled
routers, and as earlier mentioned, the Cisco switches may be replaced with cheaper D-Link switches.
5.2 Server Hardware All servers will be located in the server room at the CWASA Head Office at Dampara. The servers will
include domain controllers, file servers, email servers, online billing servers, and any other dedicated
servers CWASA may wish to acquire in the future. The servers will be rack-mounted in the server room,
with a full-time HVAC system installed.
28 | P a g e
For the Domain Controllers (at least 2 No.), the following specifications are proposed: Dell PowerEdge
T430 tower servers (64 bit), 4 GB RAM, 1TB HDD, Intel Xeon E5-2603 V4. Additional hard disks may be
procured, depending on the need. For the server OS, Windows Server 2012 R2 (Enterprise) is
recommended. There is no need for extra hardware for the DHCP/DNS functions. For file storage, one
of the DCs can be used as a file server. Further file storage can be provided using a Synology DiskStation
Network Attached Storage (NAS) solution, which can also be used for on-site backup (about 12TB) set
up as NAS. As an additional security measure, DiskStation NAS can be set up at selected Zonal offices
to provide secondary backup. There will be a need to procure a vendor to establish offsite backup as
per Task 1.3.4 of the CWASA MIS Plan.
5.3 Email Solution For the email server, a Dell OptiPlex core i7 or core i5 desktop computer with 8 GB RAM and 1 TB HDD,
running on Ubuntu 16 server (open source), and with Zimbra Collaboration Server (the community
edition is free, but there is also a paid option), is recommended. This is a cheaper option to Microsoft
Exchange. There will be need to setup email archiving, to purchase SSL certificates, and to acquire an
antivirus and anti-spam solution for the mail server (e.g. Bitdefender).
5.4 Hardware and Data Security It is recommended that both biometric access control and CCTV monitoring be implemented for the
server room at the CWASA Head Office. Furthermore, a Cisco ASA firewall will be implemented.
Endpoint antivirus solutions such as Kaspersky, Bitdefender or Sophos will offer protection for client
computers.
In summary, the following minimum IT infrastructure is recommended for the Head Office and the
offshore sites (i.e., Zonal Offices and Water Treatment Plants).
NETWORK SETUP:
Head Office:
• 2-Tier (minimum) server room, equipped with HVAC solution and backup power
• Cisco ASA firewall
• Cyberoam (CR500iNG XP)
• Cisco catalyst switches 2900 series or later
• Cat6 cabling and wall jacks
• Wireless access points (Unifi UAP-AC outdoor)
• Racks
Branch Offices (for each)
• Cyberoam (CR100iNG)
• Cisco catalyst switches 2900 series or later
• Cat6 cabling and wall jacks
• Wireless access points (Unifi UAP-AC outdoor)
• Rack
29 | P a g e
Water Treatment Plants (for each)
• Cyberoam (CR50iNG)
• Cisco catalyst switches 2900 series or later
• Cat6 cabling and wall jacks
• Wireless access points (Unifi UAP-AC outdoor)
• Rack
SERVERS:
Domain Controllers:
• Dell PowerEdge T430 tower servers (64 bit), 4 GB RAM, 1TB HDD, Intel Xeon E5-2603 V4 (2
pieces)
• Additional hard disks, depending on the need
• Windows Server 2012 R2 (Enterprise) licenses
Email:
• Dell OptiPlex core i7 or core i5 desktop computer, 8 GB RAM and 1 TB HDD
• Ubuntu 16 server (open source)
• Zimbra collaboration server
• Need to setup email archiving
• Need to purchase SSL certificates
• Antivirus and anti-spam solution (e.g. Bitdefender security for mail servers)
DNS/DHCP:
• No need for extra hardware
File Storage:
• One of the Domain Controllers can be used as a file server
• Synology DiskStation can be used for further file storage and on-site backup (about 12TB)
set up as NAS
• Need to procure a vendor for offsite backup solution
30 | P a g e
6.0 STAFF CAPACITY DEVELOPMENT AND ON-THE-JOB TRAINING
REQUIREMENTS Under Task 6 of the CWSISP-S31 package (Development and implementation of a staff training and
capacity development programme), a comprehensive assessment of staff competencies (C), training
needs (TN) and capacity development needs (CDN) for CWASA staff across the board has been carried
out. The analysis considered planned training activities under Tasks 3, 4, 5, 7, 8, 9 and 11 of the Utility
Modernization Umbrella consultancy in order to promote synergies, minimize duplication and enable
an integrated approach to the resulting Training and Capacity Development (TCD) interventions.
Specifically for Task 5, which is the subject of this report, the staff training and capacity development
programme targets on-the-job-training for all staff on good information management systems and
practices. It should be noted that from findings of the Revised CWASA Maturity Scorecard and Baseline
Assessment (Task 10) undertaken at the end of 2015, CWASA was graded at a level of 1.5 (i.e. between
initial and basic levels) on the Water Utility Maturity (WUM) model with respect to the Information
and Knowledge Management indicator, an attribute used to gauge utility maturity under the Tools
dimension of the WUM framework. On the related indicators of Monitoring & Evaluation and Internal
& External Communication, CWASA was graded at a level of 1 and 1.5 respectively (Fig. 3).
Fig. 3: CWASA’s Maturity Scorecard 2015. (Maturity levels: 1 = Initial; 2 = Basic; 3 = Proactive; 4 =
Flexible; 5 = Progressive)
31 | P a g e
According to the staff training and capacity development needs assessment carried out under Task 6,
the following gaps and areas for capacity improvement were identified relating to the three indicators
above (Information & Knowledge Management, Monitoring & Evaluation, and Internal & External
Communication):
Improved competencies and motivation for information management and knowledge sharing
An integrated and accessible system for knowledge sharing
A policy for knowledge and information sharing
A well-structured monitoring and evaluation system
An effective link between monitoring data and management decision-making
Increased communication skills of management staff
Improved staff - stakeholder interaction
An external communication policy
A procedure for internal communication, including documentation of meeting results
Based on the identified capacity gaps and a detailed appraisal of staff categories/classes requiring
training in the respective functional areas, and given the low level at which CWASA has been scored
on the WUM model with regard to information management, training in basic software applications
has been identified as an immediate priority training area, targeting selected staff spanning all
operational areas of CWASA.
As a starting point, it is planned that, in the next phase of implementation of Task 5 of this assignment,
a training programme shall be rolled out addressing the identified priority capacity gaps in information
management. The main mode of delivery of this plan shall be On-the-Job Training (OJT), whereby
instruction sessions shall be complemented by supervised practice assignments, one-on-one hand-
holding, coaching, as well as practice drills.
32 | P a g e
APPENDICES
33 | P a g e
Appendix 1: List of Persons Met and Interviewed
Wing Division/Circle Name Position Contact Details Area Discussed Specific Issues Discussed
Finance ICT Circle Shafiqur Bashar Russel
Systems Analyst
[email protected] ICT/Billing Hardware issues - IT infrastructure in existence - Gaps - Proposed improvements
Software issues - Systems in existence - Gaps - Proposed improvements
Training requirements
Timelines for project implementation
Engr. Lutfe Jahan
Computer Programmer
Accounts Circle
Raktim Deb Accounts Officer
[email protected]; 01676-020197
Accounts Functions under Accounts Circle
Current status of accounting software solutions
Challenges/limitations of accounting software
Nazmun Nahrine
Budget Officer (with Additional Charge as Revenue Officer - Accounts)
[email protected]; 01929-965990
Budgeting; Revenue Accounts
Budget preparation process
Management of revenue accounts (revenue collection through banks and mobile service providers)
Challenges encountered and proposals for improvements
Sales Division Md. Golam Sankar
Executive Engineer (Sales); Additional Duty as SE-MODs
Functions of MODs
Overview of functions/responsibilities under MOD zones
Complaints handling process
Challenges encountered
34 | P a g e
Wing Division/Circle Name Position Contact Details Area Discussed Specific Issues Discussed
Md. Jasim Uddin
Assistant Engineer (Sales)
[email protected]; 01711-356769; 01611-356769
New Connection Process
Description of New Connection process
Challenges encountered
Proposals for improvements
Revenue Division
S.M. Badruddoza
Revenue Officer
[email protected]; 031-616042; 01819-352039
General activities of Revenue Division
Meter reading process
Bill preparation
DTW licensing
Customer complaints handling
Erfan Sazzad Revenue Officer
[email protected]; 01913-980384
Engineering Office of the DMD
Razan Kumar Sankar
DMD Engineering; PD PANI
PANI Project; General engineering operations
Timelines & deliverables for PANI-2
Plans for mainstreaming PANI outputs
Performance data flow within Engineering wing
Office of the Chief Engineer
Engr. Muhammad Zohurul Hoque
Chief Engineer; PD KWSP
[email protected]; 01819-940263; 031-2851698
General engineering operations; Activities under KWSP
Performance improvement proposals
Staff capacity improvement requirements
Status of SCADA system implementation
Design Division
Selim Nawaz Draftsman 01926-991869 MIS Report MIS report data categories
Sources of data for the MIS report
Procedure for report compilation
Challenges encountered
Proposals for improvements
PD CWSISP Courtesy call
Brief on objectives of assignment
PANI Project Keya Chowdhury
Assistant Engineer
[email protected] GIS activities under PANI project
Customer surveying and updating activities to date within KSA
Systems and software applications in use for GIS function
35 | P a g e
Wing Division/Circle Name Position Contact Details Area Discussed Specific Issues Discussed
Challenges
Proposed improvements
Dampara Water Works (MOD2)
Tridib Chowdhury
Overseer, Water Works, MOD-2
01814-771795 Water Bowser management, Complaints management
Water bowser sales process (application, payment, delivery)
Complaints handling process
Water distribution balancing (rationing) activities
MOD2 Division
Engr. Abdur Rouf
Executive Engineer; also EE for KWSP1
[email protected]; 01735-328292; 031-617973
SCADA system; General zonal engineering Ops.
Typical MOD engineering operations, as exemplified by MOD2
Customer complaints handling
Progress of SCADA system implementation
Administration Office of the Secretary
Md. Shamsuddoha
Secretary [email protected]; 031-614269, 01711-196668
HR matters Overview of HR issues
Gaps in information management systems and practices
Public Relations Division
Kazi Nurjahan Shila
Public Relations Officer;
Information Officer for
CWASA
[email protected]; [email protected]; 031-615242
PR and Communication matters; Customer Care
Duties and responsibilities of PRO
Description of internal communication systems and practices
“Right to Information Act” obligations
36 | P a g e
Appendix 2: Summary of Process Audit and Assessment for CWASA’s Key
Business Processes
SALIENT FEATURES/PROCESS DESCRIPTION Business Process/ Function: Water Treatment & Production Location/Host Department/ Process Owner: The respective WTPs (Mohara, Karnafuli, Kalurghat), under the Treatment & Production Circle of the Engineering Wing
Water Treatment Plants (WTPs)
Currently two fully functional WTPs: A 90 MLD Surface WTP located at Mohara, and a 68 MLD Ground WTP and Booster Station located at Kalurghat.
A third 143 MLD water treatment plant (Karnaphuli WTP) is expected to be commissioned later this year
Plans to construct a fourth surface WTP at Modunaghat by the end of 2017.
Mohara: Conventional treatment (clarification, filtration, disinfection) of raw water extracted from R. Halda.
Kalurghat: Iron removal (through aeration and sedimentation and subsequent disinfection) from groundwater channelled from approx. 27 deep tube wells (DTWs)
Deep Tube Wells (DTWs)
94 to 96 DTWs in existence across CWASA.
Daily production records submitted by telephone and SMS from Design Division.
The SMSs go to: - SE (MOD) - Chief Engineer - DMD (Engineering) - MD
Karnafuli Water & Sanitation Project (KWSP):
Funded by JICA.
Launch scheduled for September 2016.
KWSP serves three zones within the Karnafuli Service Area (KSA).
Each of the three zones consists of nine blocks, and each block has 8-10 DMAs.
KSA constitutes 60-70% of the CWASA service area.
Entire water distribution network within the KSA to be replaced under the KWSP-2 project.
HR development necessary, targeting capacity and skills of staff handling the engineering function.
Majority of these staff are below 50 years of age; they need training and mind change towards a service-oriented culture.
SCADA System:
9 pumps located at Nasirabad (implemented under KWSP1, and near completion).
There is a provision for four extra pumps, to be implemented under KWSP2.
Reservoir works have been implemented in such a way that manual operation is possible.
There is provision, however, for a SCADA system, but there has been very slow progress to date towards its implementation.
The SCADA system is to be implemented under KWSP2.
Control room to be located at Nasirabad. An Executive Engineer has already been identified to head this function.
Aimed at connecting the WTP with DMAs in the distribution network.
SCADA equipment (to be) obtained from Siemens (who are the sub-contractor for the SCADA system).
37 | P a g e
SALIENT FEATURES/PROCESS DESCRIPTION Some Identified Shortcomings:
DTW maintenance is currently outsourced to an annual (yearly) contractor, with a target maximum downtime (recovery time) of 72 hours in the event of DTW breakdown, or else the contractor is liable to being penalised. But it is difficult to track compliance to this requirement.
Daily reports should be available to Management, for purposes of tracking operational status and performance of DTWs.
Tracking of DTW performance is also important as a means of assessing the competence of the contractors.
Business Process/ Function: Water Distribution and Network Operation & Maintenance Location/Host Department/ Process Owner: MOD Zones, under the MOD Circle of the Engineering Wing
Key functions/processes include: - Water production (DTWs) - Water supply to customers - Network maintenance
Typical MOD Operations (Exemplified by Mod 2):
DTW production data collected daily and entered into computer.
Production data includes both flow and electricity meter readings.
Hard-copy printout dispatched to HQ (SE-MOD, CE, DMD-Eng) and Design Division (EE-Design).
There are frequent breakdowns of the DTWs, sometimes caused by power outages from the PDB.
There are around 700 street hydrants, mainly situated in slum areas, where water is sold at domestic rates.
There are no fire hydrants in Chittagong.
Leakages and other small pipeline maintenance jobs are handled by the zone, while electromechanical equipment maintenance is outsourced to yearly contractors.
Instructions to contractors are issued verbally. Feedback from contractors is also received verbally.
Complaints are received either by phone or by physical visits to the zonal office by customers. Reports Generated:
Water production from DTWs (daily, hardcopy)
Electricity consumption
Count of reported incidences (compiled, classified and submitted monthly)
Engineering operations report (feeds into MIS report, and consists of): - Production from DTWs - Power consumption - Maintenance - Construction works in progress
Monthly production reports per DTW: - Pump No - Volume of water produced - Electricity consumed - No. of hours of downtime - Total running hours
Water Bowser Sales:
There is a water bowser management software system implemented at Dampara Water Works.
Four categories of water bowser services: - Large tanker for urgent requirements (10,000 litres at 2500 Tk, delivered within 24 hours) - Normal tanker (1400 Tk, supplied on priority basis)
38 | P a g e
SALIENT FEATURES/PROCESS DESCRIPTION - Own carriers (private tankers typically purchase 1 m3 at 100 Tk) - Free supply (done in emergency situations)
The process is as follows: - Application information entered into system - Application form printed out and signed by applicant - Demand Note issued in triplicate to applicant - Applicant takes Demand Note to WASA bank and deposits required fees - Delivery Order issued in quadruplicate - Water bowser delivery is scheduled and implemented
Payments are only made at the WASA bank at Dampara.
There is only one sale point, located at Dampara; however, there are two delivery points, one located at Dampara and the other at Kalurghat.
Water that is delivered is typically stored in underground reservoirs. Some Identified Shortcomings:
No explicit performance targets for MOD engineering operations.
No mechanism for tracking progress towards target achievement.
Necessary for capacity development (for XEN MODs) to achieve self-reliance in implementing engineering works, rather than solely relying on the use of yearly contractors, even for piecemeal tasks (delegated works).
Decision making within the Engineering Wing is currently highly centralised. It should be possible to delegate authority to XEN (MODs) to implement contingency plans.
There is scope for improvement of operations of MODs, to a more integrated functioning with centralised reporting.
Business Process/ Function: New Connection Implementation Location/Host Department/ Process Owner: Sales Division, under the Finance Wing
Process for New Connections Implementation: (i) Customer purchases and submits application form (in duplicate) to XEN-MODs (ii) Site visit by SAE (iii) Application approved by: DMD-Finance (up to ¾” connection); MD (1” and above) (iv) Demand Note issued to customer (v) Customer makes payment in bank for connection materials and security deposit (vi) Work order issued to connection team (vii) Where required, road cutting permission is sought from CCC (viii) Connection implemented by connection team (ix) Account Number issued by Sales Division (x) Completion Report sent to Revenue Division (xi) Revenue Division submits account details to Computerised Billing section for account creation in
Billing System Additional Notes:
New connection application form is purchased from WASA Bank at 200 Tk.
Additional requirements include the following: - Property ownership form - National ID and photograph - Location sketch (from Certificate of Title) - Undertaking by property co-owners, if any
Security deposit: 30,000 Tk for domestic premises; 30,000 Tk for landlord and 60,000 Tk for tenant, for commercial premises.
Connection team consists of a plumbing mistry and an assistant plumbing mistry.
39 | P a g e
SALIENT FEATURES/PROCESS DESCRIPTION Account No consists of the Mohalla (area) code and a serial number within the Mohalla.
Two customer files are prepared: One copy goes to Revenue Division, and the other copy stays with the Sales Division.
Connection process takes on average 7 to 15 days.
On average, 250 to 300 new connections are made per month.
It takes approx. two months from connection to submission of customer details to the Revenue Division.
Sales Division is responsible for maintenance of service lines for the first six months, after which they become the responsibility of the respective MOD Zone.
Sales Division also handles relocation of service lines as well as connection enlargement.
The Division is considering outsourcing (sub-contracting) the new connection process as a way of meeting annual targets, currently set at 5000 new connections for this FY.
All record-keeping and information management within the Sales Division is manual. Sales Division maintains a manual register of customer account details, which include the following information: - Meter No - Meter size - Customer name and address - Account No - Connection date - Consumption category - Completion date
Some Identified Shortcomings:
Lack of a computerised information management system to handle the new connection process.
Process too bureaucratic, with too many approval levels.
The main delay in the connection process is as a result of these approval levels, otherwise connection itself takes about 7 days.
Current staffing levels for the new connection teams are insufficient to meet new connection targets; they consist of only three plumbing mistries and two assistant plumbing mistries.
JICA staff under the PANI project have made efforts to translate and digitise the New Connection form for online (digital) use; however, the challenge with this is that there are no computers in the Sales Division to facilitate this process.
Business Process/ Function: Meter Reading and Billing Location/Host Department/ Process Owner: Computerised Billing Section, under the ICT Division of the Finance Wing
Billing:
New connection details from Sales Division are used to create customer accounts in billing system.
Meter readings from Revenue Division are used to generate monthly bills for water consumed.
Customers access their bills through the CWASA website.
SMS notifications are also sent to customers upon billing.
Customers make payments through participating banks and/or mobile service providers.
There are three participating mobile service operators and 34 participating banks.
Internet VPN connectivity is used to upload billing data to mobile operator servers daily.
Likewise, bill payment data is transferred to CWASA’s online billing server from the participating banks daily.
However, a common complaint is that customers sometimes make payments but the banks delay to post these payments.
Billing Software:
40 | P a g e
SALIENT FEATURES/PROCESS DESCRIPTION Microsoft SQL Server database (backend)
Visual Basic Desktop Application (frontend)
Connectivity to Mobile Service Operators over VPN Some Identified Shortcomings:
The Billing system in its current form does not cater for a number of key commercial and revenue functions, such as new connections, meter reading, customer inquiry, customer account maintenance, and service changes.
Often, customers with billing-related issues/complaints come right up to the individual officers in the Computerised Billing Section, causing a lot of disruption/distraction.
Proposed the establishment of a separate help desk/counter specifically for billing related issues and complaints.
Decentralisation of revenue operations to zones would require dedicated staff to handle Billing and IT functions at Zonal level.
Business Process/ Function: Revenue Management Location/Host Department/ Process Owner: Revenue Circle, under the Finance Wing
Functions under the Revenue Circle:
Meter reading
Billing preparation (provision of metering data to ICT Division)
Bill delivery (physical bills)
Follow up and collection of arrears
Disconnections and reconnections
Meter servicing
Licencing of Deep Tube Wells, including: - processing of applications - handling payments (annual, for the period Mar-Feb)
Responding to customer complaints relating to: - requests for instalment payments - connection status - changes of tariff categories
Meter Management:
Whereas the meter installation function is handled by the Sales Division, meter servicing, disconnection and reconnection are done by the Revenue Division.
There is a tender process currently underway to sub-contract/outsource the activity of bulk replacement of faulty customer water meters.
Some Identified Shortcomings:
Staffing inadequacies.
Insufficient IT equipment and support.
No register for customer complaints handling.
Customers often have to physically move from desk to desk in order to have their issues resolved.
Delays in customer complaints handling.
No reports/data submitted regarding revenue collection; reporting is done by the ICT Division.
Insufficient number of meter inspectors.
There are supposed to be five disconnection squads, but these are not evident on the ground.
No anomalies handling process. Recommendations:
41 | P a g e
SALIENT FEATURES/PROCESS DESCRIPTION Computerisation of records.
Use of hand-held meter reading devices, to avoid data manipulation.
Business Process/ Function: Accounting and Financial Management Location/Host Department/ Process Owner: Accounts Circle, under the Finance Wing
The Accounts Circle consists of four Sections, located on different floors of the building.
The Accounts Management section handles the following functions: - Preparation of final accounts - Management of fixed assets - Tracking of project works in progress - Inventory management
The Revenue Accounts section handles the revenue tracking function.
The Accounts Finance section handles payments to suppliers and service providers.
The Budget section deals with budget preparation, including both estimation and rectification of budgets. Accounting Software:
“Dheraaj” software (made in India) was previously acquired for the accounting function. However, it was never fully implemented.
Tally software was obtained in 2003 and is currently in use.
Software housed on dedicated server, and is accessible to all staff of the Accounts Circle.
Data is backed up onto a desktop computer.
Support provided by local Tally supplier. Budgeting:
Every September, all Divisions and Departments are notified of their budgetary status.
They respond with their budgetary projections for the coming FY.
A budget is drafted by the Budget Officer in consultation with the Chief Accounts Officer and DMD (Finance).
In December, the draft budget is reviewed by a collective meeting of all Divisional and Departmental Heads.
The draft budget is submitted to the ministry for review and approval.
A final budget meeting is held to discuss and disseminate the approved budget.
Project budgeting is a separate activity, with mid-term project budgets prepared by the Budget Officer for submission to the ministry.
The budget preparation process is manual (but also involves the use of Excel spreadsheets). Revenue Accounts:
Revenue Officer (Accounts) receives information from participating banks on monthly revenue collections made on behalf of CWASA.
Submits this information to the Secretary for onward transmission to the ministry.
Revenue is obtained from water sales at customer connections, new connection fees, DTW licensing, and water bowser sales.
Some Identified Shortcomings:
Out of the 12 staff of the Accounts Management section, only 3 staff work with Tally.
Backlog in data entry into Tally. Entry of data for the 2013-2014 FY only 60% completed to date.
The Tally software requires customisation in order for it to suit the accounting requirements of CWASA.
There is no interface with the Sales, Billing and Revenue functions.
There is no budgeting functionality.
No stores/inventory management functionality.
42 | P a g e
SALIENT FEATURES/PROCESS DESCRIPTION No payroll management functionality.
Insufficient number of computers.
Insufficient staffing levels.
With the billing software, it is not possible to view revenue collection information from the WASA bank based at HQ (Janatha Bank), as well as the mobile service providers, in real time on a daily basis.
Out of the three staff available for the Revenue Accounts function, two are set to retire.
There is only one staff in the Accounts Circle who handles the budgeting process, namely the Budget Officer. Moreover, the Budget Officer holds an additional charge as Revenue Officer (Accounts).
Business Process/ Function: Customer Complaints Handling Location/Host Department/ Process Owner: MOD Zones, under the MOD Circle of the Engineering Wing
Customer Help Desks are located at CWASA offices.
There are four Complaint Handling centres; one at Dampara Water Works (MOD2), two at Jubilee Road (MOD4), and one at Agrabad (MOD1).
The most common categories of customer complaints are: - Leakage - Dirty water - No water
Customer either walks in or calls with a complaint.
Complaint details are captured in a manual complaints register.
Details captured include: Date; Time; Complaint No; Address; Type of Complaint; How received; Remarks; Repairing time; Description of size; Other description; Materials used; Signatures of supervisor, SAE, and AE; Remarks.
For MOD2, there are 2 response teams, each consisting of two staff, using two tempus (three-wheeler bikes).
Supervision of field works is by physical inspection, and is carried out by pipeline supervisors, SAE, and AE.
Monthly reports are submitted to: CE, SE-MOD, DMD (Eng).
Typical report contents include: - Total complaints received - Leakages - Leaks repaired - Water shortages - Water shortages solved - Attended (total)
Some Identified Shortcomings:
There is no Call Centre, neither is there a toll-free line for reporting of customer complaints.
Manual complaints tracking registers, which in many cases are not even used.
No mechanism in place for tracking progress of resolution of reported cases.
No escalation mechanisms in place for uncompleted tasks.
Communication with field staff is by use of personal mobile phones (no company owned mobile phones available).
Shortage of trained manpower (mistry) and tools (die sets, slide wrenches, pipe wrenches, spades and hoes).
Need a mechanism for Top Management overview, and escalation, of leak repair activities.
The Systems Analyst is currently developing a computerised Complaints Tracking System (CTS); however, so far there seems to be little interest within the Finance Wing regarding this system.
Business Process/ Function: Human Resource Management Location/Host Department/ Process Owner: Secretary, under the Administration Wing
All HR management processes are manual.
43 | P a g e
SALIENT FEATURES/PROCESS DESCRIPTION A Personal File (PF) is maintained for each staff.
Currently, 20 grades of staff, excluding the top two grades.
The Accounts Division performs salary computations, including leave payments, provident fund deductions, and contract gratuity.
From this year, salary calculation will be made easier, due to a system introduced across the country that harmonises salary increment/notching dates to 1st July for all government employees.
Payroll Management:
Currently handled by the Computerized Billing Section.
Utilise Foxpro-based system, a stand-alone system which is near-obsolete.
Computation of staff monthly salaries and emoluments.
Generation of payslips. Recommendations:
Payroll/HR system (HRMS), required to also handle leave management, staff movements, staff transfers, Provident Fund deductions, etc.
The Systems Analyst proposes that this system be developed internally.
Business Process/ Function: Monitoring & Evaluation (Management Reporting) Location/Host Department/ Process Owner: Design Division, under the Construction Circle of the Engineering Wing
MIS Report Compilation: Function currently performed by Draftsman, using the following steps: (i) Calls up relevant officers in various units/departments (refer to Appendix 4) and asks them to furnish
their respective performance data. (ii) Performance data is submitted in hard-copy format to Draftsman. (iii) Draftsman enters and compiles the data using the MIS Report template developed under the JICA-
funded PANI project. (iv) MIS Report is reviewed and subjected to the following chain of approvals: XEN-Design; SE-Construction;
DMD-Engineering; MD. (v) Approved report is subsequently circulated to 38 different personnel/officers across CWASA. MIS Report Contents (refer to detailed example in Appendix 3):
Connection data
Tariff rates
Billing & Collection data
Financial data
Water supply data
Personnel data
Customer services data Some Identified Shortcomings:
Delayed data submission, which leads to a time lag of about two months in report preparation (the latest circulated MIS report usually applies to a period about two months prior).
Errors in submitted data.
The MIS Report lacks information on stock/inventory levels. Recommendations:
Improved reporting times.
Improved data accuracy/correctness.
44 | P a g e
SALIENT FEATURES/PROCESS DESCRIPTION Propose development of a centralized data collection system.
Business Process/ Function: Customer Mapping & GIS Location/Host Department/ Process Owner: Currently performed by JICA-funded PANI Project office, for customers within the Karnaphuli
GIS:
2-3 engineers from CWASA seconded to the PANI project have been trained to handle the GIS function.
Field surveying is carried out by five engineers deployed under PANI (JICA staff). Training of CWASA survey staff is ongoing.
Integration with Billing and Sales divisions is planned to take place this year.
In addition to customer data, the piped network within the project (KSA) area has been mapped. No mapping of the piped network exists outside the KSA.
About 50,000 to 60,000 customers within the KSA have been mapped to date.
Surveying of households outside KSA was previously planned to be included under CWSISP, but was later excluded.
Available customer GIS data consists of: - Customer location - Account No - Meter No
PANI GIS staff currently engaged in updating customer data obtained from the Sales Division into the GIS database.
However, this data has not yet been utilised by CWASA in day-to-day commercial operations. GIS Software specifications:
ArcGIS 10.1 Desktop
4 desktop licences
Three persons trained in the use of ArcGIS.
Also use Microsoft Access for data management. Some Identified Shortcomings:
There is a disconnect between GIS under PANI and the Sales Division.
Computer equipment is insufficient. For example, there are no computers within the Sales Division to handle the GIS data.
Difficult (uncooperative) customers hinder the household survey process.
Recommended a workshop to create awareness and promote GIS uptake by CWASA.
Logistics (laptops) and training of CWASA staff required to mainstream the GIS function within CWASA.
Business Process/ Function: ICT Support Provision Location/Host Department/ Process Owner: Computerised Billing Section, under the ICT Division of the Finance Wing
Computer Hardware:
Servers: 3 No. servers for Billing, i.e. online, offline and internal backup; 1 No. server for Accounts.
Desktop PCs: Approx. 50-60 PCs in existence across CWASA. Communication Systems:
Intercom system in existence for internal communication within HQ.
Landlines in use at HQ for external communication by key staff.
Position-based corporate email addresses created on CWASA domain webmail for 30-40 key positions (e.g. [email protected])
45 | P a g e
SALIENT FEATURES/PROCESS DESCRIPTION Networking:
Limited LAN coverage at HQ.
Limited Wi-Fi also implemented for HQ. CWASA Website:
Maintained by the Computerized Billing Section.
URL: www.ctg-wasa.org.bd Some Identified Shortcomings: Computer Hardware & Networking Infrastructure:
Firewall procured but not configured (not implemented by vendor).
Existing LAN is implemented in a disorganized manner, and is not easy to secure.
There is no WAN connectivity to other CWASA facilities/installations outside the HQ.
Insufficient backup servers.
Insufficient power backup (UPS) systems.
No off-shore Disaster Recovery (DR) site.
No Service Level Agreements (SLAs) with suppliers in place for maintenance of hardware/software systems.
Communication Systems:
No company mobile phones in use, resulting in the widespread use of personal mobile phones for company business.
Corporate email addresses that were established on the CWASA domain have not been adopted for use. IT Support:
No dedicated IT support teams in place.
No IT infrastructure performance monitoring software.
Low levels of computer literacy, with only approx. 20% of staff computer savvy.
There is a general apathy towards the use of ICT systems. Most staff think it is the ICT Division alone who should use ICT systems, and not they themselves within their respective departments.
Not ready for the business expansion anticipated after completion/commissioning of KWSP. Proposed the outsourcing of an external service provider for IT support.
Business Process/ Function: Procurement & Transport Location/Host Department/ Process Owner: Transport & Procurement Section, under the Administration Wing
There is no centralized Procurement and Disposal unit (PDU) in CWASA. The procurement function is currently performed directly by the various business units, and is not an integrated function. This makes it difficult to monitor and control.
Business Process/ Function: Public Relations Management Location/Host Department/ Process Owner: Public Relations Section, under the Administration Wing
Main Responsibilities:
Liaise with print and electronic media on behalf of CWASA.
Monitor views expressed through media.
Advise CWASA management on media related issues.
Arrange press conferences.
Publish tender notices in print media.
Dispatch press releases to print and electronic media.
46 | P a g e
SALIENT FEATURES/PROCESS DESCRIPTION Manage telecommunication system within CWASA:
- Ensure that key staff are equipped with landlines - Follow up reported faults on telephones
Display adverts, e.g. supplementaries.
Run school/community awareness campaigns.
Was nominated as CWASA Information Officer under the “Right to Information Act 2009”.
Under this Act, citizens can request for any information using a prescribed type of form, following which the Information Officer must: - process requests - refer requests to relevant officers - ensure that information is provided to the concerned citizens within the duration prescribed under the law (20 working days).
However, she often has to push in order to get the data she requires, by: - making phone calls - visiting offices - knocking on doors - following up, etc.
On Internal Communications:
Intercom system exists, with support provided by MOD2.
However, field staff end up having to use their personal mobile phones to communicate with office staff, because there are no office mobile lines.
On email communication:
Most office processes are still manual.
Culture of electronic communication not yet prevalent among staff.
Computers themselves are now available, but their usage is still low. On Social Media:
Not a commonly used medium for communication.
Usage mostly common/associated with teenagers.
In general, internet usage itself is low. Recommendations:
Have dedicated helplines (mobile) for customers to use in lodging their complaints.
Provide these contact numbers on display adverts.
Business Process/ Function: Project Management Location/Host Department/ Process Owner:
No centralized Project Monitoring Unit in CWASA. Instead, project management is a responsibility delegated to selected officers designated as Project Directors (PDs) for the various internally and externally funded capital development projects.
Identified Shortcoming:
Insufficient documentation of engineering works (including as-built drawings, resources applied, equipment used, money spent etc.)
47 | P a g e
Appendix 3: Sample Management Information Systems (MIS) Report for CWASA (April 2016)
48 | P a g e
49 | P a g e
50 | P a g e
Appendix 4: Sources of Data for MIS Report
51 | P a g e
52 | P a g e
Appendix 5: Summary of Critical Data and Information Generated and Managed for each Key Business Process
Key Business Processes
Responsible Business
Unit
Major Functions/ Process Stages
Critical Data/ Information Generated Data Source/ Repository
Information Outputs (Performance
Measures) feeding into MIS Report
Water Treatment & Production
Water Treatment & Production Circle, under the Engineering Wing
Abstract raw water from source
Treat water
Convey treated water to reservoir storage for subsequent distribution
River water levels
Raw water quality measurements
Raw water pump hours
Raw water flow volumes
Raw water pump electricity consumption
Chemical usage
Treated water pump hours
Treated water flow volumes
Treated water pump electricity consumption
Treated water quality measurements
Booster pump hours
Booster flow volumes
Booster pump electricity consumption
Plant downtime
Plant electromechanical equipment failures handled
Plant PPM tasks accomplished
Plant staff deployment
SCADA system operational data
River water level sensors
Production flow meters
Electricity meters
Conductivity & Turbidity meters
Laboratory test result logs
Chemical usage logs
Incident registers
PPM logs
SCADA system logs
Capacity of Surface WTP (E3)
Capacity of Ground WTP (E4)
Production (distributable water) (E15)
Unit production costs (E16)
Water quality sample (E19)
Satisfactory sample in chlorine level (E20)
Satisfactory sample in microbiological level (E21)
Water Distribution and Network O&M
MOD Circle, under the Engineering Wing
Pump water from DTWs to direct distribution or to GWTP
Distribute water to consumers
DTW levels (static water level; drawdown)
DTW production volumes
DTW water quality measurements
DTW electricity consumption
DTW functional status
DTW downtime due to power outages
DTW level sensors
Flow meter readings
Electricity meter readings
No. of DTWs in operation (E5)
Capacity of DTW – direct distribution (E6)
Capacity of DTW – supply to GWTP (E7)
53 | P a g e
Key Business Processes
Responsible Business
Unit
Major Functions/ Process Stages
Critical Data/ Information Generated Data Source/ Repository
Information Outputs (Performance
Measures) feeding into MIS Report
Maintain pipelines and DTWs
Handle customer complaints
DTW downtime due to electromechanical faults
DTW failures resolved by Yearly Contractor(s)
DTW flow volumes to direct supply
DTW flow volumes to Ground WTP
Water from Surface WTP
Water bowser applications received
Water bowser deliveries made
Pipeline failures reported
Pipeline failures resolved by WASA teams
Pipeline failures resolved by Yearly Contractor(s)
Customer complaints received
Customer complaints resolved
Staff deployment for complaints handling
Logistics used (transport, equipment)
Repair materials used
Response time to resolution of reported complaints
Manual incident registers
Water bowser management software
Capacity of distributable water production (E8)
DTW water to users before boosters (E15.1)
Water supply coverage (A6)
Length of pipeline (E9)
Leakage occurrence (E18)
Non-Revenue Water (E17)
Leakage complaints received and attended (G3)
New Connection Implementation
Sales Division, under the Finance Wing
Receive New Connection applications
Conduct site visits and assessments
Applications received
Site visits conducted
Applications approved
Applications paid for
Work orders issued
Connections implemented
Meters issued
Copies of application forms
Copies of demand notes
Payment records from bank
Manual registers
Service connection applications received (G1.1)
Service connections given (G1.2)
54 | P a g e
Key Business Processes
Responsible Business
Unit
Major Functions/ Process Stages
Critical Data/ Information Generated Data Source/ Repository
Information Outputs (Performance
Measures) feeding into MIS Report
Process new connection applications
Effect new connections
Assign Account Numbers to new customers
Maintain new connection lines for first six months
Relocate service lines where required
Completion reports submitted to Revenue Division - Customer details - Consumption category - Account details - Meter details - Payment details
New accounts created in Computerised Billing System
Accounts under maintenance within six-month service period
Service line relocation requests
Individual customer files
Completion reports
Account details in Computerised Billing System
Meter Reading & Billing
Meter Reading: Revenue Zones of the Revenue Circle, under the Finance Wing Billing: Computerised Billing Section of the ICT Circle, under
Allocate meter reading sheets to meter inspectors
Read meters
Investigate and correct meter reading anomalies
Forward meter readings to Computerised Billing Section
Input meter readings
Number of meters read
Meter readings
Meter reading anomalies reported
Meter reading anomalies resolved
Meter readings captured in Computerised Billing System
Bills generated
Bills uploaded to CWASA website
SMS notifications (bills) dispatched to/by Mobile Service Providers
Bills printed for physical distribution
Meter reading sheets
Computerised Billing System
Servers of participating banks and mobile service providers
CWASA website domain database
Total registered connections (A1)
Meter installation rate (metering ratio) (A3.4)
Percentage of installed meters that are functional (A3.5)
No. of Street Hydrants (A4)
No. of Religious Institutions (A5)
55 | P a g e
Key Business Processes
Responsible Business
Unit
Major Functions/ Process Stages
Critical Data/ Information Generated Data Source/ Repository
Information Outputs (Performance
Measures) feeding into MIS Report
the Finance Wing
Generate bills
Upload bill data to CWASA website
Send SMS bill notifications to customers
Print physical bills
Billable (non-disconnected) connections (A1.1)
Non-billable (disconnected) connections (A1.2)
Billed connections (A1.3)
Breakdown of billable connections by customer type (A2)
Breakdown of billable connections by metering status (A3)
Bill sent out ratio (A7)
Revenue Management
Revenue Circle, under the Finance Wing
Distribute physical bills
Track payments made through banks and mobile service providers
Handle and resolve billing related complaints
Follow up payment of unpaid bills
Total amount billed
Bills distributed
Paid bills
Unpaid bills
Arrears status
Arrears payment agreements
Disconnections made
Reconnections made
Meters serviced
Meters replaced
Total collections
DTW licenses issued
DTW licenses revoked
Computerised Billing System
Servers of participating banks and mobile service providers
Manual registers
Total billing (C1)
Billing (private) (C1.1)
Billing (government) (C1.2)
Billed volume (C2)
Total collection (C3)
Collection (private) (C3.1)
Collection (government) (C3.2)
Revenue collection efficiency (C4)
56 | P a g e
Key Business Processes
Responsible Business
Unit
Major Functions/ Process Stages
Critical Data/ Information Generated Data Source/ Repository
Information Outputs (Performance
Measures) feeding into MIS Report
Carry out disconnections and reconnections
Engage arrears reduction strategies
Service water meters
Replace faulty water meters
Issue DTW licenses
Collection efficiency (private) (C4.1)
Collection efficiency (government) (C4.2)
Billing complaints received (G2.1)
Billing complaints acted on (G2.2)
Accounting & Financial Management
Accounts Circle, under the Finance Wing
Units/Functions:
Accounts Management Section: - Prepare final accounts - Manage fixed assets - Track progress of project works - Manage stores inventory
Revenue Accounts Section: - Track revenue
Asset Management:
New assets acquired
Old assets disposed of
Capital works implemented
Asset maintenance records
Asset (re)valuation
Depreciation Revenue Management:
Revenue collections via banks
Revenue collections via mobile service providers
Water bowser sales
DTW licencing fees payments
Accounts receivable (arrears)
Fixed asset register
Tally Accounting System
Computerised Billing System
Bank reports
Mobile service provider reports
Water bowser management system
Excel spreadsheets (Budgeting)
Total revenue (D1)
Water revenue (D1.1)
Revenue from tube well licensing (D1.2)
Other operating revenues (D1.3)
Interest on income (D1.4)
Total expenses (D2)
Personnel costs (D2.1)
Electricity costs (D2.2)
Chemicals (D2.3)
Depreciation (D2.4)
Other operating costs (D2.5)
57 | P a g e
Key Business Processes
Responsible Business
Unit
Major Functions/ Process Stages
Critical Data/ Information Generated Data Source/ Repository
Information Outputs (Performance
Measures) feeding into MIS Report
collection - Track arrears
Accounts Finance Section: - Handle payments to suppliers and service providers - Handle salary and wage payments to staff
Budget Section: - Prepare and manage budgets, including project budgets - Track and ensure budget compliance
Budgeting and Procurement Financing:
Budgetary allocations
Procurement plans
Budget status
Project budget status
Inventory of stock items
Purchase requisitions raised
Purchase orders issued
Invoices received for works, supplies & services
Payment vouchers raised
Payments made for works, supplies & services
Payroll Management:
Salaries & wages
Provident fund deductions
Other statutory deductions
Gratuity payments
Staff loan deductions
Foxpro database (Payroll management)
Project reports
Financial expenses (D2.6)
Net income (D3)
Cash at bank (D4)
Stock and stores (D5)
Accounts receivable (D6)
Accounts receivable from Government (D.6.1)
Accounts receivable from Private (D.6.2)
Long term loans (D7)
Operating ratio (D8)
Collection period (D9)
Customer Complaints Handling
MOD Zones of the MOD Circle, under the Engineering Wing
Receive customer complaints (submitted by phone, or by customer physically
Complaints received
Complaints assigned
Complaints tracking - Customer details - Contact No - Nature of complaint - Date/time reported
Manual Complaints Registers
Leakage complaints received and attended (G3)
58 | P a g e
Key Business Processes
Responsible Business
Unit
Major Functions/ Process Stages
Critical Data/ Information Generated Data Source/ Repository
Information Outputs (Performance
Measures) feeding into MIS Report
walking into CWASA offices)
Log complaint details in Complaints Register
Assign job(s) to (field) implementation team(s)
Take (field) action to resolve complaint issue
Update Complaints Register
- Place reported - Job allocation - Job status - Date/time resolved - Staff deployed - Action taken - Materials used - Feedback to complainant
Complaints resolved
Response time to resolution of complaints
Human Resource Management
Secretariat, under the Administration Wing
Functions:
Workforce management
Workforce scheduling
Payroll Management
Approved staff levels & grades
Staff personal details
Staff appointments and deployments
Staff job descriptions and Key Result Areas (KRAs)
Staff additional charges
Staff attendance records
Staff leave schedules
Staff appraisals and performance data
Salaries, wages & emoluments
Provident fund contributions
Promotions
Human Resource Manual
Organogram
Staff Personal Files (PF)
Manual registers
Foxpro-based payroll management system
Total no. of permanent employees (F1)
Employees in Class 1 (Officers) (F1.1)
Employees in Class 2 (Supervisory staff) (F1.2)
Employees in Class 3 (Clerical staff) (F1.3)
Employees in Class4 (Sub-clerical staff) (F1.4)
59 | P a g e
Key Business Processes
Responsible Business
Unit
Major Functions/ Process Stages
Critical Data/ Information Generated Data Source/ Repository
Information Outputs (Performance
Measures) feeding into MIS Report
Demotions
Dismissals
Retirements
Disciplinary cases
Total no. of non-permanent employees (F5)
Non-permanent employees on Work Charge (6 month contract workers) (F5.1)
Non-permanent employees on Master Roll (daily basis casual workers workers) (F5.2)
Project staff (hired by project budget) (F5.3)
No. of permanent employees per 1000 connections (F2)
Average monthly salary (F3)
Percentage of overtime to basic salary (F4)
Monitoring & Evaluation (Management Reporting)
Currently handled by the Design Division of the Construction
Request performance reports from various business units
Performance data of various categories, including the following: - Connection data - Applicable tariff - Billing & collection data - Financial data
Manual performance reports from various business units
The entire MIS Report in its current form (refer to Appendix 4 for a sample) is a monthly compilation of performance data
60 | P a g e
Key Business Processes
Responsible Business
Unit
Major Functions/ Process Stages
Critical Data/ Information Generated Data Source/ Repository
Information Outputs (Performance
Measures) feeding into MIS Report
Circle, under the Engineering Wing
Receive & collate performance data
Generate (populate) MIS report
MIS report reviewed and approved by various officers
MIS report circulated to concerned staff
- Water supply data - Personnel data - Customer services data
Selected (derived) Key Performance Indicators (KPIs): - Non-Revenue Water - Revenue Collection Efficiency - Collection Period - Staffing Ratio (staff per 1000 connections) - Operating Ratio - Metering Ratio - No. of Water Quality Samples - Leakage Occurrence (Leaks per km) - Water Supply Coverage - Average Tariff - Unit Production Costs
Compiled monthly MIS report(s)
from the various business units and key business processes.
SUPPORT PROCESSES:
Customer Mapping & GIS
MOD Zones of the MOD Circle, under the Engineering Wing; However, currently handled by JICA funded PANI project
Obtain new connection list(s) from Sales Division
Carry out field survey and mapping of new customers
Enter (plot) customer details in GIS database
Field surveys scheduled
Field surveys completed
Customer details - Customer location - Account No - Connection details - Consumption category - Metering status - Supply status
Connections updated in GIS database
New connection files from Sales Division
GIS database
Physical map printouts
Computerised Billing System
None at present
61 | P a g e
Key Business Processes
Responsible Business
Unit
Major Functions/ Process Stages
Critical Data/ Information Generated Data Source/ Repository
Information Outputs (Performance
Measures) feeding into MIS Report
Update Computerised Billing System with customer location details
Maps generated and distributed to end user departments
Customer accounts updated in Billing System
ICT Support Provision
ICT Circle, under the Finance Wing
Install and maintain IT infrastructure
Procure, install and manage software systems and applications
Develop, deploy and maintain in-house software solutions where applicable
Liaise with external hardware and software support service providers
Provide IT support services (including basic training in ICT technologies) to CWASA staff
IT hardware inventory & status
IT software systems inventory & status
IT network infrastructure inventory & status
ICT systems software licencing status
Service Level Agreements with external suppliers and service providers
IT support services: - Cases reported - Cases handled
Excel spreadsheets
None at present
62 | P a g e
Key Business Processes
Responsible Business
Unit
Major Functions/ Process Stages
Critical Data/ Information Generated Data Source/ Repository
Information Outputs (Performance
Measures) feeding into MIS Report
Procurement & Transport
Transport & Procurement Section under the Administration Wing
Oversee and coordinate the procurement and logistics function at CWASA
Allocate and coordinate CWASA transportation fleet (Trucks, Jeeps, Station wagons, Pickups, Motor cycles, Tempos, etc)
Prequalified supplier lists
Item specifications
Budgetary provisions
Procurement plans
Stock levels
Purchase requisitions
Purchase orders
Works & services rendered
Items supplied
Payments for works, supplies and services
Transportation fleet
Vehicle maintenance records
Manual registers None at present
Public Relations Management
Public Relations Section, under the Administration Wing
Functions:
Media Liaisons
Corporate Branding and Corporate Social Responsibility (CSR)
Internal Communication
Landline allocation and maintenance
“Right to Information Act”
Pressers
Adverts
Tenders
Topical issues featuring in the press (“finger on the pulse”)
Notices
Public awareness campaigns
“Right to Information Act”: - Requests received - Requests processed - Feedback to customers
Newspapers
Newspaper cuttings
Corporate policy documents - vision - mission - quality policy
Corporate strategic plan(s)
Corporate programme documents
Manual registers
None at present
63 | P a g e
Key Business Processes
Responsible Business
Unit
Major Functions/ Process Stages
Critical Data/ Information Generated Data Source/ Repository
Information Outputs (Performance
Measures) feeding into MIS Report
statutory obligations
Staff Capacity Development
Planning, Development & Training Circle, under the Engineering Wing
Functions:
Staff training
Capacity development
Staff capacity assessments
Training Needs Assessments (TNA)
Training strategies
Training plans
Identified resource persons
Participating entities/ institutions
Training budgets
Training courses delivered/undertaken
Staff trained
Training outputs/outcomes
Training Impact Assessments (TIA)
Manual reports None at present
Project Management
Designated Project Directors (PDs) for various projects, mostly under the Engineering Wing
Functions:
Overseeing the implementation of various donor funded projects, such as: - CWSISP, funded by World Bank - PANI, funded by JICA - KWSP, funded by JICA
Construction works in progress
Milestones achieved
CWASA staff seconded to projects
Project outputs/outcomes
Project reports None at present
64 | P a g e
Appendix 6: The CWASA Management Information Systems (MIS) Plan 2016-2018
STRATEGY TASKS/ACTIVITIES BY WHOM BY WHEN ESTIMATED COSTS (USD)
OBJECTIVE 1.0 Ensure that CWASA’s IT infrastructure is sufficient to meet the Authority’s information management requirements in the immediate and long term, particularly taking into consideration the anticipated growth in business subsequent to commissioning of KWSP1 and KWSP2.
1.1 Equip CWASA’s business units with sufficient computer hardware equipment and core basic software applications
1.1.1 Carry out a comprehensive inventory of computer hardware (servers, PCs, printers and associated accessories) across CWASA.
SA Immediate Nil
1.1.2 Establish the gaps in numbers of equipment required to meet the information management needs of each business unit.
SA Immediate Nil
1.1.3 Procure the required computer hardware equipment in a phased, priority-based manner.
CM/SA/EE-Proc
Mar 2018 90,000
1.1.4 Carry out a needs assessment, identify and procure sufficient software licenses for core basic applications (such as the Microsoft Office suite of applications) as well as specialised applications (such as GIS).
SA June 2018 200,000
1.2 Establish an adequate IT network infrastructure backbone for CWASA
1.2.1 Carry out a comprehensive assessment of CWASA’s current network infrastructure and identify gaps in the existing setup.
SA Immediate Nil
1.2.2 Procure an external service provider to design and implement a robust LAN (wired and/or wireless) for the CWASA HQ, as well as for each of CWASA’s main facilities/installations.
CM/SA/EE-Proc
Dec 2017 40,000
1.2.3 Procure an external service provider to implement a robust WAN (via leased lines and/or VPN) connecting CWASA’s HQ to the other key facilities/installations.
CM/SA/EE-Proc
Dec 2017 30,000
1.2.4 Procure and implement a software solution for real-time monitoring of network performance (both LAN and WAN).
CM/SA/EE-Proc
Mar 2018 10,000
65 | P a g e
STRATEGY TASKS/ACTIVITIES BY WHOM BY WHEN ESTIMATED COSTS (USD)
1.3 Implement robust IT systems security measures
1.3.1 Remodel and renovate the server room at CWASA’s HQ to acceptable industry standards (minimum Tier 2), including installing adequate ventilation/air-conditioning and secure access control.
CM/SA/EE-Proc
Dec 2017 200,000
1.3.2 Procure and install backup servers for the core IS solutions (both existing and proposed) in CWASA (billing, accounting, HR management, email, website, procurement).
CM/SA/EE-Proc
Mar 2018 Covered under 1.1.3
1.3.3 Procure and install an appropriate power backup and surge protection solution for the server room and critical locations within CWASA (such as the Computerised Billing Section).
CM/SA/EE-Proc
Mar 2018 50,000
1.3.4 Identify an appropriate off-site location (e.g. the stores premises at Halishahar), and establish a Disaster Recovery (DR) site for all mission-critical IS solutions.
CM/SA/EE-Proc
Mar 2018 100,000
1.3.5 Implement a robust solution for LAN and WAN user access control, as well as an effective firewall to secure the network against unauthorised external access.
CM/SA/EE-Proc
Jan 2018 15,000
1.4 Institute appropriate IT support mechanisms and practices
1.4.1 Establish Service Level Agreements (SLAs) with computer hardware/software suppliers for routine and preventive system maintenance
SA Mar 2018 15,000
1.4.2 Develop and implement a computerized IT Support Requests Handling system
SA Mar 2018 8,000
1.5 Improve internal and external communication systems
1.5.1 Establish a prototype Call Centre, preferably with toll-free lines from each of the (three) mobile service providers, to facilitate customer complaints logging and handling.
CM Dec 2018 50,000
1.5.2 Procure a service provider to supply and install a Voice over IP (VoIP) or IP PBX telephony solution for CWASA, to replace the current traditional PBX based system and extend intercom connectivity to other facilities/locations of CWASA. (subject to licensing guidelines for IP Telephony services in Bangladesh)
CM Dec 2018 30,000
66 | P a g e
STRATEGY TASKS/ACTIVITIES BY WHOM BY WHEN ESTIMATED COSTS (USD)
1.5.3 Acquire mobile phone lines and establish a Closed User Group (CUG) with preferential rates for CWASA staff, in partnership with one or more of the mobile service providers.
CM Dec 2017 10,000
1.5.4 Implement an effective organization-wide email solution, and train CWASA staff across the board in its use and benefits.
SA/CM Dec 2017 5,000
1.5.5 Establish social media platforms (Facebook, Twitter, WhatsApp) for CWASA, and popularise them as a means of improving internal and external information sharing and providing real time status updates of CWASA operations.
SA/CM Immediate Nil
1.5.6 Provide internet access to key and critical offices within CWASA, and train end users in basic internet usage. Includes annual (recurrent) cost for lease of data links.
SA Dec 2017 300,000
Expected Outputs:
A comprehensive inventory of IT equipment
New computer hardware (Servers, PCs, printers & accessories) procured as required
Basic and specialized software applications (both desktop and server software) and licenses procured as required
Improved and expanded LAN at each core facility/location
Corporate-wide WAN linking core facilities and locations
A network infrastructure performance monitoring solution
An upgraded server room at CWASA HQ
Backup servers for mission-critical software systems
An effective Uninterruptible Power Supply (UPS) solution
An off-site Disaster Recovery (DR) site
Effective firewall and user access control solutions
Service-Level Agreements (SLAs) with hardware and software vendors
A computerized corporate-wide IT Support Requests handling system
A functional Call Centre, preferably served by toll-free line(s)
A VoIP or IP PBX internal telephony solution
Staff equipped with company mobile phone lines on a Closed User Group (CUG)
A functional corporate-wide email system
67 | P a g e
STRATEGY TASKS/ACTIVITIES BY WHOM BY WHEN ESTIMATED COSTS (USD)
Social Media (SM) platforms to enhance both internal and external information sharing
Functional internet access for core offices
OBJECTIVE 2.0 Ensure that adequate, appropriate and effective information management systems and software solutions are in place to support CWASA’s core business processes.
2.1 Modify, improve and upgrade CWASA’s existing computerised information management systems and solutions.
(Note that, whereas the current Billing System was originally developed by an external consultant, subsequent system modifications are being done and are to be done internally by the SA/Computer programmer)
2.1.1 Develop and implement a module, within the existing Computerised Billing System, to handle the New Connection process (from application, approval and payment through to connection implementation).
SA/CP Dec 2017 15,000
2.1.2 Implement design modifications to the existing Computerised Billing System to cater for customer account maintenance across the entire commercial cycle, including account creation, meter reading management, billing, revenue and debt management, customer inquiry, report generation, handling of meter exchanges, and effecting of tariff and service changes.
SA/CP Jun 2018 15,000
2.1.3 Modify the existing interface with partnering banks and mobile service providers in order to cater for real-time two-way data synchronisation and access, SMS confirmation to customers upon receipt of payments, and handling of non-consumption related payments such as new connection fees.
SA/CP Jun 2018 15,000
2.1.4 Develop and implement a computerised Accounts Module to meet the specific requirements of CWASA, including functionality for budgeting, procurement, stores/inventory management, payroll management, and creation of an interface with the sales, billing and revenue management functions.
NB. Procurement (external tender processes) is currently handled through the EGP – Electronic Government Procurement) system, through the Central Procurement Support Unit. However, internal processes, including managing the annual procurement plan, should be included here. Payroll management has been implemented as a module in the HRMIS.
SA/CP Jun 2019 15,000
68 | P a g e
STRATEGY TASKS/ACTIVITIES BY WHOM BY WHEN ESTIMATED COSTS (USD)
2.2 Introduce new computerized information management systems and solutions
2.2.1 Develop and implement a computerized Human Resource Management Information System (HRMIS) solution addressing the full scope of CWASA’s HR information management requirements.
NB. Implementation has already commenced internally, starting with a payroll system. Personnel management system to follow.
SA /CM Dec 2018 10,000
2.2.2 Develop and implement a customized computerized Complaints Handling System (CHS), tailored to the requirements of CWASA, to log, track and manage the resolution of customer complaints.
SA Jun 2018 10,000
2.2.3 Procure and implement a computerized Meter Management System (MMS) solution for CWASA, to track and maintain data on customer meters over their lifespan.
SA/CP Jun 2019 10,000
2.2.4 Develop and implement an integrated data management system for water production data, covering the entire scope of water production, treatment and maintenance (planned and reactive) activities at the various WTPs.
SA/CP Jun 2019 10,000
2.2.5 Procure and implement a comprehensive Asset Information Management (AIM) solution for CWASA, to manage and maintain data on CWASA’s fixed assets over the entire asset lifecycle (including planning, acquisition, operation, maintenance, replacement and disposal).
CM Dec 2018 400,000
2.3 Utilize improved, modern tools and technologies for field data collection and management.
2.3.1 Equip meter inspectors with ruggedized hand-held meter reading devices to facilitate on-spot billing and generation of instant bills.
CM/CE Dec 2018 15,000
2.3.2 Procure and install (on a pilot basis) Automatic Meter Reading (AMR) enabled meters on selected critical installations that require constant consumption monitoring.
CM/CE Dec 2018 10,000
2.3.3 Procure data loggers, pipe locators, portable pressure gauges and leak detection equipment, to facilitate field investigations and rapid resolution of customer complaints.
NB. Implementation has already commenced internally, starting with a payroll system. Personnel management system to follow.
CM/CE Dec 2018 15,000
69 | P a g e
STRATEGY TASKS/ACTIVITIES BY WHOM BY WHEN ESTIMATED COSTS (USD)
2.3.4 Procure and install pre-paid meters on selected installations (e.g. street hydrants serving LICs).
CM/CE Dec 2018 60,000
Expected Outputs:
The existing Computerized Billing System remodeled and modified to provide functionality for: - New connection processing & implementation - Meter reading management - Revenue & debt management - Customer inquiry - Report generation - Meter exchanges - Tariff & service changes
The interface with partnering banks and mobile service providers modified to cater for: - Real time data synchronization and access - SMS confirmations to customers upon payment - Handling of non-consumption related payments
The existing Tally accounting software modified and customized to cater for: - Budgeting - Procurement, logistics, stores and inventory management - Payroll management - Interface with sales, billing and revenue management functions
A computerized Human Resource Management Information System (HRMIS) procured and implemented
A computerized Complaints Handling System (CHS) developed and implemented
A computerized Meter Management System (MMS) procured and implemented
An integrated data management system for water production & treatment and plant maintenance developed and implemented
A computerized Asset Information Management (AIM) solution procured and implemented
Improved, modern field data collection tools and technologies procured and deployed: - Hand-held meter reading devices - Automatic Meter Reading (AMR) enabled meters - Pre-paid meters - Data loggers, pipe locators, portable pressure gauges and leak detection equipment
70 | P a g e
STRATEGY TASKS/ACTIVITIES BY WHOM BY WHEN ESTIMATED COSTS (USD)
OBJECTIVE 3.0 Ensure that CWASA’s organizational structure, staffing levels, staff culture, attitude, mindset and capabilities are adequate to meet CWASA’s information management requirements.
3.1 Make necessary modifications to the organizational structure to cater for the information management and performance monitoring requirements of CWASA.
3.1.1 Establish a dedicated Performance Monitoring & Evaluation (PME) Unit within CWASA, preferably as a stand-alone unit reporting to the MD.
MD/ DMD(A)
Dec 2018 Nil
3.1.2 Centralize the monitoring and coordination of all procurement activities under the Administration Wing, in order to improve transparency, efficiency and documentation of the procurement function.
NB. If Procurement is centrally monitored through the EGP. Then we drop
MD/ DMD(A)
Mar 2018 Nil
3.1.3 Establish an Infrastructure Asset Management (IAM) Division under the Construction Circle of the Engineering Wing, to cater for the Strategic Asset Management function in CWASA.
MD/ DMD(E)
Dec 2018 Nil
3.1.4 Establish a centralized Planning & Infrastructure Development (PID) Unit in CWASA (under the Engineering Wing), charged with planning, supervising, monitoring and documenting project activities under the various internally and externally funded capital works projects.
MD/ DMD(E)
Dec 2018 Nil
3.1.5 Review the structure of the ICT Circle with a view to establishing staffing capacity to meet IT support requests and requirements across CWASA.
MD/ DMD(A)/SA
Dec 2017 Nil
3.2 Re-orient staff culture and mindsets towards adoption of information systems and computerized information management practices.
3.2.1 Carry out awareness campaigns to demystify and popularise computer usage amongst CWASA staff.
SA/CM Immediate Nil
3.2.2 Provide training to staff across the board in basic computer software applications (word-processing, spreadsheets, presentation software, internet usage, email communication).
NB. Prepare materials for awareness campaigns –drafts to be provided by NWSC as part of the implementation hand-holding process.
SA/CP Dec 2017 1,000
71 | P a g e
STRATEGY TASKS/ACTIVITIES BY WHOM BY WHEN ESTIMATED COSTS (USD)
3.2.3 Provide specialised training to staff charged with use of the different existing and new information systems and software solutions, in the application of these systems and solutions.
SA/CP Dec 2017 8,000
3.3 Undertake Business Process Re-engineering for critical business processes, with a view to phasing out manual methods of data management to the extent possible and replacing them with more streamlined, computerized methods.
3.3.1 Organize brainstorming workshops to identify key business processes and formulate improvement strategies
All DMDs Dec 2017 Nil
3.3.2 Implement process changes and modifications in a phased, prioritized manner.
All HODs Dec 2017 Nil
3.3.3 Provide the associated computer systems and solutions to match the requirements of modified business processes.
SA Jun 2018 Refer to 2.1 & 2.2
Expected Outputs:
CWASA’s organization structure modified to create the following units: - A Performance, Monitoring & Evaluation (PM&E) unit under the MD’s office; - A Procurement Monitoring Unit under the Administration wing; - An Infrastructure Asset Management (IAM) unit under the Engineering wing; - A Planning & Infrastructure Development (PID) unit under the Engineering wing.
ICT Circle staffing reviewed and strengthened to include capacity for IT support service provision.
Computer appreciation, sensitization and awareness campaigns implemented.
Staff trained in basic and specialized computer software applications.
Key business processes re-engineered to phase out manual methods of data management and introduce streamlined computerized methods.
OBJECTIVE 4.0 Improve efficiency and effectiveness of CWASA’s performance monitoring and management reporting.
4.1 Review and revise CWASA’s performance monitoring framework to ensure that it is ICT
4.1.1 Develop and implement an ICT strategy for upscaling adoption and utilization of ICT for improving performance monitoring and management reporting.
DMD(F) Jun 2018 Nil
72 | P a g e
STRATEGY TASKS/ACTIVITIES BY WHOM BY WHEN ESTIMATED COSTS (USD)
enabled, process oriented, target driven, and that it encompasses all key and support business processes.
4.1.2 Formulate explicit performance targets for critical stages of key business processes, with accountability for target achievement at all levels.
All DMDs/ HODs
Dec 2017 Nil
4.1.3 Institute mechanisms for continuous tracking of progress towards target achievement.
All DMDs/ HODs
Dec 2017 Nil
4.1.4 Institute effective mechanisms to monitor compliance of sub-contractors to set performance targets.
All DMDs/ HODs
Immediate Nil
4.1.5 Develop targets and performance indicators for support processes not currently covered within the MIS report (such as Customer mapping & GIS; ICT support services; Procurement & transport; Public relations; Training & staff capacity development; and Project management).
All DMDs/ HODs
Dec 2017 Nil
4.2 Improve CWASA’s data analysis and report generation practices.
4.2.1 Improve the efficiency of management reporting through development and routine application of system-generated reports for all key technical and commercial business processes.
SA/ All HODs
Dec 2017 Covered under 2.1 & 2.2
4.2.2 Institute the practice of meter reading audit and analysis, for improved meter reading accuracy.
CM Immediate Nil
4.2.3 Institute an anomalies generation and handling process in order to identify and address meter reading anomalies prior to billing.
CM Immediate Nil
4.3 Streamline and address gaps in key business processes hindering effective information management and efficient process flows.
4.3.1 Institute a mechanism for tracking progress of resolution of reported customer complaints, including escalation mechanisms in the event of non-action and delays.
CM Jun 2018 Nil
4.3.2 Establish a dedicated customer help desk for billing related complaints.
NB. Complaints desk already established at Dampara, not just for billing issues but for all issues.
CM Dec 2017 Nil
4.3.3 Improve meter reading practices to utilise system defined meter reading Book, Walk, Sequence cycles and system generated meter reading sheets, and phase out the use of inefficient and outdated manual practices.
CM/SA Dec 2018 Nil
73 | P a g e
STRATEGY TASKS/ACTIVITIES BY WHOM BY WHEN ESTIMATED COSTS (USD)
4.4 Improve and streamline information sharing and information flow.
4.4.1 Set strict timelines for submission of performance data and reports, and enforce adherence to these timelines.
All DMDs Immediate Nil
4.4.2 Institute mechanisms for timely data validation and performance verification, to avoid or minimize errors in management reporting.
All DMDs Immediate Nil
4.4.3 Institute mechanisms for proper documentation and information sharing on capital project works (including as-built drawings, resources applied, equipment used, money spent etc.)
DMD(E) Immediate Nil
Expected Outputs:
A strategic plan document detailing practical measures for upscaling the application of ICT in CWASA’s performance monitoring and management reporting
A matrix of Key Performance Indicators (KPIs), with SMART (specific, measurable, achievable, realistic and time-bound) performance targets specified for all key and support business processes
A robust framework for performance tracking
System-generated reports developed and implemented for key business processes
Meter reading audits instituted and operationalized
Meter reading/billing anomalies handling instituted and operationalized
Complaints tracking and escalation system instituted and operationalized
A dedicated help desk for billing related complaints established
Re-engineered, modernized meter reading practices instituted and operationalized
Performance data verification and validation mechanisms instituted and operationalized
Capital works project information sharing mechanisms instituted and operationalized
OBJECTIVE 5.0 Ensure that relevant outputs from various ongoing projects are harmonized and mainstreamed, and that technology transfer and staff capacity development is fully achieved as planned.
5.1 Follow up the effective completion, operationalization and mainstreaming of undertakings under the JICA PANI project that impact on information
5.1.1 Implement and effectively operationalize the SCADA system for the Karnaphuli Water Treatment Plant.
NB. SCADA system partly implemented to date. Optic fibre installation yet to be completed. KWTP and the two reservoirs to be linked. The contractor for the SCADA system is Yukogawa (Japanese).
PD KWSP2 Dec 2017 KWSP2 Funds
5.1.2 Complete the surveying, mapping and updating in GIS of customer connections within the Karnaphuli Service Area (KSA).
PD PANI/ PD KWSP2
Dec 2017 KWSP2 Funds
74 | P a g e
STRATEGY TASKS/ACTIVITIES BY WHOM BY WHEN ESTIMATED COSTS (USD)
management practices in CWASA.
5.1.3 Upscale the surveying and mapping of customer connections and water distribution mains outside of the KSA.
PD PANI/PD KWSP2/
CM
Dec 2017 KWSP2 Funds
5.1.4 Transfer and make available GIS data on the surveyed and mapped customer connections and water distribution mains, currently maintained within the JICA PANI project offices, to the relevant mainstream business units within CWASA (specifically, the Sales Division under the Finance wing, the Design Division of the Construction Circle under the Engineering wing, and the various MOD Zones under the Engineering wing).
NB. Note that PANI project is currently suspended, pending investigations into corruption allegations
PD PANI/PD KWSP2/
Dec 2017 Nil
5.1.5 Institute measures and procedures to mainstream the use of GIS data to improve the efficiency of relevant stages and processes of CWASA’s commercial operations, such as meter reading, bill distribution, revenue and debt management, and new connection implementation.
CM Dec 2017 Nil
5.1.6 Ditto for technical processes such as water distribution, network O&M, customer complaints handling, and planning & development of network infrastructure.
CE Dec 2017 Nil
5.1.7 Institute mechanisms for routinely updating the GIS database with new connection information and network extensions on a continuous basis.
CM/CE/PD KWSP2
Jan 2018 Nil
5.2 Follow up the training and knowledge transfer to mainstream CWASA staff of specialised skills and competencies in information management practices
5.2.1 Train CWASA mainstream staff in customer surveying, mapping and GIS data creation and maintenance.
PD PANI/PD KWSP2
Dec 2017 KWSP2 Funds
75 | P a g e
STRATEGY TASKS/ACTIVITIES BY WHOM BY WHEN ESTIMATED COSTS (USD)
from project partners/consultants/counterparts.
Expected Outputs:
SCADA system for the new Karnaphuli WTP operationalized
All CWASA customer connections mapped and updated in GIS database
Customer GIS data mainstreamed to CWASA’s technical and commercial operational business units
CWASA staff trained in GIS data management
KEY TO ABBREVIATIONS:
CE – Chief Engineer DMDs – Deputy Managing Directors CM – Commercial Manager EE-Proc – Executive Engineer, Procurement Division CP – Computer Programmer HODs – Heads of Department DMD(A) - Deputy Managing Director (Administration) PD KWSP – Project Director, Karnaphuli Water Supply Project DMD(E) - Deputy Managing Director (Engineering) PD PANI – Project Director, PANI Project DMD(F) - Deputy Managing Director (Finance) SA – Systems Analyst
76 | P a g e
Appendix 7: Assumptions and Accompanying Notes to MIS Plan Cost Estimates
ITEM DESCRIPTION Strategy/Action # Cost Estimate (USD) Accompanying Notes/Assumptions
Computer hardware 1.1.3 90,000 Assuming initial numbers as follows: 3 core servers ($5000 per server); 3 backup servers ($5000 per server); 50 new PCs ($800 per PC); 10 new network printers ($1200 per printer); 3 heavy duty printer/scanner/copiers ($1000 per machine); On-site backup (NAS).
Computer software and licenses 1.1.4 200,000 Lumpsum, to cater for core basic office applications, specialised GIS software, and antivirus solutions.
LAN implementation 1.2.2 40,000 Lumpsum, to cater for wired (Ethernet) LAN (cabling, switches, wall jacks etc.), as well as wireless access points and controllers, for HQ and offsite installations.
WAN implementation 1.2.3 30,000 Includes routers and cost (initial) of obtaining leased lines, but does not include recurrent data connection costs
Software solution for real-time monitoring of network performance
1.2.4 10,000 Acquisition costs (one-time licence plus limited period maintenance) for a network monitoring software solution e.g. Solarwinds
Server room (Tier 2) 1.3.1 200,000 Lumpsum for establishment of a Tier 2 server room, including rack cabinets, network cabling, HVAC, biometric access, CCTV
Backup servers 1.3.2 Included in 1.1.3
UPS solution for server room 1.3.3 50,000 Includes power inverter solution
Establishment of DR site (off-site secondary server room)
1.3.4 100,000 Allow for establishment of off-site Tier 1 server room for data backup and disaster recovery
Firewall solution 1.3.5 15,000 Cisco ASA firewall for HQ; Cyberoams for offsite locations (8 No.)
Call Centre 1.5.1 50,000 Assume an initial establishment of 10 call centre workstations, at approx. $5000 per workstation (incl. furniture, cabling, IT & telephony equipment, telecommunication (E1) link, LAN, Agent PCs, Headsets, CRM software, plus an allowance for a power backup solution).
VoIP/IP PBX telephony solution 1.5.2 30,000 Includes cost of on-site IP-PBX equipment and VoIP enabled phone sets, but does not include internet service costs
77 | P a g e
ITEM DESCRIPTION Strategy/Action # Cost Estimate (USD) Accompanying Notes/Assumptions
CUG solution 1.5.3 10,000 Handsets and CUG lines for at least 100 employees (Class 1 and Class 2 Officers) for a start
Corporate email solution 1.5.4 5,000 Refer to 1.1.3 for hardware requirements; for the email server software, the Zimbra open source collaboration suite is proposed. Allow here for SSL certificate purchase.
Internet and data connectivity 1.5.6 300,000 Includes annual cost of lease of data communication links
HRMIS 2.2.1 10,000 Allow for procurement of commercial off-the-shelf product that also includes payroll management functionality
MMS 2.2.3 10,000 Allow for procurement of commercial off-the-shelf product
AIMS 2.2.5 400,000 Allow for procurement of commercial off-the-shelf product
Hand-held meter reading devices 2.3.1 15,000 Assuming equipping of 40 meter readers (MIs) for a start
AMR meters for selected critical installations (large meters)
2.3.2 10,000 Assuming around 50 critical large meters to be continuously monitored for a start, at approx. $200 per connection for the meters
Leak detection equipment 2.3.3 15,000 Assuming the following numbers for a start: 1 leak correlator; 1 pipe locator; 1 ultrasonic flow meter
Pre-paid meters 2.3.4 60,000 Assuming 100 pre-paid meters (communal water dispensers) installed on selected street hydrants serving the urban poor (LICs) for a start, at a unit cost of approx. $600 (incl. accessories).